About this file
This document is an Invitation for Bid (IFB) #2024-IFB-008 from the Village of Schaumburg, Illinois, soliciting bids for the 90 North Shared Street Construction project. The Village will accept electronic bids via their OpenGov e-Procurement Portal until 11:00 am on Thursday, February 15, 2024. The project involves comprehensive street construction with a detailed bid sheet listing 221 line items covering various construction activities including tree removal, earth excavation, soil placement, pavement work, utility installations, electrical work, landscaping, and detailed site furnishings. A pre-bid meeting is scheduled for February 5, 2024, at 2:00 pm via Microsoft Teams, and all questions must be submitted by February 12, 2024, by 4:00 pm.
The bid requires substantial documentation, including bid security of 10% of the total bid price, performance security, and various certifications related to employment practices, drug-free workplace, and compliance with state laws. Bidders must provide municipal government references and complete a comprehensive vendor questionnaire. The Village reserves the right to reject any bids and will award the contract based on various factors, including compliance, delivery capabilities, and overall responsiveness. Insurance requirements are extensive, including comprehensive general liability, automobile liability, workers' compensation, and umbrella coverage, with the Village named as an additional insured. Prevailing wage requirements and substance-abuse program certifications are also mandatory for the successful bidder.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION FOR BID
2024-IFB-008
90 NORTH SHARED STREET CONSTRUCTION
Village of Schaumburg
Atcher Municipal Center
Schaumburg, IL 60193
RELEASE DATE: January 30, 2024
DEADLINE FOR QUESTIONS: February 12, 2024
RESPONSE DEADLINE: February 15, 2024, 11:00 am
RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:
https://procurement.opengov.com/portal/villageofschaumburg
INVITATION FOR BID
90 North Shared Street Construction
I. Legal Notice II. Introduction
III. Instruction to Bidders IV. Scope of Work V. Insurance Requirements
VI. Bid Sheet(s) VII. Terms and Conditions
VIII. Supplemental Conditions - Construction Bids IX. Vendor Questionnaire
Attachments:
A - Engineering Plans Shared Street
B - Specifications Shared Street
C - Uncontaminated Soil Certification
D - Geotech Report
Invitation for Bid #2024-IFB-008 Title: 90 North Shared Street Construction
1. Legal Notice
1.1. Village of Schaumburg - Invitation for Bid
The Village of Schaumburg, IL will accept electronic bids via the Village's e-Procurement Portal, OpenGov
(https://procurement.opengov.com/portal/villageofschaumburg) for 2024-IFB-008, 90 North Shared
Street Construction.
Specifications and all Contract Documents are available via the Village’s e-Procurement Portal, OpenGov. Prices quoted must be valid for a minimum of 90 days from the date of the bid opening.
Bids will be received until 11:00 am on Thursday, February 15, 2024. All bid tabulations will be made publicly available after submission deadline.
The Village of Schaumburg reserves the right to reject any and all bids or to waive any technicalities, discrepancies, or information in the bids. The Village of Schaumburg does not discriminate in admission, access to, treatment, or employment in its programs and activities.
All questions regarding this Legal Notice and the actual bid specifications shall be submitted in writing through the OpenGov Question/Answer Tab via the Village's e-Procurement portal, on or before, Monday, February 12, 2024 by 4:00 pm. Please include the section title for each question, if applicable, in order to ensure that questions asked are responded to correctly. All questions submitted and answers provided shall be electronically distributed to bidders following this solicitation on the Village's e-
Procurement Portal.
Purchasing Division
2. Introduction
2.1. Summary
The Village of Schaumburg, IL will accept sealed bids via the Village's e-Procurement Portal, OpenGov
(https://procurement.opengov.com/portal/villageofschaumburg) for 2024-IFB-008, 90 North Shared
Street Construction to be received no later than Thursday, February 15, 2024, 11:00 am. Bids submitted after the specified time will not be accepted.
2.2. Background
Schaumburg is the largest center of economic development in the State of Illinois, outside the City of
Chicago. In addition to the 9.5 million square feet of retail and restaurant space, the village has over 12 million square feet of office space and 13.5 million square feet of industrial space.
With a daytime population of 150,000, thousands of businesses, 30 hotels, over 200 restaurants, highly educated workforce, superb location and high quality of life, Schaumburg is 'The Place for Business’.
2.3. Contact Information
Fred Mullard
Project Manager
120 Center Ct
Schaumburg, IL 60193
Email: fmullard@schaumburg.com
Phone: (224) 629-3755
Department:
Engineering and Public Works
Department Head:
Mike Hall
Department Director
2.4. Timeline
Release Project Date January 30, 2024
Pre-Bid Meeting (Non-Mandatory) February 5, 2024, 2:00pm
Microsoft Teams meeting
Meeting ID: 280 272 212 421
Passcode: 8ULdhz
Question Submission Deadline February 12, 2024, 4:00pm https://procurement.opengov.com/portal/villageofschaumburg mailto:fmullard@schaumburg.com tel:(224)629-3755
Bid Submission Deadline February 15, 2024, 11:00am
3. Instruction to Bidders
3.1. Intent
The intent of this Invitation for Bid is to enable the Village of Schaumburg's Department of Engineering and Public Works to establish relationships with vendors for 90 North Shared Street Construction.
This Invitation to Bid is open to all vendors actively engaged in supplying goods/services as specified herein. A detailed description of each item/service request is listed in this solicitation.
3.2. Contract Documents
Any drawings, plans, standard conditions, special conditions, supplemental additional conditions, specifications, bid notice, bid sheet, and addendum, if any, as specified herein shall form the “Contract
Documents.” For the purpose of this bid, the word “Village” shall refer to the Village of Schaumburg, and the word “Bidder” shall refer to any person, company, or entity submitting a bid. Any work shown or described in one of the documents shall be construed as if described in all the documents.
3.3. Interpretation of Contract Documents
Each request for interpretation of the Contract Documents shall be made in writing through the
OpenGov Question/Answer Tab via the District's e-Procurement portal, on or before, Monday, February
12, 2024 by 4:00 pm. Interpretations and supplemental instructions will be electronically distributed to bidders following this solicitation on the Village’s e-Procurement Portal.
3.4. Electronic Bid Documents
Bidders intending to respond to this opportunity must create a FREE account with OpenGov by signing up at https://procurement.opengov.com/signup. This step is necessary to establish a communication link with the Village. The Bidder, not the Village, is responsible for obtaining any addenda to the original specification. Addenda and other relevant information will be posted on the Village’s e-Procurement
Portal. Addenda notifications will be emailed to all persons on record as following this ITB. Failure of any bidder to receive any such addenda or interpretation shall not relieve such bidder from any obligation under their bid as submitted. All addenda so issued shall become part of the contract documents.
3.5. Withdrawal of Bid
Bids may be withdrawn through the Village's e-Procurement Portal, the responding firm may
“unsubmit” their proposal in OpenGov. After withdrawing a previously submitted proposal, the responding firm may submit another proposal at any time up to the deadline for submitting proposals prior to the bid opening. Bidders may withdraw or cancel their bid, in written form, at any time prior to the advertised bid opening time.
3.6. Bidder’s Qualifications
No award will be made to any Bidder who cannot satisfy to the Village that they have sufficient ability and experience in this class of work, as well as sufficient capital and equipment to do the job and complete the work successfully within the time named (i.e. responsible). The Village’s decision or judgment on these matters shall be final, conclusive, and binding. The Village may make such https://procurement.opengov.com/signup investigations as it deems necessary. The Bidder shall furnish to the Village, under oath if so required, all information and data the Village may request for the purpose of investigation.
3.7. Preparation of Bid
The Bidder’s submittal shall include all required Documents and any further specified documentation as pertaining to this solicitation. The Village will strictly hold the Bidder to the terms of the bid. The bid must be executed by a person having the legal right and authority to bind the Bidder.
4. Scope of Work
4.1. Scope of Work
The Bidder shall supply all required supervision, skilled labor, transportation, new materials, apparatus, and tools necessary for the entire and proper completion of the work. The Bidder shall supply, maintain, and remove all equipment for the performance of the work and be responsible for the safe, proper, and lawful construction, maintenance, and use of the same. This work shall be completed to the satisfaction of the Village. The Bidder shall provide adequate protection of the job site to protect the general public from any injury as a result of the job. The Bidder shall provide all safeguards and suitable barricades to protect public and adjacent property. The Village is not responsible for site safety. The Bidder is solely and exclusively responsible for construction means, methods, technologies, and site safety.
4.2. Licensing and Permits
The successful Bidder and their subcontractor(s) must be licensed with the Village and shall obtain all required building permits prior to the start of any work. The Village will waive applicable Village permit fees for the specific contract. Permit application forms may be obtained from the Community
Development Department and license application forms may be obtained from the Finance Department.
5. Insurance Requirements
5.1. Insurance
The Bidder will provide certificates of insurance evidencing the following types and limits of insurance.
The certificates of insurance will specifically address each of the requirements noted below. Each insurance company shall be acceptable to the Village. The General Liability coverage shall name the
Village of Schaumburg as additional insured. All insurance noted below is primary and in no event will be considered contributory to any insurance purchased by the Village. All insurance noted below will not be canceled, reduced, or materially changed without providing the Village thirty (30) days advance notice, via certified mail.
The Bidder will provide written Proof of Endorsement, with the General Liability policy number on the endorsement.
A. Comprehensive General Liability including Products Liability/Completed Operations insurance, in an amount not less than $1,000,000/occurrence, $2,000,000/policy limit, including Broad Form
Contractual Liability insurance, in an amount not less than $1,000,000/occurrence, $2,000,000/policy limit, subject to the terms and conditions of the policy. A copy of the policy may be required.
B. Automobile Liability insurance, in an amount not less than $1,000,000 combined single limit.
Said insurance is to be extended to cover hired and non-owned vehicles.
C. Umbrella or Excess Liability coverage, the Contractor shall provide evidence of Umbrella or
Excess Liability coverage of $2,000,000.
D. Workers’ Compensation is to be provided as required by statute, by an insurance company licensed to write worker’s compensation in the State of Illinois. Employer’s Liability, in an amount not less than $500,000 each accident, $500,000 disease – policy limit, and $500,000 disease – each employee.
E. Insurance Rating – All insurance policies required by this contract shall be underwritten by insurance companies with a minimum A. M. Best rating of A:VII.
F. A certificate of insurance is required as evidence of coverage, with the Village of Schaumburg named as an additional insured. The certificate will include an “Additional Insured
Endorsement”. The same full insurance coverage provided to the named insured, whether it is the contractor or a sub-contractor, shall be provided to the Village without any limitations or endorsements that might limit or exclude coverage. If insurance is canceled for any reason whatsoever the Village will be given not less than thirty (30) days prior written notice.
Any and all deductibles or other forms of retention are the responsibility of the Contractor. All deductibles or other forms of retention are subject to the approval of the Village. Contractor will disclose to the Village in writing the amounts of any deductible or self-insured retentions on the insurance required under this contract.
Contractor waives any right of subrogation it may have or later acquire against the Village.
The Bidder shall not commence work under this contract until they have obtained all insurance required under this section and such insurance has been approved by the Village, nor shall Bidder allow any subcontractor to commence work on their subcontract until the same insurance has been obtained by the subcontractor. The Bidder and their subcontractor(s) shall maintain all insurance required under paragraphs A through D of this Section for not less than one (1) year after completion of this contract.
6. Bid Sheet(s)
NOTICE TO BIDDERS: Failure to complete the following Bid Sheet(s) may be cause for rejection of your submittal. If you are not bidding on an entire group, please provide $0.00 as the cost for such items.
NOTE: Unit prices shall include the cost of delivery (if applicable).
TABLE 1
Line Item Description Quantity Unit of
Measure Unit Cost Total
1 TREE REMOVAL (6 TO 15 UNITS
DIAMETER)
13 UNIT
2 TEMPORARY FENCE 1,724 FOOT
3 EARTH EXCAVATION 10,584 CU YD
4 REMOVAL AND DISPOSAL OF
UNSUITABLE MATERIAL
2,385 CU YD
5 FURNISHED EXCAVATION 90 CU YD
6 POROUS GRANULAR EMBANKMENT 1,932 CU YD
7 TRENCH BACKFILL 3,219 CU YD
8 GEOTECHNICAL FABRIC FOR GROUND
STABILIZATION
544 SQ YD
9 TOPSOIL EXCAVATION AND
PLACEMENT
452 CU YD
10 TOPSOIL FURNISH AND PLACE, 4" 200 SQ YD
11 NITROGEN FERTILIZER NUTRIENT 73 POUND
12 PHOSPHORUS FERTILIZER NUTRIENT 65 POUND
13 POTASSIUM FERTILIZER NUTRIENT 60 POUND
14 SODDING, SALT TOLERANT 4,070 SQ YD
15 SUPPLEMENTAL WATERING 221 UNIT
Line Item Description Quantity Unit of
Measure Unit Cost Total
16 TEMPORARY EROSION CONTROL
SEEDING
85 POUND
17 TEMPORARY DITCH CHECKS 168 FOOT
18 PERIMETER EROSION BARRIER 3,282 FOOT
19 INLET AND PIPE PROTECTION 1 EACH
20 INLET FILTERS 24 EACH
21 TEMPORARY EROSION CONTROL
BLANKET
4,070 SQ YD
22 STONE RIPRAP, CLASS A3 267 SQ YD
23 FILTER FABRIC 862 SQ YD
24 AGGREGATE SUBGRADE
IMPROVEMENT
672 CU YD
25 SUBBASE GRANULAR MATERIAL, TYPE
B 2"
683 SQ YD
26 SUBBASE GRANULAR MATERIAL, TYPE
B 6"
6,346 SQ YD
27 BITUMINOUS MATERIALS (PRIME
COAT)
3,000 POUND
28 BITUMINOUS MATERIALS (TACK
COAT)
600 POUND
29 LONGITUDINAL JOINT SEALANT 849 FOOT
30 HOT-MIX ASPHALT PAVEMENT (FULL-
DEPTH), 10"
1,334 SQ YD
31 PROTECTIVE COAT 7,928 SQ YD
32 PORTLAND CEMENT CONCRETE
SIDEWALK 5 INCH
6,145 SQ FT
Unit Cost Total
33 PORTLAND CEMENT CONCRETE
SIDEWALK 10 INCH
33 SQ FT
34 PAVEMENT REMOVAL 135 SQ YD
35 COMBINATION CURB AND GUTTER
REMOVAL
125 FOOT
36 SIDEWALK REMOVAL 2,911 SQ FT
37 CLASS D PATCHES, TYPE I, 10 INCH 3 SQ YD
38 CLASS D PATCHES, TYPE IV, 10 INCH 42 SQ YD
39 PRECAST REINFORCED CONCRETE
FLARED END SECTIONS 30"
1 EACH
40 GRATING FOR CONCRETE FLARED END
SECTION 30"
1 EACH
41 STORM SEWERS, CLASS A, TYPE 1 12" 181 FOOT
42 STORM SEWERS, CLASS A, TYPE 2 12" 659 FOOT
43 STORM SEWERS, CLASS A, TYPE 2 15" 101 FOOT
44 STORM SEWERS, CLASS A, TYPE 2 24" 304 FOOT
45 STORM SEWERS, CLASS A, TYPE 2 30" 39 FOOT
46 STORM SEWERS, CLASS A, TYPE 2 54" 233 FOOT
47 STORM SEWERS, CLASS A, TYPE 2 72" 5 FOOT
48 STORM SEWERS, RUBBER GASKET,
CLASS A, TYPE 2 12"
37 FOOT
49 STORM SEWERS, RUBBER GASKET,
CLASS A, TYPE 2 24"
315 FOOT
50 STORM SEWERS, RUBBER GASKET,
CLASS A, TYPE 2 54"
31 FOOT
Unit Cost Total
51 STORM SEWER REMOVAL 12" 19 FOOT
52 STORM SEWER REMOVAL 18" 62 FOOT
53 STORM SEWER REMOVAL 24" 91 FOOT
54 STORM SEWER REMOVAL 72" 13 FOOT
55 PIPE UNDERDRAINS, TYPE 1, 4" 96 FOOT
56 CATCH BASINS, TYPE A, 4'-DIAMETER,
TYPE 8 GRATE
1 EACH
57 CATCH BASINS, TYPE A, 4'-DIAMETER,
TYPE 11 FRAME AND GRATE
5 EACH
58 CATCH BASINS, TYPE A, 5'-DIAMETER,
TYPE 11 FRAME AND GRATE
1 EACH
59 CATCH BASINS, TYPE C, TYPE 8 GRATE 3 EACH
60 CATCH BASINS, TYPE C, TYPE 11
FRAME AND GRATE
1 EACH
61 MANHOLES, TYPE A, 4'-DIAMETER,
TYPE 1 FRAME, CLOSED LID
5 EACH
62 MANHOLES, TYPE A, 5'-DIAMETER,
TYPE 1 FRAME, CLOSED LID
6 EACH
63 MANHOLES, TYPE A, 8'-DIAMETER,
TYPE 1 FRAME, CLOSED LID
2 EACH
64 MANHOLES, TYPE A, 9'-DIAMETER,
TYPE 1 FRAME, CLOSED LID
2 EACH
65 VALVE VAULTS, TYPE A, 5'-DIAMETER,
TYPE 1 FRAME, CLOSED LID
6 EACH
66 MANHOLES TO BE ADJUSTED 1 EACH
67 MANHOLES TO BE RECONSTRUCTED 1 EACH
Unit Cost Total
68 REMOVING MANHOLES 1 EACH
69 FILLING CATCH BASINS 1 EACH
70 COMBINATION CONCRETE CURB AND
GUTTER, TYPE B-6.12
2,608 FOOT
71 NON-SPECIAL WASTE DISPOSAL 2,240 CU YD
72 SOIL DISPOSAL ANALYSIS 1 EACH
73 REGULATED SUBSTANCES PRE-
CONSTRUCTION PLAN
1 L SUM
74 REGULATED SUBSTANCES FINAL
CONSTRUCTION REPORT
1 L SUM
75 REGULATED SUBSTANCES
MONITORING
30 CAL DA
76 ENGINEER'S FIELD OFFICE, TYPE A 15 CAL MO
77 MOBILIZATION 1 L SUM
78 TRAFFIC CONTROL AND PROTECTION,
STANDARD 701502
1 L SUM
79 TRAFFIC CONTROL AND PROTECTION,
STANDARD 701601
1 L SUM
80 TRAFFIC CONTROL AND PROTECTION,
STANDARD 701801
1 L SUM
81 TEMPORARY PAVEMENT MARKING -
LINE 6"- PAINT
188 FOOT
82 THERMOPLASTIC PAVEMENT
MARKING - LETTERS AND SYMBOLS
109 SQ FT
83 THERMOPLASTIC PAVEMENT
MARKING - LINE 4"
874 FOOT
Unit Cost Total
84 THERMOPLASTIC PAVEMENT
MARKING - LINE 6"
296 FOOT
85 THERMOPLASTIC PAVEMENT
MARKING - LINE 12"
39 FOOT
86 THERMOPLASTIC PAVEMENT
MARKING - LINE 24"
23 FOOT
87 PAINT PAVEMENT MARKING -
LETTERS AND SYMBOLS
12 SQ FT
88 PAINT PAVEMENT MARKING - LINE 4" 1,849 FOOT
89 PAINT PAVEMENT MARKING - LINE 6" 48 FOOT
90 PAINT PAVEMENT MARKING - LINE
24"
27 FOOT
91 PAVEMENT MARKING REMOVAL -
WATER BLASTING
375 SQ FT
92 ELECTRIC SERVICE INSTALLATION 2 EACH
93 ELECTRIC UTILITY SERVICE
CONNECTION
1 L SUM
94 UNDERGROUND CONDUIT,
GALVANIZED STEEL, 2 1/2" DIA.
300 FOOT
95 UNDERGROUND CONDUIT,
GALVANIZED STEEL, 4" DIA.
275 FOOT
96 UNDERGROUND CONDUIT, PVC, 1/2"
DIA.
1,894 FOOT
97 UNDERGROUND CONDUIT, PVC, 1"
DIA.
730 FOOT
98 UNDERGROUND CONDUIT, PVC, 2"
DIA.
405 FOOT
99 UNDERGROUND CONDUIT, PVC, 3"
DIA.
1,086 FOOT
Unit Cost Total
100 UNDERGROUND CONDUIT, PVC, 4"
DIA.
172 FOOT
101 UNDERGROUND CONDUIT, PVC, 6"
DIA.
405 FOOT
102 UNDERGROUND CONDUIT, COILABLE
NONMETALLIC CONDUIT, 1" DIA.
258 FOOT
103 UNDERGROUND CONDUIT, COILABLE
NONMETALLIC CONDUIT, 1 1/4" DIA.
68 FOOT
104 UNDERGROUND CONDUIT, COILABLE
NONMETALLIC CONDUIT, 3" DIA.
1,489 FOOT
105 UNIT DUCT, 600V, 3-1C NO.4, 1/C
NO.4 GROUND, (XLP-TYPE USE), 1
1/4" DIA. POLYETHYLENE
2,117 FOOT
106 ELECTRIC CABLE IN CONDUIT, 600V
(XLP-TYPE USE) 1/C NO. 3/0
440 FOOT
107 LIGHT POLE FOUNDATION, METAL,
15" BOLT CIRCLE, 8 5/8" X 6'
2 EACH
108 WEED CONTROL, PRE-EMERGENT
GRANULAR HERBICIDE
24 POUND
109 REMOVE ABANDONED GAS MAIN 119 FOOT
110 BIKE PATH REMOVAL 119 SQ YD
111 JUNCTION CHAMBER NO. 1 1 EACH
112 EXPLORATION TRENCH, SPECIAL 200 FOOT
113 DETECTABLE WARNINGS (SPECIAL) 278 SQ FT
114 WATER MAIN REMOVAL 317 FOOT
115 MANHOLES, SANITARY, 4'-DIAMETER,
TYPE 1 FRAME, CLOSED LID
8 EACH
Unit Cost Total
116 SANITARY MANHOLES TO BE
ADJUSTED
1 EACH
117 VALVE VAULTS TO BE REMOVED 1 EACH
118 SIGN PANEL - TYPE 1 (SPECIAL) 89 SQ FT
119 SIGN PANEL - TYPE 2 (SPECIAL) 20 SQ FT
120 TELESCOPING STEEL SIGN SUPPORT
(SPECIAL)
231 FOOT
121 BASE FOR TELESCOPING SIGN
SUPPORT, SPECIAL
6 EACH
122 LIGHTING CONTROLLER (SPECIAL) 1 EACH
123 LIGHT POLE FOUNDATION, 24"
DIAMETER, SPECIAL
250 FOOT
124 LIGHT POLE FOUNDATION, 24"
DIAMETER, OFFSET
24 FOOT
125 BREAKAWAY DEVICE, TRANSFORMER
BASE (SPECIAL)
26 EACH
126 GYPSUM PLACEMENT 1,036 POUND
127 CONCRETE TRUCK WASHOUT 1 L SUM
128 COMPOST FURNISH AND PLACE,
SPECIAL
192 CU YD
129 PAVEMENT MARKING (SPECIAL) 1,520 SQ FT
130 BARRICADES, TYPE III 3 EACH
131 STABILIZED CONSTRUCTION
ENTRANCE
146 SQ YD
132 CONSTRUCTION LAYOUT 1 L SUM
133 TEMPORARY INFORMATION SIGNING 100 SQ FT
Unit Cost Total
134 SANITARY SEWER 8" 593 FOOT
135 SANITARY SEWER 10" 319 FOOT
136 CATCH BASINS, TYPE A, 4'-DIAMETER,
DEPRESSED FRAME AND GRATE
14 EACH
137 CLEANOUT 15 EACH
138 OBSERVATION WELL 8 EACH
139 PIPE UNDERDRAINS, TYPE 1 (SPECIAL),
4"
652 FOOT
140 PIPE UNDERDRAINS, TYPE 2 (SPECIAL),
4"
1,070 FOOT
141 PORTLAND CEMENT CONCRETE
PAVEMENT 12", TYPE 1
1,195 SQ YD
142 PORTLAND CEMENT CONCRETE
PAVEMENT 12", TYPE 2
1,276 SQ YD
143 PERMEABLE CONCRETE PAVERS 18,836 SQ FT
144 4" X 16" CONCRETE PAVERS ON 8"
PCC SLAB
384 SQ FT
145 4" X 16" CONCRETE PAVERS ON 5"
PCC SLAB
8,518 SQ FT
146 8" X 24" CONCRETE PAVERS ON 5"
PCC SLAB
6,204 SQ FT
147 8" X 8" CONCRETE PAVERS ON 5" PCC
SLAB
923 SQ FT
148 FLUSH CONCRETE CURB 1,691 SQ FT
149 PLANTER CURB 1,879 FOOT
150 DUCTILE IRON WATER MAIN, 6"
(OPEN CUT)
91 FOOT
Unit Cost Total
151 DUCTILE IRON WATER MAIN, 8"
(OPEN CUT)
81 FOOT
152 DUCTILE IRON WATER MAIN, 10"
(OPEN CUT)
1,017 FOOT
153 DUCTILE IRON WATER MAIN, 12"
(OPEN CUT)
252 FOOT
154 DUCTILE IRON WATER MAIN, 16"
(OPEN CUT)
79 FOOT
155 DUCTILE IRON WATER MAIN FITTINGS
- ADDITIONAL
5,000 POUND
156 WATER VALVES, 8" 1 EACH
157 WATER VALVES, 10" 3 EACH
158 WATER VALVES, 12" 1 EACH
159 WATER VALVES, 16" 1 EACH
160 FIRE HYDRANT EXTENSION 6 FOOT
161 FIRE HYDRANT WITH AUXILIARY
VALVE AND VALVE BOX
5 EACH
162 CONNECT TO EXISTING WATER MAIN 3 EACH
163 WATER SERVICE CONNECTION 2" 1 EACH
164 FLUSH, PRESSURE TEST AND
CHLORINATE
1 L SUM
165 HYDRANT SIGNAGE 5 EACH
166 UNIT DUCT, 600V, 4-1C NO. 8, 3-1C
NO. 4, 1/C NO. 4 GROUND, (XLP-TYPE
USE), 1 1/2" DIA. POLYETHYLENE
1,060 FOOT
Unit Cost Total
167 UNIT DUCT, 600V, 3-1C NO. 4, 1/C
NO. 4 GROUND, (XLP-TYPE USE), 1
1/2" DIA. POLYETHYLENE
144 FOOT
168 UNIT DUCT, 600V, 4-1C NO. 8, 6-1C
NO. 4, 1/C NO. 4 GROUND, (XLP-TYPE
USE), 2" DIA. POLYETHYLENE
1,553 FOOT
169 ELECTRIC CABLE IN CONDUIT, 600V
(XLP-TYPE USE) 3-1/C NO. 14, 1/C NO.
14 GROUND
2,196 FOOT
170 ELECTRIC CABLE IN CONDUIT, 600V
(XLP-TYPE USE) 3-1/C NO. 8, 1/C NO. 8
GROUND
522 FOOT
171 ELECTRIC CABLE IN CONDUIT, 600V
(XLP-TYPE USE) 4-1/C NO. 4
200 FOOT
172 LUMINAIRE, LED, TYPE 1 22 EACH
173 LUMINAIRE, LED, TYPE 2 2 EACH
174 SECURITY BOLLARD WITH
PEDESTRIAN LIGHTING
47 EACH
175 SECURITY BOLLARD FOUNDATION,
18" X 18" X 36"
47 EACH
176 FESTOON LIGHTING 1 LSUM
177 LIGHT POLE, 20 FT. ROUND TAPERED
STEEL
4 EACH
178 LIGHT POLE, SPECIAL, TYPE 1 24 EACH
179 LIGHT POLE, SPEICAL, TYPE 2 2 EACH
180 TREE OUTLET PEDESTAL BOX, DOUBLE
GANG
23 EACH
181 TREE OUTLET PEDESTAL BOX
FOUNDATION
23 EACH
Unit Cost Total
182 LIGHT POLE, SPECIAL (FURNISH ONLY) 3 EACH
183 LUMINAIRE, LED, TYPE 1 (FURNISH
ONLY)
2 EACH
184 LUMINAIRE, LED, TYPE 2 (FURNISH
ONLY)
1 EACH
185 BREAKAWAY DEVICE, TRANSFORMER
BASE (SPECIAL) (FURNISH ONLY)
1 EACH
186 HANDHOLE, COMPOSITE CONCRETE
12" X 12"
9 EACH
187 HANDHOLE, COMPOSITE CONCRETE
13" X 24"
4 EACH
188 WEATHERPROOF ENCLOSURE 8 EACH
189 MEDIAN SOIL MIX FURNISH AND
PLACE
679 CU YD
190 INFILTRATION SOIL MIX FURNISH AND
PLACE
237 CU YD
191 TRASH RECEPTACLE 2 EACH
192 PLANTER SEAT WALL 88 LIN FT
193 BIKE RACK 6 EACH
194 REMOVABLE BOLLARD 16 EACH
195 METAL BENCH 4 EACH
196 PRECAST CUBE 6 EACH
197 PLANTER 45 EACH
198 STONE STEPS 1 LSUM
Unit Cost Total
199 PERENNIAL PLANT, ALLIUM
TANGUTICUM, SUMMER BEAUTY
ONION, 1 GALLON, CONTAINER
GROWN
227 EACH
200 PERENNIAL PLANT, AQUILEGIA
CANADENSIS, WILD COLUMBINE, 1
GALLON, CONTAINER GROWN
58 EACH
201 PERENNIAL PLANT, ASCLEPIAS
INCARNATA, SWAMP MILKWEED, 1
GALLON, CONTAINER GROWN
15 EACH
202 PERENNIAL PLANT, BOUTELOUA
GRACILIS, BLUE GRAMA, 1 GALLON,
CONTAINER GROWN
442 EACH
203 PERENNIAL PLANT, CALAMINTHA
NEPETA, LESSER CATMINT, 1 GALLON,
CONTAINER GROWN
246 EACH
204 PERENNIAL PLANT, CAREX
SPRENGELII, LONG-BEAKED SEDGE, 1
GALLON, CONTAINER GROWN
107 EACH
205 PERENNIAL PLANT, CAREX
VULPINOIDEA, BROWN FOX SEDGE, 1
GALLON, CONTAINER GROWN
241 EACH
206 PERENNIAL PLANT, CHELONE GLABRA,
WHITE TURTLEHEAD, 1 GALLON,
CONTAINER GROWN
117 EACH
207 PERENNIAL PLANT, HEMEROCALLIS
SPP, GOING BANANAS DAYLILY, 1
GALLON, CONTAINER GROWN
66 EACH
208 PERENNIAL PLANT, IRIS VIRGINICA,
VIRGINIA BLUE FLAG IRIS, 1 GALLON,
CONTAINER GROWN
53 EACH
209 PERENNIAL PLANT, LOBELIA
SIPHILITICA, BLUE LOBELIA, 1 GALLON,
CONTAINER GROWN
99 EACH
Unit Cost Total
210 PERENNIAL PLANT, NEPETA X
RACEMOSA, WALKERS LOW CATMINT,
1 GALLON, CONTAINER GROWN
60 EACH
211 PERENNIAL PLANT, PENSTEMON
DIGITALIS, BEARDTONGUE, 1 GALLON,
CONTAINER GROWN
39 EACH
212 PERENNIAL PLANT, PTEROCAULON
PYCNOSTACHEUM, BLACKROOT, 1
GALLON, CONTAINER GROWN
17 EACH
213 PERENNIAL PLANT, RUDBECKIA
FULGIDA, BLACK EYED SUSAN, 1
GALLON, CONTAINER GROWN
72 EACH
214 PERENNIAL PLANT, SALVIA
NEMEROSA, CARADONNA SAGE, 1
GALLON, CONTAINER GROWN
245 EACH
215 PERENNIAL PLANT, SCHYZACHYRIUM
SCOPARIUM, LITTLE BLUESTEM, 1
GALLON, CONTAINER GROWN
167 EACH
216 SHRUB, CORNUS SERICEA 'CARDINAL',
CARDINAL DOGWOOD, 5 GALLON,
CONTAINER GROWN
25 EACH
217 SHRUB, CORNUS SERICEA 'SMNCSBD',
ARCTIC FIRE YELLOW DOGWOOD, 3
GALLON, CONTAINER GROWN
18 EACH
218 TREE, BETULA NIGRA, 2"-2.5"
CALIPER, BALLED AND BURLAPPED
4 EACH
219 TREE, NYSSA SYLVATICA, 2"-2.5"
CALIPER, BALLED AND BURLAPPED
6 EACH
220 TREE, QUERCUS BICOLOR, 2"-2.5"
CALIPER, BALLED AND BURLAPPED
3 EACH
221 TREE, TAXODIUM DISTICHUM, 2"-2.5"
CALIPER, BALLED AND BURLAPPED
6 EACH
Unit Cost Total
TOTAL
7. Terms and Conditions
7.1. Compliance with Laws
The Bidder shall at all times observe and conform to all laws, ordinances, and regulations of the Federal, State, and local governments, which may in any manner affect the preparation of bids or the performance of the contract.
7.2. Alternate
Any reference in these specifications to manufacturer’s name, trade name, or catalog number (unless otherwise specified) is intended as a standard only. The Village’s written decision of approval or disapproval of a proposed substitution shall be final.
Alternate bids will be considered only if received at the time stated for receipt of the bids. Bidders are cautioned that, if an alternate bid(s) involves an increase in the Bid Sum, the Bid Deposit, if required, shall be ample or be increased to cover the alternate Bid Sum or the entire bid may be rejected.
7.3. Freedom of Information Act (FOIA)
The Village is required by Public Act 96-542 to comply with freedom of information requests (FOIA) within five (5) business days of a record request. All contractors used by the Village may be in possession of records covered by this act and therefore will be required to provide the Village with those records upon request and within the time frame of the Act.
7.4. Confidentiality
As a public agency, the Village is required to adhere to Freedom of Information Public Act 96-542. If a responding firm intends to request confidentiality on any portion of a bid, the submittal shall also include a redacted copy of the bid. Limited redactions will be considered. However, entire full redaction of bid submittals will not be considered for award. If a redacted copy is not provided, the original submittal may be released by the Village as received.
7.5. Bid Review
The Village reserves the right to reject any or all bids and/or to waive any irregularities or disregard any informality in the bids and bidding when, in its opinion, the best interest of the Village will be served by such action. Furthermore, the Village reserves the right to award each item to a different Bidder, or all items to a single Bidder unless otherwise noted on in this solicitation. The Village may determine as follows: 1) an equal or alternative is a satisfactory substitute; 2) an early delivery date is entitled to more consideration than price; 3) an early delivery date is to be disregarded because of the reputation of the
Bidder for not meeting delivery dates; 4) a Bidder is not a responsible Bidder; and 5) what exceptions or deviations from written specifications will be accepted.
No bid will be accepted from or contract awarded to any person, firm, or corporation that is in arrears or is in default to the Village upon any debt or contract, or that is a defaulter, as surety or otherwise, upon any obligation to the Village, or had failed to perform faithfully any previous contract with the Village.
7.6. Form of Contract
The form of contract between the Village and the successful Bidder will be a purchase order referencing the bid specification, the bid submitted by the successful Bidder, and the resulting purchasing order.
7.7. Bid Results
Following the bid opening, bid tabulations will be posted on the Village’s e-Procurement Portal. Bid tabulations posted on-line represent “as read” submittals at time of the bid opening. They do not represent contract award. Final awards will be posted when approved.
7.8. Delivery
Where applicable, all materials shipped to the Village must be shipped F.O.B. delivered, designated location, Schaumburg, Illinois. If the delivery is made by truck, arrangements must be made in advance by the Bidder, with concurrence by the Village, for receipt of the materials. The materials must be delivered where directed. Truck deliveries will be accepted at the Public Works Facility between 7:00 a.m. and 3:30 p.m. and at all other Village locations 8:00 a.m. and 4:00 p.m., weekdays only.
NOTE: The Public Works Facility does have a raised loading dock. All other Village locations do not have access to a raised loading dock. Deliveries requiring removal from the delivery truck via a forklift provided by the Village must be arranged with the Village twenty-four (24) hours in advance of the expected delivery date.
7.9. Inspections
The Village shall have the right to inspect any materials, components, equipment, supplies, services, or completed work specified herein. Any of said items not complying with these specifications are subject to rejection at the option of the Village. Any items rejected shall be removed from the premises of the
Village and/or replaced at the entire expense of the successful Bidder.
7.10. Prevailing Wage
Not less than the Prevailing Wages as found by the Illinois Department of Labor (IDOL) or determined by the court on review shall be paid to laborers, workmen, and mechanics performing work under this contract. Current standards are available on the Illinois Department of Labor website at www.state.il.us/agency/idol/ (820 ILCS 130/1 et. seq.) (Wages of employees on Public Works –
Prevailing Wage Act, Illinois Revised Statutes, Chapter 48, Section 39S-1 et seq.) Contractors are responsible for paying prevailing wage, when required, based on the most current IDOL standards, throughout the term of the contract.
In 2018, the Illinois General Assembly passed legislation to make changes to the certified payroll portion of the Prevailing Wage Act. When Governor Pritzker took office in 2019, SB 203 was signed into law (PA
100-1177). Prior to the law, certified payrolls were submitted to the local or state public body funding the project. Under the new law, the Illinois Department of Labor is charged with developing and maintaining an online portal where all prevailing wage construction contractors file their certified payrolls with the department, otherwise known as Certified Transcript of Payroll portal.
820 ILCS 265/15 requires the successful contractor, before work commences, to file with the Public Body certification that they have a substance-abuse program and provide drug testing.
7.11. Payment
Payment shall be made within 30 days of invoice receipt and approval, unless otherwise specified in the agreed upon contract. All invoices must include the PO number associated with the order and shall be submitted to the Village of Schaumburg, Accounts Payable Division, 101 Schaumburg Court, Schaumburg, IL 60193. If prevailing wage is a requirement of the contract, the invoice must include IDOL filing certificate and waivers. Failure to submit all documentation as specified may result in delay of invoice payment.
7.12. Period of Unemployment
Public Act 30 ILCS 570 Employment of Illinois Workers on Public Works Act must be adhered to in entirety by the awarded contractor. This act requires the use of Illinois workers on Public Works projects during periods of excess unemployment, which means any month immediately following 2 consecutive calendar months during which the level of unemployment in the State of Illinois has exceeded 5% as measured by the United States Bureau of Labor Statistics in its monthly publication of employment and unemployment figures. Due to the COVID-19 pandemic, this provision is currently applicable.
7.13. Toxic Substance
Prior to delivery of any material which is caustic, corrosive, flammable, or dangerous to handle, the supplier will provide written directions as to methods of handling such products, as well as the antidote or neutralizing material required for its first aid. (Materials Safety Data Sheet).
7.14. Guarantees and Warranties
All guarantees and warranties required shall be furnished by the Bidder and shall be delivered to the
Village before final payment on the contract is issued.
7.15. Termination of Contract
The Village reserves the right to terminate in whole or any part of this contract, upon written notice to the Bidder, in the event of default by the Bidder. Default is defined as failure of the Bidder to perform any of the provisions of this contract or failure to make sufficient progress so as to endanger performance of this contract in accordance with its terms. In the event of default and termination, the
Village may procure, upon such terms and in such a manner as the Village may deem appropriate, supplies, or services similar to those terminated. The Bidder shall be liable for any excess costs for such similar supplies or service unless evidence is submitted to the Village that, in the sole opinion of the
Village, clearly proves that failure to perform the contract was due to causes beyond the control and without the fault or negligence of the Bidder.
8. Supplemental Conditions - Construction Bids
8.1. Examination of Premises, Measurements, and Elevations
The Bidder shall verify all measurements relative to the work, shall be responsible for the correctness of same. The Bidder will examine the site and the premises and satisfy themselves as to the existing conditions under which the Bidder will be obligated to operate. Failure of the Bidder to notify the
Village, in writing, of any condition(s) or measurement(s) making it impossible to carry out the work as shown and specified, will be construed as meaning no such conditions exist and no additional moneys will be added to the contract. The successful Bidder must notify all utility companies that are a part of
J.U.L.I.E. of the responsibility of each utility company to locate its utilities. The Village will not accept any liability or pay any additional costs in the event any unknown utilities are uncovered which may result in the redesign, delay, or need for additional equipment on the job site.
No claim whatsoever will be allowed to any contract for changes, extra work, or material, not included in the Bidder’s original bid, or for a greater amount of money than the contract states is to be paid, for any reason, including, but not limited to subsurface or latent physical conditions, or unknown physical conditions at the site. The Bidder is responsible for making a full examination of the site of the proposed work, and bid documents, specifications, general conditions, plans, special provisions, and contract forms before submitting their bid. The Bidder is responsible for fully informing themselves as to the quality and quantity of materials required, and the character of the work to be performed.
8.2. Change Orders
After the contract award, changes in or additions to the work and/or a change in the amount of money to be paid to the Bidder must be the result of an approved change order first ordered by the Director of the lead department and approved by the Village Manager and/or the Village Board.
50 ILCS 525/5 require the successful contractor verify any change order request you receive from a subcontractor will not exceed 49% of your original subcontract amount. Any needed change order that will increase the subcontract by 50% or more will require your opening up that portion of the work to competitive bidding.
8.3. Failure to Execute
Failure to execute the contract shall, at the option of the Village, constitute a breach of the agreement made by acceptance of the bid, and the Village shall be entitled to forfeiture of the certified check, bank draft, or Bid Bond accompanying the bid that is required, not as a penalty, but as liquidated damages. In the event of failure of a Bidder to whom an award of contract has been made, to execute the contract and furnish a Performance Bond within ten (10) days after notification of award, such award may be nullified and an award may be made to the next lowest responsive and responsible Bidder approved by the Village.
8.4. Bid Security
Each bid shall be accompanied by a bid security in the amount of 10% of the total amount bid. Bid security shall be in the form of a certified check or cashier’s check, drawn on a responsible bank doing business in the United States and made payable to the Village of Schaumburg, or a Bid Bond by a surety company which is satisfactory to the Village and is qualified to do business in Illinois.
Electronic copies are acceptable for submission, with the original being submitted no later than
Thursday, February 15, 2024, 11:00 am to:
Village of Schaumburg
Purchasing Division
Atcher Municipal Center
101 Schaumburg Ct
Schaumburg, IL 60193
Electronically produced bid security, with digital signature and notary stamp, will be acceptable. Bids not accompanied by a bid security will be rejected. The bid security of the unsuccessful Bidders (if in the form of a certified check or cashier’s check) will be returned after the contract is awarded, or earlier, if the Village does not deem it necessary to retain the Bid Security. The bid security of the accepted
Bidder, (if in the form of a certified check or cashier’s check) will be returned either upon execution of a contract and submittal of a performance bond, if required by the specifications, or where no performance bond is required, when, in the Village’s estimation, the contract has been satisfactorily completed. When the bid security is submitted in the form of a bid bond, the bond will become null and void following the award of contract and the Village’s receipt of the Performance Bond, if required by the specifications. Should the Bidder fail to fulfill the contract as set forth, the bid security shall become payable to the Village as liquidated damages.
8.5. Performance Security
The successful Bidder shall furnish as performance security a Performance Bond acceptable to the
Village prior to the start of any work. The bond shall be in the sum of 100% of the contract amount. The performance bond shall: 1) serve as security for faithful performance of the work; and 2) guarantee the work against defective workmanship and material for a period of not less than one (1) year following acceptance of the work. For contract awards that are less than $100,000.00, a Letter of Credit, in a form suitable to the Village, may be submitted as performance security, instead of a Performance Bond.
8.6. Waiver of Lien
Where applicable, a Waiver of Lien and Contractor’s Affidavit must be submitted by the Bidder, verifying that all subcontractors and material invoices have been paid prior to the Village approving final payment.
9. Vendor Questionnaire
9.1. Authorized Person(s)*
Please provide the following information for each person(s) authorized to submit a response on behalf of your organization:
Name
Title
Phone Number
Email Address
*Response required
9.2. Equal Employment Opportunity Clause*
EQUAL EMPLOYMENT OPPORTUNITY CLAUSE required by the Illinois Fair Employment Practices
Commission as a material term of all public contracts.
During the performance of this contract, the contractor agrees as follows:
A. That it will not discriminate against any employee or applicant for employment because of race, color, religion, sex, national origin, or ancestry; and further, that it will examine all job classifications to determine if minority persons or women are underutilized and will take appropriate affirmative action to rectify any such under utilization.
B. That, if it hires additional employees in order to perform this contract, or any portion hereof, it will determine the availability (in accordance with the Commission’s Rules and Regulations for
Public Contracts) of minorities and women in the area(s) from which it may reasonably recruit and it will hire for each job classification for which employees are hired in such a way that minorities and women are not underutilized.
C. That, in all solicitations or advertisements for employees placed by it or on its behalf, it will state that all applicants will be afforded equal opportunity without discrimination because of race, color, religion, sex, national origin, or ancestry.
D. That it will send to each labor organization or representative of workers with which it has or is bound by a collective bargaining or other agreement or understanding, a notice advising such labor organization or representative of the contractor’s obligations under the Illinois Fair
Employment Practices Act and the Commission's Rules and Regulations for Public Contracts. If any such labor organization or representative fails or refuses to cooperate with the contractor in its efforts to comply with such Act and Rules and Regulations the contractor will promptly so notify the Illinois Fair Employment Practices Commission and the contracting agency and will recruit employees from other sources when necessary to fulfill its obligations there under.
E. That it will submit reports as required by the Illinois Fair Employment Practices Commission’s
Rules and Regulations for Public Contracts, furnish all relevant information as may from time to time be requested by the Commission or the contracting agency, and in all respects comply with the Illinois Fair Employment Practices Act and the Commission’s Rules and Regulations for Public
Contracts.
F. That it will permit access to all relevant books, records, accounts, and work sites by personnel of the contracting agency and the Illinois Fair Employment Practices Commission for purposes of investigation to ascertain compliance with the Illinois Fair Employment Practices Act and the
Commission’s Rules and Regulations for Public Contracts.
G. That it will include verbatim or by reference the provisions of paragraphs 1 through 7 of this clause in every performance subcontract as defined in Section 2.10 (b) of the Commission's
Rules and Regulations for Public Contracts so that such provision will be binding upon every such subcontractor; and that it will also include the provisions of paragraphs 1,5, 6, and 7 in every supply subcontract as defined in Section 2.10(a) of the Commission’s Rules and
Regulations for Public Contracts so that such provisions will be binding upon every such subcontractor. In the same manner as with other provisions of this contract, the contractor will be liable for compliance with applicable provisions of this clause by all its subcontractors; and further it will promptly notify the contracting agency and the Illinois Fair Employment Practices
Commission in the event any subcontractor fails or refuses to comply therewith. In addition, no contractor will utilize any subcontractor declared by the Commission to be non-responsible and therefore ineligible for contracts or subcontracts with the State of Illinois or any of its political subdivisions or municipal corporations.
The Village of Schaumburg does not discriminate on the basis of disability status in admission or access to, or treatment or employment in, its programs and activities.
☐ Please confirm
*Response required
9.3. Alternates*
Please provide any proposed substitution to the specifications in this solictation for consideration by the
Village of Schaumburg. If you will not be requesting any alternates, please provide a document stating that.
*Response required
9.4. Bid Security *
Each bid shall be accompanied by a certified cashier’s check, or bid bond, in the amount of ten percent
(10%) of the total bid price, payable to Village of Schaumburg, Illinois, as a guarantee that the bidder, if its bid is accepted, will promptly execute the Agreement.
Please upload a copy of your bid bond/cashier's check. Bidder must also submit an original copy of the bid guarantee to be received no later thanThursday, February 15, 2024 addressed to:
Purchasing Division
Jillian Ostman
Atcher Municipal Center
101 Schaumburg Ct
Schaumburg, IL 60193
Please have the Bidder Name, Contract Title ("90 North Shared Street Construction"), and Contract
Number ("2024-IFB-008") listed clearly on the outside of the envelope.
*Response required
9.5. Performance Security*
The successful Bidder shall furnish as performance security a Performance Bond acceptable to the
Village prior to the start of any work. Each of the bonds shall be in the sum of 100% of the contract amount. The performance bond shall: 1) serve as security for faithful performance of the work; and 2) guarantee the work against defective workmanship and material for a period of not less than one (1) year following acceptance of the work. For contract awards that are less than $100,000.00, a Letter of
Credit, in a form suitable to the Village, may be submitted as performance security, instead of a
Performance Bond.
☐ Please confirm
*Response required
9.6. Bid Sheet*
By submitting a response to this solicitation, the authorized person(s), confirms having examined the specifications and all conditions affecting the specified project, offer to furnish all services, labor, and incidentals specified for the price as provided with their response.
The Bidder certifies that they are not barred from bidding on this contract as a result of a conviction for the violation of state laws prohibiting bid rigging or bid rotating, (720ILCS 5/33E-1, et seq.) and is not delinquent in any taxes to the Illinois Department of Revenue. (65ILCS 5/11-42.1-1)
It is understood that the Village reserves the right to reject any and all bids and to waive any irregularities and that the prices contained herein will remain valid for a period of not less than sixty (60) days.
The bidder proposes to complete the following project as more fully described in the specifications for the following: in this solicitation document.
☐ Please confirm
*Response required
9.7. Subcontractor Utilization*
If it is the Contractor’s intention to utilize a subcontractor(s) to fulfill the requirements of this contract, the Village must be advised of the subcontractor’s company name, address, telephone and fax numbers, and a contact person’s name at the time of bid submittal.
☐ Please confirm
*Response required
9.8. Subcontractor*
Will you be utilizing a subcontractor?
☐ Yes
☐ No
*Response required
9.9. Subcontractor Information*
Please provide the following information for each subcontractor that will be utilized on this project:
Subcontractor's Company Name
Address
Telephone
Email Address
Contact Person's Name at the time of Bid Submittal
If no subcontractor will be utilized, please type "N/A".
*Response required
9.10. Indemnification*
The Bidder hereby agrees to protect, defend, indemnify, and save harmless the Village against loss, damage, or expense from any suit, claim, demand, judgment, cause of action, or shortage initiated by any person whatsoever, arising or alleged to have arisen out of work described herein, except that in no instance shall the Bidder be held responsible for any liability, claim, demand, or cause of action attributable solely to the negligence of the Village.
☐ Please confirm
*Response required
9.11. Not Barred by Law*
By submitting a response to this solicitation, the bidder hereby certifies that the item(s) proposed is/are in accordance with the specifications as noted and that the prices quoted are not subject to change; and that on behalf of the organization, is not barred by law from submitting a bid to the Village for the project contemplated herein because of a conviction for prior violations of either Illinois Compiled
Statutes, 720 ILCS 5/33E-3 (Bid Rigging) or 720 ILCS 5/33-4 (Bid Rotating).
☐ Please confirm
*Response required
9.12. Not Delinquent in Payment*
By submitting a response to this solicitation, the bidder hereby certifies that the item(s) proposed is/are in accordance with the specifications as noted and that the prices quoted are not subject to change; and that on behalf of the organization, is not delinquent in payment of any taxes to the Illinois Department of Revenue in accordance with 65 ILCS 5/11-42.1.
☐ Please confirm
*Response required
9.13. Drug-Free Workplace*
By submitting a response to this solicitation, the bidder hereby certifies that the item(s) proposed is/are in accordance with the specifications as noted and that the prices quoted are not subject to change; and that on behalf of the organization, provides a drug free workplace pursuant 30 ILCS 580/1, et seq.
☐ Please confirm
*Response required
9.14. Substance-Abuse Program*
By submitting a response to this solicitation, the bidder hereby certifies that the item(s) proposed is/are in accordance with the specifications as noted and that the prices quoted are not subject to change; and that on behalf of the organization, certifies they have a substance-abuse program and provide drug testing in accordance with 820 ILCS 265/1 et. seq., Public Act 095-0635
☐ Please confirm
*Response required
9.15. Illinois Human Rights Act*
By submitting a response to this solicitation, the bidder hereby certifies that the item(s) proposed is/are in accordance with the specifications as noted and that the prices quoted are not subject to change; and that on behalf of the organization, is in compliance with the Illinois Human Rights Act 775 ILCS 5/1.101, et seq. including establishment and maintenance of sexual harassment policies and program.
☐ Please confirm
*Response required
9.16. Detail Exceptions Sheet*
Any exceptions must be clearly noted on the Detail Exceptions Sheet(s). Failure to do so may be reason for rejection of the bid. It is not our intention to prohibit any potential Bidder from bidding by virtue of the specifications, but to describe the material and services actually required. The Village reserves the right to accept or reject any or all exceptions.
DETAIL EXCEPTIONS SHEET MUST BE SUBMITTED WITH THE BID RESPONSE.
Please download the below documents, complete, and upload.
• Detail_Exceptions_Sheet.pdf https://government-project.s3.us-west-2.amazonaws.com/7998/765d8853-9d7d-4d01-b4d9-dda54159cee8_Detail_Exceptions_Sheet.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=AKIARC2J5PZDCCU66EXN%2F20240213%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20240213T180518Z&X-Amz-Expires=72000&X-Amz-Signature=ee8a6ae95aef2c79488f84850f3cdf46c3ef05f2005ed2817813d578bf4a1088&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22Detail_Exceptions_Sheet.pdf%22&x-id=GetObject
9.17. Provide 3 Municipal Government References*
Project Name: _______________________
Year Completed: _____________________
Location and Agency: _________________
Contact Person Name and Number: _____
9.18. Upload any additional project docs (not required)