About this file
This document is an Attachment to a federal contract opportunity titled "DFSP Ozol, CA O&M Remediation Systems" with Solicitation Number SPE60324R0504. The attachment is a detailed pricing worksheet for Ozol PPW, which lists the required services, deliverables, drilling/well installation, and miscellaneous items along with estimated quantities and unit prices. The contract is seeking small businesses to provide environmental assessment, long-term management, potential implementation of new remedial systems, operations of in-place remediation systems, and emergency response services for the DFSP Ozol, CA site. Key details include an estimated yearly price of $250,000, a base period price of $1,000,000, and an option period price of $125,000 for a total evaluated price of $1,125,000. The services cover long-term monitoring, operation, and maintenance of remediation systems, public meetings, and other related environmental remediation activities.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30_SPE60324R05040002.PDF | ||
| ATTACHMENT 1 - Ozol PWS.pdf | ||
| SF30_SPE60324R05040001.PDF | ||
| ATTACHMENT 4 - Past Performance Reference List.xlsx | XLSX spreadsheet | |
| ATTACHMENT 3 - PPQ.pdf | ||
| Solicitation SPE603-24-R-0504.pdf | ||
| ATTACHMENT 6 - Wage Det 2015-5623 Rev 24.pdf | ||
| ATTACHMENT 5 - Joint Venture Consent Form.docx | DOCX document | |
| ATTACHMENT 2 - Ozol PPW.xlsx | XLSX spreadsheet | |
| ATTACHMENT 1 - Ozol PWS.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ozol PPW
COMPANY &
LOCATION:
| PREPARER | ||
| NAME: | DATE PREPARED: |
| REFERENCE ITEM | CLIN | TYPE | ITEM DESCRIPTION | ESTIMATED QUANTITY PER YEAR | UNIT | UNIT PRICE | Total Price (Estimated Quantity x Unit Price) | |
| DELIVERABLES | ||||||||
| 001 | 0001 | REP | Draft Project Management Plan (includes SAP and HASP) | 1 | EA | $0.00 | $0.00 | |
| 002 | 0001 | REP | Final Project Management Plan | 1 | EA | $0.00 | $0.00 | |
| 003 | 0001 | REP | Kickoff Meeting Minutes | 1 | EA | $0.00 | $0.00 | |
| 004 | 0001 | REP | Quarterly Project Management Review Meeting & Minutes | 4 | EA | $0.00 | $0.00 | |
| 005 | 0001 | REP | Quarterly Regulatory Agency Meeting & Minutes | 4 | EA | $0.00 | $0.00 | |
| 006 | 0001 | REP | Contract Closure Meeting | 1 | EA | $0.00 | $0.00 | |
| 007 | 0001 | REP | Monthly Utility Invoicing Summary | 12 | EA | $0.00 | $0.00 | |
| 008 | 0001 | REP | Upper Tank Farm Groundwater Treatment System Monthly Remedial System Status Report | 12 | EA | $0.00 | $0.00 | |
| 009 | 0001 | REP | Upper Tank Farm DPE System Monthly Remedial System Status Report | 12 | EA | $0.00 | $0.00 | |
| 010 | 0001 | REP | Administration Area Remedial System Monthly Status Report | 12 | EA | $0.00 | $0.00 | |
| 011 | 0001 | REP | Administration Area (Generator Bldg) DPE Remedial System Monthly Status Report | 12 | EA | $0.00 | $0.00 | |
| 012 | 0001 | REP | Semi-Annual Groundwater Monitoring Report | 1 | EA | $0.00 | $0.00 | |
| 013 | 0001 | REP | Annual Groundwater Monitoring Report | 1 | EA | $0.00 | $0.00 | |
| 014 | 0002 | REP | Facility Compliance Quarterly Summary Report | 4 | EA | $0.00 | $0.00 | |
| 015 | 0003 | REP | Facility Maintenance Monthly Summary Report | 12 | EA | $0.00 | $0.00 | |
| SERVICES | ||||||||
| 016 | SVC | Asbestos Site Supervisor or Safety Officer price per hour | 40 | EA | $0.00 | $0.00 | ||
| 017 | SVC | Asbestos worker price per hour | 40 | EA | $0.00 | $0.00 | ||
| 018 | SVC | Biologist/Botanist 1 price per hour | 20 | EA | $0.00 | $0.00 | ||
| 019 | SVC | Biologist/Botanist 2 price per hour | 20 | EA | $0.00 | $0.00 | ||
| 020 | SVC | Buyer price per hour | 110 | EA | $0.00 | $0.00 | ||
| 021 | SVC | Certified Industrial Hygenist price per hour | 40 | EA | $0.00 | $0.00 | ||
| 022 | SVC | Chemist 1 price per hour | 200 | EA | $0.00 | $0.00 | ||
| 023 | SVC | Chemist 2 price per hour | 100 | EA | $0.00 | $0.00 | ||
| 024 | SVC | Chemist 3 price per hour | 50 | EA | $0.00 | $0.00 | ||
| 025 | SVC | Cost Accountant price per hour | 240 | EA | $0.00 | $0.00 | ||
| 026 | SVC | Drafter (including CAD, hardware & software) price per hour | 260 | EA | $0.00 | $0.00 | ||
| 027 | SVC | Engineer 1 (Staff) price per hour | 1600 | EA | $0.00 | $0.00 | ||
| 028 | SVC | Engineer 2 (Project) price per hour | 1240 | EA | $0.00 | $0.00 | ||
| 029 | SVC | Engineer 3 (Senior) price per hour | 800 | EA | $0.00 | $0.00 | ||
| 030 | SVC | Environmental Scientist 1 price per hour | 1880 | EA | $0.00 | $0.00 | ||
| 031 | SVC | Environmental Scientist 2 price per hour | 1040 | EA | $0.00 | $0.00 | ||
| 032 | SVC | Environmental Scientist 3 price per hour | 400 | EA | $0.00 | $0.00 | ||
| 033 | SVC | Environmental Technician price per hour | 1600 | EA | $0.00 | $0.00 | ||
| 034 | SVC | Geologist 1 price per hour | 1580 | EA | $0.00 | $0.00 | ||
| 035 | SVC | Geologist 2 price per hour | 1200 | EA | $0.00 | $0.00 | ||
| 036 | SVC | Geologist 3 price per hour | 800 | EA | $0.00 | $0.00 | ||
| 037 | SVC | Health and Safety Officer price per hour | 40 | EA | $0.00 | $0.00 | ||
| 038 | SVC | Heavy Equipment operator price per hour | 80 | EA | $0.00 | $0.00 | ||
| 039 | SVC | Hydrogeologist 1 price per hour | 120 | EA | $0.00 | $0.00 | ||
| 040 | SVC | Hydrogeologist 2 price per hour | 100 | EA | $0.00 | $0.00 | ||
| 041 | SVC | Laborer price per hour | 320 | EA | $0.00 | $0.00 | ||
| 042 | SVC | Project Manager price per hour | 850 | EA | $0.00 | $0.00 | ||
| 043 | SVC | QA/QC Officer price per hour | 200 | EA | $0.00 | $0.00 | ||
| 044 | SVC | Remediation System Operator price per hour | 260 | EA | $0.00 | $0.00 | ||
| 045 | SVC | Secretary price per hour | 225 | EA | $0.00 | $0.00 | ||
| 046 | SVC | Site Labor Foreman price per hour | 80 | EA | $0.00 | $0.00 | ||
| 047 | SVC | Specialized Construction Manager (includes travel and per-diem) | 200 | EA | $0.00 | $0.00 | ||
| 048 | SVC | Specialized Heavy Equipment Operator (includes travel and per-diem) | 200 | EA | $0.00 | $0.00 | ||
| 049 | SVC | Specialized Hydrogeologist 2 (includes travel and per-diem) | 200 | EA | $0.00 | $0.00 | ||
| 050 | SVC | Toxicologist / Risk Assessor 1 price per hour | 200 | EA | $0.00 | $0.00 | ||
| 051 | SVC | Toxicologist / Risk Assessor 2 price per hour | 140 | EA | $0.00 | $0.00 | ||
| 052 | SVC | Toxicologist/ Risk Assessor 3 price per hour | 100 | EA | $0.00 | $0.00 | ||
| 053 | SVC | Traffic Control Engineer price per hour | 80 | EA | $0.00 | $0.00 | ||
| FACILITY MAINTENANCE | ||||||||
| 054 | SVC | Laborer/Contractor (Line riding, inspections) | 180 | EA | $0.00 | $0.00 | ||
| 055 | SVC | Electrician | 120 | EA | $0.00 | $0.00 | ||
| 056 | SVC | Laborer (e.g. trash picker) | 100 | EA | $0.00 | $0.00 | ||
| 057 | SVC | Maintenance Mechanic | 40 | EA | $0.00 | $0.00 | ||
| DRILLING, WELL INSTALLATION, AND OTHER INVESTIGATION SERVICES | ||||||||
| 058 | DRL | Mobilization Cost for HSA drill rig (soil boring/probe/well install) | 4 | EA | $0.00 | $0.00 | ||
| 059 | DRL | Mobilization Cost for Rotosonic drill rig (soil boring/probe/well install) | 4 | EA | $0.00 | $0.00 | ||
| 060 | DRL | HSA boring, price of 2 1/4" ID, up to 20 feet | 1 | EA | $0.00 | $0.00 | ||
| 061 | DRL | HSA boring, cost per foot of 2 1/4" ID, from 21 to 40 feet | 20 | FT | $0.00 | $0.00 | ||
| 062 | DRL | HSA boring, cost per foot of 2 1/4" ID, 41 to 80 feet | 40 | FT | $0.00 | $0.00 | ||
| 063 | DRL | HSA boring, cost per foot of 2 1/4" ID, 81 to 150 feet | 70 | FT | $0.00 | $0.00 | ||
| 064 | DRL | HSA boring, price of 4 1/4" ID, up to 20 feet | 1 | EA | $0.00 | $0.00 | ||
| 065 | DRL | HSA boring, cost per foot of 4 1/4" ID, from 21 to 40 feet | 20 | FT | $0.00 | $0.00 | ||
| 066 | DRL | HSA boring, cost per foot of 4 1/4" ID, 41 to 80 feet | 40 | FT | $0.00 | $0.00 | ||
| 067 | DRL | HSA boring, cost per foot of 4 1/4" ID, 81 to 150 feet | 70 | FT | $0.00 | $0.00 | ||
| 068 | DRL | HSA boring, price of 8 1/4" ID, up to 20 feet | 2 | EA | $0.00 | $0.00 | ||
| 069 | DRL | HSA boring, cost per foot of 8 1/4" ID, from 21 to 40 feet | 40 | FT | $0.00 | $0.00 | ||
| 070 | DRL | HSA boring, cost per foot of 8 1/4" ID, 41 to 80 feet | 80 | FT | $0.00 | $0.00 | ||
| 071 | DRL | HSA boring, cost per foot of 8 1/4" ID, 81 to 150 feet | 70 | FT | $0.00 | $0.00 | ||
| 072 | DRL | Sonic boring, price of 4" ID, up to 20 feet | 1 | EA | $0.00 | $0.00 | ||
| 073 | DRL | Sonic boring, cost per foot of 4" ID, from 21 to 40 feet | 20 | FT | $0.00 | $0.00 | ||
| 074 | DRL | Sonic boring, cost per foot of 4" ID, 41 to 80 feet | 40 | FT | $0.00 | $0.00 | ||
| 075 | DRL | Sonic boring, cost per foot of 4" ID, 81 to 150 feet | 70 | FT | $0.00 | $0.00 | ||
| 076 | DRL | Sonic boring, price of 6" ID, up to 20 feet | 2 | EA | $0.00 | $0.00 | ||
| 077 | DRL | Sonic boring, cost per foot of 6" ID, from 21 to 40 feet | 40 | FT | $0.00 | $0.00 | ||
| 078 | DRL | Sonic boring, cost per foot of 6" ID, 41 to 80 feet | 80 | FT | $0.00 | $0.00 | ||
| 079 | DRL | Sonic boring, cost per foot of 6" ID, 81 to 150 feet | 70 | FT | $0.00 | $0.00 | ||
| 080 | DRL | Sonic boring, price of 8" ID, up to 20 feet | 2 | EA | $0.00 | $0.00 | ||
| 081 | DRL | Sonic boring, cost per foot of 8" ID, from 21 to 40 feet | 40 | FT | $0.00 | $0.00 | ||
| 082 | DRL | Sonic boring, cost per foot of 8" ID, 41 to 80 feet | 80 | FT | $0.00 | $0.00 | ||
| 083 | DRL | Sonic boring, cost per foot of 8" ID, 81 to 150 feet | 70 | FT | $0.00 | $0.00 | ||
| 084 | DRL | Monitoring well installation, cost of 2" SCH 40 PVC including all | ||||||
| materials, up to 20 feet, in HSA or Sonic boring | 2 | EA | $0.00 | $0.00 | ||||
| 085 | DRL | Monitoring well installation, cost per foot of 2" SCH 40 PVC monitoring well from 21 to 40 feet, in HSA or Sonic boring | 20 | FT | $0.00 | $0.00 | ||
| 086 | DRL | Monitoring well installation, cost per foot of 2" SCH 40 PVC monitoring | ||||||
| well from 41 to 80 feet, in HSA or Sonic boring | 40 | FT | $0.00 | $0.00 | ||||
| 087 | DRL | Monitoring well installation, cost per foot of 2" SCH 40 PVC monitoring | ||||||
| well from 81 to 150 feet, in HSA or Sonic boring | 70 | FT | $0.00 | $0.00 | ||||
| 088 | DRL | Monitoring well installation, additional cost per foot, 2" 304 Stainless | ||||||
| Steel in place of SCH 40 PVC, in HSA or Sonic boring | 80 | FT | $0.00 | $0.00 | ||||
| 089 | DRL | Monitoring well installation, cost per 4" SCH 40 PVC monitoring well | ||||||
| up to 20 feet, in HSA or Sonic boring | 40 | EA | $0.00 | $0.00 | ||||
| 090 | DRL | Monitoring well installation, cost per 4" SCH 40 PVC monitoring well | ||||||
| from 21 to 40 feet, in HSA or Sonic boring | 40 | FT | $0.00 | $0.00 | ||||
| 091 | DRL | Monitoring well installation, cost per 4" SCH 40 PVC monitoring well | ||||||
| from 41 to 80 feet, in HSA or Sonic boring | 80 | FT | $0.00 | $0.00 | ||||
| 092 | DRL | Monitoring well installation, cost per 4" SCH 40 PVC monitoring well | ||||||
| from 81 to 150 feet, in HSA or Sonic boring | 70 | FT | $0.00 | $0.00 | ||||
| 093 | DRL | Monitoring well installation, additional price per foot of 4" 304 Stainless | ||||||
| Steel in place of SCH 40 PVC, in HSA or Sonic boring | 80 | FT | $0.00 | $0.00 | ||||
| 094 | DRL | Monitoring Well, Install flush mount box for 2" or 4" well | 10 | EA | $0.00 | $0.00 | ||
| 095 | DRL | Monitoring Well, Install above grade (4x4 pad), steel casing casing | 10 | EA | $0.00 | $0.00 | ||
| 096 | DRL | Mobilization Cost, Well Decommissioning | 4 | EA | $0.00 | $0.00 | ||
| 097 | DRL | Decommission 2" dia. vertical well, grout in place, remove top 5' of | ||||||
| casing, cost per foot | 120 | EA | $0.00 | $0.00 | ||||
| 098 | DRL | Decommission 4" dia. vertical well, grout in place, remove top 5' of | ||||||
| casing, cost per foot | 120 | EA | $0.00 | $0.00 | ||||
| 099 | DRL | Decommission 6" dia. vertical well, grout in place, remove top 5' of casing, cost per foot | 40 | EA | $0.00 | $0.00 | ||
| 100 | DRL | Decommission 2" dia. vertical well, overdrill and grout, cost per foot | 120 | EA | $0.00 | $0.00 | ||
| 101 | DRL | Decommission 4" dia. vertical well, overdrill and grout, cost per foot | 120 | EA | $0.00 | $0.00 | ||
| 102 | DRL | Decommission 6" dia. vertical well, overdrill and grout, cost per foot | 40 | EA | $0.00 | $0.00 | ||
| 103 | DRL | Well Development, 2" dia. including all equipment and supplies, per well | 40 | EA | $0.00 | $0.00 | ||
| 104 | DRL | Well Development, 4" dia. including all equipment and supplies, per well | 40 | EA | $0.00 | $0.00 | ||
| 105 | DRL | Well Inspection - Down Hole Camera Inspection, vertical well, to | ||||||
| include report of findings, per Half Day | 1 | EA | $0.00 | $0.00 | ||||
| 106 | DRL | DPT (Direct Push Technology) Drilling, Mobilization price | 1 | EA | $0.00 | $0.00 | ||
| 107 | DRL | DPT BORING, price per day, including all tooling | 10 | EA | $0.00 | $0.00 | ||
| 108 | DRL | DPT SOIL SURVEY - Price per unit (10 points/unit) - up to 5 feet | ||||||
| depth, DPT Rig, per day | 2 | EA | $0.00 | $0.00 | ||||
| 109 | DRL | DPT SOIL & GAS SURVEY - Price per unit (10 points/unit) - greater than 5 | ||||||
| to 15 feet depth, DPT Rig, per day | 2 | EA | $0.00 | $0.00 | ||||
| 110 | DRL | SOIL & GAS SURVEY - Price per unit (10 points/unit) - up to 5 feet depth, hand auger, per day | 2 | EA | $0.00 | $0.00 | ||
| 111 | DRL | SOIL & GAS SURVEY - Price per unit (10 points/unit) - greater than 5 | ||||||
| to 15 feet depth, hand auger, per day | 2 | EA | $0.00 | $0.00 | ||||
| 112 | DRL | SOIL & GAS SURVEY - Report of findings, Draft, Draft Final and Final | 2 | EA | $0.00 | $0.00 | ||
| 113 | DRL | SURVEY - Boring/Well location survey (price per 10) | 4 | EA | $0.00 | $0.00 | ||
| 114 | DRL | SURVEY - Physical Survey price per half day (includes surveyor, crew, | ||||||
| and equipment) | 4 | EA | $0.00 | $0.00 | ||||
| 115 | DRL | UTILITY CLEARANCE - Geophysical/GPR Survey, Price per unit (10,000 linear feet) to include in report of findings | 8 | EA | $0.00 | $0.00 | ||
| 116 | DRL | UTILITY CLEARANCE - Geophysical/GPR Survey, half day field work to include in report of findings | 8 | EA | $0.00 | $0.00 | ||
| MISCELLANEOUS | ||||||||
| 117 | MIS | Brass Long-shackle monitoring well locks, keyed alike, each | 12 | EA | $0.00 | $0.00 | ||
| 118 | MIS | Backhoe Mobilization/Demobiliztion | 2 | EA | $0.00 | $0.00 | ||
| 119 | MIS | Backhoe Loader, 2WD, 14 ft boom, multipurpose bucket, per day including fuel | 1 | EA | $0.00 | $0.00 | ||
| 120 | MIS | Backhoe Loader, 4WD, 14 ft boom, multipurpose bucket, per day including fuel | 1 | EA | $0.00 | $0.00 | ||
| 121 | MIS | Crane Mobilization/Demobiliztion | 2 | EA | $0.00 | $0.00 | ||
| 122 | MIS | Crane rental, price per day including fuel | 3 | EA | $0.00 | $0.00 | ||
| 123 | MIS | Disposal, Hazardous (for VOCs) per gallon | 110 | EA | $0.00 | $0.00 | ||
| 124 | MIS | Disposal, Hazardous (for heavy metals) per gallon | 110 | EA | $0.00 | $0.00 | ||
| 125 | MIS | Disposal, Hazardous (for VOCs) per Drum | 2 | EA | $0.00 | $0.00 | ||
| 126 | MIS | Disposal, Hazardous (for heavy metals) per Drum | 2 | EA | $0.00 | $0.00 | ||
| 127 | MIS | Disposal, Non-hazardous soil, per Ton | 300 | EA | $0.00 | $0.00 | ||
| 128 | MIS | Disposal, Non-hazardous (solids/soil with PFAS) per Drum | 50 | EA | $0.00 | $0.00 | ||
| 129 | MIS | Disposal, Non-hazardous (liquid with PFAS) per Drum | 50 | EA | $0.00 | $0.00 | ||
| 130 | MIS | Disposal, Non-hazardous (solids/soil with PFAS) per ton | 500 | EA | $0.00 | $0.00 | ||
| 131 | MIS | Disposal, Non-hazardous (liquid with PFAS) bulk truck per gallon | 2000 | EA | $0.00 | $0.00 | ||
| 132 | MIS | Camera, Digital (Nikon SRL or equivalent) price per day | 10 | EA | $0.00 | $0.00 | ||
| 133 | MIS | Digitial Photographic documentation - Electronic Submittal to DLA | 10 | EA | $0.00 | $0.00 | ||
| 134 | MIS | Disposable Bailers, each | 40 | EA | $0.00 | $0.00 | ||
| 135 | MIS | Disposable Tubing (3/8-in, 500ft) | 1000 | EA | $0.00 | $0.00 | ||
| 136 | MIS | Drum, 55-Gallon DOT Approved, Steel or Plastic | 55 | EA | $0.00 | $0.00 | ||
| 137 | MIS | Dump Truck, 5-7 CY - Mobilization/Demobiliztion | 2 | EA | $0.00 | $0.00 | ||
| 138 | MIS | Dump Truck, 5-7 CY, price per day including fuel | 2 | EA | $0.00 | $0.00 | ||
| 139 | MIS | Dump Truck, 5-7 CY with operator, price per day including fuel | 2 | EA | $0.00 | $0.00 | ||
| 140 | MIS | Contractor's processing and payment of various permits and fees (i.e. applications, regulatory assessments, easements, right of entry, utilities), | ||||||
| per $1000 value | 10 | EA | $0.00 | $0.00 | ||||
| 141 | MIS | EPA 5035 Sample Container or equivalent, per each 8260 analysis | 300 | EA | $0.00 | $0.00 | ||
| 142 | MIS | Excavator delivery | 1 | EA | $0.00 | $0.00 | ||
| 143 | MIS | Excavator, minimum 19,000-lbs up to 25,000-lbs, price per day including fuel | 1 | EA | $0.00 | $0.00 | ||
| 144 | MIS | Excavator, Mini-excavator (3500 lb) delivery | 1 | EA | $0.00 | $0.00 | ||
| 145 | MIS | Excavator, Mini-excavator (3500 lb) price per day including fuel | 1 | EA | $0.00 | $0.00 | ||
| 146 | MIS | Forklift Mobilization/Demobiliztion | 2 | EA | $0.00 | $0.00 | ||
| 147 | MIS | Forklift/Telehandler, 6-8K, multipurpose bucket, per week, includes fuel | 2 | EA | $0.00 | $0.00 | ||
| 148 | MIS | Flame Ionization Detector price per day includes shipping | 35 | EA | $0.00 | $0.00 | ||
| 149 | MIS | Frac Tank mobilization/demobilization | 6 | EA | $0.00 | $0.00 | ||
| 150 | MIS | Frac Tank (single or double walled 8,400 gallon capacity) price per month | 6 | EA | $0.00 | $0.00 | ||
| 151 | MIS | Frac Tank (single walled 20,000 gallon capacity) price per month | 6 | EA | $0.00 | $0.00 | ||
| 152 | MIS | Frac Tank (double walled 20,000 gallon capacity) price per month | 1 | EA | $0.00 | $0.00 | ||
| 153 | MIS | Subcontract Tank Cleaning (Frac Tank) - 1 each | 1 | EA | $0.00 | $0.00 | ||
| 154 | MIS | Generator (4000 watt) price per day including fuel | 20 | EA | $0.00 | $0.00 | ||
| 155 | MIS | HDPE fittings (flanged and welded fittings and valves) - 1 LOT | 1 | EA | $0.00 | $0.00 | ||
| 156 | MIS | HDPE piping (1.5-in to 2-in diameter) per 10 feet | 1 | EA | $0.00 | $0.00 | ||
| 157 | MIS | HDPE piping (4-in to 6-in diameter) per 10 feet | 10 | EA | $0.00 | $0.00 | ||
| 158 | MIS | HDPE piping (double-walled 2-in to 4-in diameter) per 10 feet | 10 | EA | $0.00 | $0.00 | ||
| 159 | MIS | Hydroseeding - per 100 sf (includes all labor and materials using | ||||||
| standard seed mixes) | 8 | EA | $0.00 | $0.00 | ||||
| 160 | MIS | Lawn mower, riding, rental price per day including fuel | 2 | EA | $0.00 | $0.00 | ||
| 161 | MIS | Lawn mower, riding, enclosed, rental price per day including fuel | 2 | EA | $0.00 | $0.00 | ||
| 162 | MIS | Lawn mower, walk-behind, rental price per day including fuel | 5 | EA | $0.00 | $0.00 | ||
| 163 | MIS | Monitoring well skimming sock 1.5"x2', 20 per pack, including | ||||||
| installation materials up to 70 ft | 10 | EA | $0.00 | $0.00 | ||||
| 164 | MIS | Oil/Water interface probe price per day | 35 | EA | $0.00 | $0.00 | ||
| 165 | MIS | Oxygen Analyzer / Explosimeter Combustible Gas Monitor price per day including shipping | 5 | EA | $0.00 | $0.00 | ||
| 166 | MIS | Photoionization Detector price per day including shipping | 35 | EA | $0.00 | $0.00 | ||
| 167 | MIS | Pickup Truck (1/2 ton) price per day including fuel | 430 | EA | $0.00 | $0.00 | ||
| 168 | MIS | PVC Piping, 1" or 2" diameter, price per foot | 1 | EA | $0.00 | $0.00 | ||
| 169 | MIS | PVC Piping, 4" diameter, price per foot | 100 | EA | $0.00 | $0.00 | ||
| 170 | MIS | PVC Piping, 6" diameter, price per foot | 100 | EA | $0.00 | $0.00 | ||
| 171 | MIS | Pressure washer (gas or electric) rental price per day including fuel | 3 | EA | $0.00 | $0.00 | ||
| 172 | MIS | Roll-Off Container with liner and cover, Delivery and monthly rental, 20 | 10 | EA | $0.00 | $0.00 | ||
| 173 | MIS | Rough Terrain/Off-Road Utility Vehicle (e.g. Gator) price per day including fuel | 2 | EA | $0.00 | $0.00 | ||
| 174 | MIS | Silt Fence price per 50 feet (Installed) | 4 | EA | $0.00 | $0.00 | ||
| 175 | MIS | Skid steer mobilization/demobilization | 2 | EA | $0.00 | $0.00 | ||
| 176 | MIS | Skid steer rental price per day including fuel | 5 | EA | $0.00 | $0.00 | ||
| 177 | MIS | Straw Bale, including installation | 20 | EA | $0.00 | $0.00 | ||
| 178 | MIS | Straw Wattle (8.5"x25' or equivalent), includes installation | 4 | EA | $0.00 | $0.00 | ||
| 179 | MIS | Super Silt Fence price per 50 feet, includes installation | 4 | EA | $0.00 | $0.00 | ||
| 180 | MIS | Tedlar Bags price per dozen | 10 | EA | $0.00 | $0.00 | ||
| 181 | MIS | Temporary Berms or Spill Containment (12'x50'), each | 1 | EA | $0.00 | $0.00 | ||
| 182 | MIS | Temporary restroom & sink, delivery, installed, with service price per week | 2 | EA | $0.00 | $0.00 | ||
| 183 | MIS | Traffic control, Traffic control devices (including arrow board and cones) 1 truck including fuel and 1 laborer price per day | 4 | EA | $0.00 | $0.00 | ||
| 184 | MIS | Troll 9500 Water Quality Meter w/200 feet of cable or equivalent, price | ||||||
| per week | 4 | EA | $0.00 | $0.00 | ||||
| 185 | MIS | Utility truck price per day including fuel | 30 | EA | $0.00 | $0.00 | ||
| 186 | MIS | Vacuum truck (70 BBL) with operator price per half day including fuel | 26 | EA | $0.00 | $0.00 | ||
| 187 | MIS | Water level meter price per day | 40 | EA | $0.00 | $0.00 | ||
| 188 | MIS | Water Tank mobilization/demobilization | 4 | EA | $0.00 | $0.00 | ||
| 189 | MIS | Water Tank (single walled 2,500 gallon) price per month | 4 | EA | $0.00 | $0.00 | ||
| 190 | MIS | Water truck with operator price per day including fuel | 24 | EA | $0.00 | $0.00 | ||
| 191 | MIS | Well Caps (2-in and 4-in) | 20 | EA | $0.00 | $0.00 | ||
| 192 | MIS | Dumpster/Bin 3-yd or 4-yd, per month | 12 | EA | $0.00 | $0.00 | ||
| ANALYTICAL TESTING | ||||||||
| 193 | LAB | ASTM D1298 API gravity liquid Petroleum Products | 1 | EA | $0.00 | $0.00 | ||
| 194 | LAB | CA-WET (STLC - extraction only) | 4 | EA | $0.00 | $0.00 | ||
| 195 | LAB | CA-WET (STLC - CCR Metals Title 22 - 6010/7470/7471 only) | 4 | EA | $0.00 | $0.00 | ||
| 196 | LAB | EPA 160.1 (Total Dissolved Solids (TDS)) | 36 | EA | $0.00 | $0.00 | ||
| 197 | LAB | EPA 160.2 (Total Suspended Solids (TSS)) | 36 | EA | $0.00 | $0.00 | ||
| 198 | LAB | EPA 300.0 (Anions including SO4, NO2, NO3, Cl) | 76 | EA | $0.00 | $0.00 | ||
| 199 | LAB | EPA 350.1 (Ammonia as Nitrogen) | 16 | EA | $0.00 | $0.00 | ||
| 200 | LAB | EPA 353.2 (Nitrate-Nitrite Nitrogen) | 16 | EA | $0.00 | $0.00 | ||
| 201 | LAB | EPA 351.4 (TKN) | 12 | EA | $0.00 | $0.00 | ||
| 202 | LAB | EPA 365.3 (Total Phosphorous) | 12 | EA | $0.00 | $0.00 | ||
| 203 | LAB | EPA 376.2 (Sulfide, Dissolved) | 12 | EA | $0.00 | $0.00 | ||
| 204 | LAB | EPA 410.4 (COD) | 12 | EA | $0.00 | $0.00 | ||
| 205 | LAB | EPA 6010/7470/7471 (CCR Metals Title 22 - 6010/7470/7471) | 6 | EA | $0.00 | $0.00 | ||
| 206 | LAB | EPA 6010 (Individual Metal 6010) | 46 | EA | $0.00 | $0.00 | ||
| 207 | LAB | EPA 1010 (Ignitability) | 12 | EA | $0.00 | $0.00 | ||
| 208 | LAB | EPA 1311 (TCLP - extraction only) | 4 | EA | $0.00 | $0.00 | ||
| 209 | LAB | EPA 1311 (TCLP - Full Toxicity Characterization) | 4 | EA | $0.00 | $0.00 | ||
| 210 | LAB | EPA 1311/6010B/C/7471A (TCLP Metals) | 14 | EA | $0.00 | $0.00 | ||
| 211 | LAB | EPA 1311/8270C/D (TCLP SVOCs) | 4 | EA | $0.00 | $0.00 | ||
| 212 | LAB | EPA 1311/ZHE/8260B/C (TCLP VOCs) | 4 | EA | $0.00 | $0.00 | ||
| 213 | LAB | Draft EPA 1633 (PFAS in Water) | 400 | EA | $0.00 | $0.00 | ||
| 214 | LAB | Draft EPA 1633 (PFAS in Soil) | 400 | EA | $0.00 | $0.00 | ||
| 215 | LAB | EPA 1664 (N-Hexane Extractable Material) | 12 | EA | $0.00 | $0.00 | ||
| 216 | LAB | EPA 1668A (PCB) | 6 | EA | $0.00 | $0.00 | ||
| 217 | LAB | EPA 7196A/7199 (Hexavalent Chromium) | 12 | EA | $0.00 | $0.00 | ||
| 218 | LAB | EPA 7470 / 7471 (Mercury) | 12 | EA | $0.00 | $0.00 | ||
| 219 | LAB | EPA 8015B/C (Extractables) | 260 | EA | $0.00 | $0.00 | ||
| 220 | LAB | EPA 8015B/C (Purgeables) | 260 | EA | $0.00 | $0.00 | ||
| 221 | LAB | EPA 8015B/C (Extractables) with silica gel cleanup | 250 | EA | $0.00 | $0.00 | ||
| 222 | LAB | EPA 8015B/C Carbon Chain Speciation, purgeables plus extractables, C4-C44 | 510 | EA | $0.00 | $0.00 | ||
| 223 | LAB | EPA 8081/A (Organochlorine Pesticides (OCP)) | 4 | EA | $0.00 | $0.00 | ||
| 224 | LAB | EPA 8151A (Chlorinated Herbicides ) | 4 | EA | $0.00 | $0.00 | ||
| 225 | LAB | EPA 8260B/5035 (VOCs 8260B/5035 +Oxygenates +TPHG) | 510 | EA | $0.00 | $0.00 | ||
| 226 | LAB | EPA 8260B/C (VOCs (BTEX/MTBE/Naphthalene only)) | 125 | EA | $0.00 | $0.00 | ||
| 227 | LAB | EPA 8260B/C (Full list) | 12 | EA | $0.00 | $0.00 | ||
| 228 | LAB | EPA 8260M BTEX and oxygenates in air | 48 | EA | $0.00 | $0.00 | ||
| 229 | LAB | EPA 8270C/D (SVOCs) | 12 | EA | $0.00 | $0.00 | ||
| 230 | LAB | EPA 8270C/D SIM (PAH-SIM) | 22 | EA | $0.00 | $0.00 | ||
| 231 | LAB | EPA 9023 (Total Extractable Organic Halides (EOX)) | 24 | EA | $0.00 | $0.00 | ||
| 232 | LAB | EPA 9045 (pH) | 24 | EA | $0.00 | $0.00 | ||
| 233 | LAB | EPA 9014 (Cyanide in water) | 30 | EA | $0.00 | $0.00 | ||
| 234 | LAB | Oil Viscosity per ASTM D7152 - 11(2016) | 2 | EA | $0.00 | $0.00 | ||
| 235 | LAB | SM5210 (BOD) | 24 | EA | $0.00 | $0.00 | ||
| 236 | LAB | SM5310 B/C/D (TOC ) | 24 | EA | $0.00 | $0.00 | ||
| 237 | LAB | SM5520B/G (Oil and Grease) | 24 | EA | $0.00 | $0.00 | ||
| 238 | LAB | SM5540 (Surfactant) | 24 | EA | $0.00 | $0.00 | ||
| 239 | LAB | EPA 5.10, Alkalinity in water as CaCO3 | 48 | EA | $0.00 | $0.00 | ||
| 240 | LAB | EPA SW-846/Method 9035: Sulfate (SO42-), aqueous | 48 | EA | $0.00 | $0.00 | ||
| 241 | LAB | EPA 236.1: Dissolved ferrous iron, Fe 2+, 3+, aqueous | 48 | EA | $0.00 | $0.00 | ||
| 242 | LAB | EPA 15: Hydrogen sulfide (H2S), aqueous | 48 | EA | $0.00 | $0.00 | ||
| 243 | LAB | ASTM D-2216/ EPA Method 8000C: Soil moisture | 48 | EA | $0.00 | $0.00 | ||
| 244 | LAB | TO-15 (VOCs) in Air, soil gas source, including summa can rental | 48 | EA | $0.00 | $0.00 | ||
| 245 | LAB | TO-15 (VOCs) in Air, soil gas source, including Tedlar bag | 24 | EA | $0.00 | $0.00 | ||
| 246 | LAB | TO-17 (VOCs) in Air, soil gas, with sorbent tubes | 12 | EA | $0.00 | $0.00 | ||
| 247 | LAB | TO-3 (VOCs) in Air, soil gas source, including summa can rental | 24 | EA | $0.00 | $0.00 | ||
| 248 | LAB | TO-3 (VOCs) in Air, soil gas source, including Tedlar bag | 12 | EA | $0.00 | $0.00 | ||
| 0007 | Utilities (electricity, natural gas, water, sewer) | $250,000.00 | ||||||
| Decimal multiplier applied to unit price for Reference Items 193-248 for 24 hour expedited turn around time | ||||||||
| Decimal multiplier applied to unit price for Reference Items 193-248 for 72 hour expedited turn around time | ||||||||
| Decimal multiplier applied to unit price for Reference Items 193-248 for 5 day expedited turn around time | ||||||||
| Yearly Estimated Price | $250,000.00 | |||||||
| Base Period Price | $1,000,000.00 | |||||||
| Option Period Price | $125,000.00 | |||||||
| Total Evaluated Price | $1,125,000.00 | |||||||
| Instructions to Complete Form: Offeror must fill out all cells shaded in green. Other cells are locked for editing. Offeror must identify all assumptions and exceptions in Section I of Technical Management Proposal. | ||||||||
| Also, pricing for equipment is inclusive of an operator for an 8-hour shift, only when the Reference Item includes “operator” in the description. Otherwise the pricing provided is for the specified piece of equipment; the operator price will be billed using the applicable reference item. | ||||||||
| NOTES | ||||||||
| SVC | Services | |||||||
| DRL | Drilling and Well Installation | |||||||
| REP | Reporting | |||||||
| MIS | Miscellaneous | |||||||
| LAB | Laboratory Services |