About this file
This is a Special Provisions document for the Washington Suburban Sanitary Commission (WSSC) Water in Maryland, outlining submittal procedures and construction requirements for the Buckler Road Water Main Replacement project. The project involves installing approximately 2.17 miles of water mains consisting of 0.33 miles of 4-inch diameter pipe, 1.35 miles of 8-inch diameter pipe, and 0.49 miles of 10-inch diameter pipe, along with approximately 1.14 miles of water house connections in Clinton, Prince Georges County, Maryland. Sealed responses are due via WSSC's eProcurement Portal by 2:00 pm on Wednesday, June 3, 2026, with late responses not accepted. The special provisions require contractors to provide project signs at five specified locations: the corners of Brandywine Road and Hellen Lee Drive, Brandywine Road and Buckler Road, Brandywine Road and Florence Court, Terence Drive and Paros Drive, and Clinton Manor Drive and Pin Oak Street.
The contract is subject to the American Iron and Steel (AIS) Act requirements, mandating that contractors submit a certification letter from manufacturers or suppliers on letterhead within two weeks of the Notice to Proceed identifying all products subject to AIS requirements, and before incorporating any AIS-eligible materials into the work. Contractors must submit all required AIS material certifications and identify any items for which AIS waivers are sought, with notifications to WSSC required within two days of waiver submittal or approval/rejection. Additionally, if construction encounters existing Lead Service Lines (LSL), Galvanized Requiring Replacement (GRR) service lines, or unknown service line materials, contractors must immediately cease activities and report to the WSSC Contract Manager before resuming work, with coordination required before construction begins if impacts to homes with LSL, GRR, or unknown service line materials are known.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract. No. SP-01330-1 Rev. 5-10-2023
SPECIAL PROVISIONS
SECTION 01330
SUBMITTAL PROCEDURES
Follow the requirements of Standard Specifications Section 01330 except as specified herein.
PART 1 GENERAL
1.1 DESCRIPTION
ADD
B. Compliance with the American Iron and Steel Act
1. This project or segment thereof is to be constructed in accordance with these contract documents and is subject to the requirements of the American Iron and Steel Act (AIS). AIS requirements are included by reference or attachment to the Contract Documents.
2. The CONTRACTOR shall provide all necessary documentation required to demonstrate compliance with the requirements of AIS. This material includes but is not limited to project material list and corresponding AIS certifications.
3. If a waiver is required for any provisions of the AIS requirements, follow the Step-By-Step Waiver Process described in the AIS document included in the Contract Documents. Notify WSSC of any submitted, approved or rejected waiver within 2 days of submittal or approval/rejections received. Approval of a waiver is the sole responsibility of the Contractor.
1.2 SUBMITTAL REQUIREMENTS
A. General
9. For materials subject to AIS, submit a certification letter from the manufacturer or supplier indicating that materials provided for the project meet the AIS requirements. The certification letter must be on manufacturer letterhead, specifically identify the project for which the certification applies, and meet all certification requirements identified in the AIS documents.
B. Process and Requirements
Contract. No. SP-01330-2 Rev. 5-10-2023
8. Within two weeks of the Notice to Proceed (NTP), submit a letter for information identifying all products for which AIS requirements apply.
9. Submit all AIS required material certifications before incorporating any AIS eligible materials into the work.
1.3 SUBMITTALS
A. Schedules, 1. Material Supply Availability
b. Within 14 days of the Notice to Proceed, submit a list of products subject to AIS requirements. If applicable, identify any items the Contractor believes are eligible for and for which the CONTRACTOR intends to submit an AIS waiver.
c. Include submittals and review times for project materials in the project schedule. Identify all materials subject to AIS in the schedule and if applicable, include anticipated submittal and review requests for any AIS waivers. No additional Contract time will be granted for review or denial of a waiver for which compliant materials are available.
SP-02514 April 2024
SPECIAL PROVISION
SECTION 02514
WATER MAIN REPLACEMENT WITH EXISTING LEAD,GRR OR UNKNOWN SERVICE LINE
PART 1 GENERAL
1.1 INTENT
A. It is the intent of this section to provide guidance in the event existing Lead Service Line (LSL), Galvanized Requiring Replacement (GRR) or unknown material service are encountered during watermain replacement located in the public Right of Way.
B. Commission records available may not confirm the presence of LSL,GRR service line within the project limits.
1.2 DESCRIPTION
A. The Contractor shall coordinate with WSSC Contract Manager before the construction begins.
If the construction is known to impact any homes with LSL, Galvanized Requiring Replacement (GRR), or homes with unknown service line material, construction shall not begin until WSSC notifies customers and verifies pipe material and/or coordinates for replacement of the service line prior to water main construction.
B. If the Contractor unexpectedly encounters an LSL or GRR during construction, the Contractor shall immediately cease further activities on the service line and report to WSSC Contract Manager on additional actions before construction resumes.
**WSSC Water**
SP-01500-1
SPECIAL PROVISIONS
SECTION 01500
TEMPORARY FACILITIES AND CONTROLS
Follow requirements of Standard Specifications Section 01500 except as specified herein.
PART 1 GENERAL
1.4 PROJECT SIGNS
B. Water Main Replacements, Relocations, and Cleaning and Lining Contracts.
5. Provide at:
a. Corner of Brandywine Rd and Hellen Lee Drive
b. Corner of Brandywine Rd and Buckler Rd
c. Corner of Brandywine Rd and Florence Court
d. Corner of Terence Dr and Paros Dr
e. Corner of Clinton Manor Dr and Pin Oak St
| SP Articles 1- 14.pdf |
| SP 01330 AIS.pdf |
| SP 02514.pdf |