Statement_of_Work.pdf
PDF 152 KB Posted
- Attached to
- COLLECTION CONDITION SURVEY FOR MOCR Federal contract opportunity
- Solicitation number
- 140P5324Q0044
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity issued by the National Park Service (NPS) to conduct a Collection Condition Survey and stabilizing treatment for museum collections at Moores Creek National Battlefield (MOCR) in North Carolina.
The key requirements of the SOW include: 1) Conducting an on-site Collection Condition Survey of all objects on exhibit, 2) Performing basic cleaning or stabilizing treatments as necessary, and 3) Producing a report that identifies the conservation and preservation needs of the individual objects and which exhibited items are too fragile to remain on exhibit. The contract is a firm fixed price procurement with an approximate period of performance from August 2024 to August 2025. The procurement is a 100% small business set-aside under NAICS code 541990 with an estimated value under $19.5M. Interested offerors must be registered in the System for Award Management (SAM) prior to award. The solicitation closes on August 9, 2024 at 1:00PM EST.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P5324Q0044_Amd_0003.pdf | ||
| Questions_and_Answers_-_Amendment_3_0003.pdf | ||
| Sol_140P5324Q0044_Amd_0002.pdf | ||
| Amendment_2_Additional_Questions_0002.pdf | ||
| 140P5324Q0044_Questions_and_Answers_0001.pdf | ||
| Sol_140P5324Q0044_Amd_0001.pdf | ||
| Statement_of_Work_Rev_7-19-2024_0001.pdf | ||
| DOL_Wage_Determination.pdf | ||
| Sol_140P5324Q0044.pdf | ||
| MOCR_Exhbit_Catalog_Records.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work
For
Collection Condition Survey and Stabilizing Treatment for Collections at
Moores Creek National Battlefield
National Park Service
Confidentiality
The information developed under this Contract is the property of the U. S. Government and shall be kept in strict confidence.
Introduction
This project consists of an on-site visit by a professional conservator or conservators to complete a
Collection Condition Survey for museum collections associated with Moores Creek National Battlefield
(MOCR). The project includes survey of objects in storage and on exhibit at the park in Currie, North
Carolina, and cleaning and stabilizing of objects currently on exhibit. Objects to be surveyed and cleaned/treated include 18th century weapons and associated accoutrements, coins, commemorative items
(see list in Attachment A).
Information about National Park Service Collection Condition Surveys can be found in the NPS Museum
Handbook, Volume I, Chapter 3: Preservation (https://www.nps.gov/museum/publications/MHI/MHI.pdf)
The address for park headquarters is:
40 Patriots Hall Dr.
Currie, NC 28435
I. Background
Moores Creek National Battlefield has been impacted by several natural disasters (particularly hurricanes) in the last several years. Increased humidity from flooding events and the necessity to handle objects while transporting them to safety has impacted their condition.
II. Purpose and NPS Responsibilities
A. The purpose of the work is to
1) Conduct an on-site Collection Condition Survey (CCS) for all objects on exhibit.
2) Perform basic cleaning or stabilizing treatments as necessary.
3) Produce a report that: identifies the conservation and preservation needs of individual objects exhibited at MOCR and identify which exhibited items are too fragile to remain on exhibit.
The survey shall focus on material stability to determine object conservation treatment needs including determining and recording the condition of individual objects or groups of objects in the collection in need of professional conservation treatment. The survey report shall also include recommendations for preventive care, routine cleaning/upkeep and improvements to exhibit conditions.
The results of the survey will provide guidance to park and regional curatorial staff in setting priorities for object stabilization and/or treatment, and preservation management of the park collections. The survey will also facilitate budgeting, scheduling, and subsequent https://www.nps.gov/museum/publications/MHI/MHI.pdf communications with conservators regarding treatment. Object-specific data, using a compatible documentation or software format that identifies equivalent ICMS data fields from the survey will be entered into ICMS (or its successor), the park's automated collections management system.
B. Post-award, the park will provide all requested documents to provide specific context and information about the history of park collections.
C. Approved in advance by the superintendent, the COR or park designee will provide on-site:
• supervised access to museum exhibit space
• opening and closing of exhibit cabinets and other containers that may be locked
• assistance with moving heavy or unwieldy objects
• access to museum property accountability (catalog and accession) and conservation
(treatment and survey) records when required
• answers to questions about existing environmental monitoring and control, preventive care of objects, uses of objects, plans for future acquisition and disposition of objects, plans for future exhibition of objects, and the park's pest management program
• other information as needed
III. Conservator Tasks
The conservator will
A. The contractor is responsible for travel to the park site, professional, editorial, and duplication services required to produce a Collection Condition Survey report. This document shall include the following sections:
• Executive Summary
• Project Background
• An assessment of the exhibit space which features the following topics
i. Facility and Storage Furniture
ii. Housekeeping
iii. IPM
iv. Environmental Conditions
v. Fire/Security
• Observations/Recommendations for upkeep, preventative maintenance, and/or professional conservation including completion times and treatment priorities for exhibited objects
• Spreadsheet of item level survey results
B. Conduct an entrance interview with the NPS upon arrival at the park. The purpose of the interview is to explain to the staff the conservator's methodology and anticipated survey schedule and to detail any local support that may be needed.
C. Conduct a hands-on survey of collections on exhibit by examining each object individually.
Catalog information for the exhibited objects is provided in Appendix A. The following factors shall be considered in determining the object condition and conservation treatment needs of objects on exhibit.
• The nature of the environment in which collections are stored or exhibited including building structure, temperature, relative humidity, dust, natural and artificial light sources, pests, air pollution, and other agents of deterioration, as well as the local climate conditions.
• Storage methods, mounts, and techniques including appropriateness, quality, and efficiency of use.
• Evidence of recent damage or deterioration, including failure of preservation treatments, damage to objects during their use for interpretation and study, effects of visitor handling or vandalism, and deterioration due to adverse environmental factors.
• When preventive maintenance treatment or simple treatments can be done by the park, park staff will be identified, the treatment will be briefly described, and materials will be recommended. All recommended materials shall be commonly used by conservators and selected for reversibility, stability, and ease of use. Materials shall be described generically, though brand names also may be given for reference purposes. Provide instructions for park staff to follow when carrying out work that the conservator recommends, they perform. In most instances, instructions will be common practices.
• Any other general or specific issues concerning the collection's preservation, conservation, and/or treatment needs.
D. Upon completion of the survey, the conservator will meet with the NPS to review the survey results. The close-out meeting can be conducted virtually or in person and should cover the findings and recommendations the conservator anticipates including in their report. At this time, the conservator will gather any data or information not already obtained that will be required for production of the survey report.
E. Provide a time estimate required for a professional conservator to carry out each recommended treatment. If possible, provide a cost estimate for the treatment if done by a conservator specializing in that discipline. The park can use this information to program funds to accomplish the work. When appropriate, note economies of cost or other benefits that might be realized by simultaneously treating similar objects, or objects with similar treatment needs.
IV. Contractor Qualifications
A conservator performing or supervising the conservation of works of art, objects, or architectural features should have as a minimum the qualifications as defined in the American Institute for
Conservation’s (AIC) definition of Professional Associate and have achieved Professional Associate status with AIC or compatible status in a similar conservation organization:
• EDUCATION: an undergraduate university degree in conservation or historic preservation with an emphasis on conservation, or the international equivalent [or the equivalent in work experience under a qualified conservator, in addition to the training and experience noted below]:
• TRAINING: The applicant is required to have:
o two years of full-time formal education or related supervised training in conservation method and theory OR o two years of full-time formal education or related supervised training in a field appropriate to other professional involvement in conservation (e.g., chemistry for conservation scientists, library science for library preservation administrators, art history for museum conservation administrators, business management for administrators).
• EXPERIENCE: The applicant is required to have three years of full-time work or its part-time equivalent in conservation or in a conservation related profession after training. Program training internships may not be counted toward this requirement.
• PROFFESSIONAL ETHICS: Applicants must demonstrate ability to adhere to the AIC Code of Ethics and Guidelines for Practice. [See Appendix Two] Evidence may include: recent examination forms; proposed and completed treatment forms; reports of scientific investigations; lecture materials; planning documents; survey reports, etc. The conservator must comply with the Code of Ethics and Guidelines for Practice of the American Institute for Conservation (AIC) in all work performed.
V. Deliverables and Payment Schedule
A. Provide an electronic file of the draft report via secure file sharing site (Microsoft Teams). Each line must be numbered on the left side of the page. The following must be included; a title page listing the park name, the conservator's name, project completion date and numbered table of contents.
B. The final CCS report must be on 8 1/2" x 11" neutral pH, high alpha cellulose, white paper such as Permalife Bond Paper or equivalent, single-sided and paginated, and printed using carbon-based, black laser printer ink. The following must be included; a title page listing the park name, the conservator's name, project completion date, and paginated table of contents. An electronic copy and two hard copies must be provided to the park. The electronic file (submitted through secure file sharing site) must be labeled with the same title as the report as the file name.
C. Photographic documentation:
The conservator must provide the following:
• Digital files with full color images of each object in an uncompressed TIFF format and
JPEGS with Dublin Core metadata provided for each image and transmitted via USB thumb drives and/or external hard drives. Contractor is responsible for acquiring appropriate thumb drives and/or external hard drives for transmission.
• The filename for the images will include the catalog number associated with the object. If there is more than one object per original number they will be labeled as “a, b, c” accordingly. This number will also appear in the image. This can either be on a card during image capture or added as a layer in Adobe Photoshop after the images are taken.
• A signed release form granting copyrights of all photographs to the park. (See NPS Museum
Handbook, Part III, Figure 3.4, Assignment of Copyright by Contractor.
https://www.nps.gov/museum/publications/MHIII/mh3ch3.pdf). The Conservator may keep a copy of each image for private or educational use. Images kept by the Conservator may not be used in for-profit publications, for commercial distribution, or for exhibitions by the surveyor or any other individual or institution without written permission from the
Superintendent or Museum Curator. The credit line shall include the following information:
"Courtesy of the National Park Service," Park Name, Object Name, Object Date, Catalog
Number.
A separate file with a list of photographic captions will be prepared, and uploaded to the same file sharing site with the report. When applicable, the captions will link directly to an object's accession or catalog number.
PROJECT SCHEDULE
Task Date
Award Contract TBD
Kick-off Conference Call Within 30 calendar days of contract award
Site Visit/On-site work Within 60 calendar days of kick-off call
Complete Report Draft due Within 45 calendar days of site visit
NPS Review of Complete Report Draft Within 30 calendar days of receipt of the draft
Consultant Responses Within 14 calendar days of completion
NPS Review of Consultant Responses Within 14 calendar days of completion
Final review and close-out meeting Within 30 calendar days of receipt
Final Acceptance Upon acceptance of project completion
POINTS OF CONTACT:
Contracting Officer
TBD
Contracting Officer’s Representative
Dr. Elanor Sonderman
Staff Curator, Museum and Archival Services Branch
Southeast Regional Office
470-990-0055
Elanor_sonderman@nps.gov
VI. Protection of Information
All information and documentation gathered or produced by the Contractor during the course of this work shall be held in strictest confidence and shall be fully protected from access by unauthorized persons.
Any documentation furnished by the site and retained by the Contractor during the course of the work or thereafter shall be secured in a locked filing cabinet or safe at a minimum. During the initial visit to the site, the Contractor shall indicate to the park curatorial staff the manner in which he/she intends to secure any documentation the site may furnish; the park curatorial staff will have the prerogative to specify when more stringent security must be provided for any particular documentation furnished to the Contractor.
Documentation that cannot be secured to the park curatorial staff’s satisfaction still will be furnished to the Contractor, but only for on-site use.
Notes and other information produced by the Contractor, including all versions and copies of his/her report and any drawings that may be produced, shall be secured in a locked filing cabinet or safe, at a minimum. Word processor and other computer files shall be secured in an equivalent manner, such as by retaining files only on CDs or flash drives kept in a safe, rather than on a hard drive, and by the use of passwords or encryption. During the initial visit to the site, the Contractor shall indicate to the park curatorial staff the manner in which he/she intends to secure computer data generated during the course of the work; the park curatorial staff will have the prerogative of specifying that additional security measures be taken whenever circumstances so dictate.
All documents and other work developed in the performance of this contract, shall be and remain the sole property of the Government and may be used on any other work without additional compensation to the
Contractor, with respect, thereto, the Contractor agrees not to assert any rights and not to establish any claim under the patent or copyright laws. The Contractor, for a period of 3 years after final payment under this contract, agrees to furnish and provide access to all retained materials on the request of the
Contracting Officer. Unless otherwise provided in this contract, the Contractor shall have the right to retain copies of all such materials beyond such period.
RIGHTS IN DATA - SPECIAL WORKS
(FAR 52.227-17) (DEC 2007)
A. Definitions. As used in this clause—
“Data” means recorded information, regardless of form or the media on which it may be recorded. The term includes technical data and computer software. The term does not include information incidental to contract administration, such as financial, administrative, cost or pricing, or management information.
“Unlimited rights” means the rights of the Government to use, disclose, reproduce, prepare derivative works, distribute copies to the public, and perform publicly and display publicly, in any manner and for any purpose, and to have or permit others to do so.
B. Allocation of Rights.
(1) The Government shall have—
(i) Unlimited rights in all data delivered under this contract, and in all data first produced in the performance of this contract, except as provided in paragraph (c) of this clause.
(ii) The right to limit assertion of copyright in data first produced in the performance of this contract, and to obtain assignment of copyright in that data, in accordance with paragraph (c)(1) of this clause.
(iii) The right to limit the release and use of certain data in accordance with paragraph
(d) of this clause.
(2) The Contractor shall have, to the extent permission is granted in accordance with paragraph
(c)(1) of this clause, the right to assert claim to copyright subsisting in data first produced in the performance of this contract.
C. Copyright.
(1) Data first produced in the performance of this contract.
(i) The Contractor shall not assert or authorize others to assert any claim to copyright subsisting in any data first produced in the performance of this contract without prior written permission of the Contracting Officer. When copyright is asserted, the Contractor shall affix the appropriate copyright notice of 17 U.S.C. 401 or 402 and acknowledgment of Government sponsorship (including contract number) to the data when delivered to the Government, as well as when the data are published or deposited for registration as a published work in the U.S.
Copyright Office. The Contractor grants to the Government, and others acting on its behalf, a paid-up, nonexclusive, irrevocable, worldwide license for all delivered data to reproduce, prepare derivative works, distribute copies to the public, and perform publicly and display publicly, by or on behalf of the Government.
(ii) If the Government desires to obtain copyright in data first produced in the performance of this contract and permission has not been granted as set forth in paragraph
(c)(1)(i) of this clause, the Contracting Officer shall direct the Contractor to assign (with or without registration), or obtain the assignment of, the copyright to the Government or its designated assignee.
(2) Data not first produced in the performance of this contract. The Contractor shall not, without prior written permission of the Contracting Officer, incorporate in data delivered under this contract any data not first produced in the performance of this contract and that contain the copyright notice of 17 U.S.C. 401 or 402, unless the Contractor identifies such data and grants to the Government, or acquires on its behalf, a license of the same scope as set forth in paragraph
(c)(1) of this clause.
D. Release and use restrictions.
Except as otherwise specifically provided for in this contract, the Contractor shall not use, release, reproduce, distribute, or publish any data first produced in the performance of this contract, nor authorize others to do so, without written permission of the Contracting Officer.
E. Indemnity.
The Contractor shall indemnify the Government and its officers, agents, and employees acting for the Government against any liability, including costs and expenses, incurred as the result of the violation of trade secrets, copyrights, or right of privacy or publicity, arising out of the creation, delivery, publication, or use of any data furnished under this contract; or any libelous or other unlawful matter contained in such data.
The provisions of this paragraph do not apply unless the Government provides notice to the
Contractor as soon as practicable of any claim or suit, affords the Contractor an opportunity under applicable laws, rules, or regulations to participate in the defense of the claim or suit, and obtains the Contractor’s consent to the settlement of any claim or suit other than as required by final decree of a court of competent jurisdiction; and these provisions do not apply to material furnished to the Contractor by the Government and incorporated in data to which this clause applies.
In the event that the Government uses any of the above-mentioned materials for purposes other than those covered under this contract or other than for which it was provided, the Contractor shall not be held liable for any personal or property damage arising from such use.