Standardized Proposal Breakdown.xls

XLS spreadsheet 47 KB Posted

Attached to
Modernize Elevator System at ROC ATCT in Rochester, NY Federal contract opportunity
Solicitation number
697DCK-24-R-00146
Issued by
Department of Transportation Federal Aviation Administration Southwestern Region

About this file

This document is a Standardized Proposal Breakdown template for a federal contract opportunity to modernize the elevator system at the Frederick Douglass Greater Rochester Air Traffic Control Tower in Rochester, NY. The solicitation number is 697DCK-24-R-00146, and the total estimated cost range for the requirement is $400,000 to $600,000. The NAICS code is 238290 with a $22.0 million size standard, and the effort is set aside for small businesses. Key details include: the required components for the modernization effort (electronics/controls/software, electrical, mechanical, safety equipment, cab interior), construction/installation tasks (mobilization, demolition, installation, permits), and performance maintenance requirements (monthly fee, monitoring). The proposal breakdown template provides a format for vendors to input their associated equipment, labor, and other costs. A site visit is scheduled for April 17, 2024, and all RFIs must be submitted by April 19, 2024. Proposals are due by 5:00 pm on May 3, 2024 via email to the Contracting Officer.

View the file

Other files for this federal contract opportunity

Other files attached to Modernize Elevator System at ROC ATCT in Rochester, NY, newest first.
File Type Posted
21 SIR Amendment 1.pdf PDF
RFI Responses.pdf PDF
3f Performance Work Statement.pdf PDF
3f Elevator Information Sheet.pdf PDF
Past Performance Questionnaire.pdf PDF
16 Screening Information Request.pdf PDF
9 Wage Determination.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Modernization

Standardized Proposal BreakdownDATE PREPARED: MMM DD - YYYY
PROJECT:
VENDOR:
PREPARER:PREPARER'S CONTACT INFORMATION:
ITEMEQUIPMENT COSTS - $LABOR COSTS - $OTHER COSTS - $TOTAL ITEM COST - $
TOTALTOTALTOTAL
Modernization Requirements:
Electronics/Controls/Softwarethiat$ - 0$ - 0
Electrical$ - 0$ - 0$ - 0
Mechanical/Drives/Sheaves/Traveling Cable$ - 0$ - 0$ - 0
Safety Equipment$ - 0$ - 0$ - 0
Cab Interior/Finishes$ - 0$ - 0$ - 0
Additional Items (please specify):$ - 0$ - 0$ - 0
Subtotal$ - 0$ - 0$ - 0
Construction/Install:
Mobilization/Demobilization$ - 0$ - 0$ - 0$ - 0
Removal/Demolition$ - 0$ - 0$ - 0$ - 0
Installation$ - 0$ - 0$ - 0$ - 0
Permits$ - 0$ - 0$ - 0$ - 0
Additional Items (please specify):$ - 0$ - 0$ - 0$ - 0
Subtotal$ - 0$ - 0$ - 0$ - 0
After Hours Variance:
Modernization/Construction$ - 0$ - 0$ - 0$ - 0
Additional Items (please specify):$ - 0$ - 0$ - 0$ - 0
Subtotal$ - 0$ - 0$ - 0$ - 0
Profit$ - 0$ - 0
Overhead$ - 0$ - 0
MODERNIZATION TOTAL$ - 0
Performance Maintenance:
Maintenance Fee (monthly)$ - 0$ - 0$ - 0$ - 0
Maintenance Monitoring (as required)$ - 0$ - 0$ - 0$ - 0
Additional Items (please specify):$ - 0$ - 0$ - 0$ - 0
Subtotal$ - 0$ - 0$ - 0$ - 0
Profit$ - 0$ - 0
Overhead$ - 0$ - 0
MAINTENANCE TOTAL (Annual) Base Year$ - 0
Maintenance Option Year 1
Maintenance Option Year 2
Maintenance Option Year 3
Maintenance Option Year 4
Instructions For Use: Enter the component cost in the white cells only. The pink cells have embedded formulas. Entering data directly into these cells will overwrite the embedded formulas. Include a narrative description of the modernization effort along with your technical proposal and standardized proposal breakdown.