This is a Special Conditions and Technical Specifications document for the City of Indianapolis Department of Public Works (DPW) related to RS-26-001 Crack Sealing 2026, a sealed bid procurement for pavement crack sealing and joint filling services. The project encompasses crack sealing work across numerous city streets totaling approximately 81.2 linear miles, with specific locations and quantities detailed in the Capital Improvement Plan database. Sealed bids are due October 1, 2026, at 10:00 a.m. prevailing local time, with bids accepted either through the Procurement Portal or in Room 1560 of the City County Building. The work involves sealing longitudinal and transverse cracks and filling other cracks in existing asphalt pavement using specified materials including PG 58S-28 asphalt binder and CrackMaster 3405 hot pour crack sealant, with work restricted to streets not resurfaced within the previous five years unless directed by the engineer.

Payment for crack sealing and filling services will be made by the ton of material used, with the cost of all materials, cover aggregate, temporary traffic controls, cleaning, and incidentals included in the bid price. Measurement and payment procedures comply with the latest approved edition of the Indiana Department of Transportation Standard Specifications, with specific requirements for material quality testing, weather limitations (minimum ambient temperature of 40 degrees Fahrenheit), and surface preparation standards. The contract requires compliance with Indiana Plan/Affirmative Action certification requirements, E-Verify procedures, prevailing wage and labor standards, and worker classification verification. Successful bidders must contribute at least 15 percent of their total contract price through their own organization's work, materials, or services, and maintain insurance coverage with occurrence limits of $1,000,000 and general aggregate limits of $2,000,000.

View the file

Other files

File Type Posted
RS-26-001_Crack_Sealing_2026_(Addendum_#1_Revision).pdf PDF
Additional_Declarations.pdf PDF
RS-26-001_Contract_Package.pdf PDF
Post_Bid_Documents.pdf PDF
General_Conditions.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL CONDITIONS Page i April, 2019

SPECIAL CONDITIONS

April 2019

Table of Contents

SC 1 Work Schedule Transmittal 1

SC 2 Right-of-Way 1

SC 3 Scope of Work 1

SC 4 Changes in Contract Time 2 (Use only when completion dates are specific calendar dates)

SC 5 Measurement And Payment 2

SC 6 Stockpiled Materials 8

SC 7 Service Connections Prior to Substantial and Final Completion 12

Note: Any of these Special Conditions may or may not be used in a particular project.

The designer shall carefully review the General Conditions for each project to determine, in consultation with DPW, which of these Special Conditions should be used and whether any additional project-specific Special Conditions are needed.

SPECIAL CONDITIONS Page 1

SPECIAL CONDITIONS

April 2019

SC 1 Work Schedule Transmittal

The following shall replace paragraph 2.7.4 of the General Conditions:

2.7.4 CONTRACTOR shall provide OWNER and CONSTRUCTION INSPECTOR, by 1:30 p.m. of the preceding weekday workday, a list of all Work activities scheduled for the following day. The list shall be submitted to OWNER by email at Owen.Williams@indy.gov The CONSTRUCTION INSPECTOR’s email address shall be furnished at the Pre-Construction Meeting for notification of the work schedule. All Work scheduled for Saturday and/or Monday shall be submitted by 1:30 p.m. on the preceding Friday. Failure of CONTRACTOR to provide such notice shall entitle OWNER to disallow payment for materials placed and Work performed that day.

SC 2 Right-of-Way

The following shall be an addition to paragraph 4.1 of the General Conditions:

All right-of-way required for the construction of this project has not yet been acquired. The following parcel(s) that remain to be acquired at the time of preparing this project for bidding are:

ANTICIPATED

STATION NAME DATE OF ACQUISITION

CONTRACTOR shall not perform any Work or encroach upon any parcel(s) referenced above until ENGINEER has issued written notification.

OWNER specifically disclaims any guarantee or warranty that any of these parcels will be acquired by the above dates. Should any or all said parcels not be acquired by the anticipated date(s), CONTRACTOR’s sole remedy shall be limited to an extension of contract time, as provided in Article 11.

CONTRACTOR shall not be entitled to any change in contract price due to any delays or hindrances in acquiring these parcels.

SC 3 Scope of Work

The following shall be an addition to paragraph 9.1 of the General Conditions:

OWNER reserves the right to increase or decrease the Scope of Work by adding and/or deleting [resurfacing] or [curb, sidewalk and ramp removal and replacement] or [sewer pipe mailto:steven.cassidy@indy.gov jcole Cross-Out

SPECIAL CONDITIONS Page 2 and structures] to this contract outside of the original construction limits, within [specify township] township.

SC 4 Changes in Contract Time [Use only when completion dates are specific calendar dates]

The following shall be an addition to paragraph 11.4 of the General Conditions:

An extended date of Substantial Completion, Intermediate, and Final Completion shall be allowed for each calendar day for delay in the issuance of the Notice to Proceed if the Notice to Proceed is not issued within 45 days of the bid award except if the delay is due to the failure of the Contractor to furnish requested forms or information.

SC 5 Measurement and Payment

The following shall be added to paragraph 13.2 of the General Conditions:

13.2.1 Measurement and payment for all items as listed within the “Contract Pay Items” (Section 100 of the Technical Specifications, labeled per UNIT or LUMP SUM) will be in accordance to the procedures as described within the latest approved and adopted edition of the Indiana Department of Transportation Standard Specifications, unless specified otherwise within the Technical Specifications.

13.2.2 If a “Contract Pay Item” for a particular item is not listed within the latest approved and adopted edition of the INDOT Standard Specifications, refer to the Technical Specification, which will set out payment and measurement herewith.

13.2.3 Measurement of Quantities for Sanitary Sewer Systems:

1. Measurement of sanitary sewers shall be listed within the “Description of Pay Items” for sanitary sewer systems.

13.2.4 Measurement of Quantities for Streets and Roads:

1. Streets and Roads Measurement: General Requirements.

a. The method of measurement and computations to be used in determination of quantities of material furnished and of Work performed under the contract will be those methods generally recognized as conforming to good engineering practice.

b. Unless otherwise specified, longitudinal measurements for base, surface, and shoulder area computations will be made along the centerline of the actual surface of the roadway. No deduction will be made along the centerline of the actual surface of the roadway. No deduction will be made for individual fixtures having an area of 10 Sq. Ft. or less. Unless otherwise

SPECIAL CONDITIONS Page 3 specified, transverse measurements for area computations will be the neat line dimensions shown on the plans or ordered in writing.

c. Structures will be measured according to neat lines shown on the plans or as altered to fit field conditions.

d. When a complete structure or structural unit (in effect lump sum Work) is specified as the unit of measurement, the unit will be constructed to include all necessary fittings and accessories.

e. All Work, which is measured by the linear foot, will be measured parallel to the base or foundation upon which Work is placed, unless otherwise specified.

f. A station when used as a definition or term of measurements will be 100 linear feet.

g. The term gage, when used in connection with the measurement of metal plates or sheets, will mean the U.S. Standard Gage except when the referenced AASHTO, ASTM, or other specifications for a material specifies that it be ordered and measured in terms of thickness.

h. When the term gage refers to the measurement of wire, it will mean the U.S.

Steel Wire Gage except when the reference AASHTO, ASTM, or other specification for the wire specifies that it be ordered and measured in terms of a wire size number or diameter.

i. The term ton will mean the short ton consisting of 2,000 pounds avoirdupois.

All materials which are measured or proportioned by mass (weight) shall be weighed on accurate approved scales, which are in accordance with all requirements and specifications adopted, by the Indiana State Board of Health, Division of Weights and Measures. Competent qualified personnel at designated locations shall accomplish the weighing.

13.2.5 Scales and Measurement by Mass (Weight):

1. All materials for which measurements are obtained by mass (weight) shall be weighed on approved scales, which, except as hereinafter provided for out-of-state scales, shall be tested and sealed, by the Indiana State Board of Health, Division of Weights and Measures. This inspection shall have been made within a period of not more than one year prior to the date of use for weighing material. A scale, which as been tested and approved within this one-year period and which has been repaired or dismantled or moved to another location, shall again be tested and approved before it is eligible for weighing.

All interested parties, such as OWNER, CONTRACTOR, or the owner of the scales, may request an inspection of the scales in question. The latest inspection shall take precedence over all previous inspections. Automatic printer systems may be used with HMA plant scale systems under certain conditions in accordance with Section 409 in the latest approved and adopted

SPECIAL CONDITIONS Page 4 edition of the INDOT Standard Specifications. If automatic printer systems are used, the same inspection, testing, and scaling requirements specified herein for scales shall apply to HMA plant batch scales and printer systems.

2. A motor-truck scale shall have a suitable undercarriage of such construction that shall safely carry and weigh an amount equal to 80% of the rated capacity of the scale on either end of the scale platform. When so loaded, the stresses in the lever system shall not exceed the stresses allowable under AREA specifications. The load carried per 25 mm (1 in.) of knife-edged bearing shall not exceed 2270 kg (5,000 lb.)

3. The scale platform shall be of such length and width as to conveniently accommodate all trucks containing materials, which need to be weighed. The entire truckload shall rest on the scale platform and shall be weighed as one draft.

4. If material is weighed on truck scales, weigh tickets showing the net mass (weight) of each load of material delivered shall be supplied for use in computing quantities. The tickets shall contain the weight ticket serial number, date, contract number, source of supply, material designation such as size or type, DMF or JMF number for HMA, truck number, time weighed, gross mass (weight) direct reading if scale is of the direct reading type, tare, net mass (weight) and moisture content if applicable. The CONTRACTOR for its records may furnish a duplicate ticket. The original, and duplicate if furnished, tickets will be signed at the weighing site and at the point of incorporation into the Work. No additional payment will be made for furnishing, maintaining, and operating scales.

5. The mass (weight) of materials weighed outside Indiana and intended for use on the project may be determined on scales tested and approved by the proper governmental unit having authority where the scales are located. In such case, OWNER shall be furnished with a certified copy of such inspection and approval which, to be acceptable, shall have been made within one year prior to the time of such weighing. Out-of-state truck scales used shall be in accordance with all pertinent provisions as they apply to truck scales accepted within the State of Indiana. They shall be subject to approval and inspection by OWNER or ENGINEER and to the requirements applicable to such scales located within Indiana.

6. If materials are shipped by rail, the car mass (weight) may be accepted provided payment is made for only the actual mass (weight) of the materials.

Car masses (weights) will not be acceptable for material to be passed through mixing plants. Trucks used to haul material being paid for by mass (weight) shall be weighed empty daily at such times as directed. Each truck shall bear a plainly legible identification mark.

7. General Requirements:

SPECIAL CONDITIONS Page 5

a. The method of measurement and computations to be used in determination in approved vehicles and measured therein at the point of delivery. Vehicles for this purpose may be of the size or acceptable type provided the body is of such shape that the actual contents may be determined readily and accurately. All vehicles shall be loaded to at least their water level capacity. All loads shall be leveled when directed after the vehicles arrive at the point of delivery.

b. When requested and approved in writing, material specified to be measured by the cubic yard may be weighed. Factors for conversion from mass (weight) measurement to volume measurement will be determined and shall be agreed to by CONTRACTOR before such method of measurement of pay quantities is used.

i. In computing volumes of excavation, the average end area method or other acceptable methods will be used.

ii. If excavation is measured by cross sections, the following will apply:

1. Unless otherwise provided, where sodded areas are involved, the cross sections will be considered as located at the surface of the sod.

2. If the cost of excavation is specifically included in the payment of a pay item of Work, the final sections will be taken at the finished surface of the Work.

3. If the cost of excavation is not specifically included in the payment for a pay item of Work, the final sections will be taken at the limits of the authorized excavation.

4. Unauthorized wastage of material will be deducted. Only such quantities as are actually incorporated in to the completed Work will be included in the final estimate.

8. Additional Requirements:

a. Partial payment will not be allowed on an estimate for materials of less than $10,000 in value.

b. OWNER may consider partial payment for stockpiled materials having a value over $25,000. This consideration will only take place when the Work on the controlling operation has been delayed and justifies an extension of more than 60 calendar days or 40 Work days in accordance with the General Conditions and Contract Documents. Partial payment will be the delivered cost verified by invoices, except it will not exceed 50% of the contract unit price.

SPECIAL CONDITIONS Page 6

c. All materials when so paid for under this requirement will become the property of OWNER in the event of default on the part of CONTRACTOR.

OWNER may use, or cause to be used, such materials in the construction of the Work provided for in the Contract.

d. Although payment may have been made for materials, CONTRACTOR shall be responsible for loss or damage to the materials. Such materials shall be replaced with no additional payment.

e. Approval of partial payment for stockpiled materials will not constitute final acceptance of such materials for use in completing the Work. Structural Steel members and pavement reinforcing steel may be subjected to additional inspection and testing prior to final acceptance and incorporation into the Work. All other stockpiled pay items will be subjected to additional inspection and testing prior to final acceptance and incorporation into the Work.

f. Partial payments for stockpiled materials that are a portion of the pay item will be deducted from estimates due CONTRACTOR as the material is incorporated in the Work.

13.2.6 Measurement of Asphalt Materials:

1. If an asphalt material is to be paid for directly, it will, except as hereinafter provided, be weighed and paid for by the ton. If ENGINEER decides that weighing is not feasible, the asphalt material may be measured by volume and converted to tons. The conversion will be based on the unit weight as determined in the laboratory.

2. If asphalt material is to be measured by volume, the gallon in tank cars will measure it, distributor tanks, tanks, or drums. Certified calibration of tank cars, distributor tanks and certified quantities in drums in which asphalt materials are delivered or stored shall be furnished.

3. If asphalt material is furnished in drums, the producer shall stencil the amount in each drum plainly on the drumhead. The amount so indicated will be accepted as the quantity furnished. However, the amount in each drum may be checked in accordance with the requirements set out herein.

4. Tank car deliveries will be measured by volume and converted to tons.

5. Volumes will be measured at 60o F or will be corrected to the volume at 60o F in accordance with ASTM D 1250 for asphalts or ASTM D 633 for tars.

6. Net certified scale weights or certified weights in the case of rail shipments will be used as a basis of measurement, subject to correction when asphalt material has been lost from the car or the distributor, is wasted, or is otherwise not incorporated into the Work.

SPECIAL CONDITIONS Page 7

13.2.7 Measurement of Portland Cement Concrete.

1. For design and production, portland cement concrete will be measured by the cubic yard. The relative yield will be determined in accordance with Section 505 in the latest approved and adopted edition of the INDOT Standard Specifications. Payment for portland cement concrete will be in the unit designated for the specified use.

13.2.8 Measurement of Aggregates:

1. Unless otherwise provided, all aggregates for which measurements are obtained by the cubic yard will be measured at the truck loading point in truck beds that have been measured, stenciled, and approved. They may be weighed and converted to cubic yards by a conversion factor computed at sufficient intervals to ensure correct measurement.

2. Free water in all aggregates for which payment is made as a separate pay item on a weight basis shall be drained prior to weighing and selection of samples.

Samples for determination of moisture content shall be taken immediately prior to the time the material is to be weighed. The number of moisture tests will be governed by moisture conditions. Moisture contents shall be determined on the basis of oven dry weight by drying samples to constant weight at 110°C.

However, if ovens are not available for drying samples, other methods, which give equivalent results, may be used. Moisture content shall be computed to the nearest 0.5% in accordance with the formula as follows:

Percent of Wet weight of sample-Dry weight of sample Moisture (M) = ---------------------------------------------------------× 100%

Dry weight of sample

3. The percent of moisture shall be noted on each weight ticket.

4. The wet weight will be used for the basis of payment, if the percent of moisture is determined to be less than 6% for B borrow; 9% of optimum moisture content, as determined in accordance with AASHTO T 99 except as modified in Section 203 in the latest approved and adopted edition of the INDOT Standard Specifications, whichever is greater, for size No. 53 or No. 73 aggregates or modifications thereof when specified; or 4% for aggregates of all other specified sizes including sand.

5. If the percent of moisture exceeds the limitations set out above, the weight to be paid for will be the gross weight of aggregate minus the weight of the excess moisture computed as follows:

(100+m) Weight to be paid for = G × -----------------

(100+M) in which:

SPECIAL CONDITIONS Page 8

G = Gross weight of material M = Percent of moisture in the aggregate to the nearest 0.5% bases on oven dry weight m = Percent of moisture permitted in the wet aggregate to be paid for based on oven dry weight

13.2.9 Measurement of Timber or Lumber;

1. Timber or lumber will be measured by the thousand feet board measure or MFBM actually incorporated in the Work. Measurement will be based on nominal widths and thicknesses and the extreme length of each piece.

13.2.10 Manufactured Material:

1. If standard manufactured materials are specified such as fence, wire, plates, rolled shapes, pipe, or conduit, and such materials are identified by gate, unit weight, or section dimensions, such identification will be considered to be nominal weights or dimensions. Unless more stringently controlled by tolerances in cited specifications, manufacturing tolerances established by the industries involved will be accepted.

13.2.11 Scope of Payment:

1. If it is agreed in writing that the quantities of certain items or portions of items of Work, as set forth in the contract documents, are in substantial agreement with actual quantities of Work performed, compensation there of will be based on the quantities set forth in the contract without measurement thereof upon completion of the Work. Compensation based on contract quantities as agreed shall be accepted as full payment for such items or portions of items.

2. If CONTRACTOR has previously agreed in writing to accept photogrammetric methods of measurement for common excavation and borrow, the OWNER may utilize such methods of measurements as the basis of payment.

Computation of volumes shall be in accordance with Section 203 in the latest approved and adopted edition of the INDOT Standard Specifications.

SC 6 Stockpiled Materials

The following shall be an addition to paragraph 13.3 of the General Conditions:

13.3.1 Description

1. This Work shall consist of the partial payment for certain stockpiled materials.

13.3.2 General Requirements:

1. After certified copies of costs are presented, partial payments may be allowed for tested and acceptable nonperishable materials purchased or produced

SPECIAL CONDITIONS Page 9 expressly to be incorporated into the Work and delivered in the vicinity of the project, or stored in approved storage facilities. Such materials shall be limited to pipe, sewer structures, permanent pumps, manholes, Structural Steel, Concrete Structural Members, pavement reinforcing steel, pavement contraction joints, granular base and sub-base materials, aggregates for signals, signs, and luminaries.

13.3.3 Pipe, Pumps, Controls, Structures, Wet Wells and Manholes:

1. Partial payment for any of these pay items will be considered only when the total quantity for an entire structure, or designated unit of a structure as specified on the plans, has been stored on site in an acceptable manner.

a. Delivered to the Job Site: Partial payment made under the requirements of this paragraph will be the delivered cost of the pipe and manholes or structures, as verified by invoices, including freight, furnished by CONTRACTOR. However, such partial payment will not exceed 75% of the contract unit price as set out in the Schedule of Pay Items for pipe or manholes or structures. Prior to authorizing partial payment, verification will be obtained that all required inspection has been made and the items are acceptable and they are acceptably stored.

b. Acceptably Stored at the Contractor’s, Fabricator's or Manufacturer's Storage Facilities. Partial payment made under the requirements of this paragraph will be the delivered cost of grinder pumps, pumps, controls and wet wells, minus freight charges, as verified from invoices furnished by CONTRACTOR. However, such partial payment will not exceed 70% of the contract unit price as set out in the Schedule of Pay Items under the lump sum items of Grinder Pumps or Lift Stations. Under this requirement, all invoices shall show the location of where the material is being stored.

Prior to authorizing partial payment, verification will be obtained that all required inspection has been made, the items are acceptable and they are acceptably stored.

13.3.4 Structural Steel and Concrete Structural Members:

1. Partial payment for either of these pay items will be considered only when the total quantity for an entire structure, or designated unit of a structure as specified on the plans, has been completely fabricated.

a. Delivered to the Job Site. Partial payment made under the requirements of this paragraph will be the delivered cost of the Structural Steel and Concrete Structural Members, as verified by invoices, including freight, furnished by CONTRACTOR. However, such partial payment will not exceed 75% of the contract unit price as set out in the Schedule of Pay Items for Structural Steel or Concrete Structural Members. Prior to authorizing partial payment, verification will be obtained that all required inspection has been made and the members are acceptable.

SPECIAL CONDITIONS Page 10

b. Acceptably Stored at the Fabricator's or Manufacturer's Storage Facilities.

Partial payment made under the requirements of this paragraph will be the delivered cost of and Concrete Structural Members, minus freight charges, as verified from invoices furnished by CONTRACTOR. However, such partial payment will not exceed 70% of the contract unit price as set out in the Schedule of Pay Items for Structural Steel or Concrete Structural Members. Under this requirement, all invoices shall show the location of where the material is being stored. Prior to authorizing partial payment, verification will be obtained that all required inspection has been made, and the members are acceptable and they are acceptably stored.

13.3.5 Dowel Bar Assemblies:

1. Partial payment made under the requirements herein will be the delivered cost of the dowel bar assemblies stored within the project limits or at a storage facility adjacent to the project site. Basis of payment for the dowel bar assemblies shall be the paid invoices furnished by CONTRACTOR. Prior to authorizing partial payment, verification will be obtained that the dowel bars have been tested and are acceptable.

13.3.6 Granular Base, Sub-base Materials, and Aggregates for HMA and Concrete Pavements:

1. Partial payment made under the requirements of this paragraph will be made upon presentation of paid invoices or certified copies of the cost for the production of such materials. The partial payment shall not exceed 30% of the unit price bid for the base or sub-base material item as set out in the Schedule of Pay Items. The invoice or certified copies of the cost shall include an estimated quantity of the materials stored for partial payment. ENGINEER shall verify the estimated quantity of materials before payment.

2. The approved storage site shall be within the project limits, at CONTRACTOR's adjacent storage facility, or at a production site where the designated materials are either assigned to, or owned by CONTRACTOR.

3. Materials stored under this requirement shall be kept separate from other production and shall not be used except on the assigned contract, unless otherwise approved in writing.

4. Testing shall be provided as directed, during production. Prior to authorizing partial payment, verification will be obtained that the materials have been tested and are acceptable.

13.3.7 Bridge Expansion Joints:

1. Type SS:

a. Partial payment will be the delivered cost of the expansion joint SS, as verified by invoices, except it will not exceed 75% of the contract unit price

SPECIAL CONDITIONS Page 11 for expansion joint SS. Prior to authorizing partial payment, verification will be obtained that all required inspections have been made and the joint is acceptable.

2. Type M:

a. Partial payment will be the delivered costs of the expansion joint M, as verified by invoices, except it will not exceed 75% of the contract unit price for expansion joint M. Prior to authorizing partial payment, verification will be obtained that all required inspections have been made and the joint is acceptable.

13.3.9 Structural Supports for Signals, Signs and Luminaries:

1. Partial payment will be the delivered cost of the materials, as verified by the invoices, except it will not exceed 50% of the contract unit price for the structural support which is stored within the project limits or at an approved storage facility adjacent to the project site. Prior to authorizing partial payment, verification will be obtained that the material has been tested and is acceptable.

13.3.10 Precast Concrete Median Barrier:

1. Partial payment for precast concrete median barrier as stockpiled material will be the delivered cost of the materials, including freight, as verified by invoices furnished by CONTRACTOR. Such partial payment will not exceed 50% of the contract unit price for the median barrier. The concrete barrier shall be stored within the project limits or at an approved storage facility adjacent to the project in order for stockpiled material payment to be favorably considered.

13.3.11 Method of Measurement:

1. No measurement will be made. However, the amount will be substantially verified before authorization for payment.

13.3.12 Basis of Payment:

1. Stockpiled materials, which are authorized for payment in accordance with the requirements herein, will be paid for in accordance with the Contract Documents.

2. Payment will be made under:

Pay Item English Pay Unit Symbol Stockpile Material, LFT

Type of Material

EACH

CYS

SYS

TON

SPECIAL CONDITIONS Page 12

LBS

Structural Steel LS Structural Members, Concrete LS Structural Expansion Joint_____ LFT

Type

SC 7 Service Connections Prior to Substantial and Final Completion

The following shall be an addition to paragraph 13.12 of the General Conditions:

CONTRACTOR agrees that if OWNER authorizes a request by governing authorities to make a connection(s), it will be made after Partial Substantial Completion and prior to Final Acceptance of the Project. Such requests for connection will be accompanied by a certification from the Marion County Health Department documenting that the connection is necessary to eliminate an existing health hazard. Non-emergency connections may also be allowed with approval from OWNER. Partial Substantial Completion shall be defined as the completion of all requirements necessary to enable the proper functioning of the sanitary sewer and necessary appurtenances both adjacent to and downstream of the property having the existing health hazard. This shall include, but not be limited to, all necessary testing as required by the laws and regulations of OWNER and the Contract Documents. OWNER shall determine partial Substantial Completion.

END OF SPECIAL CONDITIONS

ADOPTED

11-12-2024

408-DPW-001 – SEALING OR FILLING CRACKS AND JOINTS

This technical specification is intended for inclusion in contracts at the direction of the DPW Project Manager and pavement engineer only.

Description This work shall consist of sealing or filling longitudinal and transverse cracks and joints in existing asphalt pavement in accordance with the City of Indianapolis Standard General Conditions for Construction Contracts, current edition, Article 6.30. If a street that is on Appendix “A” does not appear to have been resurfaced within the last 5 years, it shall not be crack sealed unless directed by the ENGINEER.

Full lane width transverse cracks and longitudinal joints shall be sealed. All other cracks shall be filled.

Materials Materials shall be in accordance with the following:

Asphalt Binder, PG 58S-28* ........................................902.01(a) and

902-DPW-001

Asphalt Emulsion for Crack Filling, AE-90S .............. 902.01(b) Fine Aggregates, No. 23 or No. 24 .............................. 904.02 Joint Sealing Materials ................................................. 906.02(a)2

* A PG 58S-28 asphalt binder shall be used to fill cracks on a surface that is milled in accordance with 306, and polypropylene fibers shall be used only in conjunction with warranted micro-surfacing.

CONSTRUCTION REQUIREMENTS

Equipment A distributor in accordance with 409.03 shall be used when crack filling with asphalt emulsion or an indirect-heat double boiler kettle with mechanical agitator shall be used when filling with hot poured material. An indirect-heat double boiler kettle with mechanical agitator shall be used when routing and sealing. Air compressors shall be capable of producing a minimum air pressure of 100 psi.

Weather Limitations Sealing or filling operations shall not be conducted on a wet surface, when the ambient temperature is below 40°F, or when other unsuitable conditions exist, unless approved by the Engineer.

Sealing Cracks and Joints Cracks and joints shall be cleaned by blowing with compressed air or by other suitable means. The operation shall be coordinated such that routed materials do not encroach on pavement lanes carrying traffic and all routed materials are disposed of in accordance with 104.07. Cracks and joints shall be sealed with hot poured joint sealant to within 1/4 in. below the surface in accordance with the manufacturer’s recommendations.

408-DPW-001

ADOPTED

11-12-2024

408-DPW-001

Filling Cracks Cracks shall be cleaned by blowing with compressed air or by other suitable means.

Asphalt material shall be placed utilizing a “V” shaped wand tip, to allow the penetration of the materials into the cracks. The cracks shall be completely filled or overbanded not to exceed 5 in., or as required. All excess asphalt material shall be removed from the pavement. The filled cracks shall be covered with sufficient fine aggregate or other suitable material to prevent tracking of the asphalt materials. All excess cover material shall be removed from the pavement within 24 h, when directed. Application of asphalt materials shall be completed without covering existing pavement markings. When traffic is to be maintained within the limits of the section, temporary traffic control measures in accordance with 801 shall be used. Treated areas shall not be opened to traffic until the asphalt material has been absorbed.

Existing crosswalks and decorative crosswalks are to be gapped and covered to protect from crack fill material dripping, tracking or covering them in any way.

Method of Measurement Sealing and filling of cracks and joints in asphalt pavements will be measured by the ton of material used.

Basis of Payment Sealing and filling of cracks and joints in asphalt pavements will be paid for by the ton of material used for the type specified.

Payment will be made under:

Pay Item Pay Unit Symbol

Cracks and Joints in Asphalt Pavement, Seal ....................... TON Cracks in Asphalt Pavement, Fill .......................................... TON

The cost of all materials, cover aggregate, temporary traffic controls, cleaning, and all necessary incidentals shall be included in the cost of the pay items in this section.

PRODUCT DESCRIPTION

CrackMaster 3405 is a single component, hot applied crack and joint sealant. When melted and properly applied it forms a resilient crack sealant for both asphaltic and cementatious pavements. CrackMaster 3405 meets ASTMD3405, ASTM-D6690 Type I, II, and III, AASHTO-M301.

USES

CrackMaster 3405 is designed to seal expansion joints, longitudinal and transverse cracks, joints between concrete and asphalt shoulders, and random cracks in both asphalt and concrete pavements.

COMPOSITION

As supplied, CrackMaster 3405 is supplied in solid blocks comprised of asphaltic resins and synthetic polymer rubber.

COLOR

Black.

LIMITATIONS

Do not overheat material. Cracks must be free from moisture, dust, loose aggregate and other contaminates prior to application.

TECHNICAL DATA

CrackMaster 3405 meets the following material requirements when tested in accordance with ASTM D6690 Type 1, II, & III, AASHTO M324, Type II, ASTM D3405, and SSS-1401C (see chart below).

Chemical & Physical Analysis

Recommended Pour Temperature 370-390°F

Maximum Heating Temperature 410°F

Cone Penetration at 25°C 90 Max.

Resiliency 60% Min.

Flow at 140°F (5h) 3 mm Max.

Bond: -20°F/50% Ext Passes 3 cycles

Bond: 0°F/100% Ext Passes 3 cycles

Bond, water immersed Passes 3 cycles at 50% ext.

at -29°C

Specific Gravity 1.14

Asphalt Compatibility Compatible

Viscosity 35 ± 20 poise

ENVIRONMENTAL CONSIDERATIONS

CrackMaster 3405 is considered a non-hazardous material.

INSTALLATION

Proper surface preparation will facilitate adequate adhesion and consequently the maximum service life of the sealant. The crack must be free from moisture, dust, and loose aggregate. Routing or wire brushing are preferred methods followed by a compressed air heat lance immediately prior to sealing. The substrate and air temperature must be above 40°F.

METHODS

CrackMaster 3405 shall be melted in a conventional oil jacketed unit equipped with an agitator and temperature control device for both material and heat transfer oil. Carefully insert blocks of material (with plastic bag) into melting equipment with agitator turned off. Load material slowly to avoid splashing.

After the initial load of material has reached the recommended pouring temperature (370-390°F), fresh material may be added as sealant is used. Melt only enough material that will be used the same day.

Avoid overheating material. Excessive heat could cause material to gel in the equipment or fail in crack and joints. A significant viscosity increase accompanied by stringiness signals the approach of gelation. If this occurs, immediately remove the material from the melter and dispose of it.

IMPORTANT

Protective apparel is recommended with application of CrackMaster 3405. The extremely hot material will cause severe burns on contact with skin. OSHA Safety Regulations require workers to wear the following types of safety attire (see current OSHA/Safety Regulations for additional information): Hard hat with face shield; long sleeved shirt buttoned at the wrist; heat resistant gloves;

long, cuffless pants; and safety toed work boots. Make certain all area around melter is clear of all debris and flammable materials. Avoid breathing vapors. Use with adequate ventilation.

MIXING PROCEDURES

Use material as supplied. Do not blend with other materials. After CrackMaster 3405 is melted it should be agitated or recirculated.

SMT-191

REVISED 3/20/23

Technical Data Sheet

Geographical Performance of CrackMaster 3405 Pavement Temperatures (Farenheit)

-40 -30 -20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160

Scale: Recommended Limited Not Recommended

CRACKMASTER 3405

Hot Pour Crack Sealant

Appendix "B"

Page

APPLICATION

Apply heated CrackMaster 3405 using either a pump and wand system or a pour pot. For best results the sealant depth to width ratio should not exceed 2 to 1 (i.e.

2-inches deep to 1-inch wide). The cooled sealant height should not exceed 1/8” above surrounding pavement.

Using a sealing shoe or squeegee, band the material 2 to 3 inches wide over the crack.

ESTIMATING MATERIAL REQUIREMENTS

Use the following chart as a guideline for estimating material requirements (based upon pounds of material needed for 100 feet of cracks):

Crack Width Depth Lbs/100 Ft

3/8” 3/8” 6.9 lbs.

3/8” 1/2” 9.3 lbs.

1/2” 1/2” 12.3 lbs.

1/2” 1” 24.7 lbs.

3/4” 1/2” 18.5 lbs.

3/4” 3/4” 27.8 lbs.

The above coverage rates are only a guideline. Actual material usage may vary due to width of application and thickness of material above pavement surfaces.

PRECAUTIONS

Cracks must be free from moisture, dust, dirt, and debris.

Both substrate and air temperature must be above 40°F.

Keep boxes of material dry during storage. Do not store in direct sunlight.

PACKAGING AND AVAILABILITY

CrackMaster 3405 is supplied in both meltable packaging and cardboard cartons. CrackMaster Hot Pour Crack Sealants are supported by a nationwide network of SealMaster facilities along with a national and international network of professional applicators.

WARRANTY AND DISCLAIMER

The statements made on this technical data sheet are believed to be true and accurate and are intended to provide a guide for approved application practices.

As workmanship, weather, construction, condition of pavement, tools utilized, and other variables affecting results are all beyond our control, the manufacturer warrants only that the material conforms to product specifications and any liability to the buyer or user of this product is limited to the replacement value of the product only. The manufacturer expressly disclaims any implied warranties of merchantability or fitness for a particular purpose.

Copyright © InFrasys, Inc. All rights reserved. Reproduction of any of this material is strictly prohibited.

SMT-191

REVISED 3/20/23

Technical Data Sheet

CRACKMASTER 3405

Hot Pour Crack Sealant

Phone: 1-800-395-7325 www.sealmaster.net

Appendix "B"

Page

CIP Database Capital Outputs

EID Element Name From/At To Capital Output Unit Code

Proposed Quantity

E0026-791 Rutherglen Way Dandy Trail Kathcart Way Crack Sealing LMiles 0.1 E0026-790 Blain Way Glen Stewart Way Kathcart Way Crack Sealing LMiles 0.2 E0026-789 Glen Stewart Way Kimcoe Ln Blain Way Crack Sealing LMiles 0.3 E0026-788 Kimcoe Ln Deliane Ct Glen Stewart Way Crack Sealing LMiles 0.1 E0026-787 Delaine Ct Kartpath Way Cul-de-sac Crack Sealing LMiles 0.1 E0026-781 Kathcart Way Kimcoe Ln Cul-de-sac Crack Sealing LMiles 0.3 E0026-301 Michigan St I-70 ( On Ramp) W South St Crack Sealing LMiles 2.4 E0025-702 16th St Delaware St College Ave Crack Sealing LMiles 2.0 E0025-699 16th St Waterway Blvd Indiana Ave Crack Sealing LMiles 4.0 E0024-573 80th St Keystone Ave Westfield Blvd Crack Sealing LMiles 1.5 E0023-539 Central Ave 29th St 34th St Crack Sealing LMiles 2.5 E0023-537 Doctor MLK Jr St Fall Creek Blvd 30th St Crack Sealing LMiles 1.8 E0023-534 Kessler Blvd E DR Allisonville Rd Emerson Way Crack Sealing LMiles 1.8 E0023-527 Westfield Blvd 75th St 79th St Crack Sealing LMiles 1.3 E0023-526 Alabama St North St Market St Crack Sealing LMiles 1.3 E0023-525 Calvary St Fletcher Ave I-65 ramp Crack Sealing LMiles 0.4 E0023-524 County Line Rd N Meridian St (SR 135 S Madison Ave (473' west of M Crack Sealing LMiles 6.6 E0023-522 Delaware St Fort Wayne Ave 16th St Crack Sealing LMiles 2.6 E0023-521 Emerson Ave Prospect St English Ave Crack Sealing LMiles 1.3 E0023-520 Fletcher Ave S Pine ST Calvary St Crack Sealing LMiles 0.5 E0023-519 Madison Ave McCarty St New York St Crack Sealing LMiles 1.3 E0023-518 McCarty St East St Virginia Ave Crack Sealing LMiles 0.5 E0023-517 Michigan St Indiana Ave College Ave Crack Sealing LMiles 3.1 E0023-516 New York St West St College Ave Crack Sealing LMiles 4.0 E0023-513 Ohio St Capital Ave College Ave Crack Sealing LMiles 4.2 E0023-512 Pennsylvania St 11th St Vermont St Crack Sealing LMiles 2.3 E0023-511 Pennsylvania St South St McCarty St Crack Sealing LMiles 0.8 E0023-508 Post Rd E Raymond St E Washington St Crack Sealing LMiles 4.6 E0023-507 South St Pennsylvania St East St Crack Sealing LMiles 0.9 E0023-505 Stop 11 Rd McFarland Rd Five Points Rd Crack Sealing LMiles 8.9

RS-26-001 Street List

CIP Database Capital Outputs

EID Element Name From/At To Capital Output Unit Code

Proposed Quantity

E0023-503 Greenridge Dr W 86th St Carroll Rd Crack Sealing LMiles 9.8

RS-26-001 CIB.pdf
RS-26-001 Front Ends.pdf
END OF INSTRUCTIONS TO BIDDERS
PART 6
PART 7
ADDITIONAL DECLARATIONS
Residing in __________________ County, State of ____________________
PART II
Non-Compliance Procedure
POST-BID SUBMITTAL
(SEE ITB 6.1)
INDIANA PLAN/AFFIRMATIVE ACTION CERTIFICATION
(Bidders with more than 15 employees)
Bidder’s Certification
(Bidder) certifies for itself and its subcontractors that:
Title: ________________________________
1. The definitions in IC 5-16-3 are incorporated by reference into this Section.
2. In accordance with IC 5-16-13-9, the Bidder, as a “Tier 1 contractor” (as defined in IC 5-16-3-4), if awarded a contract for the Work contemplated by this Bid must contribute:
(a) Work performed by the tier 1 contractor’s employees;
(b) Materials supplied directly by the tier 1 contractor;
(c) Services supplied directly by the tier 1 contractor’s employees; or
(d) Any combination of subdivisions (a) through (d);
at least fifteen percent (15%) of the tier 1 contractor’s total contract price as determined at the time the contract is awarded.
NOTE: In accordance with Subsection 6.8.1 of the City of Indianapolis Standard General Conditions for Construction Contracts the successful Bidder is required to perform with its own organization Work amounting to not less than thirty percent (30%) o...
3. In accordance with IC 5-16-13-10, if awarded a contract for the Work contemplated by this Bid, the Bidder, as a “Tier 1 contractor”, and each “Tier 2 contractor” and “Tier 3 contractor” (as defined in IC 5-16-3-4 (i.e., subcontractors and sub-subco...
(a) For the each occurrence limit, one million dollars ($1,000,000).
(b) For the general aggregate limit, two million dollars ($2,000,000).
NOTE: The successful Bidder, its subcontractors and sub-subcontractors, are required to maintain all insurance coverage as provided for in Article 5 of the City of Indianapolis Standard General Conditions for Construction Contracts.
4. In accordance with IC 5-16-13-11, if awarded a contract for the Work contemplated by this Bid, the Bidder as a “Tier 1 contractor” and each “Tier 2 contractor” and “Tier 3 contractor” employed to perform Work on the Project:
(a) Shall submit, before Work begins, the E-Verify case verification number for each individual who is required to be verified under IC 22-5-1.7. An individual who is required to be verified under IC 22-5-1.7 whose final case result is final non-conf...
(b) May not pay cash to any individual employed by the contractor for Work done by the individual on the Project.
(c) Must be in compliance with the federal Fair Labor Standards Act of 1938, as amended (29 U.S.C. 201-209) and IC 22-2-2-1 through IC 22-2-2-8.
(d) Must be in compliance with IC 22-3-5-1 and IC 22-3-7-34.
(e) Must be in compliance with IC 22-4-1 through IC 22-4-39.5.
(f) Must be in compliance with IC 4-13-18-1 through IC 4-13-18-7.
(g) Must comply with IC 5-16-13-12, if applicable.
5. In accordance with IC 5-16-13-12, if awarded a contract for the Work contemplated by this Bid, the Bidder as a “Tier 1 contractor” and each “Tier 2 contractor” employed to perform Work on the Project, if they employ fifty (50) or more journeymen:
(a) Must provide access to a training program applicable to the tasks to be performed in the normal course of the employee’s employment with the contractor.
(b) Shall participate in an apprenticeship training program that meets the standards established by the United States Department of Labor, Bureau of Apprenticeship and Training.
(c) May comply with this section through any of the following:
(1) An apprenticeship program.
(2) A program offered by Ivy Tech Community College of Indiana.
(3) A program offered by Vincennes University.
(4) A program established by or for the contractor.
(5) A program offered by an entity sponsored by the United States Department of Labor, Bureau of Apprenticeship and Training.
(6) A program that results in the award of an industry recognized portable certification.
6. In accordance with IC 5-16-13-13, if awarded a contract for the Work contemplated by this Bid, the payroll and related records of the Bidder as a “Tier 1 contractor” and each “Tier 2 contractor” and “Tier 3 contractor” employed to perform Work on ...
(a) Preserved by the contractor for a period of three (3) years after completion of the Project Work; and
(b) Open to inspection by the Indiana Department of Workforce Development (DWD).
In accordance with IC 5-16-13-14, if the City of Indianapolis suspects a misclassification of one (1) or more workers by a contractor in any contractor tier working on the Project may request in writing that DWD investigate the suspected worker miscla...
7. In accordance with IC 5-16-13-15, if the City of Indianapolis reasonably suspects the Bidder awarded a contract for the Work contemplated by this Bid or any “Tier 2 contractor” and “Tier 3 contractor” employed to perform Work on the Project has vio...
(a) If the suspected violation concerns or is related to any of the following provisions, the City shall refer the matter to the appropriate agency as follows:
(1) For a suspected violation of IC 5-16-13-11(1) (E-Verify), the Indiana Department of Labor.
(2) For a suspected violation of IC 5-16-13-11(3) (the federal FLSA or state minimum wage law), the Indiana Department of Labor.
(3) For a suspected violation of IC 5-16-13-11(4) (worker’s compensation or occupational diseases), the Worker’s Compensation Board of Indiana.
(4) For a suspected violation of IC 5-16-13-11(5) (unemployment insurance), the Department of Workforce Development.
(b) If the suspected violation concerns a provision of IC 5-16-13 other than a provision listed in subdivision (a), the City shall require the contractor to remedy the violation not later than thirty (30) days after the City notifies the contractor of...
(1) May not exceed forty-eight (48) months; and
(2) Begins on the date of substantial completion of the Project.
A finding by the City that a contractor is not responsible under this section may not be used by another public agency in making a determination as to whether the contractor is responsible for purposes of that public agency’s award of a public works ...
RS-26-001 SC.pdf
RS-26-001 TS.pdf
RS-26-001 material spec.pdf
RS-26-001 bid 3.pdf
Bid3Form
RS-26-001 Street List.pdf
Sheet1

File details come from the government source that posted it. Updated .