About this file
This is a Statement of Work (SOW) for avionics modernization and navigation system upgrades to a Gulfstream (GV) Series aircraft, Serial Number 570, operated by NASA Armstrong Flight Research Center.
The contractor shall accomplish two integrated avionics upgrade packages during a single coordinated maintenance visit with an estimated downtime not exceeding 20 working days. The first package involves ASC183B DU885 PlaneDeck installation with Synthetic Vision (PDSV), which includes replacing six DU880 CRT displays with six DU885 LCD units, integrating PDSV software, installing new cursor control devices, upgrading the database loader from DL-900/950 to DL-1000, removing legacy cooling hardware, performing Symbol Generator software upgrades through Honeywell, and conducting comprehensive functionality verification. The installation must be performed at a Gulfstream authorized facility under applicable Supplemental Type Certificates (STCs). The second package involves replacing three existing Honeywell Laseref Inertial Reference Units (IRUs) with three new Laseref IV units, including alignment and leveling per STC requirements and any necessary Honeywell core/credit processing. Key contractual requirements include project management and weekly status reports, a project kickoff within one month of award, quality management system compliance with SAE AS9100 and FAA 14 CFR Part 145 standards, controlled-access facility provisions with perimeter fencing, NASA aircraft inspection and maintenance support, and comprehensive closeout documentation. Deliverables include a kickoff presentation, PlaneDeck installation completion package with as-installed configuration and test results, Laseref IV upgrade completion package with alignment records, and a final closeout report due in the contract's final month. Acceptance requires delivery of completion packages with STC compliance evidence, successful test procedures, customer inspection and aircraft acceptance, and verification that all NASDAT (NASA Airborne Science Data and Telemetry System) functions continue to operate properly following the upgrades.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 - Q-1.pdf | ||
| Sol. NASA GV Avionics & Display Upgrades.pdf | ||
| Attachment 3 - Q-3.pdf | ||
| SF 1449.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
Avionics Modernization and Navigation System Upgrades for Gulfstream (GV) Serial Number 570
1.0 Introduction/Background
NASA Armstrong Flight Research Center intends to modernize flight deck display systems and inertial navigation capability on Gulfstream (GV) Serial Number 570 to improve operational efficiency, reliability, and safety, and to provision the aircraft for future growth. The modernization includes installation of Honeywell PlaneDeck DU885 LCD primary flight displays with Synthetic Vision (PDSV) and replacement of the existing Honeywell Laseref Inertial Reference Units (IRUs) with Laseref IV units, certified under applicable Supplemental Type Certificates (STCs).
2.0 Scope of Work
The Contractor shall accomplish two integrated avionics upgrade packages during a single coordinated maintenance visit:
• ASC183B DU885 PlaneDeck Installation with Synthetic Vision (PDSV). Replace six DU880 CRTs with six DU885 LCDs; integrate PDSV; install related controls, database loader, and wiring modifications; remove legacy cooling hardware; and perform associated rack modifications. This modernization provides high resolution graphics, SVS terrain/obstacle/runway depiction, Jeppesen electronic charts/maps, moving maps, new cursor control devices (CCD), and DL1000 database loader capability. Effectivity: all Gulfstream V aircraft. PDSV Certification: Gulfstream STC.
• Triple Honeywell Laseref IV Upgrade. Remove existing Laseref IRUs and install three new Laseref IV IRUs in the avionics racks, certified using Gulfstream’s existing STC, including any Honeywell core/credit processing and alignment inspections.
The estimated downtime for the combined work scope should not exceed 20 working days, contingent on lead time prerequisites and final induction schedule at a mutually agreed authorized facility.
3.0 Description of Tasks / Technical Requirements
The following definitions differentiate between requirements and other statements contained in this statement of work:
Shall This is the only verb used for binding requirements.
Should/May These verbs are used for stating non-mandatory goals.
Will This verb is used for stating facts or declaration of purpose.
3.1 Project Management
The Contractor shall provide project management support for the work accomplished under this statement of work such as schedule, cost, and technical supervision.
3.2 Project Status Reports
The Contractor shall provide weekly status updates for the two designated avionics‑upgrade items.
These updates may be delivered via email or brief teleconference, as appropriate. Each weekly update shall include:
• A summary of progress made during the reporting week.
• Identification of any technical, schedule, or integration issues requiring Government awareness or action.
• A running list of action items and the current status of each (open, in progress, or closed).
• Updated percent-complete estimates for each of the two avionics‑upgrade items relative to planned milestones.
3.3 Kickoff & Planning
Contractor shall conduct a project kickoff within 1 month of award to confirm objectives, schedule, milestones, deliverables, and facility induction plan. Contractor shall deliver the Kickoff Presentation to the COR and copy the CO per delivery instructions.
3.4 Contract Surveillance
NASA reserves the right to conduct surveillance inspections at any location and at any time where work is being conducted during the contract period to ensure compliance with contract requirements. The Contractor shall support these surveillance activities as required.
4.0 Baseline Contract
4.1 ASC183B DU885 PlaneDeck Installation (PDSV)
4.1.1 Display System Replacement. Contractor shall remove six (6) DU-880 CRTs and install six (6) DU-885 LCD display units with PDSV software, including modifications to DU racks, mating plugs, connectors, and interface wiring.
4.1.2 Cooling Hardware Removal. Contractor shall permanently remove existing DU cooling fans, filters, ducting, and associated wiring.
4.1.3 CCDs & Controls. Contractor shall install pilot and co-pilot Cursor Control Devices (CCDs) in cockpit side consoles with associated wiring and two annunciator/switches above the Display Controllers to activate/deactivate PDSV (pilot and co-pilot).
4.1.4 Database Loader Upgrade. Contractor shall replace existing DL-900/950 loader with DL-1000 for improved field loading of software/databases (FMS/Charts/Maps), leveraging USB/SanDisk media for database updates across all displays.
4.1.5 Symbol Generator (SG) Software Upgrade. Contractor shall remove SGs and coordinate shipment to Honeywell for PDSV software load; upon completion, SGs shall be reinstalled.
4.1.6 Interior Access. Contractor shall perform interior removal/reinstallation (e.g., headliners, sidewalls).
4.1.7 Functionality & Features Verification. Contractor shall verify PlaneDeck capabilities including Class 3 Jeppesen charts, moving map navigation aids, SVS PFD terrain/obstacle/runway depictions, pilots electable video inputs, maintenance pages, new CCDs, DL1000 loader operation, and reliability improvements.
4.1.8 Certification Basis & Authorized Facilities. Contractor shall accomplish installation under the applicable Gulfstream STC and at a Gulfstream authorized facility.
4.2 Triple Honeywell Laseref IV Upgrade
4.2.1 Removal/Installation. Contractor shall remove existing Laseref IRUs and install three
(3) Honeywell Laseref IV IRUs in avionics racks, aligned and leveled per STC requirements.
6.2 Acceptance Criteria
• Delivery of completion packages (Section 4.1/4.2) with evidence of STC compliance, as installed configuration records, successful test procedures, and discrepancy resolution/approved deferrals.
• Customer inspection and aircraft acceptance per Work Authorization terms at the performing facility.
• The NASA Airborne Science Data and Telemetry System (NASDAT) serves as the airborne platform for the Airborne Science Program (ASP) Sensor Network system, providing experimenters and their instruments with direct Ethernet access and satellite communications. The Contractor shall coordinate with Government engineers and technicians to evaluate any NASDAT related wiring impacts resulting from the upgrades.
This coordination shall include a review of all wiring changes to ensure continued compatibility with existing NASDAT internal modifications, including its use of IRU data.
Acceptance requires successful completion of this review and Government confirmation that all NASDAT functions operate properly following the upgrades.
6.3 Warranties
• The Contractor shall submit, and recover whenever possible, warranty claims for the Government for parts and labor. The Contractor shall maintain internal records of the warranty program, which shall be available for review of Government personnel. The Contractor shall pass through to the Government any supplier warranties acquired by the Contractor as a result of the work performed under this contract.
7.0 Security / Controlled-Access Facilities
Due to the sensitivity of the aircraft, the Contractor shall provide controlled-access facilities for NASA aircraft that, at a minimum, the facility shall be protected by perimeter fencing that encloses either the immediate aircraft area or the entire contractor complex.
8.0 Government Furnished Items / Equipment (GFI/GFE)
The Government will, as applicable, provide: aircraft access, existing aircraft records/data, and any Government provided services explicitly identified. The Government will not proceed with installation approvals until the NASA CO/COR authorization is provided where required.