ASCPV Clarifications 17 Feb 11.pdf
PDF 58 KB Posted
- Solicitation number
- SPRWA1-11-R-ASCPV
About this file
Solicitation clarifications and information
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ASCPVC Atch A 15 Mar 11.xls | XLS spreadsheet | |
| SPRWA1-11-R-ASCPV-0003.pdf | ||
| SPRWA1-11-R-ASCPV-0002.pdf | ||
| ASCPV Authorization Letter.pdf | ||
| ASCPV Clarifications 24 Jan 11.docx | DOCX document | |
| Atch A ASCPVC RFP Items Unlocked 24 Jan 11.xlsx | XLSX spreadsheet | |
| Atch B-ASCPVC NIINs Cons and DLRs 27 Dec 10 Revised.xlsx | XLSX spreadsheet | |
| SPRWA1-11-R-ASCPV-0002.xps | XPS file | |
| SPRWA1-11-R-ASCPV-0001.pdf | ||
| ASCPV Attach 2 - Consent Form.docx | DOCX document | |
| SPRWA1-11-R-ASCPV.doc | DOC document | |
| ASCPV cFolders FACT SHEET.docx | DOCX document | |
| ASCPV Attach 3 - Questionaire.docx | DOCX document | |
| ASCPV Attachment B NIINs Cons and DLRs 13 Dec 10.xlsx | XLSX spreadsheet | |
| ASCPV Attach 4 - Transmittal.docx | DOCX document | |
| ASCPV Attach 5 - Client Authorization.docx | DOCX document | |
| ASCPV Attach 6 - Questionaire Tracking Record.docx | DOCX document | |
| ASCPVC Attachment A RFP Items 14 Dec 10.xlsx | XLSX spreadsheet | |
| ASCPV Attach 1 - FACTS Sheet.docx | DOCX document | |
| ASCPVC Final SOW 13 Dec 10.docx | DOCX document |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Clarifications to SPRWA1‐11‐R‐ASCPV solicitation 17 Feb 2011
When accessing WICAP only, use solicitation number SPRWA1‐11‐R‐ASCP.
The contractor only needs to complete in WICAP the NSNs he is quoting on atthe present time. If he is quoting the peacetime portion of an NSN he must quote surge concurrently.
In Attachment A PLT for the first article and PLT for the productions articles are considered to be the same. USG review time is in addition to the stated PLT.
All items on Attachment A are to be bid. Failure to provide a bid on all items on Attachment A will render your entire proposal non‐responsive and ineligible for award. Full data packages have been provided.
All responses are to be provided in the volume where the information is requested.
All volume III information is to be forwarded to Lynn Donnelly per the address provided.
If mylars are available, they will be provided to the successful offeror within 30 days of contract award.
Solicitation:
Sow 2.8 Surge and Sustainment: Surge and Sustainment (S&S) requirements references FAR 52.211‐
9000. The correct FAR references are as follows: 52.217‐9006, 9007, 9008, 9009 and 9010
Attachment A: NSN 1560‐01‐560‐1386 is deleted