Statement-of-Work-Spearfish Asbestos r1.docx

DOCX document 59 KB Posted

Attached to
BLK NF Spearfish WC Asbestos Abatement
Solicitation number
1240LP25Q0113
Issued by

About this file

This Statement of Work (SOW) details an asbestos abatement project for the United States Department of Agriculture (USDA) Forest Service at the Black Hills National Forest's Spearfish Work Center in South Dakota. The project requires a licensed South Dakota state-certified asbestos removal contractor to remove approximately 1,025 square feet of asbestos containing building material (ACBM) from the interior walls and ceiling of a flammable paint storage shed, with the goal of decommissioning an unsafe and unhealthy building that is no longer in use.

Key technical requirements include providing all necessary labor, materials, equipment, and disposal services in compliance with federal and state regulations. The contractor must submit multiple deliverables, including an Accident Prevention Plan, Action Submittals, Product Data, Shop Drawings, and a Contractor Quality Control Plan, with most documents required 10 days prior to beginning on-site work. The project site is located approximately 2 miles south of Spearfish, SD at an elevation of 4,375 feet, and is open year-round. The Forest Service has already purchased and installed a prefabricated replacement storage building in fiscal years 2022-2023, making this asbestos removal a preparatory step for the building's final decommissioning.

View the file

Other files

File Type Posted
Spearfish WC Flamm Storage Specs Draft Final 15Sept2025.pdf PDF
_1240LP25Q0116.pdf PDF
Drawings Final 23May2025.pdf PDF
WD 2015-5377 r29 20250708.pdf PDF
Site Map.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

United States Department of Agriculture Forest Service Black Hills National Forest Northern Hills Ranger District Spearfish Work Center Flammable Storage Building Asbestos Abatement Statement of Work

Contents

Project3
General Information3
1.0 Scope of Work3
2.0 Background3
Contractor Requirements3
3.0 Technical Requirements / Tasks3
4.0 Government Furnished3
5.0 Deliverables / Schedule3
6.0 Travel4
7.0 Contractor’s Key Personnel4
8.0 Security Requirements4
9.0 Data Rights4
10.0 Section 508 – Electronic and Information Technology Standards4
Attachment4

Project Northern Hills Ranger District Spearfish Work Center Flammable Storage Building Asbestos Abatement

General Information

1.0 Scope of Work

Work for this project requires the Contractor to be responsible for supplying all labor, materials, equipment, supplies, utilities, transportation, disposal, and applicable fees to complete the work identified below in accordance with these Specifications, Drawings, and applicable Federal and State laws and regulations.

To promote public health and safety, removal of approximately 1025 square feet of Asbestos Containing Building Material (ACBM) from the interior of the Flammable Paint Storage Shed and dispose. The ACBM is identified as asbestos wall and ceiling board. Removal of hazardous materials in interest of public safety and decommissioning of older building no longer in use as flammable storage.

2.0 Background

Decommission unsafe and unhealthy Spearfish Work Center Flammable Storage Building. It has asbestos cement paneling on interior walls and ceiling. Project removes asbestos then demolishes building. Forest purchased prefabricated replacement storage in fiscal year 2022 and it was installed in fiscal year 2023.

This project is located at the Black Hills National Forest, Spearfish Work Center, 525 Tinton Road, Spearfish, South Dakota 57783. The location is approximately 2 miles south of Spearfish, SD on Tinton Road.

The elevation of the site is approximately 4,375 feet above mean sea level. The Project Site is open year-round.

Contractor Requirements

3.0 Technical Requirements / Tasks

Describe the specific tasks or work the contractor must perform. Provide direction on any specific methodologies.

· Work for this project requires the Contractor to be responsible for supplying all labor, materials, equipment, supplies, utilities, transportation, disposal, and applicable fees to complete the work identified below in accordance with these Specifications, Drawings, and applicable Federal and State laws and regulations

· Contractors should demonstrate a thorough understanding of the project requirements and attention to detail is crucial for quality construction. Strong communication skills are essential for coordinating with clients, subcontractors and other stakeholders. Past experience in asbestos removal is beneficial.

· A licensed South Dakota state-certified asbestos removal service shall be obtained for asbestos removal and disposal operations.

· Contractors should have the capacity to handle the specific project requirements and deliver within the specified timeline.

· A full copy of the Contract Specifications can be found with this solicitation.

· A full copy of the Contract Construction Plans can be found with this solicitation.

4.0 Government Furnished

There are no Government Furnished Materials associated with this project.

5.0 Deliverables / Schedule

Key Deliverables

Item No.
Deliverable / Item Title
Description
Frequency
Reference
Delivery Format
Due By
1
Accident Prevention Plan
Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project
Once
Specifications General Requirements 2.2.A
Via email to COR
10 days prior to on-site work beginning
2
Action Submittals
Written and graphic information that requires Contracting Officer’s(CO's) responsive action.
Prepare and submit Action Submittals required by individual Specification Sections.
Specifications General Requirements 3.4
Submit four copies of each submittal, unless otherwise indicated.
Before beginning work on individual item
3
Product Data
Collect information into a single submittal for each element of construction and type of product or equipment.
Submit four copies or one electronic pdf copy of each submittal, unless otherwise indicated.
Specifications General Requirements 3.4.B
Submit four copies of each submittal, unless otherwise indicated.
Before beginning work on individual item
4
Shop Drawings
Prepare Project-specific information, drawn accurately to scale in electronic format.
Submit four copies or one electronic pdf copy of each submittal, unless otherwise indicated.
Specifications General Requirements 3.4.C
Submit four copies of each submittal, unless otherwise indicated.
Before beginning work on individual item
5
Requests for Information (RFI’s)
Immediately on discovery of the need for additional information or interpretation of the Contract Documents, prepare and submit an RFI in electronic form.
Submit four copies or one electronic pdf copy of each submittal, unless otherwise indicated.
Specifications General Requirements 3.4.D
Submit four copies of each submittal, unless otherwise indicated.
Before beginning work on individual item
6
Contractor Quality Control Submittals
Provide electronic Quality Control submittals, including design data, certifications, manufacturer's instructions, manufacturer's field reports, and other quality-control submittals as required under other Sections of the Specifications.
Submit four copies or one electronic pdf copy of each submittal, unless otherwise indicated.
Specifications General Requirements 3.4.E
Submit four copies of each submittal, unless otherwise indicated.
Before beginning work on individual item
Item No.
Deliverable / Item Title
Description
Frequency
Reference
Delivery Format
Due By
7
Contractor Quality Control Plan
Provide a written Contractor Quality Control (CQC) plan.
Once
Specifications General Requirements 3.4.F
Submit four copies of each submittal, unless otherwise indicated.
At the time of the preconstruction conference.
8
Quality Control Documentation
Maintain Quality Control Daily Reports and Daily Test Report Information Sheets (samples attached) of quality control activities and tests.
Maintain Quality Control Daily Reports and Daily Test Report Information Sheets (samples attached) of quality control activities and tests.
Specifications General Requirements 3.4.G
Submit four copies of each submittal, unless otherwise indicated.
As work begins on individual items
9
Application for Payment
Comply with requirements specified in the Contract Clauses and Division 01 Section “Definition of Items & Measurement and Payment”. Provide in electronic format.
Bi-Monthly
Specifications General Requirements 3.4.H
Submit four copies of each submittal, unless otherwise indicated.
As work begins on individual items

Informational Submittals Contractor’s Quality Control Daily Construction Reports Cost Breakdown Schedule of Values Accident Prevention Plan Material Test Reports Field Test Reports Manufacturer's Instructions

Prepare and submit Informational Submittals required by other Specification Sections.
Prepare and submit Action Submittals required by individual Specification Sections.
Specifications General Requirements 3.5.A-H
Submit two copies of each submittal, or one electronic pdf unless otherwise indicated.
Before beginning work on individual item
11
Contractor's Construction Schedule
Provide a construction schedule that incorporates the full contract period.
Specifications General Requirements 3.6.A-D
Via email to COR
10 days prior to on-site work beginning and with each Progress Payment Request.
Item No.
Deliverable / Item Title
Description
Frequency
Reference
Delivery Format
Due By
12
Testing Agency Qualifications
proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
Once
Specifications Quality Requirements 1.4.A
Digital file Via email to COR
Before beginning work on individual item
13
Permits, Licenses, and Certificates
submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.
Once
Specifications Quality Requirements 1.4.B
Digital file Via email to COR
Before beginning work on individual item
14
Test and Inspection Reports
Prepare and submit certified written reports specified in other Sections
Prepare and submit test and inspection reports as required by individual Specification Sections.
Specifications Quality Requirements 1.5.A
Digital file Via email to COR
Submit test and inspection reports as required by individual Specification Sections.

6.0 Travel

Travel is the responsibility of the contractor.

7.0 Contractor’s Key Personnel

The Contractor is to provide name, position title and contact information of company executive responsible for the project. Contractor is to provide an onsite superintendent at all times.

8.0 Security Requirements

The Contractor is to install and maintain suitable barriers to ensure the protection of the public, employees, and facilities. Protect persons, motor vehicles, surrounding buildings, plants, and surrounding surfaces or buildings from harm resulting from Contractor’s work.

Site gate lockout procedures will be established if applicable.

9.0 Data Rights

Data will not be produced with this construction contract.

10.0 Section 508 – Electronic and Information Technology Standards When information technology is to be acquired, include language describing Section 508 requirements.

Information technology will not be acquired with this construction contract.