Statement of Work (SOW) SMTC Barracks HVAC Repairs.pdf
PDF 133 KB Posted
- Solicitation number
- 31040RFQ260000704
About this file
This is a Statement of Work (SOW) for HVAC motorized valve and DOAS repairs at USCG SMTC Barracks located at 1308 Northwest Boulevard, Chesapeake, VA 23322. The contractor must provide all labor, materials, and equipment to restore full operational capability to failed HVAC systems within a period not to exceed 45 working days after contract award, operating Monday–Friday from 0700 to 1530 EST. The work includes replacing failed chilled water (CHW) and hot water (HW) valves with actuators and valve bodies in 13 rooms across two floors (Rooms 101–106, 201–203, 205, 207–210), repairing Building DOAS unit CHW valve replacement, troubleshooting and repairing Training Room (AHU-2) thermostat controls, conducting chiller and boiler water testing with comprehensive treatment plan recommendations, and replacing restricted or inaccessible balancing valves. Additionally, the contractor must install 1H/1C thermostats with integrated 3-speed automatic fan control for all 4-pipe AHUs. All repairs must comply with current UFC standards and manufacturer specifications, with the contractor responsible for creating and finishing any required access points.
Quality assurance requirements mandate verification of valve actuation, thermal performance, control sequences, and hydrostatic integrity for each serviced unit. Deliverables include a detailed service report within five business days post-repair, operational test and balance data, and water analysis and treatment plan prior to system flush if required. The contractor must provide qualified personnel with a dedicated Project Manager available via telephone during business hours and responding to technical problems within 24 hours. All personnel, including subcontractors, must obtain DBIDS credentials for facility access, with the contractor solely responsible for coordination with the Visitor Control Center. Travel costs must be included in overall pricing without separate line items. The SOW specifies compliance with OSHA regulations, EPA environmental standards, fire marshal notifications for suppression-affecting activities, and Lock Out/Tag Out coordination with Facilities Division representatives. Reports must be Microsoft Office-compatible, and the QAE retains the right to inspect and reject work not meeting specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Controls diagram.pdf | ||
| SF30 Amendment 0003.pdf | ||
| SF30 Amendment 0002.pdf | ||
| Amendment 0002 NSA NWA ACCESS FORM SECNAV 5512.pdf | ||
| Attachment 1 - SOW.pdf | ||
| SF30 Amendment 0001.pdf | ||
| Poster SCA Poster.pdf | ||
| SF-18 RFQ.pdf | ||
| FAR Clauses and Deviations Services.pdf | ||
| Wage rate determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
PAGE 1/4
STATEMENT OF WORK (SOW)
Project Title: HVAC Motorized Valve and DOAS Repairs Location: USCG SMTC Barracks: 1308 Northwest Blvd Chesapeake, VA 23322
• 1.0 BACKGROUND AND OBJECTIVE
1.1 A functional assessment conducted that identified multiple failures within the HVAC infrastructure at the USCG SMTC Barracks.
1.2 The objective is to restore full operational capability to the HVAC systems by replacing failed components, correcting control issues, and verifying water quality.
1.3 The work consists of the contractor providing all labor, materials and equipment as required to complete the work listed herein this SOW.
• 2.0 APPLICABLE DOCUMENTS
2.1 All repairs shall comply with current UFC (Unified Facilities Criteria) and manufacturer specifications.
• 3.0 TECHNICAL REQUIREMENTS
3.1 Air Handling Unit (AHU) Valve Replacements
3.1.1 The Contractor shall remove, furnish new valves and replace all failed chilled water (CHW) and hot water (HW) valves as specified in the Task Matrix below.
3.1.2 Each replacement shall include the actuator and valve body to ensure full responsiveness.
3.1.3 If access points are required to complete this work, the contractor will be responsible for creating the access point as well as the prep, repair and finishing of the surface back to pre-work condition.
Task ID Room CHW Valve Action HW Valve Action
3.1.2.1 101 Replace Replace
3.1.2.2 102 Replace Replace
3.1.2.3 103 Replace Replace
3.1.2.4 104 Replace Replace
3.1.2.5 106 Replace Replace
3.1.2.6 201 Replace Replace
3.1.2.7 202 Replace Replace
3.1.2.8 203 Replace Replace
3.1.2.9 205 Replace Replace
3.1.2.10 207 Replace Replace
3.1.2.11 208 Replace Replace
PAGE 2/4
3.1.2.12 209 Replace Replace
3.1.2.13 210 Replace Replace
3.2 DOAS Unit and Specialty AHU Repairs
3.2.1 Building DOAS: Replace the failed chilled water valve.
3.2.2 Training Room (AHU-2): Troubleshoot and repair the failed thermostat controls to restore fan and CHW valve actuation.
3.2.3 If access points are required to complete this work, the contractor will be responsible for creating the access point as well as the prep, repair and finishing of the surface back to pre-work condition.
3.3 Water Quality and System Maintenance
3.3.1 Conduct Chiller and Boiler water testing to verify chemical characteristics.
3.3.2 Provide a comprehensive water treatment plan based on test results.
3.3.3 Perform a full system flush only if testing indicates excessive fouling or contamination.
• 4.0 TECHNICAL REQUIREMENTS
4.1 System Upgrades
4.1.1 Balancing Valves: Replace existing balancing valves that are currently restricted or inaccessible.
4.1.2 Thermostat Upgrades: Install 1H/1C thermostats for 4-pipe AHUs with integrated 3-speed automatic fan control in all rooms.
4.1.3 If access points are required to complete this work, the contractor will be responsible for creating the access point as well as the prep, repair and finishing of the surface back to pre-work condition.
• 5.0 QUALITY ASSURANCE AND TESTING
5.1 The Contractor shall perform the following verifications for each unit serviced:
ID Requirement Standard of Acceptance
5.1.1 Valve Actuation Smooth, full-range movement on command from thermostat.
5.1.2 Thermal Performance Verified CHW and HW temperature deltas across coils.
5.1.3 Control Sequence Correct fan-speed and mode switching (Cool/Heat).
5.1.4 Hydrostatic Integrity Zero leaks at all connection points under operational pressure.
• 6.0 DELIVERABLES
ID Deliverable Deadline
6.1.1 Detailed Service Report 5 business days post-repair.
6.1.2 Operational Test & Balance Data Included with Service Report.
6.1.3 Water Analysis & Treatment Plan Prior to system flush (if required).
PAGE 3/4
• 7.0 PERSONNEL AND CONDUCT
7.1 Qualified Personnel: The Contractor must provide qualified personnel to perform all requirements specified in this SOW.
7.2 Key Personnel - Project Manager: The Project Manager must be available via telephone between 0700 and 1530 EST, Monday–Friday, and respond to technical problems within 24 hours.
7.3 Employee Conduct: Contractor employees must maintain a professional appearance and comply with all Government regulations (fire, safety, security, weapons policies).
7.4 Removal for Misconduct: The Government may direct the Contractor to remove any employee for misconduct or security reasons; this does not relieve the Contractor of service obligations.
• 8.0 SITE ACCESS AND SECURITY
8.1 DBIDS Credentials: All personnel (including subcontractors) must obtain Defense Biometric Identification System (DBIDS) credentials for unescorted access.
8.2 Registration Responsibility: The Contractor is solely responsible for coordinating with the Visitor Control Center (VCC). Failure to obtain credentials resulting in delays is the Contractor's responsibility.
• 9.0 PERIOD AND PLACE OF PERFORMANCE
9.1 Period of Performance: Not to exceed 45 working days after contract award.
9.2 Place of Performance: 1320 Northwest Blvd, Chesapeake, VA 23322.
9.3 Hours of Operation: 0700 to 1530 EST, Monday–Friday. After-hours or holiday work requires written QAE approval.
9.4 Travel: Travel costs for delivery and installation must be included in the overall cost and not listed as a separate line item.
• 10.0 ADMINISTRATIVE AND OPERATIONS
10.1 Award Notification: The contractor must immediately notify the QAE of the intended start date upon award.
10.2 Contractor Furnished Property: The Contractor must provide all labor, materials, and equipment.
10.3 General Report Requirements: All reports must be in electronic format compatible with Microsoft Office (read/write capability).
10.4 Acceptance Inspection: Upon completion, the QAE will conduct an inspection and has the right to reject work contrary to the specification.
• 11.0 SAFETY AND ENVIRONMENTAL
11.1 Safety Compliance: Abide by OSHA regulations 29 CFR 1910 and 29 CFR 1926.
11.2 Fire Marshal Notification: Provide written notice to the Base Fire Marshal for activities affecting fire suppression or egress.
11.3 Lock Out/Tag Out: Lock Out/Tag Out requires a Facilities Division representative and cannot be conducted solely by the contractor.
11.4 Environmental Protection: Abide by EPA 40 CFR and ICSPORTSVA INSTM5090.2.
11.5 Hazardous Materials: The contractor is responsible for the disposal of hazardous materials in accordance with federal and local guidelines.
• 12.0 GENERAL PROVISIONS
PAGE 4/4
12.1 Permits: Obtain all licenses and permits at no additional expense to the government.
12.2 Workmanship: Accomplish work with the best standard practices using experienced tradesmen.
12.3 Oral Modification: Only the Contracting Officer has the authority to modify the terms of this contract.