This Statement of Work (SOW) details a retention pond rehabilitation project for the U.S. Geological Survey (USGS) at the J.W. Powell Federal Building in Reston, VA. The project involves restoring the approximately 0.3-acre stormwater retention pond to its original design capacity and functionality, with specific requirements including sediment and vegetation removal, mechanical and structural maintenance, and compliance with Virginia Department of Environmental Quality regulations. The contractor must conduct a comprehensive assessment, submit a detailed work plan, and complete the project within 90 calendar days of the Notice to Proceed, with key deliverables including a work plan submittal, nutrient loading calculations, and project closeout.
The scope of work encompasses removing accumulated sediment, leaf debris, cattails, woody vegetation, and non-native plants; inspecting and restoring mechanical elements like valves and sluice gates; and ensuring site protection and restoration. The project requires calculating nutrient load reductions, providing total sediment removal volume, and maintaining sustainable practices by using environmentally friendly products. The contractor must follow various federal standards and regulations, including GSA safety specifications, OSHA guidelines, and sustainability requirements. The project is classified as Controlled Unclassified Information (CUI) and includes photographic exhibits showing the current condition of the pond, inflow pipe, and outflow areas.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Retention Pond Maintenance, J.W. Powell Federal Building, VA1648
Controlled Unclassified Information (CUI)
April 2025 Controlled Unclassified Information (CUI)
Back to Top
PROJECT IDENTIFICATION
Project Title:
Storm Water Retention Pond Rehabilitation
Building:
J. W. Powell Federal Building
Building ID #:
VA1648
Building Location
12201 Sunrise Valley Drive, Reston, VA 20192
Project Number
7108369
SOW Author:
TBA
Back to Top
THIS PAGE LEFT
INTENTIONALLY
BLANK
Back to Top
1.1. PROJECT INFORMATION
This project entails the required efforts to ensure the existing storm water management pond continues to meet its intended function. The pond is located at the U.S. Geological Survey National
Center, 12201 Sunrise Valley Drive, Reston VA. The pond and associate embankment were constructed when the building was built in 1972. Extensive repairs to rebuild the pond and embankment were completed in 1992. A copy of the plans for the rebuild are available upon request.
The site and pond are federally owned property. It is adjacent to Sunrise Technology Park. The area around the pond is relatively clear.
To be considered successful, the Work shall
• Deliver the project on time and within budget.
• Meet all project milestones.
• Establish and maintain positive relations with public authorities, jurisdictions, and neighborhood.
• Ensure a safe work environment during construction for workers and authorized visitors on the construction site.
• Manage the completion of the project with the spirit of partnering.
• Provide timely reports and communications.
• Ensure that all sensitive documents are handled, distributed, archived, and destroyed according to established project procedures.
1.2. ROLES AND RESPONSIBILITIES
Contracting Officer’s Representative (COR): The USGS COR will monitor contract/project progress and is responsible for the general administration and technical coordination of this project.
The COR is the Government's point of contact for post award information exchange, design submission reviews, construction inspection/tests, and all administrative duties associated therewith.
Contractor: The Contractor is solely responsible for the work (including all labor, equipment, materials, inspections, planning, supervision, and contract coordination) to meet requirements of the
SOW. The Contractor shall raise concerns or questions directly to the COR prior to discussion with the agency or customer.
Customer initiated changes: Following project award, the Contractor shall bring to the attention of the COR, in writing, any directly requested changes to clarify any concerns or qualifications of the
SOW.
Contractor Initiated Changes: Following award, Contractor initiated changes from this scope of work are subject to government approval. All Contractor initiated changes shall be separately documented. The Contractor shall provide all information necessary to satisfy the government as to need, benefit, or comparability of all changes for government approval.
1.3. QUOTE SUBMISSION REQUIREMENTS
See Attachment A “Instructions to Offerors” of RFQ for detailed submission and quote formatting requirements.
It is recommended that the Contractor attends Site Visit(s) to walk the project prior to providing a quote.
Back to Top
2. SCOPE OF WORK (SOW)
2.1. DESCRIPTION OF WORK
The U.S. Geological Survey (USGS) Headquarters Campus requires services necessary to restore the stormwater retention pond to its original design capacity and functionality. Located at the USGS
National Center, 12201 Sunrise Valley Drive, Reston, VA, the approximately 0.3-acre wet pond is part of the facility’s Municipal Separate Storm Sewer System (MS4). This pond supports both peak discharge control during storm events and pollutant reduction in compliance with MS4 permitting requirements.
Accumulated sediment and overgrowth have diminished the pond’s capacity and performance. This project entails all routine and non-routine efforts required to return the pond to full operational status in accordance with federal and state stormwater regulations.
Regulatory Compliance
• Perform all work in accordance with the Virginia Department of Environmental Quality
(VADEQ) regulations for wet pond rehabilitation under the MS4 program.
• Comply with applicable requirements outlined in the Virginia Erosion and Stormwater
Management Program (VESMP), the Virginia Stormwater Management Handbook, and the
Virginia Stormwater Management Program (VSMP).
• Complete all routine and non-routine efforts activities required under these regulations, including maintenance of mechanical and structural components.
Nutrient Removal Calculation
• Calculate and provide estimates of nutrient loading reductions resulting from the dredging activities. This shall include:
1. Total Nitrogen (TN) and Total Phosphorus (TP) load reductions, expressed in pounds per year (lbs/year).
2. Estimate change in nutrient load reduction resulting from project.
3. Assumptions, calculation methods, and data sources must be documented and submitted as part of the final project report.
4. Provide total volume of sludge removed in cubic yards.
Sediment and Vegetation Removal
Remove excess accumulated sediment from the pond to restore its designed depth and capacity.
Take care not to disturb or damage any existing pond liner or the underlying silt or clay base. The contractor must measure and report the amount of sediment removed to the project manager.
• Remove:
1. Leaf debris and cattails from the pool area
2. Woody vegetation and trees from the pond embankment
3. Non-native vegetation within and surrounding the pond
• Inspect and restore the trash rack on the inlet structure to proper condition.
• Replace the riprap downstream of the inlet headwall as needed.
Mechanical and Structural Maintenance
• Inspect, maintain, and repair existing mechanical elements such as:
1. Valves
2. Sluice gates
Back to Top
3. Locks
4. Access hatches
• Maintain and restore existing plantings and any newly installed vegetation related to the pond restoration.
Site Protection and Restoration
• Identify and avoid any underground or above-ground utilities during all project activities.
• Repair any damage to roads, sidewalks, structures, or other infrastructure caused during construction.
• Ensure all workers are briefed on and comply with plant protection measures.
• Restore any disturbed landscape around the pond to its original condition or better.
2.2. SCOPE OF WORK
Furnish all labor, materials, supervision and equipment required for installation of all items contained in the drawings (if applicable) and scope of work. All work is to be performed in accordance with this statement of work, drawings, exhibits and all attachments and shall be consistent with industry standard best practices unless otherwise noted. Work shall be performed and completed at a time and date coordinated with facility activities to minimize impact on operations. Perform area clean-up, secure work areas and inform appropriate personnel of work completion.
2.3. MATERIAL ORDER/DELIVERY
Ensure appropriate materials for the completion of this project are received and staged on-site prior to commencing any work if needed. The USGS COR shall inspect and approve all building materials and all replacement materials prior to the start of work.
2.4. PROCEDURES
The entire scope of work must be followed by the Contractor. Each item must be adhered to, including notifications of job award, discussion of the project prior to starting, job schedule information, etc. Upon award, the contractor must fully read, understand, and provide this document to each member of the team that will be working on this project. Each team member and technician on the job site must fully understand these expectations. Failure to correctly complete any of these items may result in penalties and result in extra costs for the Contractor.
3. PROJECT DELIVERABLES
3.1. PROJECT DELIVERABLES
The overall Period of Performance shall be 90 days calendar days from Notice to Proceed (NTP) through planning and Construction Administration (CA) to Project Closeout, based on the following:
Deliverable Days from Notice to Proceed
Work Plan Submittal 10 calendar days
USGS Review 20 calendar days
Calculations on Nutrient Loading
Substantial Completion 80 calendar days
Project Closeout 90 calendar days
Back to Top
3.2. SUBMISSIONS
Prior to beginning the work, the Contractor shall provide necessary shop drawings, submittals, product cut-sheets, and the project schedule for the successful completion of the project. All information shall be updated as necessary and the submission must have an approval signature of the
COR before ordering and installation.
Pond Assessment and Plan Submittal
• Conduct a full assessment of the pond, embankment, inlet/outlet structures, and associated components.
• Submit a comprehensive work plan for government review, including:
1. A detailed list of tasks
2. A project schedule
3. A sediment and sludge disposal plan, including dewatering procedures
4. A safety plan addressing worker safety, public protection, and traffic disruption mitigation
• Clearly identify any work that may impact on vehicle or pedestrian traffic and outline steps to minimize disruption.
• No work may commence until the Contracting Officer’s Representative (COR) has approved the submitted plan. The government will review the submittal within two (2) weeks.
3.3. PERMITS/ INSPECTIONS
Provide a copy of necessary permits and inspections to the COR for the work if necessary. Test and inspect all areas of work with the COR prior to project closeout.
4. PERIOD OF PERFORMANCE
4.1. PERIOD OF PERFORMANCE
This contract is to be completed within 90 days after receipt of Award.
4.2. HOURS OF WORK
All work to be performed during the normal building hours of 6:00 am - 6:00 pm, M-F. Any work creating significant noise, disruption to building activities and or disrupting traffic shall be coordinated with and approved by the COR in advance.
5. STANDARDS, CODES, AND REGULATIONS
5.1. STANDARDS
All work activities shall be performed in a manner consistent with GSA Safety Specification 01546, the guidance as set forth by OSHA, and NFPA 70, NFPA and 70E, for electrical safety of personnel and equipment. Work areas shall be established consistent with the standards for work on or around energized equipment and all appropriate electrical safety considerations shall be taken.
5.2. GSA REQUIREMENTS, CODES & REGULATIONS
This project shall comply with all the latest editions of all applicable codes.
● 2021 PBS P100, with 2022 Addendum Facilities Standards for the Public Buildings Service, including all applicable Standards, Criteria and Guides listed therein https://www.gsa.gov/cdnstatic/P100%202022%20Addendum%20Final_.pdf
Back to Top
● PBS P-120, Public Buildings Service Cost and Schedule Management Policy Requirements, November 7, 2022
● Architectural Barriers Act Accessibility Standard (ABAAS)
● PBS Order 3490.3 CHGE 1, “Security for Sensitive Building Information Related to Federal
Buildings, Grounds, or Property”, March 22, 2021
● PBS CAD Standards, March 10, 2021
● IAQ Guidelines for Occupied Buildings under Construction by SMACNA
● Occupational Safety and Health regulations for construction and general industry; 29 CFR Parts
1926 and 1910
● Section 01546 – Safety and Health Specification (see attachments)
● International Code Council Codes (ICC)
● National Fire Protection Association (NFPA) National Fire Codes and Standards
● Egress issues shall meet NFPA 101 Life Safety Code
● Section 889
● PBS Building Commissioning Guide
● Guidance for Electric Metering in Federal Buildings
● National Historic Preservation Act of 1966, as amended, and its implementing regulations (36
CFR 800)
● Secretary of the Interior’s Standards for the Treatment of Historic Properties (36 CFR 68)
● The Guiding Principles for Sustainable Federal Buildings
● GSA Fine Art Collection Policies & Procedures 2017
● GSA Stormwater Management Submission
● 40 CFR 61 National Emission Standards for Hazardous Air Pollutants
● 40 CFR 763 Asbestos
● 49 CFR 107 Hazardous Materials Program Procedures
● 49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials
Communications, Emergency Response Information, and Training Requirements
● EPA Mold Remediation Guidelines, September 2008
6. SUSTAINABLE PRODUCTS AND SERVICES (IF APPLICABLE)
6.1. GENERAL PRODUCT REQUIREMENTS
All products purchased by the Contractor shall meet strict sustainability requirements including, but not limited to, non-toxic, low VOC, low-embodied carbon, recycled content, energy efficient, and water conserving. Where products labeled FEMP-approved, Energy Star, EPA Safer Choice, EPEAT®-registered, WaterSense, or DesignLights Consortium® (DLC) Premium Certification exist, and are applicable for this project, they must be used. Products, technologies, and processes that help to reduce greenhouse gas (GHG) emissions or improve grid resiliency should be utilized.
If lighting fixtures will be purchased, they should be approved by the DesignLights Consortium®
(DLC) with a DLC Premium Certification—as the first priority—and Energy Star certified if no DLC rating is available. Lighting-inclusive projects shall use efficient light-emitting diode (LED) fixtures and automatic lighting controls (i.e. either occupancy or vacancy sensors—the preference is for vacancy sensors) that are linked to the Building Automation System, if present. When retrofitting an existing lighting fixture with new LED bulbs or tubular LEDs, Section 6.3.2.2 of the P100 must be followed.
https://www.gsa.gov/directives/files?file=2023-06%2FFinal%20Directive_PBS%20Cost%20and%20Schedul%20Management.pdf https://www.gsa.gov/directives/files?file=2023-06%2FFinal%20Directive_PBS%20Cost%20and%20Schedul%20Management.pdf https://www.access-board.gov/aba/ https://www.gsa.gov/directives/files/?file=2023-08%2FPBS_34903_CHGE_1_Secur_for_Sen_Build_Inform_Related_to_Fed_Build%2C_Grounds%2C_or_Property_%28Final_Word_3-22-21%29_CC044070_RV_3-30-21.pdf https://www.gsa.gov/directives/files/?file=2023-08%2FPBS_34903_CHGE_1_Secur_for_Sen_Build_Inform_Related_to_Fed_Build%2C_Grounds%2C_or_Property_%28Final_Word_3-22-21%29_CC044070_RV_3-30-21.pdf https://www.gsa.gov/real-estate/design-construction/cad-standards https://www.gsa.gov/cdnstatic/BCG_3_30_Final_R2-x221_0Z5RDZ-i34K-pR.pdf https://www.energy.gov/sites/prod/files/2014/11/f19/metering_guidance.pdf https://www.achp.gov/sites/default/files/regulations/2017-02/regs-rev04.pdf https://www.achp.gov/sites/default/files/regulations/2017-02/regs-rev04.pdf https://www.nps.gov/tps/standards/four-treatments/36cfr68.pdf https://www.sustainability.gov/pdfs/guiding_principles_for_sustainable_federal_buildings.pdf https://www.gsa.gov/cdnstatic/Fine%20Arts%20Policies%20and%20Procedures%202017%20(1).pdf https://www.gsa.gov/about-us/gsa-regions/region-8-rocky-mountain/sustainability-in-action/storm-water-wetland-management https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title40/40cfr61_main_02.tpl https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title40/40cfr763_main_02.tpl https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title49/49cfr107_main_02.tpl https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title49/49cfr172_main_02.tpl https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title49/49cfr172_main_02.tpl https://www.epa.gov/sites/production/files/2014-08/documents/moldremediation.pdf https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title49/49cfr172_main_02.tpl
Back to Top
If any pumps or motors will be purchased, they shall be NEMA Premium Efficiency rated and controlled by a Variable Frequency Drive (VFD).
If insulation will be replaced or installed, it shall be the maximum feasible insulation on tanks, pipes, fittings, valves, and other associated equipment related to the domestic hot water system in the building.
New chiller equipment, refrigerators, air conditioners, and heat pumps may only use refrigerants listed as “Acceptable” by the U.S. Environmental Protection Agency (EPA)’s Significant New
Alternatives Policy (SNAP) Program, even if EPA's "Unacceptable as of" date is in the future.
6.2. BUY CLEAN PRODUCT STANDARDS
GSA must meet federal requirements to incorporate sustainable products. Interior finishes must meet, at a minimum, the baseline environmental requirements specified in the GSA P100 facilities standards, Chapter 3, Architecture and Interior Design or the standards listed in the Green
Procurement Compilation (https://sftool.gov/greenprocurement) for finishes and construction materials not listed in the P100. The Contractor shall specify the brand name and product that shall be used to meet each applicable standard and provide the required data submittals to the COR/PM prior to the start of construction. The COR/PM will verify that the products submitted are compliant with environmental performance standards.
In addition, and Environmental Product Declaration (EPD) must be submitted for the following interior finishes:
● Acoustical Ceiling Tiles
● Broadloom/Carpet Tiles
● Masonry Partitions
● Metal Stud Partitions
● Linoleum
● Luxury Vinyl Tile (LVT) and Luxury Vinyl Plank (LVP)
● Operable Walls
● Rubber Tile
● Sheet Vinyl
● Vinyl Composition Tile (VCT)
6.3. PROOF OF COMPLIANCE
The Contractor shall, maintain a record of sustainable products purchased using the “Green Product
Compilation Compliance Reporting” form attached to this SOW as a guide to demonstrate compliance with product requirements. The Contractor shall provide copies of such documentation to the COR as required, or upon request.
7. MATERIALS AND WORKMANSHIP
7.1. MATERIALS
The Contractor shall supply materials consistent with, or exceeding, the quality of existing building components, and the materials shall be of commercial or industrial grade. Refurbished equipment meeting these standards is specifically allowed if a comparable and complete equipment and installation warranty accompanies the materials. All materials shall be verified to be of appropriate quality and condition prior to installation.
https://www.epa.gov/snap/overview-snap https://www.epa.gov/snap/overview-snap https://sftool.gov/greenprocurement
Back to Top
7.2. PREMISE PROTECTION
Appropriate actions shall be taken to ensure adequate protection to existing equipment and finishes.
The Contractor shall protect adjacent areas at all times during the work. Any damage caused as a result of the Contractor’s activities shall be repaired at no additional cost to the Government and shall in no way adversely affect required schedules and guarantees.
7.3. WORKMANSHIP
Workmanship shall conform to the best practices of the trade and to be in accordance with all Federal, State and local codes.
8. SPECIAL AND SPECIFIC REQUIREMENTS
8.1. USE OF BUILDING FACILITIES
The Contractor may use utilities, services and toilet facilities of the buildings, subject to the approval of the Building Manager. The Contractor shall prohibit his employees from disturbing papers on desks, opening desk drawers or cabinets, or using telephone or office equipment provided for official
Government use. The Contractor shall require his employees to comply with the instructions pertaining to conduct and building regulations issued by duly appointed officials.
8.2. FIRE HAZARDS
The Contractor shall take every precaution to prevent fires during the performance of this contract.
The Contractor shall furnish a covered metal receptacle to be kept on the exterior of the building to place therein all combustible material such as oily rags, waste, etc, used in the performance of the work. Paint product containers are to be kept always sealed except when in use.
The Contractor must always provide and have available, portable fire extinguishers, suitable for potential hazard(s) involved. He must also obtain from the Building Manager, a separate daily permit for any welding or cutting on a day-to-day basis (GSA Form 1755).
8.3. CONTRACTOR EMPLOYEES
Each employee of the Contractor shall be a citizen of the United States of America, or an alien who has been lawfully admitted for permanent residence as evidenced by Alien Registration Receipt Card
Form or, who presents other evidence from the Immigration and Naturalization Service that employment will not affect his immigration status.
8.4. EXTRAS
Except as otherwise provided in the contract, no charge for extra work or materials will be allowed unless the same has been ordered in writing by the Contracting Officer and the price stated in such order and approved by the Contracting Officer.
8.5. INDEMNITY
The Contractor shall save and keep harmless and indemnify the Government against any and all liability claims, and costs of whatsoever kind and nature of injury to or death of any person or persons and for loss or damage to any property (Government or otherwise) occurring in connection with or in any way incident to, or arising out of the occupancy, use, service, operations, or performance of work in connection with this contract, resulting in whole, or in part from, the negligent acts or omissions of the Contractor.
Back to Top
8.6. SECURITY PROVISIONS
If the period of performance is longer than 90 days, contractor and subcontractor employees will be required to furnish information for security clearances and comply with security regulations as imposed by the occupying agencies. The contractor will make it a specific provision of his subcontracts that these regulations be accepted. Security provisions are required in accordance with the HSPD-12 program.
8.7. ACCESSIBILITY
Architectural Barriers Act Accessibility Standard (ABAAS) is mandatory for all GSA projects within
Federal Buildings. If local accessibility standards exist, the Contractor must follow the most stringent requirements between the local standards and ABAAS.
The building ABAAS accessibility shall be always maintained.
8.8. NATIONAL HISTORIC PRESERVATION ACT (NHPA)
This building is listed in the National Register of Historic Places. Any modification to historic elements during construction shall be reviewed by the GSA Regional Historic Preservation Office
(RHPO). The RHPO will provide guidance on preservation zones and appropriate treatments.
Modifications to historic elements during construction could result in a submission and Section 106 consultation with the DC State Historic Preservation Office (SHPO). Changes shall be minimized.
8.9. NATIONAL ENVIRONMENTAL POLICY ACT (NEPA)
Pursuant to paragraph 5.3 of the PBS NEPA Desk Guide (October 1999), this project is an automatic
CATEX and requires no checklist.
8.10. FIRE & LIFE SAFETY
GSA’s Fire Protection Engineers are the authority having jurisdiction (AHJ) for all GSA owned facilities.
The means of egress shall be always maintained. Egress issues shall meet NFPA 101 (Life Safety
Code).
9. PROJECT CLOSEOUT
9.1. PAYMENTS
The Contractor shall provide a signed invoice within 10 business days of completing work/inspection according to the specific requirements of the COR. Due to the minimal dollar value of the contract, partial payments shall not be allowed, with full payment to be made following satisfactory inspection and receipt of all deliverable items.
9.2. INSTRUCTION/TRAINING/MANUALS
Operation and Maintenance manuals are not required as part of this project.
9.3. AS-BUILT DRAWINGS
This project does not require As-Built Drawings.
Back to Top
9.4. WARRANTIES
The Contractor shall provide a full warranty on all labor and materials upon installation and carry through a period of one year. The Contractor shall provide to the COR a current and complete list of all warranted items and equipment responsibilities, specific warranties and guarantees, final certifications, and similar documents at the time of acceptance/completion.
10. EXHIBITS
● Exhibit 1: Photos of pond
● Instructions, Conditions, And Notices to Offerors
Exhibit One (1) - Photos
Pond
Inflow Pipe
Outflow
(End of Exhibit)
(End of Statement of Work)