SPE60418R0406_LNG_NSGB_RFP_SF_30_Amend_0001.pdf

PDF 95 KB Posted

Attached to
Naval Station Guantanamo Bay Liquefied Natural Gas
Solicitation number
SPE60418R0406
Issued by

About this file

This is an amendment to a solicitation issued by the Defense Logistics Agency Energy for liquefied natural gas (LNG) fuel to be delivered to Naval Station Guantanamo Bay. The solicitation seeks annual deliveries of approximately 2,349,011 MMBtus of LNG from May 2020 through August 2023 to support an on-site natural gas power plant. Offerors must propose prices at or below $10.85 per MMBtu to be eligible for award. The amendment updates the table of contents, delivery period and volume requirements, removes a clause indicator, and updates ordering periods and delivery end dates in various clauses to reflect the revised period of performance. It also incorporates questions received from industry and the agency's responses into the solicitation document.

SF 30 SPE60418R0406 LNG NSGB RFP Amend 0001

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO.

4. REQUISITION/PURCHASE REQ. NO.

See Block 14

5. PROJECT NO. (If applicable)

6. ISSUED BY CODE SPE604 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE FACILITY CODE

SPE60418R0406

X

2018 JUN 08

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of OffersX is extended, is not extended.

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

12. ACCOUNTING AND APPROPRIATION DATA (If required)

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

E. IMPORTANT: Contractor is not, X is required to sign this document and return 1 copies to issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A NAME AND TITLE OF SIGNER (Type or print)

NSN 7540-01-152-8070

Previous edition unusable

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

16B. UNITED STATES OF AMERICA15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

(a) By completing Items 8 and 15, and returning

DLA ENERGY

INSTALLATION ENERGY

8725 JOHN J. KINGMAN ROAD

FORT BELVOIR VA 22060

15C. DATE SIGNED 16C. DATE SIGNED

D. OTHER (Specify type of modification and authority)

3. EFFECTIVE DATE

See Attached Continuation Sheet(s).

(X)

CHECK ONE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

2018 JUL 13

X

CYNTHIA G. RALPH

CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 2 OF 2 PAGES

SPE60418R0406 - 0001

1. The changes set forth herein are incorporated into Solicitation SPE60418R0406.

Table of Contents

2. Page 2, the Table of Contents table is hereby updated.

Section A

3. Page 3, Section A.1.2 is hereby updated to:

A.1.2 This 80 page Solicitation, Solicitation Number SPE60418R0406, is issued in accordance with FAR 16.53 as a request for proposal (RFP), Friday, June 08, 2018.

4. Page 3, Section A.1.8, is hereby updated to change the delivery period to May 2020 through November 2023.

Section B

5. Page 7, paragraph B.3.2 is hereby updated to:

B.3.2 Commissioning, Testing and Top Off period LNG requirements are estimated to be 93,961 MMBtu based on the usage profile below:

Section I

6. Page 37, FAR Clause 52.212-5 the "X" next to (60)(i) 52.247-64 is hereby deleted.

7. The delivery period and/or ordering period is hereby updated in the following clauses:

a. Page 29, FAR Clause 52.216-18 paragraph (a) last sentence is hereby updated to: Such order may be issued from

April 2020 through November 2023.

b. Page 30, FAR Clause 52.216-21 paragraph (f) is hereby updated to provide that the Contractor shall not be required to make any deliveries under this contract after November 2023.

c. Page 44, FAR Clause 52.252-2, DFARS 252.216-7006 paragraph (a) is hereby updated to: Such order may be issued from April 2020 through November 2023.

Section L

8. Page 69, Section L, paragraph numbering is hereby updated.

Other Changes

9. The RFP is hereby modified to incorporate the following additional information:

Questions submitted to the RFP requirements, along with the Government’s response.

File details come from the government source that posted it. Updated .