This specification section details requirements for generator paralleling controls for medium- and low-voltage standby and essential electrical system generators. The controls must be compatible with switchgear, engine generators, automatic transfer switches, and related components, and will be installed indoors. Key technical requirements include a master control and display panel (touchscreen or digital/analog) that provides comprehensive status monitoring, metering information, control functions, and alarm capabilities for the generator system.

The specification covers detailed operational modes including emergency, manual, and exercising modes, with specific load management and system operation protocols. Critical functions include automatic generator starting and paralleling, load transfer, synchronization, and failsafe mechanisms. The controls must ensure sufficient generating capacity, manage load distribution, and maintain system efficiency. Installation, testing, and acceptance procedures are outlined, requiring factory testing, visual inspections, systems tests, and certification by a manufacturer's representative. The document also mandates two 4-hour training sessions for personnel on equipment operation and maintenance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11-01-22

26 23 13 - 1

SECTION 26 23 13

GENERATOR PARALLELING CONTROLS

PART 1 - GENERAL

1.1 DESCRIPTION

A. This section specifies the furnishing, installation, connection, and testing of indoor control components for medium- and low-voltage paralleling Standby and Essential Electrical System generators.

B. The generator paralleling controls shall be compatible and functional with the switchgear, engine generators, automatic transfer switches, remote annunciators, and all related components.

1.2 RELATED WORK

A. Section 25 10 10, ADVANCED UTILITY METERING: Electrical metering.

B. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS:

Requirements that apply to all sections of Division 26.

C. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS:

Requirements for personnel safety and to provide a low impedance path for possible fault currents.

D. Section 26 05 73, OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY:

Short circuit and coordination study, and requirements for a coordinated electrical system.

E. Section 26 13 13, MEDIUM-VOLTAGE CIRCUIT BREAKER SWITCHGEAR: Medium-voltage enclosures, busing, and circuit breakers for generator paralleling switchgear.

F. Section 26 23 00, LOW-VOLTAGE SWITCHGEAR: Low-voltage enclosures, busing, and circuit breakers for generator paralleling switchgear.

G. Section 26 32 13, ENGINE GENERATORS: Engine generators.

H. Section 26 36 23, AUTOMATIC TRANSFER SWITCHES: Automatic transfer switches.

1.3 QUALITY ASSURANCE

A. Quality Assurance shall be in accordance with Paragraph 1.4, QUALIFICATIONS (PRODUCTS AND SERVICES) in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.

1.4 FACTORY TESTS

A. Factory Tests shall be required.

B. Factory Tests shall be in accordance with Paragraph 1.6, MANUFACTURED

PRODUCTS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL

INSTALLATIONS, and the following requirement:

26 23 13 - 2

1. Generator paralleling controls shall be tested to assure that there are no electrical or mechanical defects. Tests shall be conducted in accordance with UL and ANSI standards.

1.5 SUBMITTALS

A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements:

1. Shop Drawings:

a. Per the requirements of Section 26 23 00, LOW-VOLTAGE SWITCHGEAR.

b. Include sequences of operation and interconnecting controls diagrams, showing connections to switchgear, generators, automatic transfer switches, and remote annunciators.

2. Manuals:

a. When submitting the shop drawings, submit companion copies of complete maintenance and operating manuals, including technical data sheets, wiring diagrams, and information for ordering replacement parts.

1) The terminals of wiring diagrams shall be identified to facilitate installation, maintenance, and operation.

2) Wiring diagrams shall indicate internal wiring for each piece of equipment and the interconnection between the pieces of equipment, including related equipment specified in other sections.

3) Provide a clear and concise description of operation, including detailed information required to properly operate the equipment.

4) Approvals shall be based on complete submissions of manuals together with shop drawings.

b. If changes have been made to the maintenance and operating manuals originally submitted, submit updated maintenance and operating manuals two weeks prior to the final inspection.

3. Test Reports:

a. Two weeks prior to the final inspection, submit certified field test reports and data sheets.

4. Certifications: Two weeks prior to the final inspection, submit the following.

26 23 13 - 3

a. Certification by the manufacturer that the generator paralleling controls conform to the requirements of the drawings and specifications.

b. Certification by the Contractor that the generator paralleling controls have been properly installed, connected, and tested.

1.6 APPLICABLE PUBLICATIONS

A. Publications listed below (including amendments, addenda, revisions, supplements, and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by the basic designation only.

B. International Code Council (ICC):

IBC-21..................International Building Code

C. National Fire Protection Association (NFPA):

70-23...................National Electrical Code (NEC)

99-21...................Health Care Facilities

110-22..................Emergency and Standby Power Systems

D. National Electrical Manufacturers Association (NEMA):

250-20..................Enclosures for Electrical Equipment (1000 Volts

Maximum)

ICS 6-16................Enclosures

E. Underwriters Laboratories Inc. (UL):

50-15...................Enclosures for Electrical Equipment

508A-18.................Standard for Safety Industrial Control Panels

PART 2 – PRODUCTS

2.1 GENERATOR PARALLELING CONTROLS

A. Generator paralleling controls shall be integral to the switchgear, or housed in a separate cubicle, or be integrated into the controls on each paralleled engine generator. The functional requirements are identical for all system topologies.

B. The generator paralleling controls shall perform automatic and manual operation, synchronization, load management, monitoring, and alarm annunciation functions of the paralleled engine generator system.

C. The control logic shall be distributed between the generator paralleling controls and each engine generator such that each engine generator is capable of starting and paralleling to the bus, in the event of failure of the generator paralleling controls and receipt of a start signal from any automatic transfer switch.

26 23 13 - 4

D. The master control and display panel shall be a touchscreen panel, or a combination of digital and analog control, monitoring, and alarm devices. The generator paralleling control logic and master control and display panel shall be such that the master controls will continue to function in the event of a master control and display panel failure.

1. The master control and display panel shall indicate the following status information:

a. Status of utility-source and generator-source buses.

b. Status of each utility- and generator-source circuit breaker, including protective relays if applicable.

c. Status of each engine generator, including start, run, stop, off, automatic operation, manual operation, speed in rotations per minute (RPM), oil pressure, coolant temperature, hours of operation.

d. Status of each automatic transfer switch.

2. The master control and display panel shall indicate and trend the following metering information on a per-phase, line-to-line, line-to-neutral, and summary basis as applicable.

a. Instantaneous and average volts, amperes, kilowatts, kilovars, kilovolt-amperes, frequency, and power factor for each utility and generator bus, and for each utility and generator source.

b. Demand amperes, kilowatts, and kilovolt-amperes for each utility and generator bus, and for each utility and generator source.

3. The master control and display panel shall provide the following control functions for each generator.

a. Automatic, manual, start, stop.

4. The master control and display panel shall provide the following system control functions.

a. Automatic, manual, exercise, test with load, and test without load operation.

b. Load management functions that monitor bus loads and automatically or manually control generators to meet system requirements, including prioritization of Essential and Normal

Electrical System loads and groups of loads as shown on the drawings, and operation under failure conditions of one or more engine generators.

c. Password-protected means to alter the system programming.

26 23 13 - 5

5. The master control and display panel shall provide the following alarm functions.

a. All alarms annunciated by each engine generator.

b. All system alarms.

E. The master control and display panel shall be powered by at least two sources, which may be from engine generator start batteries and/or switchgear station batteries.

F. Interconnecting Communications Protocol and Media: The generator paralleling controls shall be interconnected to the switchgear, engine generators, automatic transfer switches and the associated operator interface panels (OIP’s) by a dedicated EGD protocol. The network shall be per the requirements of Section 27 15 00, COMMUNICATIONS

HORIZONTAL CABLING. Provide all necessary fiber optic and copper media, raceways, hardware, software, and programming necessary to establish interconnection between all components. All equipment shall share a non-proprietary and open topology and communications protocol.

2.2 OPERATOR INTERFACE PANEL

A. An OIP shall be installed at locations as shown on the drawings.

B. The OIP shall indicate alarm conditions as required by NFPA 99 and 110.

C. Include control wiring between the controller and the engine generator.

Wiring shall be as required by the manufacturer.

2.3 PARALLELING OPERATION

A. Emergency Mode:

1. Upon initiation of the automatic start sequence, all engine generators shall start. The first engine generator to achieve 90% of nominal voltage and frequency shall be connected to the bus. All first priority loads shall be transferred to the bus upon sensing availability of power on the bus. As the remaining engine generators start, their respective synchronizers shall initiate control of voltage and frequency of the oncoming set with the bus. Upon synchronizing with the bus, the oncoming engine generator shall be paralleled on the bus. Each time an additional engine generator is added to the bus, the remaining loads shall be transferred in priority sequence, until all loads are connected to the bus. The generator paralleling controls shall prevent the automatic transfer of loads to the bus until there is sufficient capacity to carry these loads. Provision shall be made to manually override the load addition circuits for supervised operation.

26 23 13 - 6

2. Load management sensing shall be furnished to ensure that sufficient generating capacity is connected to the bus to carry the load. The load management sensing shall also ensure that not more than the required capacity plus a limited reserve is connected to the bus at any time. The system in conjunction with the load management shall ensure maximum efficiency in the utilization of engine generators to ensure maximum fuel economy.

3. Load management sensing shall ensure that the on-line reserve capacity does not fall to less than 10% or exceed more than 110% of a single engine generator. Upon sensing if the connected load exceeds the present limit for an established period of time, the next engine generator will be started and paralleled. If upon sensing, the connected load is determined to be less than the preset limit for an established period of time, the last engine generator to be paralleled will be disconnected and shut down. Its controls will be automatically reset so that the engine generator will be ready for next operation.

4. While one engine generator is connected to the bus, and if the connected load exceeds the capacity of the bus, resulting in a decrease in system frequency to 58 Hz or less, load dumping will be initiated to reduce the connected load within the capacity of the bus. Similarly, with increased loading, the remaining engine generator will be signaled to start and be paralleled to the engine generator already connected to the bus, and the load dump signal will be automatically cancelled. Upon restoration of the normal source of power supply, as defined in the generator paralleling controls for an adjustable period of 0 to 30 minutes, the loads shall be transferred back to the normal power source. Subsequently, the engine generator shall be disconnected from the bus, run for an adjustable period of time up to 15 minutes maximum for cool down, and then shut down. All controls associated with operation of the engine generator shall automatically reset for the next automatic operation.

B. Manual Mode: The engine generators and automatic transfer switch(es) can be operated manually.

C. Exercising Mode: Incorporate controls so as to allow automatic and manual testing of each engine generator and remotely located transfer switch.

26 23 13 - 7

PART 3 - EXECUTION

3.1 INSTALLATION

A. Installation shall be as shown on the drawings, manufacturer’s instructions, and per Section 26 23 00, LOW-VOLTAGE SWITCHGEAR.

3.2 ACCEPTANCE CHECKS AND TESTS

A. An authorized representative of the generator paralleling controls manufacturer shall technically supervise and participate during all of the field adjustments and tests. Major adjustments and field tests shall be witnessed by the COR. The manufacturer’s representative shall certify in writing that the equipment has been installed, adjusted, and tested in accordance with the manufacturer’s recommendations.

B. Perform in accordance with the manufacturer's recommendations. In addition, include the following:

1. Visual Inspection and Tests:

a. Compare equipment nameplate data with specifications and approved shop drawings.

b. Inspect physical, electrical, and mechanical condition.

c. Vacuum-clean enclosure interior. Clean enclosure exterior.

d. Verify appropriate equipment grounding.

e. Verify appropriate anchorage and required area clearances.

2. Systems Tests:

a. Verify proper operation of all control, monitoring, trending, and alarm functions.

b. Verify undisrupted operation of the system under conditions of loss of the generator paralleling controls.

c. Test and verify continuity of all interconnecting copper and fiber optic control media.

C. Perform all acceptance checks and tests specified in Section 26 23 00, LOW-VOLTAGE SWITCHGEAR, Section 26 32 13, ENGINE GENERATORS, and

Section 26 36 23, AUTOMATIC TRANSFER SWITCHES.

3.3 FOLLOW-UP VERIFICATION

A. Upon completion of acceptance checks, settings, and tests, the

Contractor shall demonstrate that the generator paralleling controls are in good operating condition and properly performing the intended function.

3.4 INSTRUCTION

A. Furnish the services of a factory-trained technician for two 4-hour periods to instruct personnel in the operation and maintenance of the

26 23 13 - 8 generator paralleling controls and related equipment on the date requested by the COR.