Spec Combined Volume 1.pdf

PDF 7 MB Posted

Attached to
Z2DA--666-21-700 EHRM Infrastructure Upgrades Construction Sheridan WY ( (VA-23-00078941)
Solicitation number
36C77623B0073_1
Issued by

About this file

This specification document outlines requirements for a construction project to upgrade infrastructure at the Sheridan VA Medical Center in Sheridan, Wyoming to support a new Electronic Health Record Modernization system. Key work includes upgrading fiber optic cabling throughout multiple buildings and to an outlying clinic; installing new IT, electrical, and HVAC systems; conducting security assessments; and abating hazardous materials. The project involves renovations and upgrades across various campus buildings and sites. The contractor must meet safety, security, and operational protocols to minimize impacts on the medical center's ongoing operations. The specification provides detailed requirements for phasing of work, protecting existing structures and utilities, using roads and facilities, handling waste, obtaining permits, and other protocol. It also outlines requirements for as-built drawings, instructions, testing, and more.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EHRM INFRASTRUCTURE UPGRADES

Sheridan, WY 100% Specification VOLUME #1

July 13, 2023

U.S. DEPARTMENT OF

VETERAN AFFAIRS

SHERIDAN VA MEDICAL CENTER

DEPARTMENT OF VETERANS AFFAIRS

Sheridan, WY

EHRM INFRASTRUCTURE UPGRADES

July 13, 2023

ARCHITECT

FourFront Design, Inc.

517 Seventh Street Rapid City, SD 57701

(605) 342-9470

Tim Cummins, RA

CIVIL ENGINEER

WWC Engineering 1275 Maple Street, Suite F Helena, MT 59601

(406) 443-3962

Shawn Higley, PE

MECHANICAL ENGINEER

517 Seventh Street Rapid City, SD 57701

Ray Dawes, PE

ELECTRICAL ENGINEER

West Plain Engineering 1750 Rand Road Rapid City, SD 57702

(605) 348-7455

Mike Sigman, PE

Telecommunication Security

517 Seventh Street Rapid City, SD 57701

Ray Dawes, PE

FIRE PROTECTION/ALARM ENGINEER

Summit Fire Consulting 575 Minnehaha Ave. W St. Paul, Minnesota 55103

(612) 387-7050

Christopher M Leaver, PE

09-01-21

EHRM Infrastructure Upgrades - Sheridan VA Medical Center TABLE OF CONTENTS

VA Project #666-21-700 00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 00 02 Seals Page

00 01 10 Table of Contents 09-21

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 05-21

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20

01 33 23 Shop Drawings, Product Data, and Samples 06-21

01 35 26 Safety Requirements 07-20

01 42 19 Reference Standards 11-20

01 45 00 Quality Control 02-21

01 45 29 Testing Laboratory Services 11-18

01 45 35 Special Inspections

01 57 19 Temporary Environmental Controls

01 74 19 Construction Waste Management 01-21

01 81 13 Sustainable Construction Requirements 10-17

01 91 00.01 DVA/USACE Projects General Commissioning Requirements 08-19

DIVISION 02 – EXISTING CONDITIONS

02 45 00 Jacking And Boring Operations

02 82 11 Traditional Asbestos Abatement 01-21

02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21

02 83 33.13 Lead-Based Paint Removal and Disposal 01-21

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete 01-21

DIVISION 04 – MASONRY

04 05 13 Masonry Mortaring 10-17

04 05 16 Masonry Grouting 01-21

04 20 00 Unit Masonry 08-17

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18

05 50 00 Metal Fabrications 08-18

05 51 00 Metal Stairs 01-21

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

VA Project #666-21-700 00 01 10-2

SECTION NO. DIVISION AND SECTION TITLES DATE

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping 01-21

07 92 00 Joint Sealants 10-17

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21

08 14 00 Interior Wood Doors 01-21

08 71 00 Door Hardware 01-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21

09 06 00 Schedule for Finishes 01-21

09 22 16 Non-Structural Metal Framing 06-18

09 29 00 Gypsum Board 04-20

09 30 13 Tiling 01-21

09 51 00 Acoustical Ceilings 12-18

09 65 13 Resilient Base and Accessories 01-21

09 65 16 Resilient Sheet Flooring 05-18

09 65 19 Resilient Tile Flooring 05-18

09 68 00 Carpeting 01-21

09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21

10 26 00 Wall and Door Protection 01-21

DIVISION 12 – FURNISHINGS

12 32 00 Manufactured Wood Casework 09-15

12 36 00 Countertops 12-18

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16

21 13 16 Dry-Pipe Sprinkler Systems 01-15

21 22 00 Clean Agent Fire Suppression Systems 05-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20

23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment

02-20

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20

VA Project #666-21-700 00 01 10-3

SECTION NO. DIVISION AND SECTION TITLES DATE

23 07 11 HVAC and Boiler Plant Insulation 02-20

23 09 23 Direct-Digital Control System for HVAC 09-11

23 21 13 Hydronic Piping 02-20

23 23 00 Refrigerant Piping 02-20

23 31 00 HVAC Ducts and Casings 02-20

23 36 00 Air Terminal Units 02-20

23 37 00 Air Outlets and Inlets 02-20

23 40 00 HVAC Air Cleaning Devices 03-20

23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 03-20

23 81 00 Decentralized Unitary HVAC Equipment 03-20

23 81 23 Computer-Room Air-Conditioners 03-20

DIVISION 25 – INTEGRATED AUTOMATION

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17

26 05 26 Grounding and Bonding for Electrical Systems 01-17

26 05 33 Raceway and Boxes for Electrical Systems 01-18

26 05 41 Underground Electrical Construction 01-17

26 05 73 Overcurrent Protective Device Coordination Study 01-18

26 08 00 Commissioning of Electrical Systems 11-16

26 24 16 Panelboards 01-18

26 26 00 Power Distribution Units for Static Uninterruptible

Power Systems

01-18

26 27 26 Wiring Devices 01-18

26 29 21 Enclosed Switches and Circuit Breakers 01-17

26 33 53 Static Uninterruptible Power Supply 01-17

26 43 13 Surge Protective Devices 01-17

26 51 00 Interior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

27 05 26 Grounding and Bonding for Communications Systems 06-15

27 05 33 Conduits and Backboxes for Communications Systems 11-21

27 05 36 Cable Trays for Communications Systems 11-21

27 05 53 Identification for Communications Systems 07-21

27 08 00 Commissioning of Communications Systems 11-16

27 10 00 Structured Cabling 11-21

27 11 16 Communications Cabinets, Racks, Frames, And Enclosures 11-21

27 11 19 Communications Termination Blocks and Patch Panels 11-21

27 11 26 Communications Rack Mounted Power Protection and Power

Strips

11-21

27 13 13 Communications Copper Backbone Cabling 11-21

27 13 13.13 Communications Copper Cable Splicing and Terminations 11-21

27 13 23 Communications Optical Fiber Backbone Cabling 11-21

27 13 23.13 Communications Optical Fiber Splicing and Terminations 11-21

VA Project #666-21-700 00 01 10-4

SECTION NO. DIVISION AND SECTION TITLES DATE

27 15 13 Communications Copper Horizontal Cabling 11-21

27 16 19 Communications Patch Cords, Station Cords, and Cross

Connect Wire

11-21

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18

28 05 13 Conductors and Cables for Electronic Safety and

Security

10-18

28 05 26 Grounding and Bonding for Electronic Safety and

Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and

Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16

28 13 00 Physical Access Control System 10-11

28 16 00 Intrusion Detection System 10-11

28 23 00 Video Surveillance 09-11

DIVISION 31 – EARTHWORK

31 20 11 Earthwork (Short Form) 10-12

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16

05-01-20

EHRM Infrastructure Upgrades - Sheridan VA Medical Center DRAWING SHEETS VA Project #666-21-700 00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

Drawing No. Title

GENERAL

G0-00 COVER SHEET

G0-01 SHEET INDEX

G0-02 ABBREVIATIONS, SYMBOLS, LEGENDS AND

ARCHITECTURE GENERAL NOTES

G0-03 INFECTION CONTROL RISK ASSESSMENT

G0-04 PARTITION FRAMING DETAILS

HAZAROUS MATERIALS

HA1.04 BLDG 4 HAZARDOUS MATERIALS - ASBESTOS

HA1.05.1 BLDG 5 HAZARDOUS MATERIALS - ASBESTOS

HA1.06 BLDG 6 HAZARDOUS MATERIALS - ASBESTOS

HA1.07.2 BLDG 7 HAZARDOUS MATERIALS - ASBESTOS

HA1.07.B BLDG 7 HAZARDOUS MATERIALS - ASBESTOS

HA1.09 BLDG 9 HAZARDOUS MATERIALS - ASBESTOS

HA1.11 BLDG 11 HAZARDOUS MATERIALS - ASBESTOS

HA1.24 BLDG 24 HAZARDOUS MATERIALS - ASBESTOS

HA1.32 BLDG 32 HAZARDOUS MATERIALS - ASBESTOS

HA1.37 BLDG 37 HAZARDOUS MATERIALS - ASBESTOS

HA1.42 BLDG 42 HAZARDOUS MATERIALS - ASBESTOS

HA1.61 BLDG 61 HAZARDOUS MATERIALS - ASBESTOS

HL1.04 BLDG 4 HAZARDOUS MATERIALS – LEAD-BASED PAIN T

HL1.05.1 BLDG 5 HAZARDOUS MATERIALS – LEAD-BASED PA INT

HL1.06 BLDG 6 HAZARDOUS MATERIALS – LEAD-BASED PAIN T

HL1.07.2 BLDG 7 HAZARDOUS MATERIALS – LEAD-BASED PA INT

HL1.09 BLDG 9 HAZARDOUS MATERIALS – LEAD-BASED PAIN T

HL1.11 BLDG 11 HAZARDOUS MATERIALS – LEAD-BASED PAI NT

HL1.24 BLDG 24 HAZARDOUS MATERIALS – LEAD-BASED PAI NT

HL1.32 BLDG 32 HAZARDOUS MATERIALS – LEAD-BASED PAI NT

HL1.42 BLDG 42 HAZARDOUS MATERIALS – LEAD-BASED PAI NT

HL1.61 BLDG 61 HAZARDOUS MATERIALS – LEAD-BASED PAI NT

CIVIL

CG100 GENERAL NOTES AND QUANTITIES

CU100 PLAN VIEW

CU101 BUILDING 11 – PLAN AND PROFILE

VA Project #666-21-700 00 01 15 - 2

CU102 BUILDING 26,64 – PLAN AND PROFILE

CU103 BUILDING 31 – PLAN AND PROFILE

CU104 BUILDING 42 MAIN (1) – PLAN AND PROFILE

CU105 BUILDING 42 MAIN (2) – PLAN AND PROFILE

CU106 BUILDING 42 MAIN (3) – PLAN AND PROFILE

CU107 N-S MAIN (1) – PLAN AND PROFILE

CU108 N-S MAIN (2) – PLAN AND PROFILE

CU109 N-S MAIN (3) – PLAN AND PROFILE

CU110 BUILDING 35-37-90-PP – PLAN AND PROFILE

CU111 E-W MAIN (1) – PLAN AND PROFILE

CU112 E-W MAIN (2) – PLAN AND PROFILE

CU113 BUILDING 86 MAIN (1) – PLAN AND PROFILE

CU114 BUILDING 86 MAIN (2) – PLAN AND PROFILE

DT100 DETAILS

ARCHITECTURAL

A1-00 WALL TYPES

A1-01 BLDG 1 1ST FLOOR PLANS

A1-02 BLDG 2 FLOOR PLANS

A1-03 BLDG 3 BSMT FLOOR PLANS

A1-04 BLDG 4 FLOOR PLANS

A1-05 BLDG 5 1ST FLOOR PLANS

A1-06 BLDG 6 FLOOR PLANS

A1-07-B BLDG 7 BSMT FLOOR PLANS

A1-07-2 BLDG 7 2ND FLOOR PLANS

A1-08-B BASEMENT DATA CENTER

A1-08-1 BLDG 8 FLOOR PLANS

A1-09 BLDG 9 FLOOR PLANS

A1-11 BLDG 11 FLOOR PLANS

A1-24 BLDG 24 FLOOR PLANS

A1-31 BLDG 31 FLOOR PLANS

A1-32 BLDG 32 FLOOR PLANS

A1-35 BLDG 35 FLOOR PLANS

A1-36 BLDG 36 FLOOR PLANS

A1-37 BLDG 37 FLOOR PLANS

A1-42 BLDG 42 FLOOR PLANS

A1-61-1 BLDG 61 FLOOR PLANS

A1-61-2 NEW STAIR SECTIONS AND DETAILS

VA Project #666-21-700 00 01 15 - 3

A1-71-1 BLDG 71 1ST FLOOR PLANS

A1-71-3 BLDG 71 3RD FLOOR PLANS

A1-71N-1 BLDG 71N1 FLOOR PLANS

A1-71N-2 BLDG 71N2 FLOOR PLANS

A1-86-1 BLDG 86 1ST FLOOR PLANS

A1-86-3 BLDG 86 3RD FLOOR PLANS

A1-87 BLDG 87 FLOOR PLANS

A1-90 BLDG 90 FLOOR PLANS

A1-G GILLETTE FLOOR PLAN

A5-00 ROOM FINISH SCHEDULE,SIGNAGE SCHEDULE & DETAI LS

A6-00 DOOR SCHEDULE, ELEVATIONS AND DETAILS

STRUCTURAL

S1-61-1 STRUCTURAL GENERAL NOTES

S1-61-2 IBC INSPECTION TABLES

S1-61-3 STAIR OPENING FND AND FRAMING PLANS & DETAI LS

S1-61-4 STAIR FRAMING PLANS & DETAILS

MECHANICAL

M0.00 ABBREVIATIONS, SYMBOLS, LEGENDS AND MECHANICAL

GENERAL NOTES

M1.01.1 BLDG 1 1ST FLOOR PLANS

M1.02 BLDG 2 FLOOR PLANS

M1.03.B BLDG 3 BSMT FLOOR PLANS

M1.04 BLDG 4 PLANS

M1.05.1 BLDG 5 1ST FLOOR PLANS

M1.06 BLDG 6 FLOOR PLANS

M1.07.B BLDG 7 BSMT FLOOR PLANS

M1.07.2 BLDG 7 2ND FLOOR PLANS

M1.08B BLDG 8 BASEMENT DATA CENTER

M1.08 BLDG 8 FLOOR PLANS

M1.09 BLDG 9 FLOOR PLANS

M1.11 BLDG 11 FLOOR PLANS

M1.24 BLDG 24 FLOOR PLANS

M1.31 BLDG 31 FLOOR PLANS

M1.32 BLDG 32 FLOOR PLANS

M1.35 BLDG 35 FLOOR PLANS

M1.36 BLDG 36 FLOOR PLANS

M1.37 BLDG 37 FLOOR PLANS

VA Project #666-21-700 00 01 15 - 4

M1.42 BLDG 42 FLOOR PLANS

M1.61 BLDG 61 FLOOR PLANS

M1.71.1 BLDG 71 1ST FLOOR PLANS

M1.71.3 BLDG 71 3RD FLOOR PLANS

M1.71N.1 BLDG 71N1 FLOOR PLANS

M1.71N.2 BLDG 71N2 FLOOR PLANS

M1.86.1 BLDG 86 1ST FLOOR PLANS

M1.86.3 BLDG 86 3RD FLOOR PLANS

M1.87 BLDG 87 FLOOR PLANS

M1.G GILLETTE FLOOR PLANS

M4.00 MECHANICAL SCHEDULES

M5.00 MECHANICAL DETAILS

M6.00 CONTROL DIAGRAM 1

M6.01 CONTROL DIAGRAM 2

PLUMBING

P1.71.3 BLDG 71 3RD FLOOR PLUMBING PLANS

ELECTRICAL

E0-01 OVERALL ELECTRICAL SITE PLAN - AREA A

E0-02 ELECTRICAL SITE PLAN - AREA B

E0-03 A-SIDE FIBER BACKBONE ONE LINE DIAGRAM

E0-04 B-SIDE FIBER BACKBONE ONE LINE DIAGRAM

E1-01 BUILDING #1 ELECTRICAL PLANS

E1-02 BUILDING #2 ELECTRICAL PLANS

E1-03 BUILDING #3 ELECTRICAL PLANS

E1-04-B BUILDING #4 ELECTRICAL PLAN

E1-04-1 BUILDING #4 ELECTRICAL PLANS

E1-04-2 BUILDING #4 ELECTRICAL PLAN

E1-05-1 BUILDING #5 ELECTRICAL PLANS

E1-05-2 BUILDING #5 ELECTRICAL PLANS

E1-06-1 BUILDING #6 ELECTRICAL PLANS

E1-06-2 BUILDING #6 ELECTRICAL PLANS

E1-07-B BUILDING #7 ELECTRICAL PLANS

E1-07-1 BUILDING #7 ELECTRICAL PLANS

E1-07-2 BUILDING #7 ELECTRICAL PLANS

E1-08-B1 BUILDING #8 EXISTING BASEMENT ELECTRICAL P LAN

E1-08-B2 BUILDING #8 NEW CONSTR BSMNT ELECTRICAL PL ANS

VA Project #666-21-700 00 01 15 - 5

E1-08-1 BUILDING #8 ELECTRICAL PLANS

E1-08-2 BUILDING #8 ELECTRICAL PLANS

E1-09-1 BUILDING #9 ELECTRICAL PLANS

E1-09-3 BUILDING #9 ELECTRICAL PLANS

E1-11 BUILDING #11 ELECTRICAL PLANS

E1-24 BUILDING #24 ELECTRICAL PLANS

E1-31 BUILDING #31 ELECTRICAL PLANS

E1-32 BUILDING #32 ELECTRICAL PLANS

E1-35 BUILDING #35 ELECTRICAL PLANS

E1-36 BUILDING #36 ELECTRICAL PLANS

E1-37 BUILDING #37 ELECTRICAL PLANS

E1-42 BUILDING #42 ELECTRICAL PLANS

E1-61 BUILDING #61 ELECTRICAL PLANS

E1-64-1 BUILDING #64 ELECTRICAL PLANS

E1-64-2 BUILDING #64 ELECTRICAL PLANS

E1-71-1 BUILDING #71 ELECTRICAL PLANS

E1-71-3 BUILDING #71 ELECTRICAL PLANS

E1-71N-1 BUILDING #71N ELECTRICAL PLANS

E1-71N-2 BUILDING #71N ELECTRICAL PLANS

E1-71N-3 BUILDING #71N ELECTRICAL PLANS

E1-86-1A BUILDING #86 ELECTRICAL PLANS

E1-86-1B BUILDING #86 ELECTRICAL PLANS

E1-86-2 BUILDING #86 ELECTRICAL PLANS

E1-86-3 BUILDING #86 ELECTRICAL PLANS

E1-87-1A BUILDING #87 ELECTRICAL PLANS

E1-87-1B BUILDING #87 ELECTRICAL PLANS

E1-90 BUILDING #90 ELECTRICAL PLANS

E1-G-1 GILLETTE CBOC ELECTRICAL PLAN

E2 ELECTRICAL DETAILS

E3 ELECTRICAL DETAILS

E4 ELECTRICAL DETAILS & SCHEDULES

FIRE PROTECTION

FP0-00 SHEET INDEX, SYMBOLS, LEGENDS, AND FIRE

PROTECTION GENERAL NOTES

FP1-01 BLDG 1 1ST FLOOR FIRE PROTECTION

FP1-02 BLDG 2 FIRE PROTECTION

FP1-03 BLDG 3 BSMT FIRE PROTECTION

FP1-04 BLDG 4 FIRE PROTECTION

VA Project #666-21-700 00 01 15 - 6

FP1-05 BLDG 5 1ST FLOOR FIRE PROTECTION

FP1-06 BLDG 6 FIRE PROTECTION

FP1-07-B BLDG 7 BSMT FLOOR FIRE PROTECTION

FP1-07-2 BLDG 7 2ND FLOOR FIRE PROTECTION

FP1-08-B BASEMENT DATA CENTER FIRE PROTECTION

FP1-08-1 BLDG 8 FIRE PROTECTION

FP1-09 BLDG 9 FIRE PROTECTION

FP1-11 BLDG 11 FIRE PROTECTION

FP1-24 BLDG 24 FIRE PROTECTION

FP1-31 BLDG 31 FIRE PROTECTION

FP1-32 BLDG 32 FIRE PROTECTION

FP1-35 BLDG 35 FIRE PROTECTION

FP1-36 BLDG 36 FIRE PROTECTION

FP1-37 BLDG 37 FIRE PROTECTION

FP1-42 BLDG 42 FIRE PROTECTION

FP1-61-2 BLDG 61 FIRE PROTECTION

FP1-71-1 BLDG 71 1ST FLOOR FIRE PROTECTION

FP1-71-3 BLDG 71 3RD FLOOR FIRE PROTECTION

FP1-71N-1 BLDG 71N1 FLOOR FIRE PROTECTION

FP1-71N-2 BLDG 71N2 FLOOR FIRE PROTECTION

FP1-86-1 BLDG 86 1ST FLOOR FIRE PROTECTION

FP1-86-3 BLDG 86 3RD FLOOR FIRE PROTECTION

FP1-87 BLDG 87 FIRE PROTECTION

FP1-G GILLETTE FIRE PROTECTION

TELECOMMUNICATIONS SECURITY

TY-000 ELECTRICAL LEGENDS AND ABBREVIATIONS

TY-001 SITE ELECTRICAL/SECURITY NOTES

TY-002 DATA INFRASTRUCTURE SINGLE LINE - PART 1 OF 4

TY-003 DATA INFRASTRUCTURE SINGLE LINE - PART 2 OF 4

TY-004 DATA INFRASTRUCTURE SINGLE LINE - PART 3 OF 4

TY-005 DATA INFRASTRUCTURE SINGLE LINE - PART 4 OF 4

TY-006 SECURITY DETAILS

TY-1-1 BUILDING 1 TR SECURITY

TY-2-1 BUILDING 2 TR SECURITY

TY-3-B BUILDING 3 TR SECURITY

TY-4-1 BUILDING 4 TR SECURITY

TY-5-1 BUILDING 5 TR SECURITY

VA Project #666-21-700 00 01 15 - 7

TY-6-1 BUILDING 6 TR SECURITY

TY-7-B BUILDING 7 BASEMENT TR SECURITY

TY-7-2 BUILDING 7 LEVEL 2 TR SECURITY

TY-8-1 BUILDING 8 LEVEL 1 TR SECURITY

TY-8-B BUILDING BASEMENT TR SECURITY

TY-9-1 BUILDING 9 TR SECURITY

TY-11-1 BUILDING 11 TR SECURTY

TY-24-1 BUILDING 24 TR SECURITY

TY-31-2 BUILDING 31 TR SECURITY

TY-32-1 BUILDING 32 TR SECURITY

TY-35-B BUILDING 35 TR SECURITY

TY-36-1 BUILDING 36 TR SECURITY

TY-37-1 BUILDING 37 TR SECURITY

TY-42-1 BUILDING 42 TR SECURITY

TY-71-1 BUILDING 71 LEVEL 1 TR SECURITY

TY-71-3 BUILDING 71 LEVEL 3 TR SECURITY

TY-71N-1 BUILDING 71N LEVEL 1 TR SECURITY

TY-71N-2 BUILDING 71N LEVEL 2 TR SECURITY

TY-86-1 BUILDING 86 LEVEL 1 TR SECURITY

TY-86-3 BUILDING 86 LEVEL 3 TR SECURITY

TY-87-1 BUILDING 87 TR SECURITY

TY-90-1 BUILDING 90 TR SECURITY

TY-G-1 GILLETTE CBOC TR SECURITY

- - - E N D - - -

07-13-23

EHRM Infrastructure Upgrades – Sheridan VA Medical Center GENERAL REQUIREMENTS

VA Project #666-21-700 01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1. All employees of contractor or subcontractors shall have the

10-hour (Non-Supervisory Employees) or 30-hour (Supervisory

Employees)OSHA certified Construction Safety course and / or other relevant competency training, as determined by VA.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for “EHRM

INFRASTRUCTURE UPGRADES. SHERIDAN VA MEDICAL CENTER. SHERIDAN,

WYOMING,”

as required by drawings and specifications.

B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting Officer.

C. Offices of FourFront Design Inc, 517 7th Street, Rapid City, SD

57701, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Contractor shall comply with VA security management program.

VA Project #666-21-700 01 00 00 -2

E. Normal working hours for this contract will be from 7:30AM to 4:00PM local time Monday through Friday except for weekends and established Federal holidays.

F. Performing on-site work outside normal working hours will require approval from the Contracting Officer and the COR.

Requests shall be submitted via email at least 72 hours prior to the requested date and at no additional cost to the

Government. Approvals are subject to the availability of on-site staff.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes a construction project to upgrade the facility infrastructure to support the new Electronic Health Record Modernization (EHRM) system in accordance with VA OEHRM Site Infrastructure

Requirements. This includes all data closets on campus, including outlying buildings, the main server room and the

Gillette, WY Community Based Outreach Clinic (CBOC) which is owned by the Sheridan WY VAMC. The project shall include, but is not limited to, upgrading facility fiber throughout the buildings to each IT closet, provide a redundant fiber run throughout the facility to each IT closet, provide redundant fiber mains to the demarcation room from the provider point, installation of

IT outlets and electrical outlets throughout the facility, provide additional outlets in each IT closet, upgrade facility power distribution as required, upgrade facility HVAC distribution as required, physical security assessment and upgrades and hazardous material abatement.

Work by building includes:

Building 1

Hazardous Materials

N/A

Civil

Install buried fiber optic line to the exterior foundation of

VA Project #666-21-700 01 00 00 -3

Building 1. The new run of fiber optic line will require the removal and replacement of sidewalk and road crossings. There will be concrete manhole junction structures associated with this run of fiber.

Architectural

Existing flooring, wall base, ceiling, door and frame to be removed. Patch floor. Install new flooring, and new door and frame. Paint walls.

Mechanical

Tele Com 1-102: Existing mini-split evaporator to be relocated above new door, refrigerant and condensate piping to be modified and reconnected.

Electrical

Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from

Building 8 Fiber Room to existing Tele Com Room in Building 1 and provide new fiber patches on each end. Provide new temperature sensors within existing racks and provide monitoring of sensors.

Fire Protection

Demo and provide new head(s)

Telecomm Security

Modification of final connection point for cameras and PACS system to campus telecommunications networks.

Building 2

Hazardous Materials

N/A

Civil

Install buried fiber optic line to the exterior foundation of

Building 2. The new run of fiber optic line will require the removal and replacement of sidewalk.

VA Project #666-21-700 01 00 00 -4

Architectural

Existing wall, wall base, door & frame to be removed. Patch floor. Build new walls. Install new flooring, doors and frames, and plywood wallcovering. Paint walls.

Mechanical

Tele Com 2-104: New mini-split exterior condensing unit, interior evaporator and thermostat to be installed. New refrigerant and pumped condensate piping to be installed.

Electrical

Provide miscellaneous electrical modifications for renovated spaces to accommodate new Tele Com room. Provide power for new mini-split unit. Provide new communications channel rack with associated power and accessories in new Tele Com room. Provide new cable tray in new Tele Com room. Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from Building 8

Fiber Room to new Tele Com Room in Building 2 and provide new fiber patches on each end. Provide new temperature sensors within new rack and provide monitoring of sensors.

Fire Protection

Demo and provide new head(s)

Telecomm Security

Installation of new camera and PACS system.

Building 3

N/A

Civil

No associated civil work for Building 3.

Architectural

Existing flooring, doors & frames, and wall to be removed. Patch floor. Build new wall. Install new flooring, doors and frames, and plywood wallcovering. Paint walls.

VA Project #666-21-700 01 00 00 -5

Mechanical

Tele-Com 3-002: Remove existing louvers and ducting, cap and seal remaining ducts. New mini-split exterior condensing unit, interior evaporator and thermostat to be installed. New refrigerant and pumped condensate piping to be installed.

Tele-Com 3-003: New mini-split exterior condensing unit, interior evaporator and thermostat to be installed. New refrigerant and pumped condensate piping to be installed.

Electrical

Provide miscellaneous electrical modifications for renovated spaces to accommodate new Tele Com room. Provide power for two new mini-split units. Provide new communications channel rack with associated power and accessories in new Tele Com room. Provide new cable tray in new Tele Com room. Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from Building 8

Fiber Room to new Tele Com Room in Building 3 and provide new fiber patches on each end. Provide new temperature sensors within new rack and provide monitoring of sensors.

Fire Protection

Existing to remain

Building 4

First-floor front lobby, abatement is needed 9x9 vinyl floor tile with black mastic containing asbestos. Also, Windows were reported to have asbestos containing caulking and lead-based paint. Will require remediation if disturbed.

Civil

No associated civil work for Building 4.

Architectural

VA Project #666-21-700 01 00 00 -6

Existing walls, doors & frames, and ceilings to be removed. Build new walls. Install new flooring, doors & frames, ceilings, plywood wallcovering, steel gate, and window security. Paint walls.

Mechanical

Office 4-117 and 4-117A: Remove existing supply diffuser and return grille. Install new supply diffusers and return grilles from existing ducting.

Tele-Com 4-118A: Remove existing disconnected duct and diffuser.

Existing mini-split evaporator to remain in place.

Electrical

Provide miscellaneous electrical modifications for renovated spaces to accommodate expansion of existing Tele Com room and lighting, power and signal changes to nearby office spaces. Replace all telecommunications/data cabling with new

CAT 6A cable and provide new CAT 6A patch panels. Update fiber from Building 8 Fiber Room to revised Tele Com Room in Building

4 and provide new fiber patches on each end. Provide new temperature sensors within existing racks and provide monitoring of sensors.

Make modifications to emergency electrical distribution system.

Fire Protection

Demo and provide new head(s)

Modification of existing Camera and PACS System.

Building 5

No associated civil work for Building 5.

Architectural

Existing flooring, wall base, walls, doors & frames, ceilings, and window to be removed. Patch floor. Build new walls. Install new flooring, doors & frames, plywood

VA Project #666-21-700 01 00 00 -7 wallcovering, ceiling, and window security. Paint walls.

Mechanical

Tele-Com 5-114A: Remove existing radiators, cap and seal existing piping. New mini-split exterior condensing unit, interior evaporator and thermostat to be installed. New refrigerant and gravity condensate piping to be installed.

Electrical

Provide miscellaneous electrical modifications for renovated spaces to accommodate new Tele Com room and modification to additional office spaces. Provide power for new mini-split unit. Provide new communications channel rack with associated power and accessories in new Tele Com room. Provide new cable tray in new Tele Com room. Replace all telecommunications/ data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from Building 8 Fiber Room to new Tele Com

Room in Building 5 and provide new fiber patches on each end. Provide new temperature sensors within new rack and provide monitoring of sensors.

Fire Protection

Demo and provide new head(s)

Building 6

Room 114- 12"x12" VFT with black mastic containing asbestos requires abatement. Windows were reported to have asbestos containing caulking and lead-based paint. Will require remediation if disturbed.

Civil

No associated civil work for Building 6.

Architectural

Existing flooring, wall base, walls, doors & frames, ceilings, VA Project #666-21-700 01 00 00 -8 casework, and window to be removed. Patch floor. Build new walls. Install new flooring, doors & frames, plywood wallcovering, ceiling, and window security. Paint walls.

Mechanical

Tele-Com 6-101 and surrounding area: Disconnect and remove supply duct from existing supply diffusers, cap at trunk ducts.

Install new supply ducting from existing supply trunks, reconnect to existing supply diffusers. Install new fire dampers in existing duct in Tele-Com 6-101 walls.

Electrical

Provide miscellaneous electrical modifications for renovated spaces to accommodate new Tele Com room and lighting, power and signal changes to nearby office spaces. Provide new communications channel rack with associated power and accessories in new Tele Com room. Provide new cable tray in new

Tele Com room. Replace all telecommunications/ data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from Building 8 Fiber Room to new Tele Com

Room in Building 6 and provide new fiber patches on each end. Provide new temperature sensors within new rack and provide monitoring of sensors.

Fire Protection

Demo and provide new head(s) and associated piping.

Building 7

Room 001 - Asbestos-containing textured plaster to be abated.

Room 217A will require asbestos abatement of ceiling tile puck adhesive. Room 217A will also require lead remediation of plaster wall paint.

VA Project #666-21-700 01 00 00 -9

No associated civil work for Building 7.

Architectural

Basement & 2nd floor. Existing flooring, wall base, walls, doors and frames to be removed. Patch floor. Install new flooring, doors and frames, and plywood wallcovering. Paint walls.

Mechanical

Tele-Com 7-001: Remove existing fan and ducting. Existing mini-split evaporator to remain in place, re-route condensate to HAC

7-018. Relocate existing mini-split thermostat.

Tele-Com 7-217A: Remove existing fan, ducting, and grille.

Existing mini-split evaporator to remain in place.

Electrical

Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from

Building 8 Fiber Room to both existing Tele Com Rooms in

Building 7 and provide new fiber patches on each end. Provide new fiber between the two existing Tele Com rooms within this building and provide new fiber patches on each end. Provide new temperature sensors within existing racks of both existing Tele

Com Rooms and provide monitoring of sensors.

Fire Protection

Demo and provide new head(s) and associated piping.

Building 8

N/A

Civil

Install buried fiber optic line to the exterior foundation of

Building 8. The new run of fiber optic line will require road crossing.

VA Project #666-21-700 01 00 00 -10

Architectural

Existing flooring, wall base, wall, door and frame to be removed. Patch floor. Install new flooring, door and frame, and plywood wallcovering. Paint walls.

Mechanical

Tele-Com 8-124: Existing mini-split evaporator to be relocated above new door, refrigerant and condensate piping to be modified and reconnected.

Electrical

Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from

Building 8 Fiber Room to existing Tele Com Room in Building 8 and provide new fiber patches on each end.

Fire Protection

Demo and provide new head(s) and associated piping and Clean

Agent system with detectors.

Building 9

Room 102- Windows were reported to have asbestos containing caulking and lead-based paint. Will require remediation if disturbed.

Civil

No associated civil work for Building 9.

Architectural

Existing wall, door & frame to be removed. Patch floor. Install new flooring, door and frame, plywood wallcovering, and window security. Paint walls.

Mechanical

Tele-Com 9-102: Install new fire dampers in existing duct in

Tele-Com 9-102 walls.

VA Project #666-21-700 01 00 00 -11

Electrical

Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from

Building 8 Fiber Room to the existing Tele Com Room in Building

9 and provide new fiber patches on each end. Provide new temperature sensors within the existing rack of existing Tele

Com Rooms and provide monitoring of sensors.

Fire Protection

Confirm existing with new mechanical.

Building 11

Room 109- Windows were reported to have asbestos containing caulking and lead-based paint. Will require remediation if disturbed.

Civil

Install buried fiber optic line to the exterior foundation of

Building 11. The new run of fiber optic line will require the removal and replacement of sidewalk.

Architectural

Existing walls, wall base, door & frame, and ceiling to be removed. Patch floor. Build new walls. Install new flooring, door and frame, plywood wallcovering, and window security. Paint walls.

Mechanical

Tele-Com 11-109: Remove existing baseboard heaters, cap and seal piping. New mini-split exterior condensing unit, interior evaporator and thermostat to be installed. New refrigerant and pumped condensate piping to be installed.

Electrical

Provide miscellaneous electrical modifications for renovated

VA Project #666-21-700 01 00 00 -12 spaces to accommodate new Tele Com room. Provide power for new mini-split unit. Provide new communications channel rack with associated power and accessories in new Tele Com room. Provide new cable tray in new Tele Com room. Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from Building 8

Fiber Room to new Tele Com Room in Building 11 and provide new fiber patches on each end. Provide new temperature sensors within new rack and provide monitoring of sensors.

Fire Protection

Demo and provide new head(s) and associated piping.

Telecomm Security

Installation of new camera and PACS system.

Building 24

Hazardous Materials

Room 108 - abatement of 9"x9" asbestos-containing vinyl floor tile. In Room 109, windows have been identified with asbestos-containing caulking and lead-based paint; remediation will be necessary if these windows are disturbed.

Civil

Install buried fiber optic line to the exterior foundation of

Building 24. The new run of fiber optic line will require the removal and replacement of sidewalk.

Architectural

Existing flooring, walls, doors & frames, and ceilings to be removed. Patch floor. Install new flooring, door and frame, plywood wallcovering, and window security. Paint walls.

Mechanical

Tele-Com 24-109: New mini-split exterior condensing unit, interior evaporator and thermostat to be installed. New refrigerant and pumped condensate piping to be installed.

VA Project #666-21-700 01 00 00 -13 spaces to accommodate new Tele Com room. Provide power for new mini-split unit. Provide new communications channel rack with associated power and accessories in new Tele Com room. Provide new cable tray in new Tele Com room. Provide new fiber from

Building 8 Fiber Room to new Tele Com Room in Building 24 and provide new fiber patches on each end. Provide new temperature sensors within new rack and provide monitoring of sensors. Provide modifications to electrical distribution system.

Fire Protection

Confirm existing and coordinate with any MEP.

Building 31

N/A

Civil

Install buried fiber optic line to the exterior foundation of

Building 31. The new run of fiber optic line will require the removal and replacement of sidewalk and road crossings. There will be concrete manhole junction structures associated with this run of fiber.

Architectural

Existing changing room walls and casework to be removed. Patch floor. Install new plywood wallcovering. Paint wall.

Mechanical

Seamstress 31-201: New mini-split exterior condensing unit, interior evaporator, and thermostat to be installed. New refrigerant and gravity condensate piping to be installed.

Electrical

Provide power for new mini-split unit. Provide new communications cabinet with associated power and accessories in

VA Project #666-21-700 01 00 00 -14 new Tele Com space within existing Sewing Room. Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Provide new fiber from

Building 8 Fiber Room to new Tele Com space in Building 31 and provide new fiber patches on each end. Provide new temperature sensors within new cabinet and provide monitoring of sensors. Provide modifications to electrical distribution system.

Fire Protection

Confirm existing and coordinate with any MEP.

Installation of new camera.

Building 32

Room 104- 9"x9" vinyl floor tile with black mastic that requires abatement. Additionally, the window in this room has been identified with asbestos-containing caulking and lead-based paint. Remediation will be needed if the window is disturbed.

Civil

Install buried fiber optic line to the exterior foundation of

Building 24.

Architectural

Existing wall, door & frame to be removed. Patch floor. Build new wall. Install new flooring, door and frame, plywood wallcovering, and window security. Paint walls.

Mechanical

Tele-Com 32-104: Remove existing ceiling fan. New mini-split exterior condensing unit, interior evaporator and thermostat to be installed. New refrigerant and pumped condensate piping to be installed.

VA Project #666-21-700 01 00 00 -15 spaces to accommodate new Tele Com room. Provide power for new mini-split unit. Provide new communications channel rack with associated power and accessories in new Tele Com room. Provide new cable tray in new Tele Com room. Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Provide new fiber from

Building 8 Fiber Room to new Tele Com Room in Building 32 and provide new fiber patches on each end. Provide new temperature sensors within new rack and provide monitoring of sensors. Provide modifications to electrical distribution system.

Fire Protection

Confirm existing provide new head(s) and coordinate with any

MEP.

Building 35

N/A

Civil

Install buried fiber optic line to the exterior foundation of

Building 35. The new run of fiber optic line will require the removal and replacement of sidewalk and road crossings.

Architectural

Patch floor. Build new walls. Install new flooring, door and frame, and plywood wallcovering. Paint walls.

Mechanical

Tele-Com 35-002: New mini-split exterior condensing unit, interior evaporator and thermostat to be installed. New refrigerant and pumped condensate piping to be installed.

VA Project #666-21-700 01 00 00 -16 spaces to accommodate new Tele Com room. Provide power for new mini-split unit. Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from Building 8 Fiber Room to new Tele Com

Room in Building 35 and provide new fiber patches on each end. Provide new temperature sensors within existing cabinet rack and provide monitoring of sensors. Provide modifications to electrical distribution system.

Fire Protection

Demo and provide new head(s) and associated piping.

Building 36

N/A

Civil

Install buried fiber optic line to the exterior foundation of

Building 36.

Architectural

Existing wall, platform floor, ladder, and guardrail to be removed. Patch floor. Build new wall. Install new flooring, door and frame, plywood wallcovering, and window security. Paint walls. Reinstall existing ladder. Install new guardrail.

Mechanical

Tele-Com 36-104: Remove existing cabinet unit heater, cap and seal piping. New mini-split exterior condensing unit, interior evaporator and thermostat to be installed. New refrigerant and pumped condensate piping to be installed.

Electrical spaces to accommodate new Tele Com room. Provide power for new

VA Project #666-21-700 01 00 00 -17 mini-split unit. Provide new communications channel rack with associated power and accessories in new Tele Com room. Provide new cable tray in new Tele Com room. Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Provide new fiber from

Building 8 Fiber Room to new Tele Com Room in Building 36 and provide new fiber patches on each end. Provide new temperature sensors within new rack and provide monitoring of sensors.

Fire Protection

Coordinate with any new MEP equipment.

Building 37

Room 101- asbestos-containing linoleum flooring and vermiculite insulation above ceiling will need to be abated.

Civil

Install buried fiber optic line to the exterior foundation of

Building 37.

Architectural

Existing wall, door & frame, ceiling, and a/c unit to be removed. Patch floor. Build new walls. Install new flooring, door and frame, plywood wallcovering, and infill exterior wall opening. Paint walls.

Mechanical

Tele-Com 37-101A: Remove existing window AC unit. New mini-split exterior condensing unit, interior evaporator, and thermostat to be installed. New refrigerant and pumped condensate piping to be installed.

Electrical spaces to accommodate new Tele Com room. Provide power for new

VA Project #666-21-700 01 00 00 -18 mini-split unit. Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from Building 8 Fiber Room to new Tele Com

Room in Building 37 and provide new fiber patches on each end. Provide new temperature sensors within existing cabinet and provide monitoring of sensors.

Fire Protection

Confirm existing provide new piping and head(s) and coordinate with any new MEP equipment.

Building 42

Room 200- Windows have been identified with asbestos-containing caulking and lead-based paint; remediation will be necessary if these windows are disturbed.

Civil

Install buried fiber optic line to the exterior foundation of

Building 42. The new run of fiber optic line will require the removal and replacement of sidewalk and road crossings. There will be concrete manhole junction structures associated with this run of fiber.

Architectural

Install new plywood wallcovering. Paint wallcovering.

Mechanical

Garage Office 42-100: New mini-split exterior condensing unit, interior evaporator and thermostat to be installed. New refrigerant and pumped condensate piping to be installed.

Electrical

Provide power for new mini-split unit. Provide new communications cabinet with associated power and accessories in new Tele Com space within existing Garage Office. Replace all

VA Project #666-21-700 01 00 00 -19 telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from Building 8

Fiber Room to new Tele Com Room in Building 42 and provide new fiber patches on each end. Provide new temperature sensors within new cabinet and provide monitoring of sensors.

Fire Protection

Modify existing

Telecomm Security

Installation of new camera.

Building 61

Hazardous Materials

Rooms 203, 202, and 201- Windows have been identified with asbestos-containing caulking and lead-based paint; remediation will be necessary if these windows are disturbed.

Civil

Install of buried fiber optic line to the exterior foundation of

Building 61.

Architectural

Existing flooring, walls, doors & frames, stair, toilet and lavatory to be removed. Patch floor. Build new walls. Install new flooring, doors and frames, plywood wallcovering, ceilings, window security, and stairs and handrails. Paint walls.

Structural

Install new concrete footing for steel tube column that will help support existing floor. Add steel channels to support the existing floor. Install new steel stair, with steel channel stringers, steel pan treads and risers, with concrete tread infills, and concrete landing on metal deck.

Mechanical

Restroom 61-201A: Remove existing water closet, lavatory, and associated piping for installation of new stairs.

Tele-Com 61-203: New mini-split exterior condensing unit, interior evaporator and thermostat to be installed. New

VA Project #666-21-700 01 00 00 -20 refrigerant and pumped condensate piping to be installed.

Electrical

Provide miscellaneous electrical modifications for renovated spaces to accommodate new Tele Com room and new stair. Provide power for new mini-split unit. Provide new communications channel rack with associated power and accessories in new Tele

Com room. Replace all telecommunications/data cabling with new

CAT 6A cable and provide new CAT 6A patch panels. Update fiber from Building 8 Fiber Room to new Tele Com Room in Building 61 and provide new fiber patches on each end. Provide new temperature sensors within new rack and provide monitoring of sensors.

Fire Protection

Demo and new piping and heads

Telecomm Security

Installation of new camera and PACS system.

Building 64

Hazardous Materials

N/A.

Civil

N/A

Architectural

N/A.

Mechanical

N/A

Electrical

Replace select telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from

Building 8 Fiber Room to both of the existing Tele Com Rooms in

Building 64 and provide new fiber patches on each end. Provide new fiber between the two existing Tele Com rooms within this building and provide new fiber patches on each end.

Fire Protection

VA Project #666-21-700 01 00 00 -21

N/A

Telecomm Security

N/A

Building 71

Hazardous Materials

N/A

Civil

No associated civil work for Building 71.

Architectural

1st & 3rd floors. Existing flooring, wall, wall base, doors & frames, ceilings, and casework to be removed. Patch floor. Build new walls. Install new flooring, doors and frames, plywood wallcovering, window security, ceiling, and casework. Paint walls.

Mechanical

Tele-Com 71-162A: Remove existing supply duct to existing supply diffuser. Install new VAV, supply duct, fire damper and thermostat. Connect new supply duct to existing diffuser.

Tele-Com 71-310A: Existing mini-split evaporator to be relocated, refrigerant and condensate piping to be modified and reconnected.

Clean Storage 71-344 and 71-344A: Remove existing supply diffusers and duct. Cap and seal at trunk duct. Install new VAV, supply duct, diffusers, and thermostat. Install new return grille and duct. Relocate existing sink, modify and extend existing plumbing piping to new sink location.

Electrical

Provide miscellaneous electrical modifications for renovated spaces to accommodate the two new Tele Com rooms. Provide miscellaneous electrical modifications for renovated spaces related to Clean Storage and Day Room spaces. Provide new communications channel rack with associated power and accessories in each of the new Tele Com rooms. Provide new

VA Project #666-21-700 01 00 00 -22 cable tray in new first floor Tele Com room. Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Provide new fiber from

Building 8 Fiber Room to two new Tele Com Rooms in Building 71 and provide new fiber patches on each end. Provide new temperature sensors within both new racks and provide monitoring of sensors.

Fire Protection

Demo existing and install new piping and head(s). Coordinate with MEP equipment.

Building 71N

N/A

Civil

No associated civil work for Building 71N.

Architectural

1st & 2nd floors. Existing walls, wall base, door & frame, flooring and wall base to be removed. Patch floor. Build new walls. Install new flooring, door and frame, plywood wallcovering, and ceiling. Paint walls.

Mechanical

Tele-Com 71N-147: Remove existing fan, duct and grille. Existing mini-split evaporator to remain in place.

Tele-Com 71N-221: Remove existing supply and return grilles and duct, cap at trunk ducts. Existing mini-split evaporator to remain. Install new fire damper in existing duct in Tele-Com

71N-221 wall.

Clean Storage 71N-225: Remove existing piping back to mains and cap. Re-balance existing exhaust grille, install new supply diffuser and duct from existing supply duct.

VA Project #666-21-700 01 00 00 -23

Electrical

Provide miscellaneous electrical modifications for renovated spaces to accommodate new Tele Com room. Provide miscellaneous electrical modifications for construction of new Clean Storage room on second floor. Provide two new communications channel rack with associated power and accessories in new Tele Com room. Provide modifications as noted to the three existing Tele

Com rooms. Replace all telecommunications/data cabling with new

CAT 6A cable and provide new CAT 6A patch panels. Provide new fiber from Building 8 Fiber Room to all 4 of the Tele Com Rooms in Building 71N and provide new fiber patches on each end. Provide new fiber between each of the four Tele Com rooms within this building and provide new fiber patches on each end. Provide new temperature sensors within all the racks and provide monitoring of sensors. Provide electrical distribution changes on third floor.

Fire Protection

New heads and piping, coordinate existing with new MEP equipment.

Building 86

N/A

Civil

Install buried fiber optic line to the exterior foundation of

Building 86. The new run of fiber optic line will require the removal and replacement of sidewalk and road crossings.

Architectural

1st & 3rd floors. Existing walls, wall base, doors & frames, and ceilings to be removed. Patch floors. Build new walls. Install new flooring, doors and frames, and plywood wallcovering. Paint

VA Project #666-21-700 01 00 00 -24 walls.

Mechanical

Tele-Com 86-102A: Remove existing sink, cap and seal water piping below floor. Remove sanitary back below floor for extension to new condensate drain from relocated existing mini-split evaporator. Existing mini-split evaporator to be relocated and refrigerant piping to be modified and reconnected. Core drill floor and install new sanitary standpipe from existing sanitary below the floor. Extend new vent from new sanitary standpipe into ceiling and connect to existing vent. Install new gravity condensate drain from relocated mini-split evaporator to new standpipe drain.

Tele-Com 86-322: Existing mini-split evaporator to be relocated, refrigerant and condensate piping to be modified and reconnected.

Electrical

Provide miscellaneous electrical modifications for renovated spaces to accommodate new Tele Com room on first floor. Provide new communications channel rack with associated power and accessories in new Tele Com room on first floor. Provide modifications as noted to four existing Tele Com rooms. Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Provide new fiber from

Building 8 Fiber Room to three of the Tele Com Rooms in Building

86 and provide new fiber patches on each end. Provide new fiber between each of the three Tele Com rooms within this building and provide new fiber patches on each end. Provide new temperature sensors within all the racks and provide monitoring of sensors.

Fire Protection

New heads and piping, coordinate existing with new MEP equipment.

VA Project #666-21-700 01 00 00 -25

Building 87

N/A

Civil

No associated civil work for Building 87.

Architectural

Existing flooring, wall, wall base, door & frame, and ceiling to be removed. Patch floor. Build new wall. Install new flooring, door and frame, and plywood wallcovering. Paint walls.

Mechanical

No mechanical work.

Electrical

Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from

Building 8 Fiber Room to the existing Tele Com Room in Building

87 and provide new fiber patches on each end. Provide new temperature sensors within existing rack and provide monitoring of sensors.

Fire Protection

New heads and piping, coordinate existing with new MEP equipment.

Building 90

N/A

Install 413 lineal feet of buried fiber optic line to the

VA Project #666-21-700 01 00 00 -26 exterior foundation of Building 90. The new run of fiber optic line will require 101 lineal feet of road crossing. There will be one concrete manhole junction structure associated with this run of fiber.

Architectural

Attach plywood wallcovering. Paint wallcovering.

Mechanical

No mechanical work.

Electrical

Provide power for new mini-split unit. Provide new communications cabinet with associated power and accessories in new Tele Com space within existing Office. Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Update fiber from Building 8

Fiber Room to new Tele Com Room in Building 87 and provide new fiber patches on each end. Provide new temperature sensors within new cabinet and provide monitoring of sensors.

Telecomm Security

Installation of new camera.

Building Gillette

Hazardous Materials

N/A

Civil

No associated civil work for Gillette Building.

Architectural

Existing wall, door & frame to be removed. Patch floor. Build new wall. Install new flooring, door and frame, and plywood wallcovering. Paint walls.

Mechanical

Tele-Com G-129: Install new thermostat and humidity sensor.

Electrical

Replace all telecommunications/data cabling with new CAT 6A cable and provide new CAT 6A patch panels. Provide new

VA Project #666-21-700 01 00 00 -27 temperature sensors within existing racks and provide monitoring of sensors.

Fire Protection

Modify existing to avoid MEP equipment.

Building 8 Data Center

N/A

Civil

No associated civil work for Data Center.

Architectural

Existing walls, doors & frames, ramp, and ceiling to be removed. Build new walls. Install new ramp, door and frame, and air curtain. Paint ramp.

Mechanical

Server Room 8-003: Remove existing…