About this file
This is a solicitation for construction services for infrastructure upgrades at the Department of Veterans Affairs Medical Center in Sheridan, Wyoming. The solicitation seeks a contractor to perform mechanical, electrical, and low voltage system upgrades in multiple buildings on the campus. Services include mechanical system replacements and modifications, electrical system upgrades, fire alarm system work, and associated construction. The period of performance is 720 calendar days from notice to proceed. The solicitation was issued on January 13, 2023, with proposals due by February 10, 2023 and award anticipated by March 2023. The total estimated value is $5-10 million. The solicitation is unrestricted and open to small businesses. The contracting agency is the Department of Veterans Affairs Technology Acquisition Center located in Austin, Texas.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 01 G0-00thruCU114.pdf | ||
| HAZMAT_1.PDF | ||
| Wage Determination - Sheridan 11.23.pdf | ||
| Sheridan EHRM Infrastructure Upgrades - CFD Anaylsis Report FINAL.pdf | ||
| Sheridan EHRM Finish Board.pdf | ||
| S02 - Limitations on Subcontracting - Construction.docx | DOCX document | |
| Spec Combined Volume 1.pdf | ||
| 03 A1-35thruM1.G.pdf | ||
| 02 DT100thruA1-32.pdf | ||
| Site Visit Instructions.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EHRM INFRASTRUCTURE UPGRADES
Sheridan, WY 100% Specification VOLUME #2
July 13, 2023
U.S. DEPARTMENT OF
VETERAN AFFAIRS
SHERIDAN VA MEDICAL CENTER
DEPARTMENT OF VETERANS AFFAIRS
Sheridan, WY
EHRM INFRASTRUCTURE UPGRADES
July 13, 2023
ARCHITECT
FourFront Design, Inc.
517 Seventh Street Rapid City, SD 57701
(605) 342-9470
Tim Cummins, RA
CIVIL ENGINEER
WWC Engineering 1275 Maple Street, Suite F Helena, MT 59601
(406) 443-3962
Shawn Higley, PE
MECHANICAL ENGINEER
517 Seventh Street Rapid City, SD 57701
Ray Dawes, PE
ELECTRICAL ENGINEER
West Plain Engineering 1750 Rand Road Rapid City, SD 57702
(605) 348-7455
Mike Sigman, PE
Telecommunication Security
517 Seventh Street Rapid City, SD 57701
Ray Dawes, PE
FIRE PROTECTION/ALARM ENGINEER
Summit Fire Consulting 575 Minnehaha Ave. W St. Paul, Minnesota 55103
(612) 387-7050
Christopher M Leaver, PE
09-01-21
EHRM Infrastructure Upgrades - Sheridan VA Medical Center TABLE OF CONTENTS
VA Project #666-21-700 00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 00 02 Seals Page
00 01 10 Table of Contents 09-21
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 05-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20
01 33 23 Shop Drawings, Product Data, and Samples 06-21
01 35 26 Safety Requirements 07-20
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections
01 57 19 Temporary Environmental Controls
01 74 19 Construction Waste Management 01-21
01 81 13 Sustainable Construction Requirements 10-17
01 91 00.01 DVA/USACE Projects General Commissioning Requirements 08-19
DIVISION 02 – EXISTING CONDITIONS
02 45 00 Jacking And Boring Operations
02 82 11 Traditional Asbestos Abatement 01-21
02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21
02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-17
04 05 16 Masonry Grouting 01-21
04 20 00 Unit Masonry 08-17
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18
05 50 00 Metal Fabrications 08-18
05 51 00 Metal Stairs 01-21
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
VA Project #666-21-700 00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 10-17
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 14 00 Interior Wood Doors 01-21
08 71 00 Door Hardware 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 06 00 Schedule for Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 30 13 Tiling 01-21
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 01-21
09 65 16 Resilient Sheet Flooring 05-18
09 65 19 Resilient Tile Flooring 05-18
09 68 00 Carpeting 01-21
09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
10 14 00 Signage 01-21
10 26 00 Wall and Door Protection 01-21
DIVISION 12 – FURNISHINGS
12 32 00 Manufactured Wood Casework 09-15
12 36 00 Countertops 12-18
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-16
21 13 16 Dry-Pipe Sprinkler Systems 01-15
21 22 00 Clean Agent Fire Suppression Systems 05-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 02-20
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
02-20
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20
VA Project #666-21-700 00 01 10-3
SECTION NO. DIVISION AND SECTION TITLES DATE
23 07 11 HVAC and Boiler Plant Insulation 02-20
23 09 23 Direct-Digital Control System for HVAC 09-11
23 21 13 Hydronic Piping 02-20
23 23 00 Refrigerant Piping 02-20
23 31 00 HVAC Ducts and Casings 02-20
23 36 00 Air Terminal Units 02-20
23 37 00 Air Outlets and Inlets 02-20
23 40 00 HVAC Air Cleaning Devices 03-20
23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 03-20
23 81 00 Decentralized Unitary HVAC Equipment 03-20
23 81 23 Computer-Room Air-Conditioners 03-20
DIVISION 25 – INTEGRATED AUTOMATION
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 05 41 Underground Electrical Construction 01-17
26 05 73 Overcurrent Protective Device Coordination Study 01-18
26 08 00 Commissioning of Electrical Systems 11-16
26 24 16 Panelboards 01-18
26 26 00 Power Distribution Units for Static Uninterruptible
Power Systems
01-18
26 27 26 Wiring Devices 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 33 53 Static Uninterruptible Power Supply 01-17
26 43 13 Surge Protective Devices 01-17
26 51 00 Interior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-19
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Conduits and Backboxes for Communications Systems 11-21
27 05 36 Cable Trays for Communications Systems 11-21
27 05 53 Identification for Communications Systems 07-21
27 08 00 Commissioning of Communications Systems 11-16
27 10 00 Structured Cabling 11-21
27 11 16 Communications Cabinets, Racks, Frames, And Enclosures 11-21
27 11 19 Communications Termination Blocks and Patch Panels 11-21
27 11 26 Communications Rack Mounted Power Protection and Power
Strips
11-21
27 13 13 Communications Copper Backbone Cabling 11-21
27 13 13.13 Communications Copper Cable Splicing and Terminations 11-21
27 13 23 Communications Optical Fiber Backbone Cabling 11-21
27 13 23.13 Communications Optical Fiber Splicing and Terminations 11-21
VA Project #666-21-700 00 01 10-4
SECTION NO. DIVISION AND SECTION TITLES DATE
27 15 13 Communications Copper Horizontal Cabling 11-21
27 16 19 Communications Patch Cords, Station Cords, and Cross
Connect Wire
11-21
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 08 00 Commissioning of Electronic Safety and Security Systems 11-16
28 13 00 Physical Access Control System 10-11
28 16 00 Intrusion Detection System 10-11
28 23 00 Video Surveillance 09-11
DIVISION 31 – EARTHWORK
31 20 11 Earthwork (Short Form) 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
11-1-16
EHRM Infrastructure Upgrades - Sheridan VA Medical Center FIRE SUPPRESSION
VA Project #666-21-700 21 08 00 - 1
SECTION 21 08 00
COMMISSIONING OF FIRE SUPPRESSION SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. The requirements of this Section apply to all sections of Division 21.
B. This project will have selected building systems commissioned. The complete list of equipment and systems to be commissioned is specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS. A
Commissioning Agent (CxA) appointed by the VA will manage the commissioning process.
1.2 RELATED WORK
A. Section 01 00 00 GENERAL REQUIREMENTS.
B. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.
C. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
1.3 SUMMARY
A. This Section includes requirements for commissioning the Fire
Suppression systems, subsystems and equipment. This Section supplements the general requirements specified in Section 01 91 00
General Commissioning Requirements.
B. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.
1.4 DEFINITIONS
A. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.
1.5 COMMISSIONED SYSTEMS
A. Commissioning of a system or systems specified in Division 21 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Section 01 91 00 and of Division 21, is required in cooperation with the VA and the
Commissioning Agent.
B. The Fire Suppression systems commissioning will include the systems listed in Section 01 91 00 General Commissioning Requirements:
VA Project #666-21-700 21 08 00 - 2
1.6 SUBMITTALS
A. The commissioning process requires review of selected Submittals. The
Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to
Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.
B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL
COMMISSIONING REQUIREMENTS.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 CONSTRUCTION INSPECTIONS
A. Commissioning of the building fire suppression systems will require inspection of individual elements of the fire suppression construction throughout the construction period. The Contractor shall coordinate with the Commissioning Agent in accordance with Section 01 91 00 and the Commissioning plan to schedule inspections as required to support the Commissioning Process.
3.2 PRE-FUNCTIONAL CHECKLISTS
A. The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testing. The
Commissioning Agent will prepare Pre-Functional Checklists to be used to document equipment installation. The Contractor shall complete the checklists. Completed checklists shall be submitted to the VA and to the Commissioning Agent for review. The Commissioning Agent may spot check a sample of completed checklists. If the Commissioning Agent determines that the information provided on the checklist is not accurate, the Commissioning Agent will return the marked-up checklist to the Contractor for correction and resubmission. If the
Commissioning Agent determines that a significant number of completed checklists for similar equipment are not accurate, the Commissioning
Agent will select a broader sample of checklists for review. If the
Commissioning Agent determines that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the type of equipment will be returned to the Contractor for correction and
VA Project #666-21-700 21 08 00 - 3 resubmission. Refer to SECTION 01 91 00 GENERAL COMMISSIONING
REQUIREMENTS for submittal requirements for Pre-Functional Checklists, Equipment Startup Reports, and other commissioning documents.
3.3 CONTRACTORS TESTS
A. Contractor tests as required by other sections of Division 21 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL
REQUIREMENTS. All testing shall be incorporated into the project schedule. Contractor shall provide no less than 7 calendar days’ notice of testing. The Commissioning Agent will witness selected
Contractor tests at the sole discretion of the Commissioning Agent.
Contractor tests shall be completed prior to scheduling Systems
Functional Performance Testing.
3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING
A. The Commissioning Process includes Systems Functional Performance
Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems
Functional Performance Test procedures for review and approval by the
COR. The Contractor shall review and comment on the tests prior to approval. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will witness and document the testing.
The Contractor shall sign the test reports to verify tests were performed. See Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS, for additional details.
3.5 TRAINING OF VA PERSONNEL
A. Training of the VA operation and maintenance personnel is required in cooperation with the COR and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of Section 01 91 00. The instruction shall be scheduled in coordination with the COR after submission and approval of formal training plans. Refer to Section 01 91 00 GENERAL COMMISSIONING
REQUIREMENTS and Division 21 Sections for additional Contractor training requirements.
VA Project #666-21-700 21 08 00 - 4
----- END -----
01-01-15
EHRM Infrastructure Upgrades - Sheridan VA Medical Center DRY-PIPE SPRINKLER
VA Project #666-21-700 21 13 16 - 1
SECTION 21 13 16
DRY-PIPE SPRINKLER SYSTEMS
A. Design, installation, and testing shall be in accordance with NFPA 13.
B. Modification of the existing dry-pipe sprinkler system as indicated on the drawings and as further required by these specifications.
Modification spaces include IT closets and other spaces noted on drawings in Buildings 1, 2, 3, 4, 5, 6, 7, 8, 9, 11, 24, 31, 32, 35, 36, 37, 42, 61, 64, 71, 71N, 86, 87, and 90.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Section 33 10 00, WATER UTILITIES.
C. Section 07 84 00, FIRESTOPPING.
D. Section 09 91 00, PAINTING.
E. Section 28 31 00, FIRE DETECTION AND ALARM.
1.3 DESIGN CRITERIA
A. Design Basis Information: Provide design, materials, equipment, installation, inspection, and testing of the automatic sprinkler system in accordance with the requirements of NFPA 13.
1. Perform hydraulic calculations in accordance with NFPA 13 utilizing the Area/Density method, including all applicable design area increases.
2. Sprinkler Protection: Sprinkler hazard classifications shall be in accordance with NFPA 13. The hazard classification examples of uses and conditions identified in the Annex of NFPA 13 shall be mandatory. Request clarification from the Government for any hazard classification not identified. To determining spacing and sizing, apply the following coverage classifications:
a. Light Hazard Occupancies: Patient care, treatment, and customary access areas.
3. Dry-pipe Sprinkler System Volume:
a. Contractor shall indicate the calculated volume of each system on the sprinkler system shop drawings.
b. For dry-pipe sprinkler systems with volumes greater than 1893 L
(500 gal) up to 2839 L (750 gal), provide a quick opening device
VA Project #666-21-700 21 13 16 - 2 unless water delivery time calculations indicate the quick opening devices is not required.
c. For dry-pipe sprinkler systems with volumes greater than 2839 L
(750 gal), provide calculations for water delivery time.
Calculations shall demonstrate compliance with NFPA 13.
4. Nitrogen Generator Plant: Coordinate sizing of nitrogen generator and air compressor with the nitrogen generator manufacturer.
5. Hydraulic Calculations: Calculated demand including hose stream requirements shall fall no less than 10 percent below the available water supply curve.
6. Zoning:
a. Each sprinkler zone is remaining as-is as part of this project.
1.4 SUBMITTALS
A. Submit as one package in accordance with Section 01 33 23, SHOP
DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level III or Level IV Sprinkler Technician or stamped by a Registered Professional Engineer licensed in the field of Fire Protection Engineering. As the Government review is for technical adequacy only, the installer remains responsible for correcting any conflicts with other trades and building construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or binders and provide an index referencing the appropriate specification section. In addition to the hard copies, provide submittal items in
Paragraphs 1.4(A)1 through 1.4(A)5 electronically in pdf format on a compact disc or as directed by the COR. Submittals shall include, but not be limited to, the following:
1. Qualifications:
a. Provide a copy of the installing contractors state of Wyoming contractor’s license.
b. Provide a copy of the NICET certification for the NICET Level III or Level IV Sprinkler Technician who prepared and signed the detailed working drawings unless the drawings are stamped by a
Registered Professional Engineer licensed in the field of Fire
Protection Engineering.
VA Project #666-21-700 21 13 16 - 3
c. Provide documentation showing that the installer has been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
2. Drawings: Submit detailed 1:100 (1/8 inch) scale (minimum) working drawings conforming to the Plans and Calculations chapter of NFPA
13. Drawings shall include graphical scales that allow the user to determine lengths when the drawings are reduced in size. Include a plan showing the piping to the water supply test location.
3. Manufacturer’s Data Sheets: Provide data sheets for all materials and equipment proposed for use on the system. Include listing information and installation instructions in data sheets. Where data sheets describe items in addition to those proposed to be used for the system, clearly identify the proposed items on the sheet.
4. Calculation Sheets:
a. Submit hydraulic calculation sheets in tabular form conforming to the requirements and recommendations of the Plans and
Calculations chapter of NFPA 13.
b. For dry-pipe sprinkler systems with volumes more than 2838 L (750 gal), submit calculations for dry-pipe system water delivery time in accordance with NFPA 13.
6. Final Document Submittals: Provide as-built drawings, testing and maintenance instructions in accordance with the requirements in
Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. In addition, submittals shall include, but not be limited to, the following:
a. A complete set of as-built drawings showing the installed system with the specific interconnections between the system switches and the fire alarm equipment. Provide a complete set in the formats as follows. Submit items 2 and 3 below on a compact disc or as directed by the COR.
1) One full size (or size as directed by the COR) printed copy.
2) One complete set in electronic pdf format.
3) One complete set in AutoCAD format or a format as directed by the COR.
b. Material and Testing Certificate: Upon completion of the sprinkler system installation or any partial section of the system, including testing and flushing, provide a copy of a completed Material and Testing Certificate as indicated in NFPA
VA Project #666-21-700 21 13 16 - 4
13. Certificates shall be provided to document all parts of the installation.
c. Operations and Maintenance Manuals that include step-by-step procedures required for system startup, operation, shutdown, and routine maintenance and testing. The manuals shall include the manufacturer's name, model number, parts list, and tools that should be kept in stock by the owner for routine maintenance, including the name of a local supplier, simplified wiring and controls diagrams, troubleshooting guide, and recommended service organization, including address and telephone number, for each item of equipment.
d. One paper copy of the Material and Testing Certificates and the
Operations and Maintenance Manuals above shall be provided in a binder. In addition, these materials shall be provided in pdf format on a compact disc or as directed by the COR.
e. Provide one additional copy of the Operations and Maintenance
Manual covering the system in a flexible protective cover and mount in an accessible location adjacent to the riser or as directed by the COR.
1.5 QUALITY ASSURANCE
A. Installer Reliability: The installer shall possess a valid State of
Wyoming contractor's license. The installer shall have been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
B. Materials and Equipment: All equipment and devices shall be of a make and type listed by UL or approved by FM, or other nationally recognized testing laboratory for the specific purpose for which it is used. All materials, devices, and equipment shall be approved by the VA. All materials and equipment shall be free from defect. All materials and equipment shall be new unless specifically indicated otherwise on the contract drawings.
1.6 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
B. National Fire Protection Association (NFPA):
13-19...................Installation of Sprinkler Systems
VA Project #666-21-700 21 13 16 - 5
25-20...................Inspection, Testing, and Maintenance of Water-
Based Fire Protection Systems
101-21..................Life Safety Code
170-21..................Fire Safety Symbols
C. Underwriters Laboratories, Inc. (UL):
Fire Protection Equipment Directory 2011
D. Factory Mutual Engineering Corporation (FM):
Approval Guide
PART 2 PRODUCTS
2.1 GENERAL
Dry-pipe sprinkler systems shall comply with the requirements of NFPA
13.
2.2 PIPING & FITTINGS
A. Piping and fittings for sprinkler systems shall be in accordance with
NFPA 13.
1. Plain-end pipe fittings with locking lugs or shear bolts are not permitted.
2. Piping sizes 50 mm (2 inches) and smaller shall be black steel
Schedule 40 with threaded end connections.
3. Piping sizes 65 mm (2 ½ inches) and larger shall be black steel
Schedule 10 with grooved connections. Grooves in Schedule 10 piping shall be rolled grooved only.
2.3 VALVES
A. General:
1. Valves shall be in accordance with NFPA 13.
2. All existing valves to remain.
2.4 SPRINKLERS
A. All sprinklers shall be FM approved. All sprinklers shall be either upright type, dry pendent type, or dry sidewall type. Provide FM
Approved quick response sprinklers in all areas, except that standard response sprinklers shall be provided in freezers, refrigerators, elevator hoistways, elevator machine rooms, and generator rooms.
B. Temperature Ratings: In accordance with NFPA 13 except that sprinklers in elevator shafts and elevator machine rooms shall be no less than intermediate temperature rated and sprinklers in generator rooms shall be no less than high temperature rated.
C. Provide sprinkler guards in accordance with NFPA 13 and when the elevation of the head is less than 7 feet 6 inches above finished
VA Project #666-21-700 21 13 16 - 6 floor. The sprinkler guard shall be listed or approved for use with the corresponding sprinkler.
SPEC WRITER NOTE: A supervisory air system can be substituted for the supervisory nitrogen system where system conditions, such as area/assets protected and system replacement costs, warrant it.
2.5 AIR PRESSURE MAINTENANCE DEVICE
Air Pressure Maintenance Device: Air pressure maintenance device shall be UL listed or FM approved and shall automatically reduce supply air pressure to provide the pressure required to be maintained in the piping system. The device shall have a cast bronze body and valve housing complete with diaphragm assembly, spring, filter, ball check to prevent backflow, 1.6 mm (1/16 inch) restriction to prevent rapid pressurization of the system, and adjustment screw. The device shall be capable of reducing an inlet pressure of up to 680 kPa (100 psig) to a fixed outlet pressure adjustable to 70 kPa (10 psig).
2.6 SPRINKLER CABINET
A. Provide sprinkler cabinet with the required number of sprinkler heads of all ratings and types installed, and a sprinkler wrench for each type of sprinkler in accordance with NFPA 13.
B. Provide a list of sprinklers installed in the property in the cabinet.
The list shall include the following:
1. Manufacturer, model, orifice, deflector type, thermal sensitivity, and pressure for each type of sprinkler in the cabinet.
2. General description of where each sprinkler is used.
3. Quantity of each type present in the cabinet.
4. Issue or revision date of list.
2.7 SPRINKLER SYSTEM SIGNAGE
Rigid plastic, steel or aluminum signs with white lettering on a red background with holes for easy attachment. Sprinkler system signage shall be attached to the valve or piping with chain.
2.8 PIPE HANGERS, SUPPORTS AND RESTRAINT OF SYSTEM PIPING
Pipe hangers, supports, and restraint of system piping shall be in accordance with NFPA 13.
2.9 WALL, FLOOR AND CEILING PLATES
Provide chrome plated steel escutcheon plates.
VA Project #666-21-700 21 13 16 - 7
PART 3 - EXECUTION
3.1 INSTALLATION
A. Installation shall be accomplished by the licensed contractor. Provide a qualified technician, experienced in the installation and operation of the type of system being installed, to supervise the installation and testing of the system.
B. Installation of Piping: Accurately cut pipe to measurements established by the installer and work into place without springing or forcing. In any situation where bending of the pipe is required, use a standard pipe-bending template. Conceal piping in spaces that have finished ceilings. In stairways, locate piping as near to the ceiling as possible to prevent tampering by unauthorized personnel and to provide a minimum headroom clearance of 2250 mm (seven feet six inches). Piping shall not obstruct the minimum means of egress clearances required by
NFPA 101. Pipe hangers, supports, and restraint of system piping, // and seismic bracing // shall be installed accordance with NFPA 13.
C. Welding: Conform to the requirements and recommendations of NFPA 13.
D. Pitching of Pipe: Conform to the requirements of NFPA 13.
E. Drains: Provide drips and drains, including low point drains, in accordance with NFPA 13. Pipe drains to discharge at safe points outside of the building. Do not provide a direct drain connection to sewer system or discharge into sinks.
F. Supervisory Switches: Provide supervisory switches for sprinkler control valves to monitor closure of the valve and for high and low system supervisory air/nitrogen pressure to monitor abnormal system pressures.
G. Pressure Alarm Switches: Install alarm pressure switches in easily accessible locations.
I. Affix cutout disks, which are created by cutting holes in the walls of pipe for non-threaded pipe connections, to the respective pipe connection near to the pipe from where they were cut.
J. Provide escutcheon plates for exposed piping passing through walls, floors or ceilings.
L. Sleeves: Provide for pipes passing through masonry or concrete. Provide space between the pipe and the sleeve in accordance with NFPA 13. Seal this space with a UL Listed through penetration fire stop material in accordance with Section 07 84 00, FIRESTOPPING. Where core drilling is used in lieu of sleeves, also seal space around penetrations. Seal
VA Project #666-21-700 21 13 16 - 8 penetrations of walls, floors and ceilings of other types of construction, in accordance with Section 07 84 00, FIRESTOPPING.
N. Firestopping shall be provided for all penetrations of fire resistance rated construction. Firestopping shall comply with Section 07 84 00, FIRESTOPPING.
O. Painting of Pipe: In finished areas where walls and ceilings have been painted, paint primed surfaces with two coats of paint to match adjacent surfaces, except paint valves and operating accessories with two coats of gloss red enamel. Exercise care to avoid painting sprinklers. Painting of sprinkler systems above suspended ceilings and in crawl spaces is not required. Painting shall comply with Section 09
90 00, PAINTING. Any painted sprinkler shall be replaced with a new sprinkler.
P. Locate sprinkler cabinet adjacent to the dry-pipe sprinkler system riser or as directed by COR.
Q. Sprinkler System Signage: Provide rigid sprinkler system signage in accordance with NFPA 13 and NFPA 25. Sprinkler system signage shall include, but not limited to, the following:
1. Identification Signs:
a. Provide signage for each drain valve.
2. Instruction/Information Signs:
a. Provide signage indicating the number and location of low point drains.
3. Hydraulic Placards:
a. Provide signage indicating hydraulic design information. The placard shall include location of the design area, discharge densities, required flow and residual pressure at the base of riser, occupancy classification, hose stream allowance, flow test information, and installing contractor. Locate hydraulic placard information signs at each dry-pipe valve.
R. Repairs: Repair damage to the building or equipment resulting from the installation of the sprinkler system by the installer at no additional expense to the Government.
S. Interruption of Service: There shall be no interruption of the existing sprinkler protection, water, electric, or fire alarm services without prior permission of the Contracting Officer Representative. Contractor shall develop an interim fire protection program where interruptions
VA Project #666-21-700 21 13 16 - 9 involve in occupied spaces. Request in writing at least one week prior to the planned interruption.
3.2 INSPECTION AND TEST
A. Preliminary Testing: Flush newly installed systems prior to performing tests in order to remove any debris which may have been left as well as ensuring piping is unobstructed. Manually demonstrate nitrogen concentration in dry-pipe sprinkler system piping is at least 98%.
Hydrostatically test system, including the fire department connections, pneumatically test system, test air compressor fill time to operating pressure within 30 minutes, and trip test system as specified in NFPA
13, in the presence of the Contracting Officers Representative (COR) or their designated representative. For dry-pipe sprinkler systems with a quick-opening device, the system shall be trip tested with the quick-opening device functioning and with the quick-opening device disabled.
Record the time to water delivery for each test. Demonstrate pitch of pipe is in compliance with NFPA 13.
B. Final Inspection and Testing: Subject system to tests in accordance with NFPA 13, and when all necessary corrections have been accomplished, advise COR to schedule a final inspection and test.
Connection to the fire alarm system shall have been in service for at least ten days prior to the final inspection, with adjustments made to prevent false alarms. Furnish all instruments, labor and materials required for the tests and provide the services of the installation foreman or other competent representative of the installer to perform the tests. Correct deficiencies and retest system as necessary, prior to the final inspection and testing. Include the operation of all features of the systems under normal operations in test. At the conclusion of final inspection and testing, blow out dry-pipe system piping using compressed air. Verify piping is fully drained, including low point drains.
C. Post-Final Inspection: One month after final inspection and testing, the contractor shall manually verify that the system piping has a nitrogen concentration of at least 98%. Advise COR to schedule post-final inspection.
D. Final Contractual Acceptance: Final contractual acceptance will be given after successful completion of the final inspection and testing
VA Project #666-21-700 21 13 16 - 10 and post-final inspection. The warranty period shall begin after final contractual acceptance.
3.3 INSTRUCTIONS
Furnish the services of a competent instructor for not less than two hours for instructing personnel in the operation and maintenance of the system on the dates requested by the COR.
- - - E N D - - -
05-01-15
EHRM Infrastructure Upgrades - Sheridan VA Medical Center CLEAN AGENT FSS
VA Project #666-21-700 21 22 00 - 1
SECTION 21 22 00
CLEAN AGENT FIRE SUPPRESSION SYSTEMS
A. Design, installation and testing of a calculated automatic and manual fixed total flooding clean agent fire extinguishing system and releasing system in accordance with NFPA 2001, NFPA 72, NFPA 70, and
NFPA 75 and manufacturer’s written instructions for the locations shown on the contract drawings. The installation shall include all mechanical, controls and electrical components necessary for a complete and operating clean agent fire suppression system.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
B. Section 07 84 00, FIRESTOPPING
C. Section 09 91 00, PAINTING
D. Section 28 05 13, CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND
SECURITY
E. Section 28 05 28.33, CONDUIT AND BACKBOXES FOR ELECTRONIC SAFETY AND
SECURITY
F. Section 28 31 00, FIRE DETECTION AND ALARM
1.3 DESIGN CRITERIA
A. The clean agent fire extinguishing system shall be a fixed total flooding type utilizing clean agent designed to provide a uniform concentration throughout the protected spaces in accordance with NFPA
2001 for a Class C fire.
1. The system shall provide a minimum design concentration by volume, throughout the protected spaces at the minimum anticipated temperature within the protected space.
2. The design concentration within any protected space shall not exceed by volume the no observable adverse effects level (NOAEL). Special means such as mechanical exhaust, shall not be permitted to be used to achieve this criterion.
3. The clean agent shall have a global warming potential (GWP) of less than 4000 and the clean agent shall be readily available throughout the continental United States.
VA Project #666-21-700 21 22 00 - 2
4. Provide the quantity of clean agent as required by NFPA 2001 and manufacturer’s written instructions. Such factors as unenclosed openings (if any), “rundown” time of fans, time required for dampers to close, and any other feature of the facility that could affect concentration shall be taken into consideration.
1.4 SUBMITTALS
A. Submit as one package in accordance with Section 01 33 23, SHOP
DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level IV Special Hazards Suppression Systems
Technician. As the Government review is for technical adequacy only, the installer remains responsible for correcting any conflicts with other trades and building construction that arise during installation.
Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or binders and provide an index referencing the appropriate specification section. In addition to the hard copies, provide submittal items in Paragraphs 1.4 (A) 1 through
1.4 (A) 5 electronically in pdf format on a compact disc or as directed by the Contracting Officers Representative (COR). Submittals shall include, but not be limited to, the following:
1. Qualifications:
a. Provide a copy of the installing contractors state of Wyoming contractors license.
b. Provide a copy of the NICET certification for the NICET Level IV
Special Hazards Suppression System Technician who will prepare and sign the detailed working drawings.
c. Provide documentation showing that the installer has been actively and successfully engaged in the installation of clean agent fire suppression systems for the past ten years.
2. Drawings: Submit detailed 1:100 (1/8 inch) scale (minimum) working plans and drawings of the clean agent fire extinguishing system conforming to NFPA 2001. Submit detailed 1:100 (1/8 inch) scale
(minimum) working plans and drawings of the releasing system conforming to NFPA 72. Drawings shall include graphical scales that allow the user to determine lengths when the drawings are reduced in size.
3. Manufacturers Data Sheets:
VA Project #666-21-700 21 22 00 - 3
a. Provide for all materials and equipment proposed for use on the clean agent fire extinguishing system, including the releasing system. Include listing information and installation instructions in data sheets. Where data sheet describes items in addition to that item being submitted, clearly identify proposed item on the sheet.
4. Calculation Sheets:
a. Submit flow calculation sheets in tabular form conforming to the requirements of NFPA 2001. Calculations shall include total storage capacity, flooding concentrations, enclosure leakage rates, discharge times, flow through distribution network, pipe sizes, and nozzle orifice sizes.
b. Submit battery calculations sheets in tabular form conforming to the requirements of NFPA 72.
c. Submit voltage drop calculations in tabular form. Calculations shall indicate circuit amperage draw, wire resistance, circuit length, and voltage drop. The voltage drop shall demonstrate that voltage provided at the each appliance is within its operating voltage range. Voltage drop calculations shall assume an initial voltage of 20.4 volts.
5. Clean Agent Recharging Certification: Provide a letter to the COR or his designated representative certifying that the installer maintains or has access to a clean agent recharging station. The installer shall also provide proof of the ability to recharge the largest clean agent fire extinguishing system capacity within 48 hours.
6. Test Plan: Provide a test plan to the COR or his designated representative. The testing plan shall describe the procedures to be used to test the system. The testing plan shall include a step-by-step procedure of all tests to be performed, including indication of which tests will present a disruption to building occupants. No tests shall be conducted until the testing plan is approved by the
COR or his designated representative.
7. Final Document Submittals: Provide as-built drawings, testing and maintenance instructions in accordance with the requirements in
Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
Submittals shall include, but not be limited to, the following:
VA Project #666-21-700 21 22 00 - 4
a. A complete set of as-built drawings showing the installed system with the specific interconnections between the system switches and the fire alarm equipment. Provide a complete set in the formats as follows. Submit items 2 and 3 below on a compact disc or as directed by the COR.
1) One full size (or size as directed by the COR) printed copy.
2) One complete set in electronic pdf format.
3) One complete set in AutoCAD format or a format as directed by the COR.
b. System Certification: Upon completion of the clean agent fire extinguishing system installation, including testing, the authorized representative of the manufacturer of the major equipment shall certify that the installation complies with all manufacturer’s requirements and that satisfactory total system operation has been achieved. Provide a copy of the Record of
Completion for the releasing system in accordance with NFPA 72.
c. Operating and Maintenance Manuals that include step-by-step procedures required for operation, shutdown, and routine maintenance and testing. The manuals shall include the manufacturer’s name, model number, parts list, the name of the local supplier, simplified wiring and controls diagrams, troubleshooting guide, and recommended service organization, including address and telephone number, for each item of equipment.
d. One paper copy of the System Certification and Record of
Completion and the Operating and Maintenance Manuals listed above shall be provided in a binder. In addition, these materials shall be provided in pdf format on a compact disc or as directed by the COR.
e. Provide one additional copy of the Operations and Maintenance
Manual for the system in a binder and mount in an accessible location adjacent to the storage cylinder(s).
1.5 QUALITY ASSURANCE
A. Installer Reliability: The installer shall possess a valid State of
Wyoming contractor's license. The installer shall have been actively and successfully engaged in the installation of clean agent special suppression systems for the past ten years. The installer shall maintain or have access to a clean agent recharging station. The
VA Project #666-21-700 21 22 00 - 5 installer shall provide proof of the ability to recharge the largest clean agent fire extinguishing system capacity within 48 hours.
B. Materials and Equipment: All equipment and devices shall be UL listed or approved by FM. All materials, devices, and equipment shall be approved by the VA. All materials and equipment shall be free from defect.
1.6 APPLICABLE PUIBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
SPEC WRITER NOTE: Specify the latest edition of publications at time of award of A/E contract.
B. National Fire Protection Association (NFPA):
70-2017.................National Electric Code
72-2016.................National Fire Alarm Code
75-2017.................Fire Protection of Information Technology
Equipment
170-2018................Fire Safety Symbols
2001-2018...............Installation of Clean Agent Fire Extinguishing
Systems
C. Underwriters Laboratories, Inc. (UL):
2011................... Fire Protection Equipment Directory
D. Factory Mutual Engineering Corporation (FM):
2015................... Approval Guide
1.7 WARRANTY
All work performed and all material and equipment furnished under this contract shall be free from defects and shall remain so for a period of one year from the date of acceptance of the entire installation by the
COR.
PART 2 PRODUCTS
2.1 GENERAL
All equipment and components shall be new and the manufacturer’s current model. All equipment and components shall be UL listed or FM approved for its intended use. The authorized representative of the manufacturer of the major equipment shall certify that the installation complies with all manufacturer’s requirements and that satisfactory total system operation has been achieved.
VA Project #666-21-700 21 22 00 - 6
2.2 CLEAN AGENT FIRE EXTINGUISHING SYSTEM
A. General:
1. The clean agent fire extinguishing system shall be UL listed and shall be in accordance with NFPA 2001.
B. Piping and fittings:
1. All piping and fittings shall be in compliance with NFPA 2001.
2. Multi-outlet fittings, other than tees, shall not be permitted.
3. All piping shall be reamed, blown clear, and swabbed with appropriate solvent to remove mill varnish and cutting oils before assembly.
4. Ordinary cast iron steel and non-metallic piping and fittings and flexible hoses shall not be used unless specifically required by the manufacturer.
C. Piping Support:
1. All piping shall be supported in accordance with the manufacturer’s written instructions.
2. Piping shall be supported within 12 inches (304 mm) of discharge nozzles. The supports shall prevent the upward movement of the nozzle.
D. Storage Cylinders:
1. Provide storage cylinders as required by the manufacturer’s written instructions and in accordance with NFPA 2001.
2. Cylinder assemblies shall be of steel construction designed to meet the requirements of the U.S. Department of Transportation.
3. Filling of the storage cylinders shall be by an authorized systems distributor in conjunction with a factory authorized agent filling station. Initial filling and recharge shall be performed in accordance with manufacturer’s written instructions and shall not require replacement components for normal service.
4. Cylinders shall be securely attached to the wall. Provide factory-or field-fabricated retaining brackets consisting of steel straps and channels; suitable for container support, maintenance, and tank refilling or replacement.
5. For halocarbon clean agents, storage cylinders shall be provided with a low agent pressure switch.
E. Valve Actuators:
VA Project #666-21-700 21 22 00 - 7
1. Electric valve actuators shall be of brass construction and stackable design with swivel connections to allow removal of actuators for maintenance or testing.
2. Operation of actuators shall not require replacement of components.
No electro-explosive devices may be used to actuate the valve assembly. Actuators shall include an indication if they are set or actuated.
3. Electric valve actuators shall be magnetic latch, continuous duty type for 24 VDC operation.
4. Actuation devices shall be UL listed or FM approved for use with the system.
5. Removal of the electric valve actuator shall cause a trouble on the clean agent control panel.
F. Discharge Nozzles:
1. Nozzles shall be permanently marked with the manufacturer’s part number. The nozzles shall be threaded directly to the discharge piping without the use of special adaptors.
2.3 RELEASING SYSTEM
A. General
1. The releasing system shall be an analog addressable intelligent reporting, microprocessor controlled system, capable of remote sensitivity testing of the smoke detectors, and be installed in accordance with NFPA 70, NFPA 72, and NFPA 2001.
B. Clean Agent Control Panel:
1. General:
a. The clean agent control panel shall be UL listed or FM approved and include a UL listed or FM approved releasing module.
b. Each protected space shall be provided with its own clean agent control unit.
c. All circuits shall be monitored for integrity.
d. Visually and audibly annunciate all alarm, supervisory, and trouble signals including, but not limited to main power failure, open circuit, short circuit, ground faults, and system bypass activation.
e. The panel or releasing module shall include a 0-60 second programmable timer.
VA Project #666-21-700 21 22 00 - 8
f. The clean agent control panel shall be provided with separate contacts to provide common supervisory, alarm, and trouble signals to the main building fire alarm system.
2. Enclosure:
a. The clean agent control unit shall be housed in a cabinet suitable for both recessed and surface mounting. The cabinet and front panel shall be corrosion protected, given a rust-resistant prime coat, and manufacturer's standard finish.
b. The cabinet shall contain all necessary relays, terminals, lamps, and legend plates to provide control for the system.
3. Power Supply:
a. The clean agent control unit shall derive its normal power from a
120 volt, 60 Hz dedicated supply connected to the emergency power system. Standby power shall be provided by a 24 volt DC battery as hereinafter specified. The normal power shall be transformed, rectified, coordinated, and interfaced with the standby battery and charger.
b. The power supply for smoke detection systems shall be taken from the clean agent control unit.
4. Circuit Supervision: Each alarm initiating device circuit, signaling line circuit, and notification appliance circuit, shall be supervised against the occurrence of an open, short circuit, or ground fault condition in the field wiring. These conditions shall cause a trouble signal to sound in the control unit until manually silenced by an off switch.
a. Initiating device circuits (IDC) shall be wired Class B in accordance with NFPA 72.
b. Signaling line circuits (SLC) shall be wired Class B in accordance with NFPA 72.
c. Notification appliance circuits (NAC) shall be wired Class B in accordance with NFPA 72.
5. Supervisory Alarm Devices: The low agent pressure switch and maintenance lock-out switch shall initiate a supervisory signal.
6. Trouble signals:
a. Arrange the trouble signals for automatic reset (non-latching).
b. System trouble switch off and on lamps shall be visible through the control unit door.
VA Project #666-21-700 21 22 00 - 9
7. Function Switches: Provide the following switches in addition to any other switches required for the system:
a. Remote Alarm Transmission By-pass Switch: Shall prevent transmission of all signals to the building fire alarm control unit when in the "off" position. A clean agent control unit system trouble signal shall be energized when switch is in the off position.
b. Alarm Off Switch: Shall disconnect power to notification appliance circuits on the clean agent control panel. A system trouble signal shall be activated when the switch is in the off position.
c. Trouble Silence Switch: Shall silence the trouble signal whenever the trouble silence switch is operated. This switch shall not reset the trouble signal.
d. Reset Switch: Shall reset the system after an alarm, provided the initiating device has been reset. The system shall lock in alarm until reset.
e. Lamp Test Switch: A test switch or other approved convenient means shall be provided to test the indicator lamps.
f. AHU By-Pass: Provide a means to disable air handling units shutdown and dampers from closing upon operation of an initiating device designed to interconnect with these devices. A system trouble signal shall be activated when switch is in the off position.
8. Reset2 Capability: Each clean agent control unit shall be installed and programmed so that each must be reset locally after an alarm, before the main fire alarm control unit can be reset.
C. Conduit, Boxes, and Wire
1. Conduit shall be in accordance with Section 28 05 28.33 CONDUIT AND
BACKBOXES FOR ELECTRONIC SAFETY AND SECURITY and as follows:
a. All new conduits shall be installed in accordance with NFPA 70.
b. Conduit fill shall not exceed 40 percent of interior cross sectional area.
c. All new conduits shall be 3/4 inch (19 mm) minimum.
2. Wire:
a. Wiring shall be installed in conduit.
b. Wiring shall be in accordance with NEC article 760, Section 28 05
13, CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY, and
VA Project #666-21-700 21 22 00 - 10 as recommended by the manufacturer of the fire alarm system. All wires shall be color coded.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .