90 North Shared Street Construction
Solicitation number
2024-IFB-008
Issued by
Cook County, Illinois

About this file

The document is a comprehensive set of specifications and special provisions for the 90 North Shared Street Construction project in the Village of Schaumburg, Illinois. The project involves infrastructure improvements including utility installation, pavement and sidewalk construction, storm sewer work, water main improvements, and electrical installations. The project will require adherence to Illinois Department of Transportation (IDOT) standards, with specific guidelines for construction operations, material specifications, traffic control, and environmental management. Key construction activities are to be scheduled and reported to the Engineer by 1:00 PM the previous day, with work typically permitted between 7:00 AM and 6:00 PM.

The specifications outline detailed requirements for various construction elements, including hot-mix asphalt, concrete work, erosion control, electrical installations, and landscaping. The project includes provisions for soil management, storm water pollution prevention, and compliance with environmental regulations. Contractors must implement specific erosion and sediment control practices, utilize approved structural practices, and maintain detailed documentation throughout the construction process. The project will require careful management of site safety, utility locations, and environmental controls, with potential financial penalties for non-compliance with housekeeping, dust control, and other specified standards. The comprehensive nature of the specifications indicates a complex infrastructure project with significant attention to technical and environmental details.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF ILLINOIS

SPECIAL PROVISIONS

STANDARDS

LOCATION OF PROJECT

DESCRIPTION OF PROJECT

PROJECT TIMING

CONSTRUCTION SCHEDULE

All construction activities scheduled by the Contractor or any subcontractors for the next day’s operations must be provided to the Engineer by 1:00 PM the previous day. If these scheduled construction activities are not given to the Engineer by 1:00 PM the previous day, that work will not be allowed to commence, and no compensation will be allowed for cancelled activities.

TERMS OF CONTRACT

The Village, at their discretion, reserves the right to add or delete from the scope of the improvements specified within these contract documents. No extra compensation whatsoever will be allowed because of the adjustment of any pay items or their associated quantities.

LIQUIDATED DAMAGES

UTILITY LOCATION

The Contractor must exercise extreme caution while working around existing utilities.

CONSTRUCTION OPERATIONS

7:00 AM and 6:00 PM

The Village is not responsible for site safety. The Bidder is solely and exclusively responsible for construction means, methods, technologies, and site safety.

Beginning on the date that the Contractor begins work on this project, he/she shall assume responsibility for normal maintenance of all existing roadways within the limits of the improvement. This normal maintenance shall include all repair work deemed necessary by the Engineer. Traffic control and protection for this work will be provided by the Contractor as required by the Engineer. The work involved in maintaining the existing pavement and shoulders will not be paid for separately but will be considered included in the contract unit prices for the various items of work involved, unless otherwise specified elsewhere in these Special Provisions.

INSPECTION

MATERIAL INSPECTION

HOUSEKEEPING

A housekeeping deduction in the amount of $750 per day may be assessed at the discretion of the Engineer, if at any time the Engineer deems the Contractor is not meeting the required timelines for housekeeping requests, access restoration, progress of work, backfilling, restoration, and other items as detailed in these specifications.

DUST CONTROL

A housekeeping deduction in the amount of $750 will be assessed for each 24-hour period the dust control remains uncompleted from the time the initial request is made by the Engineer.

STREET SWEEPING

A housekeeping deduction in the amount of $750 will be assessed for each 24-hour period the sweeping remains uncompleted from the time the initial request is made by the Engineer.

MOWING

A housekeeping deduction in the amount of $750 per day will be assessed if the weed removal is not completed within 3 working days from the time the initial request is made by the Engineer.

COOPERATION WITH ADJACENT CONTRACTS

PERMIT AND BONDS

PUBLIC CONVENIENCE AND SAFETY (D1)

AVAILABLE REPORTS (D1 LR)

COARSE AGGREGATE FOR BACKFILL, TRENCH BACKFILL AND BEDDING

(D-1)

FRICTION AGGREGATE (D1)

“1004.03 Coarse Aggregate for Hot-Mix Asphalt (HMA).

Up to... With...

HOT-MIX ASPHALT BINDER AND SURFACE COURSE (D1)

HOT-MIX ASPHALT – MIXTURE DESIGN VERIFICATION AND PRODUCTION

(D1)

ADJUSTMENTS AND RECONSTRUCTIONS (D1)

“602.04 Concrete.

603.05 Replacement of Existing Flexible Pavement.

603.06 Replacement of Existing Rigid Pavement.

603.07 Protection Under Traffic.

DRAINAGE AND INLET PROTECTION UNDER TRAFFIC (D1)

603.07 Protection Under Traffic.

SAW CUTTING

POROUS GRANULAR EMBANKMENT

GRATING FOR CONCRETE FLARED END SECTIONS

STORM SEWERS, RUBBER GASKET, CLASS A

OBSERVATION WELL

CLEANOUT

PIPE UNDERDRAINS, TYPE 1 (SPECIAL)

PIPE UNDERDRAINS, TYPE 2 (SPECIAL)

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (PROJECT

SPECIFIC)

: None

REMOVE ABANDONED GAS MAIN

BIKE PATH REMOVAL

JUNCTION CHAMBER

EXPLORATION TRENCH, SPECIAL

DETECTABLE WARNINGS (SPECIAL)

STORM SEWERS, PIPE UNDERDRAINS, SANITARY SEWERS, AND

WATERMAIN

STORM SEWER CONNECTIONS

MANHOLES, SANITARY, 4’ DIAMETER, TYPE 1 FRAME, CLOSED LID

SANITARY MANHOLES TO BE ADJUSTED

SIGN PANEL (SPECIAL)

TELESCOPING STEEL SIGN SUPPORT (SPECIAL)

BASE FOR TELESCOPING STEEL SIGN SUPPORT, SPECIAL

CONCRETE WASHOUT FACILITY

PAVEMENT MARKING (SPECIAL)

Dark Gray Specifications:

NAME:

COLOR: (

VISCOSITY @ 77°F, Brookfield LV #4 Spindle 60 RPM:

WEIGHT PER GALLON @ 77°F, Lb.

TOTAL SOLIDS, % By Weight:

PROPERTIES:

CATALYST, Part “B”:

AGGREGATE MOHS HARDNESS:

GEL TIME, Minutes @ 77°F:

SKID RESISTANCE (ASTM E 303)

CURE TIME, Minutes @ 77°F:

DAYTIME LUMINANCE FACTOR (Y):

CHEMICAL RESISTANCE:

APPLICATION:

Light Gray Specifications:

COLOR: (

VISCOSITY @ 77°F, Brookfield LV #4 Spindle 60 RPM:

WEIGHT PER GALLON @ 77°F, Lb.

TOTAL SOLIDS, % By Weight:

PROPERTIES: (After combination at 1:1 Part “A” to Part “B” with 4 parts Benzoyl Peroxide added to Part “B”) GEL TIME, Minutes @ 77°F:

CURE TIME, Minutes @ 77°F:

HARDNESS, Shore Durameter, Type D:

DRY FILM REFLECTANCE, % of Magnesium Oxide

CHEMICAL RESISTANCE:

APPLICATION:

NOTE:

Brick Red Specifications:

COLOR:

VISCOSITY @ 77°F, Brookfield LV #4 Spindle 60 RPM:

WEIGHT PER GALLON @ 77°F, Lb.

TOTAL SOLIDS, % By Weight:

PROPERTIES: (After combination at 1:1 Part “A” to Part “B” with 4 parts Benzoyl Peroxide added to Part “B”) GEL TIME, Minutes @ 77°F:

CURE TIME, Minutes @ 77°F:

HARDNESS, Shore Durameter, Type D:

DRY FILM REFLECTANCE, % of Magnesium Oxide:

CHEMICAL RESISTANCE:

APPLICATION:

NOTE:

Stencil Specifications:

BARRICADES, TYPE III

STABILIZED CONSTRUCTION ENTRANCE

TEMPORARY INFORMATION SIGNING

Item Article/Section

GENERAL CONSTRUCTION REQUIREMENTS

SANITARY SEWER

CATCH BASINS, DEPRESSED FRAME AND GRATE

PORTLAND CEMENT CONCRETE PAVEMENT

FLUSH CONCRETE CURB

WATER MAIN AND APPURTENANCES

Ductile iron pipe shall have an external metallic zinc-based coating with finishing layer topcoat applied according to ISO standard 8179- 1, latest edition. The mass of the zinc applied shall be 200 g/m2 of pipe surface area.

FLUSHING, PRESSURE TESTING & CHLORINATION

ALLOWABLE LEAKAGE (gallons / hour) FOR 1000 FEET OF GASKETED DUCTILE

IRON PIPE

WATER MAIN LOWERING

WATER SERVICE CONNECTION

FIRE HYDRANT WITH AUXILIARY VALVE AND VALVE BOX AUXILIARY

VALVE WITH VALVE BOX

FIRE HYDRANT EXTENSION

CONNECT TO EXISTING WATER MAIN

WATER VALVES

VALVE VAULTS, TYPE A, 5’-DIAMETER, TYPE 1 FRAME, CLOSED LID

HYDRANT SIGNAGE

WATER MAIN REMOVAL

VALVE VAULTS TO BE REMOVED

UNDERGROUND CONDUIT, PVC

TRAFFIC CONTROL PLAN

LANDSCAPING / PLANTING

General.

Nomenclature.

Submittals.

Inspection of Plant Material.

Materials for Planting.

Protection During Work and Maintenance.

TREE PRESERVATION

GYPSUM PLACEMENT

Description.

Materials.

Method of Measurement.

Basis of Payment.

PERENNIAL PLANTS

Layout of Planting:

Planting Procedures:

Mulching:

PLANTING WOODY PLANTS

Layout of Planting:

Planting Procedures:

Mulch Cover:

Wrapping of Tree Trunks:

Basis of Payment

TOPSOIL AND COMPOST

MEDIAN SOIL MIX FURNISH AND PLACE

General Requirements.

Inspections.

Preparation and Placement.

COMPOST FURNISH AND PLACE, SPECIAL

Materials.

Method of Measurement.

Basis of Payment.

SODDING, SALT TOLERANT

Sod:

Sodding Time:

Transportation:

Placing Sod:

Inspection:

Maintenance of Sodded Areas:

WEED CONTROL, PRE-EMERGENT GRANULAR HERBICIDE

Description

Materials:

Method

Method of Measurement.

SUPPLEMENTAL WATERING

METAL BENCH

BIKE RACK

REMOVABLE BOLLARD

PERMEABLE CONCRETE PAVERS

PERMEABLE JOINT OPENING AGGREGATE GRADATION REQUIREMENTS

(GRANITE CHIPS)

Sieve Size Percent Passing

ASTM No. 8

CONCRETE PAVERS

o

TABLE 1 – JOINT SAND

GRADATION REQUIREMENTS FOR JOINT SAND

ASTM C 144

Sieve Size Natural Sand

Percent Passing Manufactured Sand

Percent Passing

ASTM C 33

EXECUTION

INFILTRATION SOIL MIX FURNISH AND PLACE

General Requirements.

Inspections.

Preparation and Placement.

PLANTER CURB

PLANTER

PRECAST CUBE

PLANTER SEAT WALL

TRASH RECEPTACLES

STONE STEPS

GENERAL ELECTRICAL REQUIREMENTS

Definition.

Standards of Installation.

Safety and Protection.

Equipment Grounding Conductor.

Type of Work (discipline)

Item

Items from multiple disciplines shall not be combined on a single submittal and transmittal. Items for lighting, signals, surveillance and CCTV must be in separate submittals since they may be reviewed by various personnel in various locations

Certifications.

Authorized Project Delay.

Maintenance transfer and Preconstruction Inspection

Marking Proposed Locations for Highway Lighting System.

Inspection of electrical work

Maintenance and Responsibility During Construction.

Damage to Electrical Systems.

Testing.

Contract Guarantee.

Record Drawings.

RECORD DRAWINGS

Prior to the collection of data, the contractor shall provide a sample data collection of at least six data points of known locations to be reviewed and verified by the Engineer to be accurate within 20 feet.

Data collection prior to the submittal and review of the sample data of existing data points will be unacceptable and rejected.

Acceptance.

Final Acceptance Documentation Checklist

LOCATION

ITEM

Contractor

(Verify)

Resident Engineer

(Verify)

Record Drawings

Field Inspection Tests

GPS Coordinates

Job Warranty Letter

Catalog Cut Submittals

Lighting Inventory Form

Lighting Controller Inventory Form

Light Tower Inspection Form

General Notes:

Label must be printed; hand written labels are unacceptable and will be rejected.

Contract: 60X23 Letting: 1/20/12

Route: FAU 123 (IL 83) Limits: IL64 to IL56

Section: 123N-XYZ(L)TS County: DuPage

Acme Construction

Submittal Date 2/29/14

Items

Record Drawings Final Approved

Submittals Test Results Inventory

Warranty Letters

ELECTRIC SERVICE INSTALLATION

CONSTRUCTION REQUIREMENTS

ELECTRIC UTILITY SERVICE CONNECTION (COMED)

UNDERGROUND RACEWAYS

UNIT DUCT

Nominal Size Nominal I.D. Nominal O.D. Minimum Wall

Nominal Size Pulled Tensile

Duct Diameter

Min. force required to deform sample 50%

WIRE AND CABLE

HANDHOLE, COMPOSITE CONCRETE

LUMINAIRE, LED

IDOT DISTRICT 1 LUMINAIRE PERFORMANCE TABLE

ROADWAY LIGHTING

Luminaire, LED, Type 1

GIVEN CONDITIONS

NOTE:

PERFORMANCE REQUIREMENTS

NOTE

IDOT DISTRICT 1 LUMINAIRE PERFORMANCE TABLE

ROADWAY LIGHTING

Luminaire, LED, Type 2

GIVEN CONDITIONS

NOTE:

PERFORMANCE REQUIREMENTS

NOTE

LIGHT POLE, SPECIAL

LIGHTING CONTROLLER (SPECIAL)

LIGHT POLE FOUNDATION, METAL

LIGHT POLE FOUNDATION, 24” DIAMETER

BREAKAWAY DEVICE, TRANSFORMER BASE (SPECIAL)

TREE OUTLET PEDESTAL BOX, DOUBLE GANG

TREE OUTLET PEDESTAL BOX FOUNDATION

SECURITY BOLLARD WITH PEDESTRIAN LIGHTING

SECURITY BOLLARD FOUNDATION, 18” X 18” X 36”

FESTOON LIGHTING

LIGHT POLE, 20 FT., ROUND TAPERED STEEL

LIGHT POLE, SPECIAL (FURNISH ONLY)

LUMINAIRE, LED (FURNISH ONLY)

BREAKAWAY DEVICE, TRANSFORMER BASE (SPECIAL) (FURNISH ONLY)

WEATHERPROOF ENCLOSURE

AGGREGATE SUBGRADE IMPROVEMENT (BDE)

Effective: April 1, 2012 Revised: April 1, 2022

Add the following Section to the Standard Specifications:

“SECTION 303. AGGREGATE SUBGRADE IMPROVEMENT

303.01 Description. This work shall consist of constructing an aggregate subgrade improvement (ASI).

303.02 Materials. Materials shall be according to the following.

Item Article/Section

(a) Coarse Aggregate ...............................................................................................1004.07

(b) Reclaimed Asphalt Pavement (RAP) ...................................................................1031.09

303.03 Equipment. The vibratory roller shall be according to Article 1101.01, or as approved by the Engineer. Vibratory machines, such as tampers, shall be used in areas where rollers do not fit.

303.04 Soil Preparation. The minimum immediate bearing value (IBV) of the soil below the improved subgrade shall be according to the Department’s “Subgrade Stability Manual” for the aggregate thickness specified.

303.05 Placing and Compacting. The maximum nominal lift thickness of aggregate gradations CA 2, CA 6, and CA 10 when compacted shall be 9 in. (225 mm). The maximum nominal lift thickness of aggregate gradations CS 1, CS 2, and RR 1 when compacted shall be 24 in. (600 mm).

The top surface of the aggregate subgrade improvement shall consist of a layer of capping aggregate gradations CA 6 or CA 10 that is 3 in. (75 mm) thick after compaction. Capping aggregate will not be required when aggregate subgrade improvement is used as a cubic yard pay item for undercut applications.

Each lift of aggregate shall be compacted to the satisfaction of the Engineer. If the moisture content of the material is such that compaction cannot be obtained, sufficient water shall be added so that satisfactory compaction can be obtained.

303.06 Finishing and Maintenance. The aggregate subgrade improvement shall be finished to the lines, grades, and cross sections shown on the plans, or as directed by the Engineer. The aggregate subgrade improvement shall be maintained in a smooth and compacted condition.

303.07 Method of Measurement. This work will be measured for payment according to Article 311.08.

303.08 Basis of Payment. This work will be paid for at the contract unit price per cubic yard (cubic meter) or ton (metric ton) for AGGREGATE SUBGRADE IMPROVEMENT or at the contract unit price per square yard (square meter) for AGGREGATE SUBGRADE IMPROVEMENT, of the thickness specified.”

Add the following to Section 1004 of the Standard Specifications:

“1004.07 Coarse Aggregate for Aggregate Subgrade Improvement (ASI). The aggregate shall be according to Article 1004.01 and the following.

(a) Description. The coarse aggregate shall be crushed gravel, crushed stone, or crushed concrete. In applications where greater than 24 in. (600 mm) of ASI material is required, gravel may be used below the top 12 in (300 mm) of ASI.

(b) Quality. The coarse aggregate shall consist of sound durable particles reasonably free of deleterious materials.

(c) Gradation.

(1) The coarse aggregate gradation for total ASI thickness less than or equal to 12 in.

(300 mm) shall be CA 2, CA 6, CA 10, or CS 1.

The coarse aggregate gradation for total ASI thickness greater than 12 in. (300 mm) shall be CS 1 or CS 2 as shown below or RR 1 according to Article 1005.01(c).

COARSE AGGREGATE SUBGRADE GRADATIONS

Grad No. Sieve Size and Percent Passing 8” 6” 4” 2” #4

CS 1 100 97 ± 3 90 ± 10 45 ± 25 20 ± 20

CS 2 100 80 ± 10 25 ± 15

COARSE AGGREGATE SUBGRADE GRADATIONS (Metric)

Grad No. Sieve Size and Percent Passing 200 mm 150 mm 100 mm 50 mm 4.75 mm

CS 1 100 97 ± 3 90 ± 10 45 ± 25 20 ± 20

CS 2 100 80 ± 10 25 ± 15

(2) Capping aggregate shall be gradation CA 6 or CA 10.”

Add the following to Article 1031.09 of the Standard Specifications:

“(b) RAP in Aggregate Subgrade Improvement (ASI). RAP in ASI shall be according to Articles 1031.01(a), 1031.02(a), 1031.06(a)(1), and 1031.06(a)(2), and the following.

(1) The testing requirements of Article 1031.03 shall not apply.

(2) Crushed RAP used for the lower lift may be mechanically blended with aggregate gradations CS 1, CS 2, and RR 1 but it shall be no greater than 40 percent of the total product volume. RAP agglomerations shall be no greater than 4 in. (100 mm).

(3) For capping aggregate, well graded RAP having 100 percent passing the 1 1/2 in.

(38 mm) sieve may be used when aggregate gradations CS 1, CS 2, CA 2, or RR 1 are used in the lower lift. FRAP will not be permitted as capping material.

Blending shall be through calibrated interlocked feeders or a calibrated blending plant such that the prescribed blending percentage is maintained throughout the blending process. The calibration shall have an accuracy of ± 2.0 percent of the actual quantity of material delivered.”

80274

CONSTRUCTION AIR QUALITY – DIESEL RETROFIT (BDE)

Effective: June 1, 2010 Revised: November 1, 2014 The reduction of emissions of particulate matter (PM) for off-road equipment shall be accomplished by installing retrofit emission control devices. The term “equipment” refers to diesel fuel powered devices rated at 50 hp and above, to be used on the jobsite in excess of seven calendar days over the course of the construction period on the jobsite (including rental equipment).

Contractor and subcontractor diesel powered off-road equipment assigned to the contract shall be retrofitted using the phased in approach shown below. Equipment that is of a model year older than the year given for that equipment’s respective horsepower range shall be retrofitted:

Effective Dates Horsepower Range Model Year

June 1, 2010 1/ 600-749 2002 750 and up 2006

June 1, 2011 2/ 100-299 2003

300-599 2001 600-749 2002

750 and up 2006

June 1, 2012 2/ 50-99 2004 100-299 2003 300-599 2001 600-749 2002

750 and up 2006 1/ Effective dates apply to Contractor diesel powered off-road equipment assigned to the contract.

2/ Effective dates apply to Contractor and subcontractor diesel powered off-road equipment assigned to the contract.

The retrofit emission control devices shall achieve a minimum PM emission reduction of 50 percent and shall be:

a) Included on the U.S. Environmental Protection Agency (USEPA) Verified Retrofit Technology List (http://www.epa.gov/cleandiesel/verification/verif-list.htm), or verified by the California Air Resources Board (CARB) (http://www.arb.ca.gov/diesel/verdev/vt/cvt.htm); or

b) Retrofitted with a non-verified diesel retrofit emission control device if verified retrofit emission control devices are not available for equipment proposed to be used on the project, and if the Contractor has obtained a performance certification from the retrofit device manufacturer that the emission control device provides a minimum PM emission reduction of 50 percent.

Note: Large cranes (Crawler mounted cranes) which are responsible for critical lift operations are exempt from installing retrofit emission control devices if such devices adversely affect equipment operation.

Diesel powered off-road equipment with engine ratings of 50 hp and above, which are unable to be retrofitted with verified emission control devices or if performance certifications are not available which will achieve a minimum 50 percent PM reduction, may be granted a waiver by the Department if documentation is provided showing good faith efforts were made by the Contractor to retrofit the equipment.

Construction shall not proceed until the Contractor submits a certified list of the diesel powered off-road equipment that will be used, and as necessary, retrofitted with emission control devices.

The list(s) shall include (1) the equipment number, type, make, Contractor/rental company name; and (2) the emission control devices make, model, USEPA or CARB verification number, or performance certification from the retrofit device manufacturer. Equipment reported as fitted with emissions control devices shall be made available to the Engineer for visual inspection of the device installation, prior to being used on the jobsite.

The Contractor shall submit an updated list of retrofitted off-road construction equipment as retrofitted equipment changes or comes on to the jobsite. The addition or deletion of any diesel powered equipment shall be included on the updated list.

If any diesel powered off-road equipment is found to be in non-compliance with any portion of this special provision, the Engineer will issue the Contractor a diesel retrofit deficiency deduction.

Any costs associated with retrofitting any diesel powered off-road equipment with emission control devices shall be considered as included in the contract unit prices bid for the various items of work involved and no additional compensation will be allowed. The Contractor's compliance with this notice and any associated regulations shall not be grounds for a claim.

Diesel Retrofit Deficiency Deduction

When the Engineer determines that a diesel retrofit deficiency exists, a daily monetary deduction will be imposed for each calendar day or fraction thereof the deficiency continues to exist. The calendar day(s) will begin when the time period for correction is exceeded and end with the Engineer's written acceptance of the correction. The daily monetary deduction will be $1,000.00 for each deficiency identified.

The deficiency will be based on lack of diesel retrofit emissions control.

If a Contractor accumulates three diesel retrofit deficiency deductions for the same piece of equipment in a contract period, the Contractor will be shutdown until the deficiency is corrected.

Such a shutdown will not be grounds for any extension of the contract time, waiver of penalties, or be grounds for any claim.

80261

HOT-MIX ASPHALT (BDE)

Effective: January 1, 2024

Revise the second paragraph of Articles 1030.07(a)(11) and 1030.08(a)(9) of the Standard Specifications to read:

“ When establishing the target density, the HMA maximum theoretical specific gravity (Gmm) will be based on the running average of four available Department test results for that project. If less than four Gmm test results are available, an average of all available Department test results for that project will be used. The initial Gmm will be the last available Department test result from a QMP project. If there is no available Department test result from a QMP project, the Department mix design verification test result will be used as the initial Gmm.”

In the Supplemental Specifications, replace the revision for the end of the third paragraph of Article 1030.09(h)(2) with the following:

“ When establishing the target density, the HMA maximum theoretical specific gravity (Gmm) will be the Department mix design verification test result.”

Revise the tenth paragraph of Article 1030.10 of the Standard Specifications to read:

“ Production is not required to stop after a test strip has been constructed.”

80456

HOT-MIX ASPHALT – LONGITUDINAL JOINT SEALANT (BDE)

Effective: November 1, 2022 Revised: August 1, 2023

Add the following after the second sentence in the eighth paragraph of Article 406.06(h)(2) of the Standard Specifications:

“If rain is forecasted and traffic is to be on the LJS or if pickup/tracking of the LJS material is likely, the LJS shall be covered immediately following its application with FA 20 fine aggregate mechanically spread uniformly at a rate of 1.5 ± 0.5 lb/sq yd (0.75 ± 0.25 kg/sq m). Fine aggregate landing outside of the LJS shall be removed prior to application of tack coat.”

Add the following after the first sentence in the ninth paragraph of Article 406.06(h)(2) of the Standard Specifications:

“LJS half-width shall be applied at a width of 9 ± 1 in. (225 ± 25 mm) in the immediate lane to be placed with the outside edge flush with the joint of the next HMA lift. The vertical face of any longitudinal joint remaining in place shall also be coated.”

Add the following after the eleventh paragraph of Article 406.06(h)(2) of the Standard Specifications:

“LJS Half-Width Application Rate, lb/ft (kg/m) 1/

Lift Thickness,

in. (mm)

Coarse Graded Mixture

(IL-19.0, IL-19.0L, IL-9.5,

IL-9.5L, IL-4.75)

Fine Graded Mixture

(IL-9.5FG)

SMA Mixture

(SMA-9.5,

SMA-12.5)

¾ (19) 0.44 (0.66) 1 (25) 0.58 (0.86)

1 ¼ (32) 0.66 (0.98) 0.44 (0.66) 1 ½ (38) 0.74 (1.10) 0.48 (0.71) 0.63 (0.94) 1 ¾ (44) 0.82 (1.22) 0.52 (0.77) 0.69 (1.03) 2 (50) 0.90 (1.34) 0.56 (0.83) 0.76 (1.13)

≥ 2 ¼ (60) 0.98 (1.46)

1/ The application rate includes a surface demand for liquid. The thickness of the LJS may taper from the center of the application to a lesser thickness on the edge of the application, provided the correct width and application rate are maintained.”

Revise the second paragraph of Article 406.13(b) of the Standard Specifications to read:

“Aggregate for covering tack, LJS, or FLS will not be measured for payment.”

Add the following to the end of the second paragraph of Article 406.14 of the Standard Specifications:

“Longitudinal joint sealant (LJS) half-width will be paid for at the contract unit price per foot (meter) for LONGITUDINAL JOINT SEALANT, HALF-WIDTH.”

80446

PERFORMANCE GRADED ASPHALT BINDER (BDE)

Effective: January 1, 2023

Revise Article 1032.05 of the Standard Specifications to read:

“ 1032.05 Performance Graded Asphalt Binder. These materials will be accepted according to the Bureau of Materials Policy Memorandum, “Performance Graded Asphalt Binder Qualification Procedure.” The Department will maintain a qualified producer list. These materials shall be free from water and shall not foam when heated to any temperature below the actual flash point. Air blown asphalt, recycle engine oil bottoms (ReOB), and polyphosphoric acid (PPA) modification shall not be used.

When requested, producers shall provide the Engineer with viscosity/temperature relationships for the performance graded asphalt binders delivered and incorporated in the work.

(a) Performance Graded (PG) Asphalt Binder. The asphalt binder shall meet the requirements of AASHTO M 320, Table 1 “Standard Specification for Performance Graded Asphalt Binder” for the grade shown on the plans and the following.

Test Parameter

Small Strain Parameter (AASHTO PP 113) BBR, , 40 hrs PAV (40 hrs continuous or 2 PAV at 20 hrs)

-5 °C min.

(b) Modified Performance Graded (PG) Asphalt Binder. The asphalt binder shall meet the requirements of AASHTO M 320, Table 1 “Standard Specification for Performance Graded Asphalt Binder” for the grade shown on the plans.

Asphalt binder modification shall be performed at the source, as defined in the Bureau of Materials Policy Memorandum, “Performance Graded Asphalt Binder Qualification Procedure.”

Modified asphalt binder shall be safe to handle at asphalt binder production and storage temperatures or HMA construction temperatures. Safety Data Sheets (SDS) shall be provided for all asphalt modifiers.

(1) Polymer Modification (SB/SBS or SBR). Elastomers shall be added to the base asphalt binder to achieve the specified performance grade and shall be either a styrene-butadiene diblock, triblock copolymer without oil extension, or a styrene-butadiene rubber. The polymer modified asphalt binder shall be smooth, homogeneous, and be according to the requirements shown in Table 1 or 2 for the grade shown on the plans.

Table 1 - Requirements for Styrene-Butadiene Copolymer (SB/SBS) Modified Asphalt Binders

Test

Asphalt Grade

SB/SBS PG 64-28

SB/SBS PG 70-22

Asphalt Grade

SB/SBS PG 64-34

SB/SBS PG 70-28

SB/SBS PG 76-22

SB/SBS PG 76-28

Separation of Polymer ITP, "Separation of Polymer from Asphalt Binder" Difference in °F (°C) of the softening point between top and bottom portions 4 (2) max. 4 (2) max.

TESTS ON RESIDUE FROM ROLLING THIN FILM OVEN TEST (AASHTO T 240)

Elastic Recovery ASTM D 6084, Procedure A, 77 °F (25 °C), 100 mm elongation, % 60 min. 70 min.

Table 2 - Requirements for Styrene-Butadiene Rubber (SBR)

Test

Asphalt Grade

SBR PG 64-28

SBR PG 70-22

Asphalt Grade

SB/SBS PG 64-34

SB/SBS PG 70-28

SBR PG 76-22

SBR PG 76-28

Separation of Polymer ITP, "Separation of Polymer from Asphalt Binder" Difference in °F (°C) of the softening point between top and bottom portions 4 (2) max. 4 (2) max.

Toughness

ASTM D 5801, 77 °F (25 °C),

20 in./min. (500 mm/min.), in.-lbs (N-m) 110 (12.5) min. 110 (12.5) min.

Tenacity

ASTM D 5801, 77 °F (25 °C),

20 in./min. (500 mm/min.), in.-lbs (N-m) 75 (8.5) min. 75 (8.5) min.

TESTS ON RESIDUE FROM ROLLING THIN FILM OVEN TEST (AASHTO T 240)

Elastic Recovery

77 °F (25 °C), 100 mm elongation, % 40 min. 50 min.

(2) Ground Tire Rubber (GTR) Modification. GTR modification is the addition of recycled ground tire rubber to liquid asphalt binder to achieve the specified performance grade.

GTR shall be produced from processing automobile and/or truck tires by the ambient grinding method or micronizing through a cryogenic process. GTR shall not exceed 1/16 in. (2 mm) in any dimension and shall not contain free metal particles, moisture that would cause foaming of the asphalt, or other foreign materials. A mineral powder (such as talc) meeting the requirements of AASHTO M 17 may be added, up to a maximum of four percent by weight of GTR to reduce sticking and caking of the GTR particles. When tested in accordance with Illinois Modified AASHTO T 27 “Standard Method of Test for Sieve Analysis of Fine and Coarse Aggregates” or AASHTO PP 74 “Standard Practice for Determination of Size and Shape of Glass Beads Used in Traffic Markings by Means of Computerized Optical Method”, a 50 g sample of the GTR shall conform to the following gradation requirements.

No. 16 (1.18 mm) 100 No. 30 (600 μm) 95 ± 5 No. 50 (300 μm) > 20

GTR modified asphalt binder shall be tested for rotational viscosity according to AASHTO T 316 using spindle S27. GTR modified asphalt binder shall be tested for original dynamic shear and RTFO dynamic shear according to AASHTO T 315 using a gap of 2 mm.

The GTR modified asphalt binder shall meet the requirements of Table 3.

Table 3 - Requirements for Ground Tire Rubber (GTR)

Test

Asphalt Grade

GTR PG 64-28

GTR PG 70-22

Asphalt Grade

GTR PG 76-22

GTR PG 76-28

GTR PG 70-28

TESTS ON RESIDUE FROM ROLLING THIN FILM OVEN TEST (AASHTO T 240)

Elastic Recovery

77 °F (25 °C), 100 mm elongation, % 60 min. 70 min.

(3) Softener Modification (SM). Softener modification is the addition of organic compounds, such as engineered flux, bio-oil blends, modified vegetable oils, glycol amines, and fatty acid derivatives, to the base asphalt binder to achieve the specified performance grade. Softeners shall be dissolved, dispersed, or reacted in the asphalt binder to enhance its performance and shall remain compatible with the asphalt binder with no separation. Softeners shall not be added to modified PG asphalt binder as defined in Articles 1032.05(b)(1) or 1032.05(b)(2).

An Attenuated Total Reflectance-Fourier Transform Infrared spectrum (ATR-FTIR) shall be collected for both the softening compound as well as the softener modified asphalt binder at the dose intended for qualification. The ATR-FTIR spectra shall be collected on unaged softener modified binder, 20-hour Pressurized Aging Vessel (PAV) aged softener modified binder, and 40-hour PAV aged softener modified binder.

The ATR-FTIR shall be collected in accordance with Illinois Test Procedure 601. The electronic files spectral files (in one of the following extensions or equivalent: *.SPA, *.SPG, *.IRD, *.IFG, *.CSV, *.SP, *.IRS, *.GAML, *.[0-9], *.IGM, *.ABS, *.DRT, *.SBM, *.RAS) shall be submitted to the Central Bureau of Materials.

Softener modified asphalt binders shall meet the requirements in Table 4.

Table 4 - Requirements for Softener Modified Asphalt Binders

Test

Asphalt Grade

SM PG 46-28 SM PG 46-34

SM PG 52-28 SM PG 52-34

SM PG 58-22 SM PG 58-28

SM PG 64-22

Small Strain Parameter (AASHTO PP 113) BBR, , 40 hrs PAV (40 hrs continuous or 2 PAV at 20 hrs)

-5°C min.

Large Strain Parameter (Illinois Modified AASHTO T 391) DSR/LAS Fatigue Property, , 40 hrs PAV (40 hrs continuous or 2 PAV at 20 hrs)

The following grades may be specified as tack coats.

Asphalt Grade Use PG 58-22, PG 58-28, PG 64-22 Tack Coat”

Revise Article 1031.06(c)(1) and 1031.06(c)(2) of the Standard Specifications to read:

“ (1) RAP/RAS. When RAP is used alone or RAP is used in conjunction with RAS, the percentage of virgin ABR shall not exceed the amounts listed in the following table.

HMA Mixtures - RAP/RAS Maximum ABR % 1/ 2/

Ndesign Binder Surface Polymer Modified

Binder or Surface 3/ 30 30 30 10 50 25 15 10 70 15 10 10 90 10 10 10

1/ For Low ESAL HMA shoulder and stabilized subbase, the RAP/RAS ABR shall not exceed 50 percent of the mixture.

2/ When RAP/RAS ABR exceeds 20 percent, the high and low virgin asphalt binder grades shall each be reduced by one grade (i.e. 25 percent ABR would require a virgin asphalt binder grade of PG 64-22 to be reduced to a PG 58-28).

3/ The maximum ABR percentages for ground tire rubber (GTR) modified mixes shall be equivalent to the percentages specified for SBS/SBR polymer modified mixes.

(2) FRAP/RAS. When FRAP is used alone or FRAP is used in conjunction with RAS, the percentage of virgin asphalt binder replacement shall not exceed the amounts listed in the following table.

HMA Mixtures - FRAP/RAS Maximum ABR % 1/ 2/

Ndesign Binder Surface Polymer Modified

Binder or Surface 3/ 30 55 45 15 50 45 40 15 70 45 35 15 90 45 35 15

SMA - - - - 25

IL-4.75 - - - - 35

1/ For Low ESAL HMA shoulder and stabilized subbase, the FRAP/RAS ABR shall not exceed 50 percent of the mixture.

2/ When FRAP/RAS ABR exceeds 20 percent for all mixes, the high and low virgin asphalt binder grades shall each be reduced by one grade (i.e. 25 percent ABR would require a virgin asphalt binder grade of PG 64-22 to be reduced to a

PG 58-28).

3/ The maximum ABR percentages for GTR modified mixes shall be equivalent to the percentages specified for SBS/SBR polymer modified mixes.”

Add the following to the end of Note 2 of Article 1030.03 of the Standard Specifications.

“ A dedicated storage tank for the ground tire rubber (GTR) modified asphalt binder shall be provided. This tank shall be capable of providing continuous mechanical mixing throughout and/or recirculation of the asphalt binder to provide a uniform mixture. The tank shall be heated and capable of maintaining the temperature of the asphalt binder at 300 F to 350 F (149 C to 177 C). The asphalt binder metering systems of dryer drum plants shall be calibrated with the actual GTR modified asphalt binder material with an accuracy of 0.40 percent.”

80441

PORTLAND CEMENT CONCRETE (BDE)

Effective: August 1, 2023

Revise the second paragraph of Article 1103.03(a)(4) the Standard Specifications to read:

“ The dispenser system shall provide a visual indication that the liquid admixture is actually entering the batch, such as via a transparent or translucent section of tubing or by independent check with an integrated secondary metering device. If approved by the Engineer, an alternate indicator may be used for admixtures dosed at rates of 25 oz/cwt (1630 mL/100 kg) or greater, such as accelerating admixtures, corrosion inhibitors, and viscosity modifying admixtures.”

80451

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)

Effective: January 1, 2024

Revise the first paragraph of Article 669.04 of the Standard Specifications to read:

“ 669.04 Regulated Substances Monitoring. Regulated substances monitoring includes environmental observation and field screening during regulated substances management activities. The excavated soil and groundwater within the work areas shall be managed as either uncontaminated soil, hazardous waste, special waste, or non-special waste.

As part of the regulated substances monitoring, the monitoring personnel shall perform and document the applicable duties listed on form BDE 2732 “Regulated Substances Monitoring Daily Record (RSMDR)”.”

Revise the first two sentences of the nineteenth paragraph of Article 669.05 of the Standard Specifications to read:

“ The Contractor shall coordinate waste disposal approvals with the disposal facility and provide the specific analytical testing requirements of that facility. The Contractor shall make all arrangements for collection, transportation, and analysis of landfill acceptance testing.”

Revise the last paragraph of Article 669.05 of the Standard Specifications to read:

“ The Contractor shall select a permitted landfill facility or CCDD/USFO facility meeting the requirements of 35 Ill. Admin. Code Parts 810-814 or Part 1100, respectively. The Department will review and approve or reject the facility proposed by the Contractor based upon information provided in BDE 2730. The Contractor shall verify whether the selected facility is compliant with those applicable standards as mandated by their permit and whether the facility is presently, has previously been, or has never been, on the United States Environmental Protection Agency (U.S.

EPA) National Priorities List or the Resource Conservation and Recovery Act (RCRA) List of Violating Facilities. The use of a Contractor selected facility shall in no manner delay the construction schedule or alter the Contractor's responsibilities as set forth.”

Revise the first paragraph of Article 669.07 of the Standard Specifications to read:

“ 669.07 Temporary Staging. Soil classified according to Articles 669.05(a)(2), (b)(1), or (c) may be temporarily staged at the Contractor’s option.

Topsoil for re-use as final cover which has been field screened and found not to exhibit PID readings over daily background readings as documented on the BDE 2732, visual staining or odors, and is classified according to Articles 669.05(a)(2), (a)(3), (a)(4), (b)(1), or (c) may be temporarily staged at the Contractor’s option.

All other soil classified according to Articles 669.05(a)(1), (a)(3), (a)(4), (a)(5), (a)(6), or (b)(2) shall be managed and disposed of without temporary staging to the greatest extent practicable.

If circumstances beyond the Contractor’s control require temporary staging of these latter materials, the Contractor shall request approval from the Engineer in writing.”

Add the following paragraph after the sixth paragraph of Article 669.11 of the Standard Specifications.

“ The sampling and testing of effluent water derived from dewatering discharges for priority pollutants volatile organic compounds (VOCs), priority pollutants semi-volatile organic compounds (SVOCs), or priority pollutants metals, will be paid for at the contract unit price per each for VOC GROUNDWATER ANALYSIS using EPA Method 8260B, SVOC GROUNDWATER ANALYSIS using EPA Method 8270C, or RCRA METALS GROUNDWATER ANALYSIS using EPA Methods 6010B and 7471A. This price shall include transporting the sample from the job site to the laboratory.”

80455

SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)

Effective: November 2, 2017 Revised: April 1, 2019

Replace the second paragraph of Article 109.12 of the Standard Specifications with the following:

“ This mobilization payment shall be made at least seven days prior to the subcontractor starting work. The amount paid shall be at the following percentage of the amount of the subcontract reported on form BC 260A submitted for the approval of the subcontractor’s work.

Value of Subcontract Reported on Form BC 260A Mobilization Percentage

Less than $10,000 25% $10,000 to less than $20,000 20% $20,000 to less than $40,000 18% $40,000 to less than $60,000 16% $60,000 to less than $80,000 14%

$80,000 to less than $100,000 12% $100,000 to less than $250,000 10% $250,000 to less than $500,000 9%

$500,000 to $750,000 8% Over $750,000 7%”

80391

VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)

Effective: November 1, 2021 Revised: November 1, 2022

Add the following paragraph after the first paragraph of Article 701.08 of the Standard Specifications:

“The Contractor shall equip all vehicles and equipment with high-intensity oscillating, rotating, or flashing, amber or amber-and-white, warning lights which are visible from all directions. In accordance with 625 ILCS 5/12-215, the lights may only be in operation while the vehicle or equipment is engaged in construction operations.”

80439

WORK ZONE TRAFFIC CONTROL DEVICES (BDE)

Effective: March 2, 2020

Add the following to Article 701.03 of the Standard Specifications:

“(q) Temporary Sign Supports ...................................................................................1106.02”

Revise the third paragraph of Article 701.14 of the Standard Specifications to read:

“For temporary sign supports, the Contractor shall provide a FHWA eligibility letter for each device used on the contract. The letter shall provide information for the set-up and use of the device as well as a detailed drawing of the device. The signs shall be supported within 20 degrees of vertical. Weights used to stabilize signs shall be attached to the sign support per the manufacturer’s specifications.”

Revise the first paragraph of Article 701.15 of the Standard Specifications to read:

“ 701.15 Traffic Control Devices. For devices that must meet crashworthiness standards, the Contractor shall provide a manufacturer’s self-certification or a FHWA eligibility letter for each Category 1 device and a FHWA eligibility letter for each Category 2 and Category 3 device used on the contract. The self-certification or letter shall provide information for the set-up and use of the device as well as a detailed drawing of the device.”

Revise the first six paragraphs of Article 1106.02 of the Standard Specifications to read:

“ 1106.02 Devices. Work zone traffic control devices and combinations of devices shall meet crashworthiness standards for their respective categories. The categories are as follows.

Category 1 includes small, lightweight, channelizing and delineating devices that have been in common use for many years and are known to be crashworthy by crash testing of similar devices or years of demonstrable safe performance. These include cones, tubular markers, plastic drums, and delineators, with no attachments (e.g. lights). Category 1 devices manufactured after December 31, 2019 shall be MASH-16 compliant. Category 1 devices manufactured on or before December 31, 2019, and compliant with NCHRP 350 or MASH 2009, may be used on contracts let before December 31, 2024.

Category 2 includes devices that are not expected to produce significant vehicular velocity change but may otherwise be hazardous. These include vertical panels with lights, barricades, temporary sign supports, and Category 1 devices with attachments (e.g. drums with lights).

Category 2 devices manufactured after December 31, 2019 shall be MASH-16 compliant.

Category 2 devices manufactured on or before December 31, 2019, and compliant with NCHRP 350 or MASH 2009, may be used on contracts let before December 31, 2024.

Category 3 includes devices that are expected to cause significant velocity changes or other potentially harmful reactions to impacting vehicles. These include crash cushions (impact attenuators), truck mounted attenuators, and other devices not meeting the definitions of Category 1 or 2. Category 3 devices manufactured after December 31, 2019 shall be MASH-16 compliant. Category 3 devices manufactured on or before December 31, 2019, and compliant with NCHRP 350 or MASH 2009, may be used on contracts let before December 31, 2029.

Category 3 devices shall be crash tested for Test Level 3 or the test level specified.

Category 4 includes portable or trailer-mounted devices such as arrow boards, changeable message signs, temporary traffic signals, and area lighting supports. It is preferable for Category 4 devices manufactured after December 31, 2019 to be MASH-16 compliant; however, there are currently no crash tested devices in this category, so it remains exempt from the NCHRP 350 or MASH compliance requirement.

For each type of device, when no more than one MASH-16 compliant is available, an NCHRP 350 or MASH-2009 compliant device may be used, even if manufactured after December 31, 2019.”

Revise Articles 1106.02(g), 1106.02(k), and 1106.02(l) to read:

“(g) Truck Mounted/Trailer Mounted Attenuators. The attenuator shall be approved for use at Test Level 3. Test Level 2 may be used for normal posted speeds less than or equal to 45 mph.

(k) Temporary Water Filled Barrier. The water filled barrier shall be a lightweight plastic shell designed to accept water ballast and be on the Department’s qualified product list.

Shop drawings shall be furnished by the manufacturer and shall indicate the deflection of the barrier as determined by acceptance testing; the configuration of the barrier in that test; and the vehicle weight, velocity, and angle of impact of the deflection test. The Engineer shall be provided one copy of the shop drawings.

(l) Movable Traffic Barrier. The movable traffic barrier shall be on the Department’s qualified product list.

Shop drawings shall be furnished by the manufacturer and shall indicate the deflection of the barrier as determined by acceptance testing; the configuration of the barrier in that test; and the vehicle weight, velocity, and angle of impact of the deflection test. The Engineer shall be provided one copy of the shop drawings. The barrier shall be capable of being moved on and off the roadway on a daily basis.”

80427

BDE 2342 (Rev. 07/19/19)Page 2 of 8Printed 06/05/23

F. List all soils found within project boundaries; include map unit name, slope information, and erosivity:

805B - Orthents, clayey, undulating, T-factor = 2

G. If wetlands were delineated for this project, provide an extent of wetland acreage at the site; see Phase I report:

No wetlands present.

H. Provide a description of potentially erosive areas associated with this project:

Roadway excavation, trench excavation, and exposed soils in parkways.

I. The following is a description of soil disturbing activities by stages, their locations, and their erosive factors (e.g., steepness of slopes, length of slopes, etc.):

All work is to be completed in a single stage, consisting of - Utility installation, earth excavation, pavement and sidewalk construction.

J. See the erosion control plans and/or drainage plans for this contract for information regarding drainage patterns, approximate slopes anticipated before and after major grading activities, locations where vehicles enter or exit the site and controls to prevent offsite sediment tracking (to be added after contractor identifies locations), areas of soil disturbance, the location of major structural and non-structural controls identified in the plan, the location of areas where stabilization practices are expected to occur, surface waters (including wetlands) , and locations where storm water is discharged to surface water including wetlands.

K. Identify who owns the drainage system (municipality or agency) this project will drain into:

Village of Schaumburg

L. The following is a list of General NPDES ILR40 permittees within whose reporting jurisdiction this project is located:

Village of Schaumburg

M. The following is a list of receiving water(s) and the ultimate receiving water(s) for this site. In addition, include receiving waters that are listed as Biologically Significant Streams by the Illinois Department of Natural Resources (IDNR). The location of the receiving waters can be found on the erosion and sediment control plans:

Salt Creek Tributary D

N. Describe areas of the site that are to be protected or remain undisturbed. These areas may include steep slopes (i.e., 1:3 or steeper), highly erodible soils, streams, stream buffers, specimen trees, natural vegetation, nature preserves, etc. Include any commitments or requirements to protect adjacent wetlands.

For any storm water discharges from construction activities within 50-feet of Waters of the U.S. (except for activities for water-dependent structures authorized by a Section 404 permit, describe: a) How a 50-foot undisturbed natural buffer will be provided between the construction activity and the Waters of the U.S. or b) How additional erosion and sediment controls will be provided within that area.

There are no Waters of the US within 50 feet of the project site.

O. Per the Phase I document, the following sensitive environmental resources are associated with this project and may have the potential to be impacted by the proposed development. Further guidance on these resources is available in Section 41-4 of the BDE Manual.

303(d) Listed receiving waters for suspended solids, turbidity, or siltation.

The name(s) of the listed water body, and identification of all pollutants causing impairment:

Provide a description of how erosion and sediment control practices will prevent a discharge of sediment resulting from a storm event equal to or greater than a twenty-five (25) year, twenty-four (24) hour rainfall event:

BDE 2342 (Rev. 07/19/19)Page 3 of 8Printed 06/05/23

Provide a description of the location(s) of direct discharge from the project site to the 303(d) water body:

Provide a description of the location(s) of any dewatering discharges to the MS4 and/or water body:

Applicable Federal, Tribal, State, or Local Programs

Floodplain

Historic Preservation

Receiving waters with Total Maximum Daily Load (TMDL) for sediment, total suspended solids, turbidity or siltation TMDL (fill out this section if checked above)

The name(s) of the listed water body:

Provide a description of the erosion and sediment control strategy that will be incorporated into the site design that is consistent with the assumptions and requirements of the TMDL:

If a specific numeric waste load allocation has been established that would apply to the project's discharges, provide a description of the necessary steps to meet that allocation:

Threatened and Endangered Species/Illinois Natural Areas (INAI)/Nature Preserves

Other

Wetland

P. The following pollutants of concern will be associated with this construction project:

Antifreeze / Coolants Concrete Concrete Curing Compounds Concrete Truck Waste Fertilizers / Pesticides Paints Petroleum (gas, diesel, oil, kerosene, hydraulic oil / fluids) Soil Sediment

Solid Waste Debris Solvents Waste water from cleaning construction equipments Other (Specify)

Other (Specify) Other (Specify) Other (Specify)

II. Controls:

Other (Specify)

BDE 2342 (Rev. 07/19/19)Page 4 of 8Printed 06/05/23

This section of the plan addresses the controls that will be implemented for each of the major construction activities described in Section I.C above and for all use areas, borrow sites, and waste sites. For each measure discussed, the Contractor will be responsible for its implementation as indicated. The Contractor shall provide to the Resident Engineer a plan for the implementation of the measures indicated. The Contractor, and subcontractors, will notify the Resident Engineer of any proposed changes, maintenance, or modifications to keep construction activities compliant with the Permit ILR10. Each such Contractor has signed the required certification on forms which are attached to, and are a part of, this plan:

A. Erosion and Sediment Controls: At a minimum, controls must be coordinated, installed and maintained to:

1. Minimize the amount of soil exposed during construction activity;

2. Minimize the disturbance of steep slopes;

3. Maintain natural buffers around surface waters, direct storm water to vegetated areas to increase sediment removal and maximize storm water infiltration, unless infeasible;

4. Minimize soil compaction and, unless infeasible, preserve topsoil.

B. Stabilization Practices: Provided below is a description of interim and permanent stabilization practices, including site- specific scheduling of the implementation of the practices. Site plans will ensure that existing vegetation is preserved where attainable and disturbed portions of the site will be stabilized.