Government's_Response_to_Questions.pdf

PDF 85 KB Posted

Attached to
7, 000 GALLON ROUND HORIZONTAL TANK Federal contract opportunity
Solicitation number
SPMYM2-19-Q-1056
Issued by
Defense Logistics Agency Land and Maritime

About this file

Government's Response to Questions (A0001 to SPMYM2-19-Q-1056)

View the file

Other files for this federal contract opportunity

Other files attached to 7, 000 GALLON ROUND HORIZONTAL TANK, newest first.
File Type Posted
A0007_TO_SPMYM2-19-Q-1056.pdf PDF
ATTACHMENT_4_-_SUBMISSION_GUIDANCE_FOR_CDRL.pdf PDF
SPMYM2-19-Q-1056_(as_of_6-26-19).pdf PDF
A0006_TO_SPMYM2-19-Q-1056.pdf PDF
P0005_TO_SPMYM2-19-Q-1056.pdf PDF
EXHIBIT_A_-_Contractor_Performance_Data_Sheet.pdf PDF
A0004_TO_SPMYM2-19-Q-1056.pdf PDF
A0003_TO_SPMYM2-19-Q-1056.pdf PDF
A0002_TO_SPMYM2-19-Q-1056.pdf PDF
A0001_TO_SPMYM2-19-Q-1056.pdf PDF
ATTACHMENT_2_-_Spec_for_P701-19_7K_Tanks_Rev._B_(3-01-2019).pdf PDF
ATTACHMENT_3_-_CDRL.pdf PDF
SPMYM2-19-Q-1056.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A0001 to SPMYM2-19-Q-1056 Government’S Response to Questions

Question 1: General note #M3 states one piece seamless heads. Can two pieces be used if seam is 100% R. (X-Ray)?

Answer 1: A two piece head that is 100% R (X-Ray) is not acceptable. Head must be one piece (seamless) as stated in the general note #M3.

Question 2: Dwg. M-1480 Sheet 24. The entire header would need to be installed before the head is put on. It would facilitate installation and/ or future removal of the header if there was an internal flange. This would also facilitate the hydro-testing of the header.

Answer 2: No flanges internal to the tank are allowed in the 4” inlet line (vertical pipe) or the diffuser pipe (horizon

Question 3: The MTO or BOM does not designate the (a) or (b) clause for all of the items that pertain to the modified vessels. Is this an oversight?

Answer 3: The (a) and (b) notes (clauses) associated with the MTO/BOM were only referenced on items that used a different quantity of material between the two types of tanks. Indicate in your offer if you have a specific item referencing either note.