This document provides questions and answers regarding solicitation SPE8EJ23R0001 for the DLA FEMA Generator Program. The solicitation seeks to lease and rent diesel-powered generators of various sizes on an on-call basis to support FEMA disaster relief operations across the United States and its territories. Incumbent contractors have provided generators under previous generations of similar contracts. The guaranteed minimum order for each awardee is $35,000 and the maximum total value is $980 million over multiple one-year pricing periods. Payment will be made weekly or monthly depending on rental term. The government will handle fueling and daily maintenance of leased generators. Awardees must demonstrate the ability to deliver generators via commercial transportation to staging areas and points of need domestically and internationally using government assets if required. Field service representative labor rates will be negotiated separately for individual delivery orders.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30_SPE8EJ23R00010004.PDF | ||
| SF30_SPE8EJ23R00010002.PDF | ||
| SF30_SPE8EJ23R00010001.pdf | ||
| SF1449_SPE8EJ23R0001.pdf | ||
| Attachment 1 Price Proposal.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO.
See Block 14
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
6. ISSUED BY CODE SPE8EJ 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE FACILITY CODE
SPE8EJ23R0001
X
2023 OCT 12
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of OffersX is extended, X is not extended.
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
12. ACCOUNTING AND APPROPRIATION DATA (If required)
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A NAME AND TITLE OF SIGNER (Type or print)
NSN 7540-01-152-8070
Previous edition unusable
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
16B. UNITED STATES OF AMERICA15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
(a) By completing Items 8 and 15, and returning
DLA TROOP SUPPORT
CONSTRUCTION AND EQUIPMENT (SOE)
700 ROBBINS AVENUE
PHILADELPHIA PA 19111-5096
15C. DATE SIGNED 16C. DATE SIGNED
D. OTHER (Specify type of modification and authority)
3. EFFECTIVE DATE
See Attached Continuation Sheet(s).
(X)
CHECK ONE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED:
CONTINUED ON NEXT PAGE
PAGE 2 OF 3 PAGES
SPE8EJ23R0001 - 0003
A. The following are questions submitted by interested parties and the Government’s responses. An offeror’s question may not appear in the exact wording or in the format submitted. All page numbers listed are referring to the Request for Proposal (RFP).
1.Question: What is the name of the current contractor for this contract?
Response: There are currently five (5) contract holders for the 2nd Generation of the DLA FEMA Generator Program.
2.Question: Will there be a scheduled site visit for this opportunity?
Response: DLA does not anticipate conducting site visits for this acquisition.
3.Question: What will be the anticipated award date for this contract?
Response: The Government anticipates award of the contract(s) in 2024.
4.What will be the anticipated start date for this contract?
Response: The start date would equal the award date.
5.What is the current monthly or total annual awarded amount for this contract?
Response: Per Page 6, Caution Notice, section 8. “Due to the uncertainty associated with emergency power requirements, the Government is unable to provide forecasted quantities. Each contractor selected for award shall have a guaranteed minimum of $35,000.00. Each awardee shall have a contractual maximum of $980,000,000.00. The maximum of $980,000,000.00 also represents the maximum for the acquisition; the sum of all orders against all contracts shall not exceed $980,000,000.00. Note: Based on the most recent contracts supporting the FEMA Generator Program, the average order size during an individual event was $2 million dollars. THIS INFORMATION IS BEING PROVIDED FOR INFORMATIONAL PURPOSES ONLY. THE GOVERNMENT IS NOT OBLIGATED TO PURCHASE AT THESE LEVELS DURING CONTRACT PERFORMANCE.”
6.Question: Have funds been appropriated for this opportunity?
Response: Per Page 6, Caution Notice, section 8., “Each contractor selected for award shall have a guaranteed minimum of $35,000.00.”
7.Question: Is this an existing contract?
Response: Request for Proposal SPE8EJ-23-R-0001 represents the 3rd Generation of the program.
8.Question: Tab 2 shows only 2 locations we are delivering to for the scenario. In actual deployment how many other locations are there to be listed and will this total number of sites change with necessity?
Response: Per Page 25, Statement of Work, 6. Delivery, “The Contractor is responsible for all transportation to and from all shipping destinations. Delivery shall be to Incident Support Bases (ISB)/Staging Areas (SA), Generator Staging Bases (GSB), directly to the point of need, intermediary locations, and/or consolidation points in CONUS, Alaska, Hawaii, Commonwealths (Puerto Rico and The Northern Mariana Islands), and Territories (American Samoa, Guam and U.S. Virgin Islands). US minor Outlying Islands may also require support.”
9.Question: Is there a defined list of generator quantities, generator sizes and locations these will be shipped to?
Response: Per Page 25, Statement of Work, 3. Products, “Contractors will be required to provide prime rated diesel-powered generators with all necessary fuel tanks and fuel lines (with proper connections) via lease/rental as specified in each Delivery Order.”
“Generators for lease/rental will be in the following band sizes:
•Range 1: 15-60kW Prime rated •Range 2: 61-100kW Prime rated •Range 3: 101-200kW Prime rated •Range 4: 201-400kW Prime rated •Range 5: 401-704kW Prime rated •Range 6: 705kW-1mW Prime rated •Range 7: 1.1mW-2mW Prime rated”
With regards to locations these will be shipped to, please see the Response to Question 8.
10.Question: If a national rollout should be requested- Are we open to multiple staging/holding grounds for generator deployment? IE- warehouses in several states dispersed around the nation near airports and major freeways to quickly dispatch once needed.
Response: Per Page 25, Statement of Work, 6. Delivery, “The Contractor is responsible for all transportation to and from all shipping destinations. Delivery shall be to Incident Support Bases (ISB)/Staging Areas (SA), Generator Staging Bases (GSB), directly to the point of need, intermediary locations, and/or consolidation points in CONUS, Alaska, Hawaii, Commonwealths (Puerto Rico and The Northern Mariana Islands), and Territories (American Samoa, Guam and U.S. Virgin Islands). US minor Outlying Islands may also require support.”
11.Question: Is it ok to subcontract Trucking and Logistics companies for the event of a major deployment? Or will we be required to provide all vehicles in house?
Response: Awardees will be required to meet the requirements in the Statement of Work. Awardees may utilize subcontracting to meet these requirements.
12.Question: Can we bid regionally or only nationally?
Response: Regional offers were not requested and will be rejected as nonresponsive. Awardees will be responsible for meeting the requirements in the Statement of Work. Contractors shall provide the rapid deployment of Generator Sets to support Federal Emergency Management Agency (FEMA) Disaster Relief Operations (page 23, Statement of Work, 1.
Scope). The Contractor is responsible for all transportation to and from all shipping destinations. Delivery shall be to Incident Support Bases (ISB)/Staging Areas (SA), Generator Staging Bases (GSB), directly to the point of need, intermediary locations, and/or consolidation points in CONUS, Alaska, Hawaii, Commonwealths (Puerto Rico and The Northern Mariana Islands), and Territories (American Samoa, Guam and U.S. Virgin Islands). US minor Outlying Islands may also require support (page 25, Statement of Work, 6. Delivery).
CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 3 OF 3 PAGES
SPE8EJ23R0001 - 0003
13.Question: Tab 3 shows wire sizing to price as THHN. Should generators be deployed the NEC calls for Extra hard usage SO cord for temporary generator wiring methods. Should we be pricing that instead? Using regular THHN at those voltage would be very dangerous and pose a threat of electrocution.
Response: THHN cable is used in permanent installations and is where FEMA/USACE get the requirement to use it. While the generators are temporary installations, the code allows FEMA/USACE to use the permanent standard.
14.Question: What is the payment schedule?
Response: Per Page 28, Statement of Work, 12. Payment Rental/Lease, “Depending on the rental term, Contractors may submit invoices weekly or every 30 days.”
15.Are we offered a deposit, or monthly billing?
Response: Response: Per Page 28, Statement of Work, 12. Payment Rental/Lease, “Depending on the rental term, Contractors may submit invoices weekly or every 30 days.”
16.Can we have a federal line of credit for purchases or deployment costs?
Response: Contractors are responsible for their own financing. Subject acquisition does not provide for Government financing.
17.Question: Tab 4- How many potential field reps would you be asking to be deployed at one time? In how many locations?
Response: Tab 4 is a scenario as part of the Price Proposal. Per page 37, C. INSTRUCTIONS TO OFFERORS PRICE PROPOSAL (Volume II), section d., “Offerors shall provide a Field Service Representative price based on the scenario information provided. FSR price shall be a fully burdened/loaded labor rate and based on a one 10-hour day.”
Per page 26-27, Statement of Work, 9. Contractor Operations, “Price for a deployed FSR will be negotiated at the time of request.”
Per Page 25, Statement of Work, 5. Minimum/Maximum, “Because of the uncertainty associated with emergency power requirements, the Government is unable to provide forecasted quantities.”
18.Question: How many people do we need to deploy to manage the generators?
Per Page 26, Statement of Work, 8. Government Maintenance - Lease/Rental, “The Government will connect all generators, provide fuel, provide daily preventative maintenance, and perform return to transport maintenance at the end of service prior to contractor pick-up. Daily preventive maintenance will include checking working hour meter for operation, coolant level, oil level, fuel level and filling all fluids to proper levels, and conducting a visual inspection of all external components (connections, hoses, belts, cables, etc.) for serviceability. The government will service each generator every 240 operational hours or when otherwise directed by FEMA and in accordance with manufacturer's recommendations. Service will include changing oil, and filters(s) (oil, air, and fuel). All other fluids shall be maintained in accordance with generator set manufacturer's recommendations.”
19.Question: If there is a need for deployment overseas, do we coordinate with the Air Force or Guard units to use cargo aircraft?
Response: Per Page 26, Statement of Work, 6. Delivery, subsection c., “The Contractor is contractually obligated to be able to provide delivery via commercial transportation resources in both CONUS and OCONUS. However, the Government reserves the right to use the system that is best able to meet mission requirements. Therefore, delivery may be to a CONUS based debarkation point and then transported via federal government assets to OCONUS locations.”
20.Question: Is there a supplemental budget for deployment actions?
Response: Per Page 27 -28., Statement of Work, 11. Pricing, “For the Generators, weekly and monthly rental prices for each band size for each pricing period shall be firm fixed ceiling prices after contract award. All direct and indirect costs associated with leasing/rental of the Generators shall be included in these firm fixed prices including GPS trackers. Prices are exclusive of transportation (including transportation related equipment), BOM (support materials) and a deployed field service representative. There will be five one-year pricing periods under the contract, and they will be sequential. Pricing Periods are applicable to the Lease/Rental Price for each band size of Generators. The contractors may not exceed their firm fixed ceiling prices during the post-award competition of delivery orders. Pricing provided for the transportation scenario, BOM (support material) scenario and the deployed FSR scenario as part of the Initial Proposals are for evaluation purposes only. Post-award, selected awardees will be allowed to propose delivery order specific pricing for transportation, BOM (support material), a deployed FSR, and any other mission related requirements. Awardees shall obtain the lowest applicable transportation charges given the delivery requirements for both shipment to and return from the destination. Furthermore, the Government reserves the right to request the selected awardees to provide whatever additional data the contracting officer needs in order to determine fair and reasonable prices.”