This document is a compiled specifications file for the Santa Fe Regional Airport Runway 33 Runway Safety Area (RSA) Improvement Project in New Mexico, containing technical requirements and construction standards based on FAA Advisory Circular AC 150/5370-10H. The project consists of earthwork, grading, drainage improvements, surface restoration including seeding, and removal or relocation of obstructions to bring the RSA into compliance with applicable FAA design and safety standards while maintaining safe airport operations. Key contract items include a Contractor Quality Control Program (Item C-100), Temporary Air and Water Pollution and Soil Erosion Control (Item C-102), Mobilization (Item C-105), drainage infrastructure (Items D-701 and D-751), and pavement work including clearing and grubbing (Item P-151), excavation and embankment (Item P-152), concrete structures (Item P-610), and runway and taxiway marking (Item P-620). The specifications mandate that contractors establish and maintain an effective quality control program prior to commencing construction, with a mandatory Quality Control/Quality Assurance workshop involving the Engineer, Resident Project Representative, contractor, subcontractors, testing laboratories, and the Owner's representative before work begins.
The Contractor Quality Control Program payment is structured as a lump sum with partial payments: 25% upon CQCP approval and QC/QA workshop completion, an additional 25% when 25 percent or more of the original contract is earned, 40% when 50 percent or more of the original contract is earned, and a final 10% after final inspection and project acceptance. Mobilization costs are limited to 10 percent of the total project cost with similar partial payment provisions. All temporary erosion and pollution control work is measured as a lump sum as scheduled or directed by the Resident Project Representative. The specifications require the Contractor Quality Control Program Administrator to be a full-time employee or consultant with a minimum of five years of pavement quality control experience and specific professional qualifications including a Professional Engineer license, Engineer-in-Training certification, NICET Level IV certification, or a Bachelor of Science degree in a relevant engineering field combined with airport paving experience. The contractor must post Equal Employment Opportunity and Davis-Bacon wage rate notices prior to commencing construction activities.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
12/21/2018 AC 150/5370-10H
SAF182-19F Item C-100-1 Contractor Quality Control Program
Item C-100 Contractor Quality Control Program (CQCP)
100-1 General. Quality is more than test results. Quality is the combination of proper materials, testing, workmanship, equipment, inspection, and documentation of the project. Establishing and maintaining a culture of quality is key to achieving a quality project. The Contractor shall establish, provide, and maintain an effective Contractor Quality Control Program (CQCP) that details the methods and procedures that will be taken to assure that all materials and completed construction required by this contract conform to contract plans, technical specifications and other requirements, whether manufactured by the Contractor, or procured from subcontractors or vendors. Although guidelines are established and certain minimum requirements are specified here and elsewhere in the contract technical specifications, the Contractor shall assume full responsibility for accomplishing the stated purpose.
The Contractor shall establish a CQCP that will:
a. Provide qualified personnel to develop and implement the CQCP.
b. Provide for the production of acceptable quality materials.
c. Provide sufficient information to assure that the specification requirements can be met.
d. Document the CQCP process.
The Contractor shall not begin any construction or production of materials to be incorporated into the completed work until the CQCP has been reviewed and approved by the Resident Project Representative
(RPR). No partial payment will be made for materials subject to specific quality control (QC) requirements until the CQCP has been reviewed and approved.
The QC requirements contained in this section and elsewhere in the contract technical specifications are in addition to and separate from the quality assurance (QA) testing requirements. QA testing requirements are the responsibility of the RPR or Contractor as specified in the specifications.
A Quality Control (QC)/Quality Assurance (QA) workshop with the Engineer, Resident Project
Representative (RPR), Contractor, subcontractors, testing laboratories, and Owner’s representative must be held prior to start of construction. The QC/QA workshop will be facilitated by the Contractor. The
Contractor shall coordinate with the Airport and the RPR on time and location of the QC/QA workshop.
Items to be addressed, at a minimum, will include:
a. Review of the CQCP including submittals, QC Testing, Action & Suspension Limits for
Production, Corrective Action Plans, Distribution of QC reports, and Control Charts.
b. Discussion of the QA program.
c. Discussion of the QC and QA Organization and authority including coordination and information exchange between QC and QA.
d. Establish regular meetings to discuss control of materials, methods and testing.
e. Establishment of the overall QC culture.
100-2 Description of program.
a. General description. The Contractor shall establish a CQCP to perform QC inspection and testing of all items of work required by the technical specifications, including those performed by subcontractors. The CQCP shall ensure conformance to applicable specifications and plans with respect to
SAF182-19F Item C-100-2 Contractor Quality Control Program materials, off-site fabrication, workmanship, construction, finish, and functional performance. The CQCP shall be effective for control of all construction work performed under this Contract and shall specifically include surveillance and tests required by the technical specifications, in addition to other requirements of this section and any other activities deemed necessary by the Contractor to establish an effective level of
QC.
b. Contractor Quality Control Program (CQCP). The Contractor shall describe the CQCP in a written document that shall be reviewed and approved by the RPR prior to the start of any production, construction, or off-site fabrication. The written CQCP shall be submitted to the RPR for review and approval at least 10 calendar days before the CQCP Workshop. The Contractor’s CQCP and QC testing laboratory must be approved in writing by the RPR prior to the Notice to Proceed (NTP).
The CQCP shall be organized to address, as a minimum, the following:
1. QC organization and resumes of key staff
2. Project progress schedule
3. Submittals schedule
4. Inspection requirements
5. QC testing plan
6. Documentation of QC activities and distribution of QC reports
7. Requirements for corrective action when QC and/or QA acceptance criteria are not met
8. Material quality and construction means and methods. Address all elements applicable to the project that affect the quality of the pavement structure including subgrade, subbase, base, and surface course. Some elements that must be addressed include, but is not limited to mix design, aggregate grading, stockpile management, mixing and transporting, placing and finishing, quality control testing and inspection, smoothness, laydown plan, equipment, andtemperature management plan.
The Contractor must add any additional elements to the CQCP that is necessary to adequately control all production and/or construction processes required by this contract.
100-3 CQCP organization. The CQCP shall be implemented by the establishment of a QC organization.
An organizational chart shall be developed to show all QC personnel, their authority, and how these personnel integrate with other management/production and construction functions and personnel.
The organizational chart shall identify all QC staff by name and function, and shall indicate the total staff required to implement all elements of the CQCP, including inspection and testing for each item of work.
If necessary, different technicians can be used for specific inspection and testing functions for different items of work. If an outside organization or independent testing laboratory is used for implementation of all or part of the CQCP, the personnel assigned shall be subject to the qualification requirements of paragraphs 100-03a and 100-03b. The organizational chart shall indicate which personnel are Contractor employees and which are provided by an outside organization.
The QC organization shall, as a minimum, consist of the following personnel:
a. Program Administrator. The Contractor Quality Control Program Administrator (CQCPA) must be a full-time employee of the Contractor, or a consultant engaged by the Contractor. The
CQCPA must have a minimum of five (5) years of experience in QC pavement construction with prior QC experience on a project of comparable size and scope as the contract.
Included in the five (5) years of paving/QC experience, the CQCPA must meet at least one of the following requirements:
(1) Professional Engineer with one (1) year of airport paving experience.
SAF182-19F Item C-100-3 Contractor Quality Control Program
(2) Engineer-in-training with two (2) years of airport paving experience.
(3) National Institute for Certification in Engineering Technologies (NICET) Civil Engineering
Technology Level IV with three (3) years of airport paving experience.
(4) An individual with four (4) years of airport paving experience, with a Bachelor of Science
Degree in Civil Engineering, Civil Engineering Technology or Construction.
The CQCPA must have full authority to institute any and all actions necessary for the successful implementation of the CQCP to ensure compliance with the contract plans and technical specifications.
The CQCPA authority must include the ability to immediately stop production until materials and/or processes are in compliance with contract specifications. The CQCPA must report directly to a principal officer of the construction firm. The CQCPA may supervise the Quality Control Program on more than one project provided that person can be at the job site within two (2) hours after being notified of a problem.
b. QC technicians. A sufficient number of QC technicians necessary to adequately implement the
CQCP must be provided. These personnel must be either Engineers, engineering technicians, or experienced craftsman with qualifications in the appropriate field equivalent to NICET Level II in Civil
Engineering Technology or higher, and shall have a minimum of two (2) years of experience in their area of expertise.
The QC technicians must report directly to the CQCPA and shall perform the following functions:
(1) Inspection of all materials, construction, plant, and equipment for conformance to the technical specifications, and as required by paragraph 100-6.
(2) Performance of all QC tests as required by the technical specifications and paragraph
100-8.
(3) Performance of tests for the RPR when required by the technical specifications.
(4) Certification at an equivalent level of qualification and experience by a state or nationally recognized organization will be acceptable in lieu of NICET certification.
c. Staffing levels. The Contractor shall provide sufficient qualified QC personnel to monitor each work activity at all times. Where material is being produced in a plant for incorporation into the work, separate plant and field technicians shall be provided at each plant and field placement location. The scheduling and coordinating of all inspection and testing must match the type and pace of work activity.
The CQCP shall state where different technicians will be required for different work elements.
100-4 Project progress schedule. Critical QC activities must be shown on the project schedule as required by Section 80, paragraph 80-03, Execution and Progress.
100-5 Submittals schedule. The Contractor shall submit a detailed listing of all submittals (for example, mix designs, material certifications) and shop drawings required by the technical specifications. The listing can be developed in a spreadsheet format and shall include as a minimum:
a. Specification item number
b. Item description
c. Description of submittal
d. Specification paragraph requiring submittal
e. Scheduled date of submittal
SAF182-19F Item C-100-4 Contractor Quality Control Program
100-6 Inspection requirements. QC inspection functions shall be organized to provide inspections for all definable features of work, as detailed below. All inspections shall be documented by the Contractor as specified by paragraph 100-9.
Inspections shall be performed as needed to ensure continuing compliance with contract requirements until completion of the particular feature of work. Inspections shall include the following minimum requirements:
a. During plant operation for material production, QC test results and periodic inspections shall be used to ensure the quality of aggregates and other mix components, and to adjust and control mix proportioning to meet the approved mix design and other requirements of the technical specifications. All equipment used in proportioning and mixing shall be inspected to ensure its proper operating condition.
The CQCP shall detail how these and other QC functions will be accomplished and used.
b. During field operations, QC test results and periodic inspections shall be used to ensure the quality of all materials and workmanship. All equipment used in placing, finishing, and compacting shall be inspected to ensure its proper operating condition and to ensure that all such operations are in conformance to the technical specifications and are within the plan dimensions, lines, grades, and tolerances specified. The CQCP shall document how these and other QC functions will be accomplished and used.
100-7 Contractor QC testing facility.
a. For projects that include Item P-401, Item P-403, and Item P-404, the Contractor shall ensure facilities, including all necessary equipment, materials, and current reference standards, are provided that meet requirements in the following paragraphs of ASTM D3666, Standard Specification for Minimum
Requirements for Agencies Testing and Inspecting Road and Paving Materials:
• 8.1.3 Equipment Calibration and Checks;
• 8.1.9 Equipment Calibration, Standardization, and Check Records;
• 8.1.12 Test Methods and Procedures
b. For projects that include P-501, the Contractor shall ensure facilities, including all necessary equipment, materials, and current reference standards, are provided that meet requirements in the following paragraphs of ASTM C1077, Standard Practice for Agencies Testing Concrete and Concrete
Aggregates for Use in Construction and Criteria for Testing Agency Evaluation:
• 7 Test Methods and Procedures
• 8 Facilities, Equipment, and Supplemental Procedures
100-8 QC testing plan. As a part of the overall CQCP, the Contractor shall implement a QC testing plan, as required by the technical specifications. The testing plan shall include the minimum tests and test frequencies required by each technical specification Item, as well as any additional QC tests that the
Contractor deems necessary to adequately control production and/or construction processes.
The QC testing plan can be developed in a spreadsheet fashion and shall, as a minimum, include the following:
a. Specification item number (e.g., P-401)
b. Item description (e.g., Hot Mix Asphalt Pavements)
c. Test type (e.g., gradation, grade, asphalt content)
d. Test standard (e.g., ASTM or American Association of State Highway and Transportation
Officials (AASHTO) test number, as applicable)
SAF182-19F Item C-100-5 Contractor Quality Control Program
e. Test frequency (e.g., as required by technical specifications or minimum frequency when requirements are not stated)
f. Responsibility (e.g., plant technician)
g. Control requirements (e.g., target, permissible deviations)
The QC testing plan shall contain a statistically-based procedure of random sampling for acquiring test samples in accordance with ASTM D3665. The RPR shall be provided the opportunity to witness QC sampling and testing.
All QC test results shall be documented by the Contractor as required by paragraph 100-9.
100-9 Documentation. The Contractor shall maintain current QC records of all inspections and tests performed. These records shall include factual evidence that the required QC inspections or tests have been performed, including type and number of inspections or tests involved; results of inspections or tests; nature of defects, deviations, causes for rejection, etc.; proposed remedial action; and corrective actions taken.
These records must cover both conforming and defective or deficient features, and must include a statement that all supplies and materials incorporated in the work are in full compliance with the terms of the contract. Legible copies of these records shall be furnished to the RPR daily. The records shall cover all work placed subsequent to the previously furnished records and shall be verified and signed by the
CQCPA.
Contractor QC records required for the contract shall include, but are not necessarily limited to, the following records:
a. Daily inspection reports. Each Contractor QC technician shall maintain a daily log of all inspections performed for both Contractor and subcontractor operations. These technician’s daily reports shall provide factual evidence that continuous QC inspections have been performed and shall, as a minimum, include the following:
(1) Technical specification item number and description
(2) Compliance with approved submittals
(3) Proper storage of materials and equipment
(4) Proper operation of all equipment
(5) Adherence to plans and technical specifications
(6) Summary of any necessary corrective actions
(7) Safety inspection.
(8) Photographs and/or video
The daily inspection reports shall identify all QC inspections and QC tests conducted, results of inspections, location and nature of defects found, causes for rejection, and remedial or corrective actions taken or proposed.
The daily inspection reports shall be signed by the responsible QC technician and the CQCPA. The RPR shall be provided at least one copy of each daily inspection report on the work day following the day of record. When QC inspection and test results are recorded and transmitted electronically, the results must be archived.
b. Daily test reports. The Contractor shall be responsible for establishing a system that will record all QC test results. Daily test reports shall document the following information:
(1) Technical specification item number and description
(2) Test designation
SAF182-19F Item C-100-6 Contractor Quality Control Program
(3) Location
(4) Date of test
(5) Control requirements
(6) Test results
(7) Causes for rejection
(8) Recommended remedial actions
(9) Retests
Test results from each day’s work period shall be submitted to the RPR prior to the start of the next day’s work period. When required by the technical specifications, the Contractor shall maintain statistical QC charts. When QC daily test results are recorded and transmitted electronically, the results must be archived.
100-10 Corrective action requirements. The CQCP shall indicate the appropriate action to be taken when a process is deemed, or believed, to be out of control (out of tolerance) and detail what action will be taken to bring the process into control. The requirements for corrective action shall include both general requirements for operation of the CQCP as a whole, and for individual items of work contained in the technical specifications.
The CQCP shall detail how the results of QC inspections and tests will be used for determining the need for corrective action and shall contain clear rules to gauge when a process is out of control and the type of correction to be taken to regain process control.
When applicable or required by the technical specifications, the Contractor shall establish and use statistical QC charts for individual QC tests. The requirements for corrective action shall be linked to the control charts.
100-11 Inspection and/or observations by the RPR. All items of material and equipment are subject to inspection and/or observation by the RPR at the point of production, manufacture or shipment to determine if the Contractor, producer, manufacturer or shipper maintains an adequate QC system in conformance with the requirements detailed here and the applicable technical specifications and plans. In addition, all items of materials, equipment and work in place shall be subject to inspection and/or observation by the RPR at the site for the same purpose.
Inspection and/or observations by the RPR does not relieve the Contractor of performing QC inspections of either on-site or off-site Contractor’s or subcontractor’s work.
100-12 Noncompliance.
a. The Resident Project Representative (RPR) will provide written notice to the Contractor of any noncompliance with their CQCP. After receipt of such notice, the Contractor must take corrective action.
b. When QC activities do not comply with either the CQCP or the contract provisions or when the
Contractor fails to properly operate and maintain an effective CQCP, and no effective corrective actions have been taken after notification of non-compliance, the RPR will recommend the Owner take the following actions:
(1) Order the Contractor to replace ineffective or unqualified QC personnel or subcontractors and/or
(2) Order the Contractor to stop operations until appropriate corrective actions are taken.
SAF182-19F Item C-100-7 Contractor Quality Control Program
METHOD OF MEASUREMENT
100-13 Basis of measurement and payment. Contractor Quality Control Program (CQCP) is for the personnel, tests, facilities and documentation required to implement the CQCP. The CQCP will be paid as a lump sum with the following schedule of partial payments:
a. With first pay request, 25% with approval of CQCP and completion of the Quality Control
(QC)/Quality Assurance (QA) workshop.
b. When 25% or more of the original contract is earned, an additional 25%.
c. When 50% or more of the original contract is earned, an additional 40%.
d. After final inspection and acceptance of project, the final 10%.
BASIS OF PAYMENT
100-14 Payment will be made under:
Item C-100 Contractor Quality Control Program (CQCP)
REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
National Institute for Certification in Engineering Technologies (NICET)
ASTM International (ASTM)
ASTM C1077 Standard Practice for Agencies Testing Concrete and Concrete
Aggregates for Use in Construction and Criteria for Testing Agency
Evaluation
ASTM D3665 Standard Practice for Random Sampling of Construction Materials
ASTM D3666 Standard Specification for Minimum Requirements for Agencies Testing and Inspecting Road and Paving Materials
END OF ITEM C-100
SAF182-19F Item C-102-1 Temporary Air and Water Pollution, Soil Erosion, and
Siltation Control
Item C-102 Temporary Air and Water Pollution, Soil Erosion, and Siltation Control
DESCRIPTION
102-1. This item shall consist of temporary control measures as shown on the plans or as ordered by the
Resident Project Representative (RPR) during the life of a contract to control pollution of air and water, soil erosion, and siltation through the use of silt fences, berms, dikes, dams, sediment basins, fiber mats, gravel, mulches, grasses, slope drains, and other erosion control devices or methods.
Temporary erosion control shall be in accordance with the approved erosion control plan; the approved
Construction Safety and Phasing Plan (CSPP) and AC 150/5370-2, Operational Safety on Airports
During Construction. The temporary erosion control measures contained herein shall be coordinated with the permanent erosion control measures specified as part of this contract to the extent practical to assure economical, effective, and continuous erosion control throughout the construction period.
Temporary control may include work outside the construction limits such as borrow pit operations, equipment and material storage sites, waste areas, and temporary plant sites.
Temporary control measures shall be designed, installed and maintained to minimize the creation of wildlife attractants that have the potential to attract hazardous wildlife on or near public-use airports.
MATERIALS
102-2.1 Grass. Grass that will not compete with the grasses sown later for permanent cover per Item T-
901shall be a quick-growing species (such as ryegrass, Italian ryegrass, or cereal grasses) suitable to the area providing a temporary cover. Selected grass species shall not create a wildlife attractant.
102-2.2 Mulches. Mulches may be hay, straw, fiber mats, netting, bark, wood chips, or other suitable material reasonably clean and free of noxious weeds and deleterious materials per Item T-908. Mulches shall not create a wildlife attractant.
102-2.3 Fertilizer. Fertilizer shall be a standard commercial grade and shall conform to all federal and state regulations and to the standards of the Association of Official Agricultural Chemists.
102-2.4 Slope drains. Slope drains may be constructed of pipe, fiber mats, rubble, concrete, asphalt, or other materials that will adequately control erosion.
102-2.5 Silt fence. Silt fence shall consist of polymeric filaments which are formed into a stable network such that filaments retain their relative positions. Synthetic filter fabric shall contain ultraviolet ray inhibitors and stabilizers to provide a minimum of six months of expected usable construction life. Silt fence shall meet the requirements of ASTM D6461.
102-2.6 Other. All other materials shall meet commercial grade standards and shall be approved by the
RPR before being incorporated into the project.
SAF182-19F Item C-102-2 Temporary Air and Water Pollution, Soil Erosion, and
Siltation Control
CONSTRUCTION REQUIREMENTS
102-3.1 General. In the event of conflict between these requirements and pollution control laws, rules, or regulations of other federal, state, or local agencies, the more restrictive laws, rules, or regulations shall apply.
The RPR shall be responsible for assuring compliance to the extent that construction practices, construction operations, and construction work are involved.
102-3.2 Schedule. Prior to the start of construction, the Contractor shall submit schedules in accordance with the approved Construction Safety and Phasing Plan (CSPP) and the plans for accomplishment of temporary and permanent erosion control work for clearing and grubbing; grading; construction; paving;
and structures at watercourses. The Contractor shall also submit a proposed method of erosion and dust control on haul roads and borrow pits and a plan for disposal of waste materials. Work shall not be started until the erosion control schedules and methods of operation for the applicable construction have been accepted by the RPR.
102-3.3 Construction details. The Contractor will be required to incorporate all permanent erosion control features into the project at the earliest practicable time as outlined in the plans and approved
CSPP. Except where future construction operations will damage slopes, the Contractor shall perform the permanent seeding and mulching and other specified slope protection work in stages, as soon as substantial areas of exposed slopes can be made available. Temporary erosion and pollution control measures will be used to correct conditions that develop during construction that were not foreseen during the design stage; that are needed prior to installation of permanent control features; or that are needed temporarily to control erosion that develops during normal construction practices, but are not associated with permanent control features on the project.
Where erosion may be a problem, schedule and perform clearing and grubbing operations so that grading operations and permanent erosion control features can follow immediately if project conditions permit.
Temporary erosion control measures are required if permanent measures cannot immediately follow grading operations. The RPR shall limit the area of clearing and grubbing, excavation, borrow, and embankment operations in progress, commensurate with the Contractor’s capability and progress in keeping the finish grading, mulching, seeding, and other such permanent control measures current with the accepted schedule. If seasonal limitations make such coordination unrealistic, temporary erosion control measures shall be taken immediately to the extent feasible and justified as directed by the RPR.
The Contractor shall provide immediate permanent or temporary pollution control measures to minimize contamination of adjacent streams or other watercourses, lakes, ponds, or other areas of water impoundment as directed by the RPR. If temporary erosion and pollution control measures are required due to the Contractor’s negligence, carelessness, or failure to install permanent controls as a part of the work as scheduled or directed by the RPR, the work shall be performed by the Contractor and the cost shall be incidental to this item.
The RPR may increase or decrease the area of erodible earth material that can be exposed at any time based on an analysis of project conditions.
The erosion control features installed by the Contractor shall be maintained by the Contractor during the construction period.
Provide temporary structures whenever construction equipment must cross watercourses at frequent intervals. Pollutants such as fuels, lubricants, bitumen, raw sewage, wash water from concrete mixing
SAF182-19F Item C-102-3 Temporary Air and Water Pollution, Soil Erosion, and
Siltation Control operations, and other harmful materials shall not be discharged into any waterways, impoundments or into natural or manmade channels.
102-3.4 Installation, maintenance and removal of silt fence. Silt fences shall extend a minimum of 16 inches (41 cm) and a maximum of 34 inches (86 cm) above the ground surface. Posts shall be set no more than 10 feet (3 m) on center. Filter fabric shall be cut from a continuous roll to the length required minimizing joints where possible. When joints are necessary, the fabric shall be spliced at a support post with a minimum 12-inch (300-mm) overlap and securely sealed. A trench shall be excavated approximately 4 inches (100 mm) deep by 4 inches (100 mm) wide on the upslope side of the silt fence.
The trench shall be backfilled and the soil compacted over the silt fence fabric. The Contractor shall remove and dispose of silt that accumulates during construction and prior to establishment of permanent erosion control. The fence shall be maintained in good working condition until permanent erosion control is established. Silt fence shall be removed upon approval of the RPR.
METHOD OF MEASUREMENT
102-4.1 Temporary erosion and pollution control work required will be performed as scheduled or directed by the RPR. Completed and accepted work will be measured as follows:
a. Temporary Pollution / Soil Erosion Control - Lump sum.
102-4.2 Control work performed for protection of construction areas outside the construction limits, such as borrow and waste areas, haul roads, equipment and material storage sites, and temporary plant sites, will not be measured and paid for directly but shall be considered as a subsidiary obligation of the
Contractor.
BASIS OF PAYMENT
102-5.1 Accepted quantities of temporary water pollution, soil erosion, and siltation control work ordered by the RPR and measured as provided in paragraph 102-4.1 will be paid for under:
Item C-102-5.1 Temporary Pollution / Soil Erosion Control – Lump Sum
Where other directed work falls within the specifications for a work item that has a contract price, the units of work shall be measured and paid for at the contract unit price bid for the various items.
Temporary control features not covered by contract items that are ordered by the RPR will be paid for in accordance with Section 90, paragraph 90-05 Payment for Extra Work.
REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
Advisory Circulars (AC)
AC 150/5200-33 Hazardous Wildlife Attractants on or Near Airports
AC 150/5370-2 Operational Safety on Airports During Construction
SAF182-19F Item C-102-4 Temporary Air and Water Pollution, Soil Erosion, and
Siltation Control
ASTM International (ASTM)
ASTM D6461 Standard Specification for Silt Fence Materials
United States Department of Agriculture (USDA)
FAA/USDA Wildlife Hazard Management at Airports, A Manual for Airport Personnel
END OF ITEM C-102
SAF182-19F Item C-105-1 Mobilization
Item C-105 Mobilization
105-1 Description. This item of work shall consist of, but is not limited to, work and operations necessary for the movement of personnel, equipment, material and supplies to and from the project site for work on the project except as provided in the contract as separate pay items.
105-2 Mobilization limit. Mobilization shall be limited to 10 percent of the total project cost.
105-3 Posted notices. Prior to commencement of construction activities, the Contractor must post the following documents in a prominent and accessible place where they may be easily viewed by all employees of the prime Contractor and by all employees of subcontractors engaged by the prime
Contractor: Equal Employment Opportunity (EEO) Poster “Equal Employment Opportunity is the Law” in accordance with the Office of Federal Contract Compliance Programs Executive Order 11246, as amended; Davis Bacon Wage Poster (WH 1321) - DOL “Notice to All Employees” Poster; and
Applicable Davis-Bacon Wage Rate Determination. These notices must remain posted until final acceptance of the work by the Owner.
105-4 Engineer/RPR field office. An Engineer/RPR field office is not required.
METHOD OF MEASUREMENT
105-5 Basis of measurement and payment. Based upon the contract lump sum price for “Mobilization” partial payments will be allowed as follows:
a. With first pay request, 25%.
b. When 25% or more of the original contract is earned, an additional 25%.
c. When 50% or more of the original contract is earned, an additional 40%.
d. After Final Inspection, Staging area clean-up and delivery of all Project Closeout materials as required by Section 90, paragraph 90-11, Contractor Final Project Documentation, the final 10%.
BASIS OF PAYMENT
105-6 Payment will be made under:
Item C-105 Mobilization
REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
Office of Federal Contract Compliance Programs (OFCCP)
Executive Order 11246, as amended
SAF182-19F Item C-105-2 Mobilization
EEOC-P/E-1 – Equal Employment Opportunity is the Law Poster
United States Department of Labor, Wage and Hour Division (WHD)
WH 1321 – Employee Rights under the Davis-Bacon Act Poster
END OF ITEM C-105
| Item C-100 Contractor Quality Control Program |
| Item C-102 Temporary Air and Water Pollution |
| Item C-105 Mobilization |
| Item D-701 Pipe for Storm Drains and Culverts |
| Item D-751 Manholes, Catch Basins, Inlets and Inspection Holes |
| Item P-151 Clearing and Grubbing |
| Item P-152 Excavation, Subgrade, and Embankment |
| Item P-610 Concrete for Miscellaneous Structures |
| P-620 Runway and Taxiway Marking |