About this file
This is a Subcontractor Summary worksheet issued by the City of St. Petersburg for a sheltered contract opportunity related to a Manhole Inspection Unit procurement. The document establishes the framework for subcontractor participation on the project, permitting up to 80% of contract work to be subcontracted. Prime contractors must complete and submit this worksheet with their bid, providing detailed information on all intended subcontractors including their legal names, business addresses, contact information, trade classifications, and subcontract amounts. The worksheet specifies that only first and second tier subcontractors are permitted unless otherwise noted in the contract documents, and it identifies seven conditions under which subcontractor substitutions may be authorized after contract award, including failure to execute agreements, inadequate licensing, bankruptcy, ineligibility, non-performance, unsatisfactory work quality, or substantial project delays.
The document emphasizes that Small Business Enterprise (SBE) subcontractors used to meet SBE percentage requirements must be replaced with other SBE subcontractors if substituted, unless the prime contractor demonstrates that SBE requirements are being met through alternative means. Requests for subcontractor changes must be submitted in writing to the City's Procurement & Supply Management department, specifically to the Contracts Compliance Manager. The worksheet includes fields for tracking added and deleted subcontractors with reason codes corresponding to the authorized substitution conditions. These instructions represent the City of St. Petersburg's standard subcontracting protocol and are mandatory components of the bidding process for this sheltered contract opportunity.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Manhole_Inspection_Unit_(Addendum_#3_Revision).pdf | ||
| Tech_Addendum.pdf | ||
| Manhole_Inspection_Unit.pdf | ||
| Public_Construction_Bond.docx | DOCX document | |
| Subcontractor_Utilization_Plan.docx | DOCX document | |
| Subcontractor_Summary_Spreadsheet.xlsx | XLSX spreadsheet | |
| Light_Construction_Agreement.docx | DOCX document | |
| Performance_&_Payment_Bond_.DOCX | DOCX document | |
| Quote_Addendum.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
| City of St. Petersburg |
| Subcontractor Summary Instructions |
WORKSHEET MUST BE COMPLETED AND SUBMITTED WITH YOUR BID
1. The Subcontractor Worksheet reflects the percentage of work which may be subcontracted for this project. Refer to Contract Standards, Instructions to Bidders, Article I-13, Subcontractors for applicable rules.
2. Enter the name of your company in the Prime Contractor field.
3. Enter the name and date of Prime Contractor employee completing this form.
4. Provide all information requested on each intended subcontractor. If subcontractors will NOT be used for this project, provide a written statement on the Subcontractor List indicating the same.
5. Subcontractors may not be changed or substituted once a Prime Contractor is awarded the project (and the pre-construction meeting held), except for the following reasons:
A. Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified;
B. Subcontractor is not appropriately licensed to perform the scope of work;
C. Subcontractor becomes bankrupt or insolvent;
D. Subcontractor is ineligible to perform the work on the project;
E. Subcontractor fails or refuses to perform its subcontract;
F. Engineer determines the work performed by the subcontractor is substantially unsatisfactory and not in substantial accordance with the plans and specifications;
G. Subcontractor is substantially delaying or disrupting the progress of the work.
Requests for changes to the Subcontractor List shall be made in writing to the Procurement & Supply Management, Attention: Contracts Compliance Manager at Stephanie.Swinson@stpete.org.
6. SBE subcontractors used to meet the SBE percentage requirement, if replaced, shall be replaced with a SBE subcontractor, unless the Prime Contractor demonstrates that SBE requirements are being met in another way.
7. Restrictions on subcontracting percentage and use of multiple-tier subcontractors do not apply to FDOT LAP or federally funded projects.
Subcontractor Worksheet
| City of St. Petersburg |
| Subcontractor Summary |
| Project Name: |
| Project Number: |
| Percentage of Contract Which May be Subcontracted: 80% for Shelter Bid |
| Name of Prime Contractor: | Cells below will be "hidden" on the worksheet since they are only for Procurement's use. |
| Name/Date of Individual Completing this Form: |
| City of St. Petersburg SBE or MWBE Contractor Yes or No | Subcontractor's Name (Provide complete Legal Name) | Subcontractor's Primary Business Address | Name/Phone Number and Email Address of Subcontractor's Employee Responsible for Project Supervision | First or Second Tier Subcontractor* | Trade Classification(s) Being Subcontracted (List One Trade per Line) | Subcontract Amount ($) | Added (A) Deleted (D) | Reason Code | City Approver/Date | Add (A) and Delete (D) Legend |
| Example: Yes | XYZ Contractors, Inc. | 123 N. Burlington Ave., St. Petersburg, FL 33701 | Joe Jones - 727-555-555 Email - XYXCon@yahoo.com | First | Electrical | 13,234.00 | D | B | Employee XYZ/03-01-19 | A. Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified; |
| B. Subcontractor is not appropriately licensed to perform the scope of work; | ||||||||||
| C. Subcontractor becomes bankrupt or insolvent; | ||||||||||
| D. Subcontractor is ineligible to perform the work on the project; | ||||||||||
| E. Subcontractor fails or refuses to perform its subcontract; | ||||||||||
| F. Engineer determines the work performed by the Subcontractor is substantially unsatisfactory and not in substantial accordance with the Plans and Specifications; |
G. Subcontractor is substantially delaying or disrupting the progress of the work.
Total: 0.00
| *Only first and second tier subcontractors are permitted unless noted otherwise in the Contract Documents. | Contract Amount | |
| 0.00 | Amount Allowed to be Subcontracted |