About this file
Navajo State Park Water and Irrigation System Improvements
This specification document outlines the comprehensive construction project for the Navajo State Park Water and Irrigation System Improvements, administered by the Colorado Parks and Wildlife (CPW) division of the Department of Natural Resources. The project, identified as C15NJ1 with RQS 2017*621, encompasses the construction of a new water treatment facility, booster pump station, concrete water storage tank, wellhouse, monitoring well, access roads, and associated distribution piping and electrical systems. A mandatory pre-bid conference was scheduled for Wednesday, January 4, 2017, at 1:00 p.m., with bid opening on Thursday, January 19, 2017, at 1:30 p.m. The project scope includes process equipment installation (sodium hypochlorite metering pumps, water softening systems, chlorine analyzers), booster pump station construction with four Grundfos CR Series pumps, distribution piping in various sizes and materials (PVC and ductile iron), five fire hydrants, improvements to existing wells (installation of variable frequency drives and submersible pumps), and associated site development including new access roads, irrigation headgates, and yard piping for multiple service needs.
The contract requires the contractor to furnish all labor, materials, equipment, and incidental items necessary for complete project performance. Payment will be made on a lump-sum basis for mobilization, with 50 percent paid at 10 percent completion and the remaining 50 percent upon equipment removal from the site. Separate pricing is required for nine base bid groups covering process equipment and piping, booster pump systems, distribution piping and well improvements, site civil work for both the water treatment facility and wellhouse areas, residuals pond construction, electrical and mechanical systems, building and architectural elements, and the partially-buried concrete water tank. The project emphasizes strict adherence to water quality standards, environmental protection measures, and coordination with existing water system operations to maintain potable water supply throughout construction. Contractor responsibilities include obtaining all required permits (CDPHE approval, Colorado Department of Transportation permits, construction stormwater discharge permits), conducting equipment startup and commissioning, providing comprehensive testing and documentation, and maintaining detailed as-constructed records and record drawings upon project completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Drawings Part 1.pdf | ||
| Parks_GRCs.pdf | ||
| NSP- Elec.&Mech. Plans.pdf | ||
| Drawings Part 7.pdf | ||
| Drawings Part 4.pdf | ||
| Addend-1-Memo.pdf | ||
| Drawings Part 9.pdf | ||
| Drawings Part 3.pdf | ||
| Drawings Part 8.pdf | ||
| Drawings Part 5.pdf | ||
| Drawings Part 11.pdf | ||
| Drawings Part 6.pdf | ||
| Pre-bid sign in sheet 2017-01-04.pdf | ||
| Drawings Part 10.pdf | ||
| Specifications Part 2.pdf | ||
| Bidding Information.pdf | ||
| Bid Bond.doc | DOC document | |
| Drawings Part 12.pdf | ||
| Drawings Part 2.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Navajo State Park - Water and Irrigation System Improvements
DIVISION I – SPECIFICATIONS
PROJECT I.D. NO. C15NJ1
RQS: 2017*621
APPR. CODE RMNJ
MANDATORY PRE-BID CONFERENCE: Wednesday, January 4, 2017 at 1:00 p.m.
BID OPENING: Thursday, January 19, 2017 at 1:30 p.m.
(Page Intentionally Left Blank)
TABLE OF CONTENTS
Navajo State Park - Water and Irrigation System Improvements
C15NJ1
Division 1 - General Requirements
Section 01000 - General Requirements Section 01010 - Summary of Work Section 01023 – Minor Contract Revision Section 01000 - General Requirements Section 01010 - Summary of Work Section 01023 – Minor Contract Revision Section 01025 – Measurement and Payment Section 01050 – Field Survey Section 01100 – Alternate Products Section 01200 - Meetings Section 01300 – Submittals Section 01310 – Construction Schedules Section 01320 – Product Delivery, Handling, Storage & Inspection Section 01340 – Shop Drawings Section 01410 – Laboratory Tests Section 01450 – Testing and Inspection Section 01500 – Construction and Temporary Facilities Section 01570 – Traffic Control Section 01580 – Construction Surveying Section 01590 – Stormwater Management and Erosion Control Section 01600 – General Mechanical and Equipment Provisions Section 01631 – Request for Substitution Section 01650 – Starting of Systems Section 01700 – Contract Closeout
Division 2 - Site Work
Section 02050 - Mobilization Section 02065 – Asphalt Removal Section 02066 – Asphalt Pulverization Section 02101 – Removal of Structures and Obstruction Section 02111 – Vegetation Clearing and Grubbing Section 02112 – Tree Removal Section 02140 – Dewatering Section 02200 – Earthwork Section 02201 – Excavation and Backfill for Structures Section 02210 – Finish Grading Section 02221 – Trenching, Backfilling and Compaction Section 02222 – Embedment and Base Course Aggregate Section 02262 – Filter Materials Section 02275 – Geotextile Fabric Section 02279 – Water Quality Control Section 02513 – Bituminous Pavement Section 02545 – Aggregate Base Course Section 02580 – Pavement Marking Section 02610 – Pipe and Fittings
Section 02640– Valves and Gates Section 02645 – Fire Hydrants Section 02840 – Guardrails Section 02934 – Seeding and Mulching Section 02950 – Trees, Plants and Ground Cover
Division 3 – Concrete
Section 03100 – Concrete Formwork Section 03150 – Concrete Joints and Accessories Section 03210 – Concrete Reinforcement Section 03300 - Cast in Place Concrete
Division 4 - Masonry
Section 04200 - Masonry
Division 5 - Metals
Section 05100 – Structural Metal Framing Section 05313 – Steel Roof and Floor Deck Section 05510 – Miscellaneous Metalwork Section 05720 – Railings and Handrails
Division 6 – Wood and Plastic
Section 06100 – Rough Carpentry Section 06410 – Custom Cabinetwork
Division 7 - Thermal and Moisture Protection
Section 07120 – Fluid Applied Waterproofing Section 07160 – Bituminous Dampproofing Section 07210 – Building Insulation Section 07214 - Masonry Wall Insulation Section 07400 – Metal Roofing Section 07600 – Flashing and Sheet Metal Section 07610 – Standing Seam Metal Roofing Section 07625 – Sheet Metal Gutters and Downspouts Section 07830 – Hatches Section 07900 – Joint Sealers
Division 8 – Doors and Windows
Section 08110 – Steel Doors and Frames Section 08520 – Aluminum Windows
Division 9 – Finishes
Section 09900 – Protective Coating Section 09910 – Painting Section 09950 – Disinfection of Potable Water Facilities
Division 11 – Equipment
Section 11220 – Submersible Well Pump Section 11230 – Chemical Metering Pumps Section 11251 – Ion Exchange Softening System Section 11350 – Vertical Inline Multistate Pumps
Division 13 – Special Construction
Section 13440 – Instrumentation for Process Control: General Requirements Section 13441 – Control Loop Descriptions Section 13442 – Primary Elements and Transmitters Section 13446 – Control Auxiliaries Section 13448 – Control Panels Section 13500 – Programmable Controller System
Division 15 – Mechanical
Section 15051 – Plant Piping Section 15055 – Pipe Supports and Hangers
Division 16 – Electrical
Section 16010 – Electrical: General Requirements Section 16011 – Short Circuit, Protective Device Coordination, ARC-Flash Study Section 16111 – Conduit, Conduit Fittings, Conduit Supports Section 16115 – Underground Conduit and Ducts Section 16120 – Low-Voltage Electrical Power Conductors and Cables Section 16130 – Outlet, Pull, and Junction Boxes Section 16140 – Wiring Devices Section 16150 – Panelboards Section 16190 – Dry Type Transformers Section 16261 – Standby Engine-Generator Set: LP Fueled Section 16401 – Electric Service Section 16450 – Grounding and Bonding Section 16472 – Variable Frequency Drives and Control Equipment Section 16474 – Motor Control Centers Section 16475 – Safety Switches
(Page Intentionally Left Blank)
DIVISION 1 - GENERAL REQUIREMENTS
GENERAL CONDITION:
Please read the "General Requirements and Covenants" (dated 2003) in your possession.
They apply to all Divisions of these specifications, accompanying drawings and to this proposed project.
SECTION 01000
GENERAL REQUIREMENTS
PART 1 GENERAL
1.01 SUMMARY
A. The Contractor shall be responsible for compliance with all items specified herein. This Section is in addition to items in the General Conditions.
B. Work to be done under this Contract consists of furnishing all labor, materials, equipment and incidental items and performing all operations necessary to complete the Work in accordance with the Drawings and Specifications.
C. The Bidder is required to examine carefully the site of the proposed Work, the Drawings and Specifications. He shall satisfy himself as to the character, quality and quantities of work to be performed, materials to be furnished and the requirements of these Specifications. The submission of a Bid Proposal shall be evidence that the Bidder has made such an examination.
1.02 PARTNERING
A. The Contractor, Engineer and Owner shall agree to a partnering process during the construction of the project to:
1. Improve the working environment;
2. Reduce and rapidly resolve disputes;
3. Produce a high quality product; and
4. Eliminate or reduce delays.
B. These goals can be obtained by mutually agreeing to a cooperative strategy of commitment and honest communication. By creating trust and working as a team, all parties will benefit in producing a high quality project, which will result in successful completion of the work.
C. Problem solving will be created by a working relationship where understanding, trust and mutual cooperation are prime concerns.
D. However, partnering does not include relaxing or waving the requirements of the Contract Documents.
E. If there is an error or oversight, or a change is suggested by the Contractor that will produce a product equal to or better than that specified or shown, the parties will work together to determine the best approach while maintaining quality in the construction.
F. Any changes to the project affecting project time or contract price will be implemented by Change Order so approved.
G. All parties shall be committed to maintaining a positive attitude towards partnering and timely decision making.
1.03 VALUE ENGINEERING
Not used.
1.04 DRAWING ACCURACY AND EXISTING UTILITIES
A. Every effort has been made to identify and verify all existing facilities and utilities.
However, some of this information may have been taken from old drawings and utility company maps pertinent to the site.
B. As such, information relating to locations, sizes, or elevation of existing facilities should be considered only approximate. It shall be the responsibility of the Contractor to contact the appropriate representatives of utility companies, or utility locate companies, a minimum of 48 hours prior to the commencement of Work which might affect utility installations and to secure from such representatives information as to accurate location, size and type of such installations. The Contractor shall assume all responsibility for protection, repair and relocation of all such items encountered.
Should repair or replacement be required, work shall be performed according to the requirements of the respective utility company.
1.05 ABBREVIATIONS
A. Wherever the following abbreviations are used in these Specifications or on the Drawings, they shall be construed the same as the respective expressions represented:
AASHO or AASHTO American Association of State Highway Officials ACI American Concrete Institute AISC American Institute of Steel Construction ANSI American National Standards Institute, Inc.
ASTM American Society for Testing & Materials AWWA American Water Works Association CDOT Colorado Department of Transportation CDPHE Colorado Department of Public Health & Environment CRSI Concrete Reinforcing Steel Institute CS Commercial Standard, U.S. Department of Commerce FED. SPEC. Federal Specification NEC National Electric Code NEMA National Electrical Manufacturers Association OSHA Occupational Safety and Health Act (Federal and/or State) SSPC Steel Structures Painting Council UBC Uniform Building Code
UL Underwriters Laboratories, Inc.
1.06 STANDARD SPECIFICATION REFERENCE
A. Where reference is made in these Specifications to other Standard Specifications, it is the intent that the latest available revisions of the Specification referenced be used.
All portions of the Standard Specification referenced shall be considered a part of these Specifications unless specifically superseded herein.
1.07 CONSTRUCTION STAKING
A. The Owner will be responsible for retaining surveying services to provide one time control survey at the project site. Control survey will consist of two (2) control points for horizontal and vertical control as shown on Contract Drawings.
B. The contact for the control survey is Rob Trudeaux of Goff Engineering and Survey at
(970) 247-1705.
C. Any re-staking of control points will be done at request of Contractor on a time and materials cost basis.
D. The Contractor may self-perform or subcontract construction layout work, provided that Contractor satisfactorily proves to the Engineer that its designated layout person has the proper training and experience.
E. The Contractor shall be responsible for paying its surveyor directly.
F. The Contractor shall be responsible for coordinating all survey efforts.
SITE LAYOUT AND STAKING
1. Location points for the work will be defined with stakes and/or other means of identification prior to the start of construction. These location points, grades, and elevations are shown on the drawings. The drawings indicate existing and proposed elevations, but may be modified on the site by the Engineer.
CONSTRUCTION LIMITS
1. At the commencement of construction, the Engineer will designate the area allowed for the construction process. Restrict work to that designated area. Any changes deemed necessary shall be discussed with and approved by the Engineer.
MARSHALLING AND ACCESS
2. Limits and access to the site for use: before taking possession and use of the site, meet with the Engineer to determine the marshalling area(s) and access points to be used to execute the work. Limit access and marshalling areas agreed to at that meeting. Obtain written permission from the Division of any changes other than first agreed upon. Upon completion of all work, restore all areas to original or improved conditions.
1.08 PERMITS AND EASEMENTS
A. The Owner applied for Colorado Department of Public Health and Environment (CDPHE) approval to construct public water system facilities on July 20, 2016 and is responsible for acquiring the approval and meeting any requirements.
B. The Owner has conducted a Non-Jurisdictional determination for the project area and the US Army Corps of Engineers approved the wetland delineation on November 15, 2015. The Owner will apply for a permit and submit a Pre-Construction Notification to the US Army Corps of Engineers for the project areas that will be temporarily disturbed as a result of the project. This work will likely be authorized under Nationwide Permit No. 12 Utility Line Activities. The Contractor shall remove, store and replace wetland vegetation and comply with all other construction-related requirements of the permit.
C. The Contractor shall obtain an electrical permit from the State of Colorado. The Contractor will be responsible for coordinating inspections and meeting permit.
D. Contractor shall obtain a Colorado Department of Public Health and Environment (CDPHE) Water Quality Control Division (WQCD) Construction Stormwater Discharge permit (COR030000) and prepare the associated Stormwater Management Plan
(SWMP).
E. Contractor shall obtain a Colorado Department of Public Health and Environment (CDPHE) Water Quality Control Division (WQCD) Construction Dewatering Discharge permit (COG070000) as required for any construction dewatering activities.
F. Contractor will be fully responsible for implementing, maintaining, and meeting all requirements of all permits related to the project
G. All work is contemplated to occur within Navajo State Park and/or within the rights-of-way and easements as shown on the Construction Drawings. Contractor shall confine all work to these areas.
H. The Contractor shall be responsible for securing any and all access rights he may require for construction convenience with private individuals and landowners. The Contractor shall provide the Engineer evidence of agreements, in writing, for such access rights. All other permits required should be secured prior to commencement of Work at the Contractor's own expense.
I. The successful Contractor will be required to obtain a State of Colorado construction contractor’s license for construction operations. Proof of insurance shall be required.
No Arboles or Archuleta County-issued construction contractor’s license is required.
J. The successful Contractor will be required to obtain any and all other permits necessary for this project.
1.09 SUBSTITUTION OF MATERIALS
A. At no time shall materials be substituted for those shown on the Drawings or called for in the Specifications, unless written approval is obtained from the Engineer in writing prior to construction (see Article 6, General Requirements and Covenants). Any deviation from the Drawings and Specifications shall be accompanied by a written directive of the Engineer or his representative.
1.10 CONTROLLED AREA OF WORK
A. The Contractor shall confine all the construction work, storage of materials and all related activities to the Owner’s project site, rights-of-way, utility easements, or construction areas designated by the Engineer. The Contractor shall maintain a 20’ buffer around the elevated tank and each well and wellhouse in which only work directly related to the project shall be allowed to occur. Access and egress to the work area shall be minimized to specific points.
1.11 TEMPORARY FACILITIES
A. The Contractor, at his expense, shall provide all necessary temporary facilities for his own convenience or to meet local, state or federal requirements, including, but not limited to, potable water, sanitary waste facilities, power, telephone, internet, etc.
Contractor shall provide a field office for the Owner, Engineer and Representatives of Engineer as outlined in Section 01500. The Contractor shall also provide temporary facilities related to erosion control (see Section 01590).
1.12 CLEAN-UP
A. The Contractor will be responsible for cleaning the job site during and after construction. A continuing effort shall be made through the duration of the contract to keep all areas clean and free of all rubbish, removed vegetation, construction waste, employee waste, and other objectionable materials generated from the project. All materials as part of this work shall be disposed off-site in an acceptable manner.
Final clean-up must be approved and accepted by the Owner before the contract may be considered complete.
1.13 SUBMITTALS
A. The Contractor shall provide submittal data, as defined in Sections 01300 Submittals and 01340 Shop Drawings. Submittals shall be required on all materials having quality or dimension requirements as well as on all mechanical equipment or as called for in the Specifications.
1.14 JOB SITE RESTRICTIONS
A. Salvage. All equipment removed or extracted by the Contractor shall be provided to the Owner.
B. Staging Area. The Contractor may designate staging areas near the future water treatment plant site, as desired, so long as the requirements of Part E below are met and the Contractor provides the Engineer with a marked-up site plan at least 72 hours in advance of establishing any staging areas and receives written Engineer approval.
The Contractor will be responsible for locating, securing and paying for any additional off-site area needed.
C. Disposal Area. Some spoils will be used for re-grading Owner's property. All other materials shall be disposed of off-site at approved disposal sites or an on-site area approved by the Engineer.
D. Working Hours. Work will normally be permitted after 7:00am until 7:00pm, Monday through Friday. Other work hours must be approved in advance by Engineer in writing. Depending upon the time of the year, work may be permitted on Saturday and Sunday with Engineer approval. If approved by Engineer, written notice must be provided a minimum of 48 hours prior to this work that outlines all work items that will be performed. The Contractor will be responsible for paying overtime rates (1.5 x the standard hourly rate) for Owner, Owner’s Representative and Engineer for work necessitated by construction activities outside the permitted work hours.
E. Additional Requirements. (a) The Contractor shall not block drive-up access to existing Wells No. 5 and No. 6 nor its existing wellhouse; (b) Contractor shall not stage equipment or materials within 20’ of the elevated tank, existing wells or wellhouses;
(c) Contractor shall not block driving access to, or access along, the main park road
(d) if access to any of these facilities must be temporarily compromised, the Contractor shall provide the Owner with a request a minimum of 72 hours in advance and receive written approval prior to proceeding.
1.15 SAFETY REQUIREMENTS
A. Nothing in the Contract Documents shall be construed as relieving the Contractor from protecting all property and persons or from strictly adhering to all applicable local, state and federal safety requirements. Where there is a conflict between the Contract Documents and any applicable safety requirement, the safety requirement shall take precedence.
1.16 LAWS AND ORDINANCES
A. The Contractor shall at all times observe and comply with all federal, state and local laws, ordinances and regulations which in any manner affect the contract or Work, and shall indemnify and save harmless the Owner and the Owner’s agents against any claim arising from the violations of any such laws, ordinances and regulations, whether by the Contractor or his employees.
B. If the Contractor performs any Work knowing it to be contrary to such laws, ordinances, rules or regulations, and without notice to the Engineer, he shall bear all costs arising therefrom.
C. BUILDING CODES:
1. Local city or county building codes shall be used for all construction. Where there is no local authority and/or code, the current codes required by the Office of the State Architect, State Electrical Board or State Plumbing Board shall be utilized. Appropriate inspections and certificates shall be obtained from the state or local inspector. See relative specification section(s) for additional detail.
1.17 PROTECTION OF PUBLIC UTILITIES AND OTHER ADJOINING PROPERTY
A. The Contractor shall take all reasonable precautions for the safety of, and shall provide all reasonable protection to prevent damage, injury, or loss to other property at the site or adjacent thereto, and he shall be liable for any and all claims for such damage on account of his failure to fully provide such protection. The Contractor shall notify all public utility companies at least forty-eight (48) hours prior to commencement of any Work in the vicinity of the utilities. No Work shall commence until the utilities have been located and staked by the utility company or written consent to proceed has been given by the Engineer. If utility service must be interrupted, the Contractor shall notify the head of local administrative services (i.e., Park Manager, Water Treatment Operator), as applicable, and utility users affected by the interruption of service at least twenty-four (24) hours prior to interruption.
1.18 PROJECT PHOTOGRAPHS/VIDEOS
A. It is the Contractor's responsibility to take a sufficient number of pre-construction photographs/videos to resolve any disputes, which may arise regarding the conditions prior to and subsequent to construction. The Contractor shall provide copies of the pre-construction photographs/videos to the Engineer prior to the start of work. Any potential problems should be identified at that time.
B. Progress and record photographs/videos shall be provided by the Contractor as appropriate to resolve any disputes and to completely document the work performed as a supplement to the Record Drawings. In general, the photographs/videos should be sufficient to show that all work was properly completed in accordance with the plans and specifications.
1.19 DAMAGE TO CONSTRUCTION
A. The Contractor shall safeguard, until all work embraced by this Contract is formally accepted, all construction, both complete and incomplete, against damage and destruction, and should damage result, he will be required to reconstruct or repair it at his expense in a manner conforming to the Plans and Specifications, reconstruction shall be in a manner suitable to the Engineer.
END OF SECTION
SECTION 01010
SUMMARY OF WORK
PART 1 LOCATION:
To access the park, located in Archuleta County, take U.S. Highway 160 west from Pagosa Springs for about 17 miles, then turn south onto State Highway 151 for about 18 miles to Arboles. Turn left again onto County Road 982 and drive 2 miles to the park.
Project Address: Navajo State Park
1526 County Road 982 Arboles, CO 81121 Archuleta County
Project Coordinates: Latitude: 37°00'28.0"N Longitude: 107°24'49.9"W
PART 2 DESCRIPTION OF THE WORK:
A. This project consists of constructing a new water treatment facility and booster pump station, a new concrete partially buried water tank, a new wellhouse, a new monitoring well, a new access road; installing a new irrigation head gate and piping, installing raw water piping and treated water PVC piping; electrical and mechanical systems and associated appurtenances; completion of associated site work, and construction of improvements to existing wells. More specifically, the project scope includes, but is not limited to, the following:
1. Process Equipment and Piping
a. One Duplex Sodium Hypochlorite Metering Pump skid
b. One Water Softening Skid
c. One (of each) Chlorine analyzer, turbidimeter, and universal controller
d. One eye wash station
e. One 2” Clear PVC KoFlow Static Mixer (6 element)
f. Ball valves, PVC fittings, process piping, pipe supports and hardware, sample taps (multiple, see Drawings)
g. One Ultra Tech 2330 P4 Bladder System
h. Two 55-gallon poly-processing chemical tanks and fittings and tubing.
i. Three Harmsco Hurricane Muni 90MP Filter housing.
1) Two Harmsco HC/90-LT2 Filter Cartridges
2) One Harmsco HC/90-20 Filter Cartridge
j. One 2” Rosemount 8750WA Totalizing Magnetic Flowmeter and readout.
k. All process piping with appurtenances, supports, coatings, and labels.
l. Associated isolation valves, control valves, process analyzers, level sensors, drains, electrical equipment, and other appurtenances.
m. Startup and testing of all process equipment and systems. Note that there are significant requirements in this regard for the cation-exchange softening system and Harmsco filters.
2. Booster Pump Station
a. One 81 Gallon Dayton Bladder Tank
b. Four Grundfos CR Series in-line, centrifugal pumps
c. All process piping with appurtenances, supports, coatings, and labels.
d. Associated control/check valves, pressure gauges, process analyzers, level sensors, drains, electrical equipment, expansion joints, and other appurtenances.
3. Distribution Piping
a. 6” and 8” PVC treated water piping (high pressure)
b. 2” and 4” PVC raw water piping (high pressure)
c. 6” PVC irrigation piping (low pressure)
d. 6” PVC solids/residuals piping (low pressure)
e. 6” PVC drains
f. Five fire hydrants
g. One air release valve
h. One air release/vacuum valve
i. Associated control/check valves, thrust blocks, fittings, saddle/service taps and other appurtenances.
4. Improvements to Existing Infrastructure Wells
a. For Well No. 5:
1) Install a new VFD for well pump
b. For Well No. 6:
1) Install a new Grundfos 10SQ-290 submersible pump with a new
VFD.
c. For each of Wells Nos. 5 and 6:
1) Install communications and control equipment, new power conduit and cables in the new wellhouse for Wells Nos. 5 and 6.
2) New buried fiber optic communication lines from the new WTP building to wellhouses for Wells No. 5 and No. 6.
3) Abandonment and/or removal of valves and appurtenances along the existing water distribution alignment as noted on the drawings.
4) Connect Wells Nos. 5 and 6 to the existing tie-in point of the new 4” raw waterline.
5. Drill new Monitoring and Observation Well at the Existing Marina Site
6. Improvements to Future Candelaria-Wells
a. For each of the future Candelaria Wells install 2” raw water pipes from each well to the new 4” pipeline upstream (before) of the New Water Treatment Plant.
7. Construction of a New Water Treatment Plant
a. Construction of a new water treatment plant building and associated backup generator, and propane tank and gas lines.
8. Associated Site Development and Utilities
a. Yard piping for multiple service needs
b. Construction of new access road connecting the existing park road to the new water treatment and water tank area.
c. Grading of access, building site, and proposed parking area in order to meet flood plain requirements, access and drainage needs.
d. Installation of a new headgate off the irrigation lateral near the new water treatment and water tank area.
e. Piping of the irrigation lateral from the new water treatment and water tank area to the East and West Ponds.
f. Installation of yard piping to support the future construction of a new residuals pond.
g. 1 dry hydrant
h. Electrical transformer vault (MPEI to provide and install transformer outside of this contract)
i. All buried electrical conduit and cable shown on the plans (note: cables for electrical primaries to be supplied and installed by MPEI outside of this contract)
j. Natural gas main and service line
k. Shallow phone and internet utilities
l. Access gate at the intersection of the new access road and existing park road.
m. Fencing.
All work shall be in compliance with these specifications and construction drawings.
2.01 CONTRACTOR'S RESPONSIBILITIES
In addition to all the requirements of the Standard General Conditions and other Contract Documents:
A. Supervision:
1. The Contractor will supervise and direct the Work. He will be solely responsible for the means and methods, techniques, and procedures of construction.
2. The Contractor will employ and maintain on the Work a qualified supervisor or superintendent who shall have been designated in writing by the Contractor and the Contractor's representative at the site.
3. The supervisor shall have full authority to act on behalf of the Contractor and all communications given to the supervisor shall be as binding as if given to the Contractor.
4. The supervisor shall be present on the site at all times as required to perform adequate supervision and coordination of the Work.
The supervisor shall not be changed except with the consent of the Engineer, unless the supervisor has proven to be unsatisfactory to the Contractor and ceases to be in his employ.
B. Subcontracting
1. The Contractor may use the services of specialty Subcontractors on those parts of the Work, which under normal contracting practices are performed by specialty Subcontractors.
2. The Contractor shall not award work to Subcontractor(s) in excess of fifty (50%) percent of the Contract Price without prior written approval of the Owner.
3. The Contractor shall be fully responsible to the Owner for the acts and omissions of his Subcontractors, and or persons either directly or indirectly employed by them, as he is for the acts of persons directly employed by him.
4. The Contractor shall cause appropriate provisions to be inserted in all Subcontracts relative to the Work to bind Subcontractors to the Contractor insofar as applicable to the Work of Subcontractors and to give the Contractor the same power as regards terminating any subcontract that the Owner may exercise over the Contractor under any provision of the Contract Documents.
5. Nothing contained in this Contract shall create any contractual relations between any Subcontractor and the Owner.
6. Engineer as “specialty items” may be performed by subcontract and the cost of any such specialty items so performed by subcontractor may be deducted from the total cost before computing the amount of work required to be performed by the Contractor with his own organization. However, under no circumstances shall less than 20 percent of the total contract cost be performed by the Contractor’s organization after deduction of specialty items.
C. Safety and Protection
1. Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to:
a. All employees on the Work and other persons who may be affected thereby;
b. All the Work and all materials or equipment to be incorporated therein, whether in storage on or off the site; and
c. Other property at the site or adjacent thereto, including, but not limited to trees, shrubs, lawns, walks, pavements, roadways, structures, and utilities not designated for removal, relocation or replacement in the course of construction.
2. Contractor shall comply with all applicable laws, ordinances, rules, regulations, and orders of any public body having jurisdiction for the safety of persons or property or to protect them from damage, injury or loss; and shall erect and maintain all necessary safeguards for such safety and protection.
2.02 PROTECTION AND SAFETY PRACTICE
1. General:
a. All work shall be carried out in a safe manner in accordance with local codes and the safety requirements of the Colorado State Division of Labor.
2. Provide shoring, sheeting, barricading, bracing to prevent caving, erosion and gullying of side of excavation. The design, engineering, construction and maintenance of all temporary protection, including its adequacy and safety shall be the Contractor's responsibility and shall comply with the Occupational Safety and Health Administration (OSHA).
3. Existing Utilities
a. Colorado SB 93-155 requires that anyone that engages in any type of excavation must provide advance notice to the underground facility owners. Prior to any moving or excavating of earth, the Contractor shall call the Utility Notification Center of Colorado (UNCC) or “Common Ground Alliance” (CGA) – the “Call Before You Dig” number – at 811.
Utility owners have three business days to perform locates. If facilities are not marked within the three business days, you are required to call back to UNCC and process a Second Notice Request. UNCC encourages both Contractors and Sub-Contractors to obtain a locate ticket. A “no response” from the utility owner does not allow the Contractor to start digging. Notify the Engineer when working near utility lines or appurtenances.
4. Aquatic concerns and equipment cleaning
a. For this project; If heavy equipment is acquired or used that was previously working in another stream, river, lake, pond, or wetland, one of the following disinfection practices is necessary prior to construction to prevent the spread of New Zealand mud snails and other aquatic hitchhikers into this drainage. The practice is also necessary after project completion, prior to this equipment being used in another stream, river, lake, pond, or wetland, for the same purpose:
1) Remove all mud and debris from equipment (tracks, turrets, buckets, drags,teeth, etc.) and spray/soak equipment a 1:15 solution of Sparquat institutional cleaner and water. Keep equipment moist for at least 10 minutes OR
2) Remove all mud and debris from equipment (tracks, turrets, buckets, drags, teeth, etc.) and spray/soak equipment with water greater than 140 degrees F for at least 10 minutes.
3) Clean hand tools, boots, and any other equipment that will be used in the water using one of the above options as well.
4) Sparquat 256 Germicidal Cleaner (Spartan Chemical Company, Inc.) is available in the Denver area from Waxie Denver at (303) 749-8000 or (800) 377-4128, High Country Chemical at (303) 287-6700 and AmSan Colorado Chemical at (303) 388-9331.
5. Surface Drainage
a. Provide for surface drainage during the construction period in a manner to avoid creating a nuisance to adjacent properties.
6. Location Markers
a. Carefully maintain and protect all bench marks, corner monuments and other points. If disturbed or destroyed, replace at no cost to the Owner as directed by the Engineer.
B. Contractor's Use of Premises
1. Owner controls all lands upon which the Work is to take place. The Contractor shall not enter upon private property for any purpose without first obtaining written permission. A copy of the document giving Contractor permission to enter private property along with all terms of this agreement shall be transmitted to the Owner prior to entering property. Contractor shall be responsible for the preservation of all public and private property, trees, fences, monuments, underground structures, etc., on and adjacent to the site and shall use every precaution necessary to prevent damage or injury thereto. He shall protect carefully from disturbance or damage, all land monuments and property corners until an authorized agent has witnessed or otherwise referenced their location, and shall not remove them until directed. He shall be responsible for all damage or injury to property of any character resulting from any act, omission, neglect or misconduct in his or any Subcontractor's manner, or method or executing said Work, due to this or any Subcontractor's non-execution of said Work, or at any time due to defective work or materials, and said responsibility shall not be released until the Work shall have been completed and warranty period expired.
2. The Contractor shall be responsible for all utilities required for construction at no cost to the Owner.
3. Necessary sanitary conveniences for the use of project personnel shall be properly secluded from public observation and shall be erected and maintained by the Contractor at such points acceptable to the Engineer.
4. JOB CONDITIONS:
a. Examine the site, determine the nature of conditions to be encountered and accept the site as found upon the examination. Examination must be made prior to bidding as no additional compensation will be considered after receipt of bids for existing conditions which are required to be worked, adapted, or modified to these specifications.
2.03 OWNER COORDINATION AND NOTIFICATION
A. The Contractor shall coordinate his efforts with the Owner so as to minimize disruption of existing service and inconvenience to other adjacent contractors and adjacent property owners.
1. Set forth proposed work sequence and schedule in accordance with Section
01310 - Construction Schedules.
B. Contractor shall notify Owner a minimum of 48 hours in advance of any efforts needing coordination and/or special inspection by Owner or its representative. Such efforts include, but are not limited to:
1. Utility tie-ins
2. Utility service interruptions
3. Utility relocations
4. Service/access interruptions (including access through site along existing 2-track road as shown on Drawings)
5. Process interruptions (i.e. any work affecting operation of existing wells, well houses, water transmission pipelines, , and/or associated radio telemetry or control systems)
6. Well inspection and/or rehabilitation work
7. Equipment testing and startup
2.04 SEQUENCE OF WORK
A. Construction Sequencing: Sequencing of Work herein described, including, but not limited to, tie-ins, improvements to existing facilities, decommissioning of existing facilities, and commissioning of new facilities will be critical. Contractor shall take into account this sequence when preparing Bid and the successful Bidder shall include this sequence in the construction schedule. Coordination of Work necessary to meet the construction sequence as discussed below is the responsibility of the Contractor. The Engineer and Owner shall be updated prior to start and completion of each phase.
B. This project involves the addition of a new treatment facility to an existing water system as well as modifications to existing potable water production wells. The Owner’s ability to produce ample water of potable quality meeting all applicable state and federal regulations, must be maintained throughout construction. Temporary short-term shutdowns of individual wells are possible. All shutdowns shall be coordinated with the water supervisor with a minimum 48-hour notice. The actual startup process, sequencing and procedure shall be discussed and coordinated with the Engineer and Owner a minimum of 30 days prior to Contractor’s desired startup date.
C. The Contractor shall develop his own sequence of Work to minimize construction time, site disturbances, and interruptions of existing water system operations. Testing and startup schedule and sequence shall be thoroughly discussed and coordinated with Engineer and Owner
D. Procedures and methods other than those specified will be considered by Engineer and Owner, provided they afford equivalent continuity of operations.
E. Submit and update Progress Schedules and sub-schedules in accordance with Section 01310 - Construction Schedules.
F. Discuss Sequence of Work and Notice Required at Progress Meetings.
1. Review with and obtain Engineer’s and Owner’s input to Contractor's initial scheduling of Work sequence during preconstruction conference.
2. Review any changes in scheduling at regularly scheduled progress meetings.
3. Schedule additional construction meetings required to discuss Work sequence.
4. Refer to Section 01310 Construction Schedules for additional requirements on
Progress Schedules.
G. Inspection by public agencies.
• Provide proper facilities for such access and inspection.
• Flow of irrigation water in the Ditch, which is shown on the Drawings, and runs through the project site, must not be interrupted during the period April 15 through August 1.
Main park road utility trenching and installation, culvert work or temporary culvert installation for construction access will need to be completed outside this time window.
The Owner will allow the Contractor to use the two track drive northeast of the property as a construction access to the site.
• The new potable waterlines will not be live and on-line until plant treatment processes, pumping systems and well improvements have reached Substantial Completion.
• The existing elevated tank shall remain in-service, as-is, with its availability to provide potable water to the distribution system until the Wells Nos. 5 and 6 are brought on-line to feed the new WTP and the existing transmission line from the existing elevated tank is cut and capped.
• On a somewhat flexible schedule, proceed with well/wellhouse improvements, including any needed well rehabilitation note, however, that Well No. 6’s pump cannot be installed until the conditions prior-noted have been met. Also, the Contractor shall minimize the time that Well No. 5 is the only well able to feed the existing elevated tank and no potable well can feed the potable system directly. Therefore, the Contractor shall have Well No. 6 ready to bring on-line within two (2) weeks after the WTP treatment process, pumping and control/communication systems reach Substantial Completion and the potable water line is cut and capped.
• Work will not begin on Well No. 6 and its wellhouse without written approval from Owner. It is intended that Well No. 5, in addition to Well No. 6, be available to directly feed the potable system through the peak summer demand season in 2017. Work on Well No. 6 to be delayed until after this date includes new pump installation, new VFD and controls/telemetry work. Contractor may wish to schedule Well No. 6 inspection and potential rehab work (via Change Order only) during same mobilization.
• Complete all Wells Nos. 5 and 6 work and associated Ethernet radio and controls work in-time for it to supply influent water to the new water plant for start-up.
• Complete tie-ins for plant raw water line and both finished water lines.
• Coordinate with Owner regarding all plant commissioning activities, especially operations relating to alternating use of Wells Nos. 5 and 6 to feed plant for start-up.
• Commission new plant and obtain Engineer certification that Substantial Completion has been reached for all Well No. 6 improvements as well as all plant treatment process, pumping and communication/control systems with the following minor exceptions as related to eliminating potential cross connections between the backwash pond and the potable system:
• Obtain Substantial Completion certification for overall project and address Substantial Completion walkthrough punchlist items.
• Hold Final Acceptance walkthrough and address Final Acceptance punchlist items.
Apply for Final Payment and close-out project.
H. It will be the Contractor's responsibility to schedule and sequence his activities so as to best meet environmental conditions imposed by winter weather.
I. The Contractor shall coordinate his efforts with each Subcontractor so as to avoid conflicts and Work slowdowns.
PART 3 PRODUCTS
3.01 OWNER FURNISHED MATERIAL
The Contractor shall assume Owner contracts for the pre-purchase of a water softening skid for installation and integration with this project (refer to Section 11251 and applicable appendicized material).
Any Owner furnished material shall be delivered to the site and possession taken of the material by the Contractor. At the time transfer of material occurs, responsibility for all subsequent losses and replacement shall be solely that of the Contractor.
3.02 MAINTENANCE OF ACCESS
A. Conduct Work to interfere as little as possible with public or private travel, whether vehicular or pedestrian and with Navajo State Park personnel duties.
1. Whenever it is necessary to cross, close, or obstruct roads, driveways and walks, whether public or private, provide and maintain suitable and safe bridges, detours, or other temporary expedients for accommodation of public and private travel.
2. Give owners of private drives reasonable notice (minimum 48 hours) before interfering with accesses.
PART 4 EXECUTION
4.01 FENCES
A. Maintain all fences affected by the Work until completion of the Work.
B. Do not relocate or dismantle fences that interfere with construction operations before obtaining written permission from the fence owner with an agreement as to the length of time the fence may be left relocated or dismantled.
C. At the completion of Work, replace fences to their pre-construction condition or better and to their pre-construction location unless otherwise indicated on drawings or in specifications.
D. Refer to construction drawings for additional requirements.
4.02 UNDERGROUND OBSTRUCTIONS
A. Protect from damage any underground pipes, utilities, or structures encountered during construction.
B. Restore any damaged underground obstructions to their original condition at no cost to the Owner unless evidence of other arrangements satisfactory to all parties is presented to the Owner.
C. Before commencing Work, obtain information concerning location, type, and extent of concealed existing utilities on the site and adjacent properties.
1. Consult records and personnel of local utility companies, municipal utility departments, telephone companies, and cable television company.
2. File "Notice of Excavation" with these agencies prior to commencing Work.
D. Underground obstructions known to the Engineer are shown on the Drawings or otherwise referred to in the Specifications.
1. Locations shown may prove to be inaccurate and other obstructions not shown may be encountered.
2. Contractor is responsible to verify actual locations and to protect or restore all underground obstructions encountered.
4.03 CONSTRUCTION COMMENCEMENT
A. The Contractor shall be allowed from the date of approval of contract documents through the CONTRACT START DATE (as indicated on the Notice to Proceed letter) to submit shop drawings and product approvals and order and delivery of materials.
4.04 ADDITIONAL PROVISIONS
A. The work and the compensation, therefore, shall be as covered by these specifications consisting of furnishing all plant, labor, equipment and materials required to perform the work shown on the drawings and listed in the bid schedule, unless otherwise stipulated or approved in writing by the Engineer.
B. Navajo State Park field engineering personnel are authorized to supervise the construction of this project in accordance with the previously approved plans and specifications and change orders. All changes in the work shall be approved in writing by the Engineer before being activated in accordance with Section 4, Item 4.2 of the General Requirements and Covenants.
C. The specifications included herein are the Specifications for this project. If there should be a difference between the Specifications and the drawings, the Specifications shall govern.
4.05 CONTRACTOR RESPONSIBILITY
A. Visit the site and determine to your own satisfaction the amount and type of work to be performed to complete the project in accordance with the drawings, specifications and Contract Documents before submitting your bid.
B. Before final payment will be made on the completed contract, submit to the Owner all specified warranties, other product warranties and the Minority Business Enterprises Compliance Report.
4.06 LIQUIDATED DAMAGES
A. Liquidated damages for this project shall be a daily charge of $300 for each day beyond the specified contract time. This daily charge will be deducted from any money due the Contractor.
4.07 MEASUREMENT AND PAYMENT
A. Payment for construction shown on the drawings and specified herein shall be made as noted in the Bid Schedule and Section 9 of the General Requirements and Covenants.
4.08 SALES TAX
A. Sales tax shall not be charged on projects for the Department of Natural Resources, through the Colorado Parks & Wildlife.
B. The Department of Revenue will issue a certificate of exemption (Form No. DR172) to Contractors or subcontractors. C.R.S. 1973 as amended 39-26-114. The Colorado Parks & Wildlife State Sales Tax number is 98-02565. Forms can be obtained from the Recorded Forms Request Line at 303-238-3278, or at www.revenue.state.co.us.
http://www.revenue.state.co.us/
SECTION 01023
MINOR CONTRACT REVISION
PART 1 GENERAL
1.01 SCOPE OF WORK
A. Furnish all labor, materials and equipment required as additional work for completion of the project.
1.02 WORK INCLUDED
A. The work shall include unanticipated extra work in excess of the quantities included in the bid schedule.
1.03 PAYMENT
A. Payment for minor contract revisions shall be made at the contract unit price, negotiated basis or force account in accordance with Section 9.4 of the General Requirements and Covenants.
SECTION 01025
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.01 SUMMARY
This section describes the procedure for Application for Payment by the Contractor.
This section establishes the basis of payment, application format, application content and application review process required by the Owner before it will process the application for actual payment.
1.02 FORMAT AND DATA REQUIRED
A. Submit Applications for Payment and all other required forms and information to the Engineer.
B. Provide itemized data on continuation sheets.
C. Format, schedules, line items, and values: Those of the approved Schedule of Values.
1.03 PREPARATION OF APPLICATION FOR EACH PROGRESS PAYMENT
A. Prepare Application for Payment and all other required information to Engineer in accordance with terms and schedule established in the General Conditions, Supplemental General Conditions and the Agreement between Owner and Contractor, or as otherwise negotiated between Owner and Contractor.
B. Application Form
1. Required information completed, including that for Change Orders executed prior to the date of submittal of application.
2. Summary of dollar values to agree with the respective totals indicated on the continuation sheets.
C. Continuation Sheets
1. Total list of all scheduled component items of Work, with item number and the scheduled dollar value for each item.
2. Dollar value in each column for each scheduled line item when work has been performed.
3. Each Change Order executed prior to the date of submission shall be listed at the end of the continuation sheets.
4. List by Change Order number and description as for an original component item of work.
D. Contractor shall execute certification with the signature of a responsible officer of the Contractor's firm.
1.04 SUBSTANTIATING DATA FOR PROGRESS PAYMENTS
A. When Owner or Engineer requires substantiating data, Contractor shall submit suitable information with a cover letter identifying:
1. Project name and number.
2. Application number and date.
3. Detailed list of enclosures.
B. Submit one (1) copy of data and cover letter for each copy of application.
1.05 SCHEDULE OF VALUES
A. Refer to General Conditions for requirements.
B. Where payment is to be based on unit bid prices, correlate Schedule of Values with bid items.
C. Where payment is to be based on fixed price,…