STATEMENT OF WORK - OPTION A - REPAIR CHILLER.pdf

PDF 67 KB Posted

Attached to
FCI Aliceville Chiller Repair
Solicitation number
15B31825Q00000005-P00002
Issued by

View the file

Other files

File Type Posted
MOD 2 15B31825Q00000005 ALI Chiller Repair.pdf PDF
Photo 2.JPG JPG image
Chiller Cover Letter 03.13.25.pdf PDF
STATEMENT OF WORK-REPAIR CHILLER.pdf PDF
MOD 1 15B31825Q00000005 Chiller Repair.pdf PDF
Photo 1.jpg JPG image
Photo 3.JPG JPG image
15B31825Q00000005 Chiller Repair.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

B&F 24Z3A2R REPAIR CHILLER

OPTION A – CHILLER #2

FEDERAL CORRECTIONAL INSTITUION

ALICEVILLE, ALABAMA

OPTION A:

The Contractor shall provide all parts, materials and services to properly repair an oil leak that has been identified on a York 500-ton centrifugal chiller that was installed in 2011.

The chiller is identified as Chiller #2. The chiller is currently in service while monitoring the leak. The Contractor is solely responsible for providing any and all components for the repair associated with refrigerant that will be recovered and charged during the repair of the chiller. The Contractor will be required to perform a leak check and vacuum of the system to determine all leaks are identified and repaired. Any lubricant or filters may be changed during this leak repair associated with the repair location. The Contractor is required to perform a start up of the chiller, and verify all operating and safety controls are in working order once all repairs have been completed. Upon completion the chiller will be placed back into operational service.

All work provisions and conditions listed in the original SOW apply to this Option for

Chiller #2. The repair service shall be completed by qualified HVAC personnel using only genuine York factory parts. Seismic zone requirements, environmental compliance, life safety, NFPA, OSHA, federal, state, local codes and regulations will be considered during all phases of this project. All work shall be completed, equipment tested and adjusted per manufacturers recommendations and accepted by the Contracting Officer’s

Representative (COR) and Contracting Officer (CO).

A. SPECIFICATIONS

Manufacturer: York

Model: YKFQFQQ7-CRGS

Serial Number: SCWM518540

Refrigerant: R134A