Statement of Work_1240LU26Q0129.pdf

PDF 471 KB Posted

Attached to
ARS Concrete Slab and Carport Assembly
Solicitation number
1240LU26Q0129
Issued by

About this file

This is a Statement of Work (SOW) for construction services at the USDA-Agricultural Research Service facility in Hilo, Hawaii.

The project requires the contractor to construct a reinforced concrete foundation for a 40-foot by 8-foot containerized laboratory and install an 18-foot by 60-foot prefabricated metal carport connected to an existing carport to create a continuous 120-foot by 18-foot roof system. The concrete slab shall be minimum 6 inches thick with 2,500 PSI strength, featuring a raised 2-inch container pad and a continuous 6-inch deep by 6-inch wide water moat retaining at least 4 inches of water around the perimeter. The work includes a 3-foot perimeter sidewalk, compacted base course, waterproofing, and a 1-inch Schedule 40 PVC water supply line with accessible riser. The carport installation requires a 12-inch by 12-inch by 60-foot footing with reinforcing steel and proper anchorage. Additional scope includes 6-inch continuous corrosion-resistant metal rain gutters, six 4-inch PVC downspouts, 2-inch by 6-inch preservative-treated wood fascia, grounding and bonding by a qualified electrician, and all necessary submittals including site layouts, concrete mix designs, installation documents, and safety plans. The work must comply with federal, state, and local codes, UFGS standards, ARS 242.1M requirements, DAVIS BACON wage requirements, and current industry standards suitable for Hawaii's high-rainfall, corrosive environment. The contractor must obtain all required permits, handle site utilities coordination, provide a minimum 30-day warranty, and furnish operation and maintenance data prior to final payment.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

Concrete Foundation and Pre-Fab Steel Carport for Containerized Laboratory

USDA-ARS

DKI US PBARC

64 Nowelo St, Hilo Hawaii 96720

STATEMENT OF WORK

1.0 CONTRACT PROJECT:

a. Project Title:

Concrete foundation and pre-fab steel carport for containerized laboratory.

b. Service Location:

USDA-ARS

DKI US Pacific Basin Agricultural Research Center 64 Nowelo St. Hilo HI 96720

2.0 PROJECT CONTACT PERSONS:

a. CONTRACTING OFFICER (CO):

Paul Larsen USDA-Forest Service Phone: 406-223-4463 Email: paul.larsen@usda.gov

b. RESEARCH LEADER (RL):

Melissa Johnson Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center USDA-Agricultural Research Service 64 Nowelo Street, Hilo Hi 96720 Phone: (808) 285-7353 E-mail: melissa.johnson@usda.gov

c. ADMINISTRATIVE OFFICER (AO):

Carlee Wehrsig Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center USDA-Agricultural Research Service 64 Nowelo Street, Hilo, HI 96720 Phone: (808) 959-4312 E-mail: carlee.wehrsig@usda.gov

d. CONTRACTING OFFICER REPRESENTATIVE (COR):

Dustin Galapir Facility Operations Specialist

USDA-ARS DKI US PBARC

Phone: 808-980-2313 E-mail: dustin.galapir@usda.gov mailto:dustin.galapir@usda.gov

e. SAFETY OFFICER (CDSO) Scott Geib

Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center USDA-Agricultural Research Service 64 Nowelo Street, Hilo, Hawaii 96720 Phone: (808) 959-4335 E-mail: scott.geib@usda.gov

3.0 Purpose

The contractor shall provide all labor, supervision, professional services, equipment, tools, transportation, testing, and materials necessary to construct a reinforced concrete foundation for a government-furnished 40-foot-long by 8-foot-wide containerized laboratory and to install one government-furnished 18-foot-wide by 60-foot-long pre-fabricated metal carport to the existing carport to create a continuous roof system approximately 18 feet wide by 120 feet long. The completed work shall be weather-tight, structurally sound, code-compliant, and ready for government use.

3.1 Background and site: The work will be performed at the Daniel K. Inouye US

Pacific Basin Agricultural Research Center located at 64 Nowelo St in Hilo Hawaii.

The containerized laboratory will support the rearing of insects imported under an APHIS Controlled Import Permit. The foundation therefore includes a continuous water moat surrounding the container footprint. Hilo’s high rainfall, wind exposure, humidity, and corrosive environment shall be considered in material selection, drainage, fastening, and installation. Figure 1 shows the proposed site location.

mailto:scott.geib@usda.gov

Figure 1. Site location of proposed concrete slab and metal carport.

3.2 Design verification and submittals: Before construction the Contractor shall verify that the proposed foundation, footing, reinforcement, anchorage, structural connections, and roof continuity are compatible with the government furnished carport manufacturer’s requirements and applicable site-specific conditions.

• Site layout showing the slab, moat, sidewalks, carport, footing, downspout discharge locations, and relationship to existing improvement.

• Concrete mix design; base-course material and compaction requirements;

reinforcement plan; jointing and curing plan; proposed moat waterproofing system.

• Carport manufacturer’s installation documents; engineered anchorage details, connection details for joining the new and existing carports, and corrosion-resistant fastener specifications.

• Product data and color selection for fascia, gutters, downspouts, sealants, coatings, and other exposed materials.

• Grounding and bonding plan identifying proposed improvements and test methods.

• Work schedule, site-specific safety plan, and required permits/approvals.

3.3 Subgrade, base course, and earthwork:

• Strip unsuitable or organic material and grade the work area to the required lines and elevations.

• Provide excavation, structural fill, and compaction necessary to support the slab, footing, and sidewalks without settlement.

• Install a compacted ¾-inch aggregate base coarse beneath the concrete.

Thickness and compaction shall comply with the approved design, geotechnical or code requirements, and concrete industry standards.

• Set the finished elevation high enough to prevent water runoff from entering the containerized laboratory. Grade adjacent surfaces to drain away from the slab and building while maintaining required accessibility and safe transitions.

• Locate existing underground utilities before excavation and coordinate conflicts with the site POC before proceeding.

3.4 Concrete slab, raised container pad, and water moat: Construct a reinforced concrete assembly with the following dimensions. The contractor shall verify the resulting overall footprint and reconcile any conflict with site conditions before placement. The nominal outside footprint is approximately 47 feet by 15 feet: a 40-foot by 8-foot container pad, a 6-inch-wide moat on all sides, and a 3-foot-wide perimeter sidewalk outside the moat.

• Slab and sidewalk thickness: minimum 6 inches.

• Concrete strength: minimum 2500 PSI.

• Reinforcement: welded wire reinforcement.

• Finish: level where required for container; uniformly brush-finished to prevent slipping. Edges shall be tooled and exposed corners finished.

• Raised pad: inner area of 40 ft x 8 ft elevated by 2 inches above the adjacent perimeter walking surface.

• Water moat: Continuous moat around all four sides of the raised pad. The moat shall be 6 inches deep x 6 inches wide and shall retain at least 4 inches of water without leakage (see Figure 2).

• Waterproofing: Form or coat the moat with solid, continuous, impervious, waterproof material suitable for permanent exterior immersion, UV exposure, and anticipated cleaning. Seal joints and penetrations with compatible material.

• Perimeter sidewalk: Provide a 3-foot-wide concrete sidewalk outside the moat around the full perimeter. Maintain positive drainage away from the laboratory.

• Joints and curing: provide construction, control, and isolation joints and cure concrete in accordance with the approved placement plan and applicable industry standards.

Drawing not to scale

Figure 2. Drawing of proposed concrete slab with water moat.

3.5 Moat water supply rough-in:

• Install a 1-inch Schedule 40 PVC water-supply pipe beneath the concrete slab. Protect the pipe with a sand base layer during concrete placement.

• Terminate the interior end within the moat area with an accessible riser and hose bib or spigot. The riser shall extend at least 12 inches above the finished concrete surface and shall be securely supported.

• Extend the supply end at least 6 inches beyond the outside edge of the concrete and install a watertight temporary cap until a water source is provided.

• Pressure-test the piping before concealment and provide the test result to the government. Photograph the installed route before concrete placement.

3.6 Carport footing and anchorage: The government furnished metal carport requires continuous footing along the side not supported by existing concrete (see Figure 3).

The nominal footing dimensions are 12-inch-wide x 12-inch-high x 60-feet-long.

• Provide a properly prepared and compacted aggregate base beneath the footing.

• Provide reinforcing steel, including No. 3 and No. 4 bars where appropriate.

• Provide concrete with a minimum 28-day compressive strength of 2,500 psi, or greater where required.

• Provide embedded anchors, base plates, isolation materials, and corrosion protection compatible with manufacturer’s requirements.

40 feet

6” wide by 6” deep water moat

8 ft 1” plumbing pipe with water fixture

3 ft

Figure 3. Existing carport of the same style/size that will need to be connected to the new carport and will require installation of gutters and downspouts to prevent rain runoff onto existing sidewalk.

3.7 Carport assembly and roof connection:

• Inventory government-furnished metal carport and roof components before installation. Promptly report any missing, damaged, incompatible, or insufficient components.

• Install the 18-foot by 60-foot pre-fabricated metal carport in accordance with the manufacturer’s instructions.

• Connect the new carport to the existing carport of the same nominal style and size to create a continuous roof surface approximately 120-feet-long by 18-feet-wide (see Figure 3).

• Flash, seal, overlap, and fasten the connection so that it is structurally secure and weather-tight. Use fasteners, closures, sealants, and dissimilar-metal isolation materials suitable for Hilo’s wet, corrosive environment.

• Provide all miscellaneous clips, closures, trim, flashing, sealants, fasteners, and accessories required for a complete installation whether or not individually listed.

3.8 Fascia, gutters, and downspouts:

• Provide nominal 2-inch by 6-inch exterior-rated, preservative-treated wood fascia boards suitable for Hawaii’s wet and termite-prone environment. Treat field cuts and penetrations and coat exposed wood with an exterior protective finish.

• Provide continuous 6-inch-wide corrosion-resistant metal rain gutters along the designated roof edges. Select gutter profile, metal, gauge, brackets, and spacing to accommodate the contributing roof area and local rainfall without overflow under normal design conditions.

• Provide six 4-inch nominal-diameter ultraviolet resistant PVC downspouts, including fittings, straps, outlets, and transitions. Securely support all downspouts.

• Locate and discharge downspouts so runoff does not flow onto existing sidewalk, concrete foundation, moat, building, equipment, or areas subject to erosion. Provide splash blocks, extensions, or connections to an approved drainage point as required by layout.

• Slope gutters to drain; seal joints and end caps; and water-test the completed gutter system.

3.9 Grounding and bonding: A qualified electrician shall inspect the existing conditions and provide the grounding and bonding improvements necessary for safe, code-compliant operation of the metal carport and associated electrical system. Bond metal components as required, protect connections from corrosion, and test the completed grounding system.

4.0 PROJECT REQUIREMENTS:

a. A site visit is highly recommended to verify equipment, design, project location, equipment requirements and specifications.

b. The Contractor will work with site personnel to ensure project is accomplished in a timely manner.

c. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction and services shall comply with applicable federal, state, and local code requirements as well as current industry standards, (ie: EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.

d. All work to meet all pertinent Unified Facilities Guide Specifications (UFGS) and ARS 242.1M standards. UFGS available at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs.

ARS 242.1M available at https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/.

e. This project falls under the DAVIS BACON Wage Act.

4.1 Description of Work:

• The Contractor will provide a turn-key project satisfying all Local, State, and

Federal requirements.

• The Contractor will provide all the necessary materials and labor per Section

3.0 and properly dispose of all material being replaced.

http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/ https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/

• Contractor is responsible for any damage to adjacent equipment and miscellaneous objects that may become damaged during construction. The Contractor is responsible for making repairs to meet or exceed conditions prior to damage.

• The Contractor is responsible for visiting the site prior to submitting a bid to observe existing conditions. No compensation will be provided for conditions that would be visible during an on-site visit for persons experienced performing this type of work.

4.2 Government Furnished Equipment and Services:

• The Government does not anticipate the need in this project, but the Government will be available to assist with the identification/location of utilities as necessary.

• The Government will furnish a reasonable amount of electricity and water.

5.0 GENERAL REQUIREMENTS:

5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.

5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Owner. All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disturbances that might jeopardize on-going operations and research. Owner reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Owner prior to starting demolition operations. Contractor shall legally dispose all any materials removed that will not be retained.

5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.

5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the COR for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. Contractor is responsible for any costs incurred for equipment ordered without prior approval.

5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the COR. Quality control is the exclusive responsibility of the Contractor.

5.6 Protection of Work and Property/Safety Requirements:

a. Contractor shall furnish a Site-Specific Safety Plan (SSSP) or Accident Prevention Plan (APP) 10 days after contract award upon request. SSSP / APP shall be reviewed by the Government before construction work commences. In addition to the usual components of a safety plan, the plan shall include specific procedures to address mold encountered during the project.

b. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the COR.

c. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.

d. Contractor is responsible for verifying location of any underground utility and is responsible for any damaged caused to such utilities.

5.7 Temporary Facilities:

a. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during construction and shall repair or replace any items damaged through its own negligence.

b. Should the Contractor require any power or utility shutdowns during construction, the Contractor shall obtain approval for such shutdown from location staff or maintenance personnel as possible as possible.

5.8 Materials and Equipment:

a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.

b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/COR.

c. Government will not furnish any labor or equipment to unload or move materials or supplies.

5.9 Cleanup: The work site shall always be kept clean and free of debris. Disposal of the old equipment is required. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.

5.10 Final Payment/Contract Closeout: The following documents are REQUIRED

PRIOR TO FINAL PAYMENT (other documents may also be required):

a. General contractor’s minimum 30 days warranty on all work.

b. Operation and Maintenance Data

c. Release of liens.

d. Final Invoice

United States Department of Agriculture
Agricultural Research Service
Concrete Foundation and Pre-Fab Steel Carport for Containerized Laboratory
USDA-ARS
DKI US PBARC
64 Nowelo St, Hilo Hawaii 96720

File details come from the government source that posted it. Updated .