XLSX spreadsheet 38 KB Posted
- Attached to
- DFSP Ozol, CA O&M Remediation Systems Federal contract opportunity
- Solicitation number
- SPE60324R0504
- Issued by
- Defense Logistics Agency Energy
About this file
This document appears to be an Excel pricing worksheet for a federal contract opportunity related to environmental assessment and remediation services for the Defense Fuel Supply Point (DFSP) Ozol facility in California.
The worksheet includes detailed pricing for various deliverables, services, drilling/well installation, and miscellaneous items that would be required under the contract. Pricing is provided for labor categories, equipment rentals, analytical testing, and other related costs. The total evaluated price for the base period and option period is $1,125,000. The federal contract opportunity is solicitation number SPE60324R0504 issued by the Defense Logistics Agency Energy. The services required include long-term monitoring, operation, and maintenance of remediation systems, public meetings, and other environmental remediation activities in accordance with state and local regulations.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30_SPE60324R05040002.PDF | ||
| ATTACHMENT 2 - Ozol PPW.xlsx | XLSX spreadsheet | |
| ATTACHMENT 1 - Ozol PWS.pdf | ||
| SF30_SPE60324R05040001.PDF | ||
| ATTACHMENT 6 - Wage Det 2015-5623 Rev 24.pdf | ||
| ATTACHMENT 5 - Joint Venture Consent Form.docx | DOCX document | |
| ATTACHMENT 1 - Ozol PWS.pdf | ||
| ATTACHMENT 4 - Past Performance Reference List.xlsx | XLSX spreadsheet | |
| ATTACHMENT 3 - PPQ.pdf | ||
| Solicitation SPE603-24-R-0504.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ozol PPW
COMPANY &
LOCATION:
| PREPARER | ||
| NAME: | DATE PREPARED: |
| REFERENCE ITEM | CLIN | TYPE | ITEM DESCRIPTION | ESTIMATED QUANTITY PER YEAR | UNIT | UNIT PRICE | Total Price (Estimated Quantity x Unit Price) | |
| DELIVERABLES | ||||||||
| 001 | 0001 | REP | Draft Project Management Plan (includes SAP and HASP) | 1 | EA | $0.00 | $0.00 | |
| 002 | 0001 | REP | Final Project Management Plan | 1 | EA | $0.00 | $0.00 | |
| 003 | 0001 | REP | Kickoff Meeting Minutes | 1 | EA | $0.00 | $0.00 | |
| 004 | 0001 | REP | Quarterly Project Management Review Meeting & Minutes | 4 | EA | $0.00 | $0.00 | |
| 005 | 0001 | REP | Quarterly Regulatory Agency Meeting & Minutes | 4 | EA | $0.00 | $0.00 | |
| 006 | 0001 | REP | Contract Closure Meeting | 1 | EA | $0.00 | $0.00 | |
| 007 | 0001 | REP | Monthly Utility Invoicing Summary | 12 | EA | $0.00 | $0.00 | |
| 008 | 0001 | REP | Upper Tank Farm Groundwater Treatment System Monthly Remedial System Status Report | 12 | EA | $0.00 | $0.00 | |
| 009 | 0001 | REP | Upper Tank Farm DPE System Monthly Remedial System Status Report | 12 | EA | $0.00 | $0.00 | |
| 010 | 0001 | REP | Administration Area Remedial System Monthly Status Report | 12 | EA | $0.00 | $0.00 | |
| 011 | 0001 | REP | Administration Area (Generator Bldg) DPE Remedial System Monthly Status Report | 12 | EA | $0.00 | $0.00 | |
| 012 | 0001 | REP | Semi-Annual Groundwater Monitoring Report | 2 | EA | $0.00 | $0.00 | |
| 013 | 0001 | REP | Annual Groundwater Monitoring Report | 1 | EA | $0.00 | $0.00 | |
| 014 | 0002 | REP | Facility Compliance Quarterly Summary Report | 4 | EA | $0.00 | $0.00 | |
| 015 | 0003 | REP | Facility Maintenance Monthly Summary Report | 12 | EA | $0.00 | $0.00 | |
| SERVICES | ||||||||
| 016 | SVC | Asbestos Site Supervisor or Safety Officer price per hour | 40 | EA | $0.00 | $0.00 | ||
| 017 | SVC | Asbestos worker price per hour | 40 | EA | $0.00 | $0.00 | ||
| 018 | SVC | Biologist/Botanist 1 price per hour | 20 | EA | $0.00 | $0.00 | ||
| 019 | SVC | Biologist/Botanist 2 price per hour | 20 | EA | $0.00 | $0.00 | ||
| 020 | SVC | Buyer price per hour | 110 | EA | $0.00 | $0.00 | ||
| 021 | SVC | Certified Industrial Hygenist price per hour | 40 | EA | $0.00 | $0.00 | ||
| 022 | SVC | Chemist 1 price per hour | 200 | EA | $0.00 | $0.00 | ||
| 023 | SVC | Chemist 2 price per hour | 100 | EA | $0.00 | $0.00 | ||
| 024 | SVC | Chemist 3 price per hour | 50 | EA | $0.00 | $0.00 | ||
| 025 | SVC | Cost Accountant price per hour | 240 | EA | $0.00 | $0.00 | ||
| 026 | SVC | Drafter (including CAD, hardware & software) price per hour | 260 | EA | $0.00 | $0.00 | ||
| 027 | SVC | Engineer 1 (Staff) price per hour | 1600 | EA | $0.00 | $0.00 | ||
| 028 | SVC | Engineer 2 (Project) price per hour | 1240 | EA | $0.00 | $0.00 | ||
| 029 | SVC | Engineer 3 (Senior) price per hour | 800 | EA | $0.00 | $0.00 | ||
| 030 | SVC | Environmental Scientist 1 price per hour | 1880 | EA | $0.00 | $0.00 | ||
| 031 | SVC | Environmental Scientist 2 price per hour | 1040 | EA | $0.00 | $0.00 | ||
| 032 | SVC | Environmental Scientist 3 price per hour | 400 | EA | $0.00 | $0.00 | ||
| 033 | SVC | Environmental Technician price per hour | 1600 | EA | $0.00 | $0.00 | ||
| 034 | SVC | Geologist 1 price per hour | 1580 | EA | $0.00 | $0.00 | ||
| 035 | SVC | Geologist 2 price per hour | 1200 | EA | $0.00 | $0.00 | ||
| 036 | SVC | Geologist 3 price per hour | 800 | EA | $0.00 | $0.00 | ||
| 037 | SVC | Health and Safety Officer price per hour | 40 | EA | $0.00 | $0.00 | ||
| 038 | SVC | Heavy Equipment operator price per hour | 80 | EA | $0.00 | $0.00 | ||
| 039 | SVC | Hydrogeologist 1 price per hour | 120 | EA | $0.00 | $0.00 | ||
| 040 | SVC | Hydrogeologist 2 price per hour | 100 | EA | $0.00 | $0.00 | ||
| 041 | SVC | Laborer price per hour | 320 | EA | $0.00 | $0.00 | ||
| 042 | SVC | Project Manager price per hour | 850 | EA | $0.00 | $0.00 | ||
| 043 | SVC | QA/QC Officer price per hour | 200 | EA | $0.00 | $0.00 | ||
| 044 | SVC | Remediation System Operator price per hour | 260 | EA | $0.00 | $0.00 | ||
| 045 | SVC | Secretary price per hour | 225 | EA | $0.00 | $0.00 | ||
| 046 | SVC | Site Labor Foreman price per hour | 80 | EA | $0.00 | $0.00 | ||
| 047 | SVC | Specialized Construction Manager (includes travel and per-diem) | 200 | EA | $0.00 | $0.00 | ||
| 048 | SVC | Specialized Heavy Equipment Operator (includes travel and per-diem) | 200 | EA | $0.00 | $0.00 | ||
| 049 | SVC | Specialized Hydrogeologist 2 (includes travel and per-diem) | 200 | EA | $0.00 | $0.00 | ||
| 050 | SVC | Toxicologist / Risk Assessor 1 price per hour | 200 | EA | $0.00 | $0.00 | ||
| 051 | SVC | Toxicologist / Risk Assessor 2 price per hour | 140 | EA | $0.00 | $0.00 | ||
| 052 | SVC | Toxicologist/ Risk Assessor 3 price per hour | 100 | EA | $0.00 | $0.00 | ||
| 053 | SVC | Traffic Control Engineer price per hour | 80 | EA | $0.00 | $0.00 | ||
| FACILITY MAINTENANCE | ||||||||
| 054 | SVC | Laborer/Contractor (Line riding, inspections) | 180 | EA | $0.00 | $0.00 | ||
| 055 | SVC | Electrician | 120 | EA | $0.00 | $0.00 | ||
| 056 | SVC | Laborer (e.g. trash picker) | 100 | EA | $0.00 | $0.00 | ||
| 057 | SVC | Maintenance Mechanic | 40 | EA | $0.00 | $0.00 | ||
| DRILLING, WELL INSTALLATION, AND OTHER INVESTIGATION SERVICES | ||||||||
| 058 | DRL | Mobilization Cost for HSA drill rig (soil boring/probe/well install) | 4 | EA | $0.00 | $0.00 | ||
| 059 | DRL | Mobilization Cost for Rotosonic drill rig (soil boring/probe/well install) | 4 | EA | $0.00 | $0.00 | ||
| 060 | DRL | HSA boring, price of 2 1/4" ID, up to 20 feet | 1 | EA | $0.00 | $0.00 | ||
| 061 | DRL | HSA boring, cost per foot of 2 1/4" ID, from 21 to 40 feet | 20 | FT | $0.00 | $0.00 | ||
| 062 | DRL | HSA boring, cost per foot of 2 1/4" ID, 41 to 80 feet | 40 | FT | $0.00 | $0.00 | ||
| 063 | DRL | HSA boring, cost per foot of 2 1/4" ID, 81 to 150 feet | 70 | FT | $0.00 | $0.00 | ||
| 064 | DRL | HSA boring, price of 4 1/4" ID, up to 20 feet | 1 | EA | $0.00 | $0.00 | ||
| 065 | DRL | HSA boring, cost per foot of 4 1/4" ID, from 21 to 40 feet | 20 | FT | $0.00 | $0.00 | ||
| 066 | DRL | HSA boring, cost per foot of 4 1/4" ID, 41 to 80 feet | 40 | FT | $0.00 | $0.00 | ||
| 067 | DRL | HSA boring, cost per foot of 4 1/4" ID, 81 to 150 feet | 70 | FT | $0.00 | $0.00 | ||
| 068 | DRL | HSA boring, price of 8 1/4" ID, up to 20 feet | 2 | EA | $0.00 | $0.00 | ||
| 069 | DRL | HSA boring, cost per foot of 8 1/4" ID, from 21 to 40 feet | 40 | FT | $0.00 | $0.00 | ||
| 070 | DRL | HSA boring, cost per foot of 8 1/4" ID, 41 to 80 feet | 80 | FT | $0.00 | $0.00 | ||
| 071 | DRL | HSA boring, cost per foot of 8 1/4" ID, 81 to 150 feet | 70 | FT | $0.00 | $0.00 | ||
| 072 | DRL | Sonic boring, price of 4" ID, up to 20 feet | 1 | EA | $0.00 | $0.00 | ||
| 073 | DRL | Sonic boring, cost per foot of 4" ID, from 21 to 40 feet | 20 | FT | $0.00 | $0.00 | ||
| 074 | DRL | Sonic boring, cost per foot of 4" ID, 41 to 80 feet | 40 | FT | $0.00 | $0.00 | ||
| 075 | DRL | Sonic boring, cost per foot of 4" ID, 81 to 150 feet | 70 | FT | $0.00 | $0.00 | ||
| 076 | DRL | Sonic boring, price of 6" ID, up to 20 feet | 2 | EA | $0.00 | $0.00 | ||
| 077 | DRL | Sonic boring, cost per foot of 6" ID, from 21 to 40 feet | 40 | FT | $0.00 | $0.00 | ||
| 078 | DRL | Sonic boring, cost per foot of 6" ID, 41 to 80 feet | 80 | FT | $0.00 | $0.00 | ||
| 079 | DRL | Sonic boring, cost per foot of 6" ID, 81 to 150 feet | 70 | FT | $0.00 | $0.00 | ||
| 080 | DRL | Sonic boring, price of 8" ID, up to 20 feet | 2 | EA | $0.00 | $0.00 | ||
| 081 | DRL | Sonic boring, cost per foot of 8" ID, from 21 to 40 feet | 40 | FT | $0.00 | $0.00 | ||
| 082 | DRL | Sonic boring, cost per foot of 8" ID, 41 to 80 feet | 80 | FT | $0.00 | $0.00 | ||
| 083 | DRL | Sonic boring, cost per foot of 8" ID, 81 to 150 feet | 70 | FT | $0.00 | $0.00 | ||
| 084 | DRL | Monitoring well installation, cost of 2" SCH 40 PVC including all | ||||||
| materials, up to 20 feet, in HSA or Sonic boring | 2 | EA | $0.00 | $0.00 | ||||
| 085 | DRL | Monitoring well installation, cost per foot of 2" SCH 40 PVC monitoring well from 21 to 40 feet, in HSA or Sonic boring | 20 | FT | $0.00 | $0.00 | ||
| 086 | DRL | Monitoring well installation, cost per foot of 2" SCH 40 PVC monitoring | ||||||
| well from 41 to 80 feet, in HSA or Sonic boring | 40 | FT | $0.00 | $0.00 | ||||
| 087 | DRL | Monitoring well installation, cost per foot of 2" SCH 40 PVC monitoring | ||||||
| well from 81 to 150 feet, in HSA or Sonic boring | 70 | FT | $0.00 | $0.00 | ||||
| 088 | DRL | Monitoring well installation, additional cost per foot, 2" 304 Stainless | ||||||
| Steel in place of SCH 40 PVC, in HSA or Sonic boring | 80 | FT | $0.00 | $0.00 | ||||
| 089 | DRL | Monitoring well installation, cost per 4" SCH 40 PVC monitoring well | ||||||
| up to 20 feet, in HSA or Sonic boring | 40 | EA | $0.00 | $0.00 | ||||
| 090 | DRL | Monitoring well installation, cost per 4" SCH 40 PVC monitoring well | ||||||
| from 21 to 40 feet, in HSA or Sonic boring | 40 | FT | $0.00 | $0.00 | ||||
| 091 | DRL | Monitoring well installation, cost per 4" SCH 40 PVC monitoring well | ||||||
| from 41 to 80 feet, in HSA or Sonic boring | 80 | FT | $0.00 | $0.00 | ||||
| 092 | DRL | Monitoring well installation, cost per 4" SCH 40 PVC monitoring well | ||||||
| from 81 to 150 feet, in HSA or Sonic boring | 70 | FT | $0.00 | $0.00 | ||||
| 093 | DRL | Monitoring well installation, additional price per foot of 4" 304 Stainless | ||||||
| Steel in place of SCH 40 PVC, in HSA or Sonic boring | 80 | FT | $0.00 | $0.00 | ||||
| 094 | DRL | Monitoring Well, Install flush mount box for 2" or 4" well | 10 | EA | $0.00 | $0.00 | ||
| 095 | DRL | Monitoring Well, Install above grade (4x4 pad), steel casing casing | 10 | EA | $0.00 | $0.00 | ||
| 096 | DRL | Mobilization Cost, Well Decommissioning | 4 | EA | $0.00 | $0.00 | ||
| 097 | DRL | Decommission 2" dia. vertical well, grout in place, remove top 5' of | ||||||
| casing, cost per foot | 120 | EA | $0.00 | $0.00 | ||||
| 098 | DRL | Decommission 4" dia. vertical well, grout in place, remove top 5' of | ||||||
| casing, cost per foot | 120 | EA | $0.00 | $0.00 | ||||
| 099 | DRL | Decommission 6" dia. vertical well, grout in place, remove top 5' of casing, cost per foot | 40 | EA | $0.00 | $0.00 | ||
| 100 | DRL | Decommission 2" dia. vertical well, overdrill and grout, cost per foot | 120 | EA | $0.00 | $0.00 | ||
| 101 | DRL | Decommission 4" dia. vertical well, overdrill and grout, cost per foot | 120 | EA | $0.00 | $0.00 | ||
| 102 | DRL | Decommission 6" dia. vertical well, overdrill and grout, cost per foot | 40 | EA | $0.00 | $0.00 | ||
| 103 | DRL | Well Development, 2" dia. including all equipment and supplies, per well | 40 | EA | $0.00 | $0.00 | ||
| 104 | DRL | Well Development, 4" dia. including all equipment and supplies, per well | 40 | EA | $0.00 | $0.00 | ||
| 105 | DRL | Well Inspection - Down Hole Camera Inspection, vertical well, to | ||||||
| include report of findings, per Half Day | 1 | EA | $0.00 | $0.00 | ||||
| 106 | DRL | DPT (Direct Push Technology) Drilling, Mobilization price | 1 | EA | $0.00 | $0.00 | ||
| 107 | DRL | DPT BORING, price per day, including all tooling | 10 | EA | $0.00 | $0.00 | ||
| 108 | DRL | DPT SOIL SURVEY - Price per unit (10 points/unit) - up to 5 feet | ||||||
| depth, DPT Rig, per day | 2 | EA | $0.00 | $0.00 | ||||
| 109 | DRL | DPT SOIL & GAS SURVEY - Price per unit (10 points/unit) - greater than 5 | ||||||
| to 15 feet depth, DPT Rig, per day | 2 | EA | $0.00 | $0.00 | ||||
| 110 | DRL | SOIL & GAS SURVEY - Price per unit (10 points/unit) - up to 5 feet depth, hand auger, per day | 2 | EA | $0.00 | $0.00 | ||
| 111 | DRL | SOIL & GAS SURVEY - Price per unit (10 points/unit) - greater than 5 | ||||||
| to 15 feet depth, hand auger, per day | 2 | EA | $0.00 | $0.00 | ||||
| 112 | DRL | SOIL & GAS SURVEY - Report of findings, Draft, Draft Final and Final | 2 | EA | $0.00 | $0.00 | ||
| 113 | DRL | SURVEY - Boring/Well location survey (price per 10) | 4 | EA | $0.00 | $0.00 | ||
| 114 | DRL | SURVEY - Physical Survey price per half day (includes surveyor, crew, | ||||||
| and equipment) | 4 | EA | $0.00 | $0.00 | ||||
| 115 | DRL | UTILITY CLEARANCE - Geophysical/GPR Survey, Price per unit (10,000 linear feet) to include in report of findings | 8 | EA | $0.00 | $0.00 | ||
| 116 | DRL | UTILITY CLEARANCE - Geophysical/GPR Survey, half day field work to include in report of findings | 8 | EA | $0.00 | $0.00 | ||
| MISCELLANEOUS | ||||||||
| 117 | MIS | Brass Long-shackle monitoring well locks, keyed alike, each | 12 | EA | $0.00 | $0.00 | ||
| 118 | MIS | Backhoe Mobilization/Demobiliztion | 2 | EA | $0.00 | $0.00 | ||
| 119 | MIS | Backhoe Loader, 2WD, 14 ft boom, multipurpose bucket, per day including fuel | 1 | EA | $0.00 | $0.00 | ||
| 120 | MIS | Backhoe Loader, 4WD, 14 ft boom, multipurpose bucket, per day including fuel | 1 | EA | $0.00 | $0.00 | ||
| 121 | MIS | Crane Mobilization/Demobiliztion | 2 | EA | $0.00 | $0.00 | ||
| 122 | MIS | Crane rental, price per day including fuel | 3 | EA | $0.00 | $0.00 | ||
| 123 | MIS | Disposal, Hazardous (for VOCs) per gallon | 110 | EA | $0.00 | $0.00 | ||
| 124 | MIS | Disposal, Hazardous (for heavy metals) per gallon | 110 | EA | $0.00 | $0.00 | ||
| 125 | MIS | Disposal, Hazardous (for VOCs) per Drum | 2 | EA | $0.00 | $0.00 | ||
| 126 | MIS | Disposal, Hazardous (for heavy metals) per Drum | 2 | EA | $0.00 | $0.00 | ||
| 127 | MIS | Disposal, Non-hazardous soil, per Ton | 300 | EA | $0.00 | $0.00 | ||
| 128 | MIS | Disposal, Non-hazardous (solids/soil with PFAS) per Drum | 50 | EA | $0.00 | $0.00 | ||
| 129 | MIS | Disposal, Non-hazardous (liquid with PFAS) per Drum | 50 | EA | $0.00 | $0.00 | ||
| 130 | MIS | Disposal, Non-hazardous (solids/soil with PFAS) per ton | 500 | EA | $0.00 | $0.00 | ||
| 131 | MIS | Disposal, Non-hazardous (liquid with PFAS) bulk truck per gallon | 2000 | EA | $0.00 | $0.00 | ||
| 132 | MIS | Camera, Digital (Nikon SRL or equivalent) price per day | 10 | EA | $0.00 | $0.00 | ||
| 133 | MIS | Digitial Photographic documentation - Electronic Submittal to DLA | 10 | EA | $0.00 | $0.00 | ||
| 134 | MIS | Disposable Bailers, each | 40 | EA | $0.00 | $0.00 | ||
| 135 | MIS | Disposable Tubing (3/8-in, 500ft) | 1000 | EA | $0.00 | $0.00 | ||
| 136 | MIS | Drum, 55-Gallon DOT Approved, Steel or Plastic | 55 | EA | $0.00 | $0.00 | ||
| 137 | MIS | Dump Truck, 5-7 CY - Mobilization/Demobiliztion | 2 | EA | $0.00 | $0.00 | ||
| 138 | MIS | Dump Truck, 5-7 CY, price per day including fuel | 2 | EA | $0.00 | $0.00 | ||
| 139 | MIS | Dump Truck, 5-7 CY with operator, price per day including fuel | 2 | EA | $0.00 | $0.00 | ||
| 140 | MIS | Contractor's processing and payment of various permits and fees (i.e. applications, regulatory assessments, easements, right of entry, utilities), | ||||||
| per $1000 value | 10 | EA | $0.00 | $0.00 | ||||
| 141 | MIS | EPA 5035 Sample Container or equivalent, per each 8260 analysis | 300 | EA | $0.00 | $0.00 | ||
| 142 | MIS | Excavator delivery | 1 | EA | $0.00 | $0.00 | ||
| 143 | MIS | Excavator, minimum 19,000-lbs up to 25,000-lbs, price per day including fuel | 1 | EA | $0.00 | $0.00 | ||
| 144 | MIS | Excavator, Mini-excavator (3500 lb) delivery | 1 | EA | $0.00 | $0.00 | ||
| 145 | MIS | Excavator, Mini-excavator (3500 lb) price per day including fuel | 1 | EA | $0.00 | $0.00 | ||
| 146 | MIS | Forklift Mobilization/Demobiliztion | 2 | EA | $0.00 | $0.00 | ||
| 147 | MIS | Forklift/Telehandler, 6-8K, multipurpose bucket, per week, includes fuel | 2 | EA | $0.00 | $0.00 | ||
| 148 | MIS | Flame Ionization Detector price per day includes shipping | 35 | EA | $0.00 | $0.00 | ||
| 149 | MIS | Frac Tank mobilization/demobilization | 6 | EA | $0.00 | $0.00 | ||
| 150 | MIS | Frac Tank (single or double walled 8,400 gallon capacity) price per month | 6 | EA | $0.00 | $0.00 | ||
| 151 | MIS | Frac Tank (single walled 20,000 gallon capacity) price per month | 6 | EA | $0.00 | $0.00 | ||
| 152 | MIS | Frac Tank (double walled 20,000 gallon capacity) price per month | 1 | EA | $0.00 | $0.00 | ||
| 153 | MIS | Subcontract Tank Cleaning (Frac Tank) - 1 each | 1 | EA | $0.00 | $0.00 | ||
| 154 | MIS | Generator (4000 watt) price per day including fuel | 20 | EA | $0.00 | $0.00 | ||
| 155 | MIS | HDPE fittings (flanged and welded fittings and valves) - 1 LOT | 1 | EA | $0.00 | $0.00 | ||
| 156 | MIS | HDPE piping (1.5-in to 2-in diameter) per 10 feet | 1 | EA | $0.00 | $0.00 | ||
| 157 | MIS | HDPE piping (4-in to 6-in diameter) per 10 feet | 10 | EA | $0.00 | $0.00 | ||
| 158 | MIS | HDPE piping (double-walled 2-in to 4-in diameter) per 10 feet | 10 | EA | $0.00 | $0.00 | ||
| 159 | MIS | Hydroseeding - per 100 sf (includes all labor and materials using | ||||||
| standard seed mixes) | 8 | EA | $0.00 | $0.00 | ||||
| 160 | MIS | Lawn mower, riding, rental price per day including fuel | 2 | EA | $0.00 | $0.00 | ||
| 161 | MIS | Lawn mower, riding, enclosed, rental price per day including fuel | 2 | EA | $0.00 | $0.00 | ||
| 162 | MIS | Lawn mower, walk-behind, rental price per day including fuel | 5 | EA | $0.00 | $0.00 | ||
| 163 | MIS | Monitoring well skimming sock 1.5"x2', 20 per pack, including | ||||||
| installation materials up to 70 ft | 10 | EA | $0.00 | $0.00 | ||||
| 164 | MIS | Oil/Water interface probe price per day | 35 | EA | $0.00 | $0.00 | ||
| 165 | MIS | Oxygen Analyzer / Explosimeter Combustible Gas Monitor price per day including shipping | 5 | EA | $0.00 | $0.00 | ||
| 166 | MIS | Photoionization Detector price per day including shipping | 35 | EA | $0.00 | $0.00 | ||
| 167 | MIS | Pickup Truck (1/2 ton) price per day including fuel | 430 | EA | $0.00 | $0.00 | ||
| 168 | MIS | PVC Piping, 1" or 2" diameter, price per foot | 1 | EA | $0.00 | $0.00 | ||
| 169 | MIS | PVC Piping, 4" diameter, price per foot | 100 | EA | $0.00 | $0.00 | ||
| 170 | MIS | PVC Piping, 6" diameter, price per foot | 100 | EA | $0.00 | $0.00 | ||
| 171 | MIS | Pressure washer (gas or electric) rental price per day including fuel | 3 | EA | $0.00 | $0.00 | ||
| 172 | MIS | Roll-Off Container with liner and cover, Delivery and monthly rental, 20 | 10 | EA | $0.00 | $0.00 | ||
| 173 | MIS | Rough Terrain/Off-Road Utility Vehicle (e.g. Gator) price per day including fuel | 2 | EA | $0.00 | $0.00 | ||
| 174 | MIS | Silt Fence price per 50 feet (Installed) | 4 | EA | $0.00 | $0.00 | ||
| 175 | MIS | Skid steer mobilization/demobilization | 2 | EA | $0.00 | $0.00 | ||
| 176 | MIS | Skid steer rental price per day including fuel | 5 | EA | $0.00 | $0.00 | ||
| 177 | MIS | Straw Bale, including installation | 20 | EA | $0.00 | $0.00 | ||
| 178 | MIS | Straw Wattle (8.5"x25' or equivalent), includes installation | 4 | EA | $0.00 | $0.00 | ||
| 179 | MIS | Super Silt Fence price per 50 feet, includes installation | 4 | EA | $0.00 | $0.00 | ||
| 180 | MIS | Tedlar Bags price per dozen | 10 | EA | $0.00 | $0.00 | ||
| 181 | MIS | Temporary Berms or Spill Containment (12'x50'), each | 1 | EA | $0.00 | $0.00 | ||
| 182 | MIS | Temporary restroom & sink, delivery, installed, with service price per week | 2 | EA | $0.00 | $0.00 | ||
| 183 | MIS | Traffic control, Traffic control devices (including arrow board and cones) 1 truck including fuel and 1 laborer price per day | 4 | EA | $0.00 | $0.00 | ||
| 184 | MIS | Troll 9500 Water Quality Meter w/200 feet of cable or equivalent, price | ||||||
| per week | 4 | EA | $0.00 | $0.00 | ||||
| 185 | MIS | Utility truck price per day including fuel | 30 | EA | $0.00 | $0.00 | ||
| 186 | MIS | Vacuum truck (70 BBL) with operator price per half day including fuel | 26 | EA | $0.00 | $0.00 | ||
| 187 | MIS | Water level meter price per day | 40 | EA | $0.00 | $0.00 | ||
| 188 | MIS | Water Tank mobilization/demobilization | 4 | EA | $0.00 | $0.00 | ||
| 189 | MIS | Water Tank (single walled 2,500 gallon) price per month | 4 | EA | $0.00 | $0.00 | ||
| 190 | MIS | Water truck with operator price per day including fuel | 24 | EA | $0.00 | $0.00 | ||
| 191 | MIS | Well Caps (2-in and 4-in) | 20 | EA | $0.00 | $0.00 | ||
| 192 | MIS | Dumpster/Bin 3-yd or 4-yd, per month | 12 | EA | $0.00 | $0.00 | ||
| ANALYTICAL TESTING | ||||||||
| 193 | LAB | ASTM D1298 API gravity liquid Petroleum Products | 1 | EA | $0.00 | $0.00 | ||
| 194 | LAB | CA-WET (STLC - extraction only) | 4 | EA | $0.00 | $0.00 | ||
| 195 | LAB | CA-WET (STLC - CCR Metals Title 22 - 6010/7470/7471 only) | 4 | EA | $0.00 | $0.00 | ||
| 196 | LAB | EPA 160.1 (Total Dissolved Solids (TDS)) | 36 | EA | $0.00 | $0.00 | ||
| 197 | LAB | EPA 160.2 (Total Suspended Solids (TSS)) | 36 | EA | $0.00 | $0.00 | ||
| 198 | LAB | EPA 300.0 (Anions including SO4, NO2, NO3, Cl) | 76 | EA | $0.00 | $0.00 | ||
| 199 | LAB | EPA 350.1 (Ammonia as Nitrogen) | 16 | EA | $0.00 | $0.00 | ||
| 200 | LAB | EPA 353.2 (Nitrate-Nitrite Nitrogen) | 16 | EA | $0.00 | $0.00 | ||
| 201 | LAB | EPA 351.4 (TKN) | 12 | EA | $0.00 | $0.00 | ||
| 202 | LAB | EPA 365.3 (Total Phosphorous) | 12 | EA | $0.00 | $0.00 | ||
| 203 | LAB | EPA 376.2 (Sulfide, Dissolved) | 12 | EA | $0.00 | $0.00 | ||
| 204 | LAB | EPA 410.4 (COD) | 12 | EA | $0.00 | $0.00 | ||
| 205 | LAB | EPA 6010/7470/7471 (CCR Metals Title 22 - 6010/7470/7471) | 6 | EA | $0.00 | $0.00 | ||
| 206 | LAB | EPA 6010 (Individual Metal 6010) | 46 | EA | $0.00 | $0.00 | ||
| 207 | LAB | EPA 1010 (Ignitability) | 12 | EA | $0.00 | $0.00 | ||
| 208 | LAB | EPA 1311 (TCLP - extraction only) | 4 | EA | $0.00 | $0.00 | ||
| 209 | LAB | EPA 1311 (TCLP - Full Toxicity Characterization) | 4 | EA | $0.00 | $0.00 | ||
| 210 | LAB | EPA 1311/6010B/C/7471A (TCLP Metals) | 14 | EA | $0.00 | $0.00 | ||
| 211 | LAB | EPA 1311/8270C/D (TCLP SVOCs) | 4 | EA | $0.00 | $0.00 | ||
| 212 | LAB | EPA 1311/ZHE/8260B/C (TCLP VOCs) | 4 | EA | $0.00 | $0.00 | ||
| 213 | LAB | Draft EPA 1633 (PFAS in Water) | 400 | EA | $0.00 | $0.00 | ||
| 214 | LAB | Draft EPA 1633 (PFAS in Soil) | 400 | EA | $0.00 | $0.00 | ||
| 215 | LAB | EPA 1664 (N-Hexane Extractable Material) | 12 | EA | $0.00 | $0.00 | ||
| 216 | LAB | EPA 1668A (PCB) | 6 | EA | $0.00 | $0.00 | ||
| 217 | LAB | EPA 7196A/7199 (Hexavalent Chromium) | 12 | EA | $0.00 | $0.00 | ||
| 218 | LAB | EPA 7470 / 7471 (Mercury) | 12 | EA | $0.00 | $0.00 | ||
| 219 | LAB | EPA 8015B/C (Extractables) | 260 | EA | $0.00 | $0.00 | ||
| 220 | LAB | EPA 8015B/C (Purgeables) | 260 | EA | $0.00 | $0.00 | ||
| 221 | LAB | EPA 8015B/C (Extractables) with silica gel cleanup | 250 | EA | $0.00 | $0.00 | ||
| 222 | LAB | EPA 8015B/C Carbon Chain Speciation, purgeables plus extractables, C4-C44 | 510 | EA | $0.00 | $0.00 | ||
| 223 | LAB | EPA 8081/A (Organochlorine Pesticides (OCP)) | 4 | EA | $0.00 | $0.00 | ||
| 224 | LAB | EPA 8151A (Chlorinated Herbicides ) | 4 | EA | $0.00 | $0.00 | ||
| 225 | LAB | EPA 8260B/5035 (VOCs 8260B/5035 +Oxygenates +TPHG) | 510 | EA | $0.00 | $0.00 | ||
| 226 | LAB | EPA 8260B/C (VOCs (BTEX/MTBE/Naphthalene only)) | 125 | EA | $0.00 | $0.00 | ||
| 227 | LAB | EPA 8260B/C (Full list) | 12 | EA | $0.00 | $0.00 | ||
| 228 | LAB | EPA 8260M BTEX and oxygenates in air | 48 | EA | $0.00 | $0.00 | ||
| 229 | LAB | EPA 8270C/D (SVOCs) | 12 | EA | $0.00 | $0.00 | ||
| 230 | LAB | EPA 8270C/D SIM (PAH-SIM) | 22 | EA | $0.00 | $0.00 | ||
| 231 | LAB | EPA 9023 (Total Extractable Organic Halides (EOX)) | 24 | EA | $0.00 | $0.00 | ||
| 232 | LAB | EPA 9045 (pH) | 24 | EA | $0.00 | $0.00 | ||
| 233 | LAB | EPA 9014 (Cyanide in water) | 30 | EA | $0.00 | $0.00 | ||
| 234 | LAB | Oil Viscosity per ASTM D7152 - 11(2016) | 2 | EA | $0.00 | $0.00 | ||
| 235 | LAB | SM5210 (BOD) | 24 | EA | $0.00 | $0.00 | ||
| 236 | LAB | SM5310 B/C/D (TOC ) | 24 | EA | $0.00 | $0.00 | ||
| 237 | LAB | SM5520B/G (Oil and Grease) | 24 | EA | $0.00 | $0.00 | ||
| 238 | LAB | SM5540 (Surfactant) | 24 | EA | $0.00 | $0.00 | ||
| 239 | LAB | EPA 5.10, Alkalinity in water as CaCO3 | 48 | EA | $0.00 | $0.00 | ||
| 240 | LAB | EPA SW-846/Method 9035: Sulfate (SO42-), aqueous | 48 | EA | $0.00 | $0.00 | ||
| 241 | LAB | EPA 236.1: Dissolved ferrous iron, Fe 2+, 3+, aqueous | 48 | EA | $0.00 | $0.00 | ||
| 242 | LAB | EPA 15: Hydrogen sulfide (H2S), aqueous | 48 | EA | $0.00 | $0.00 | ||
| 243 | LAB | ASTM D-2216/ EPA Method 8000C: Soil moisture | 48 | EA | $0.00 | $0.00 | ||
| 244 | LAB | TO-15 (VOCs) in Air, soil gas source, including summa can rental | 48 | EA | $0.00 | $0.00 | ||
| 245 | LAB | TO-15 (VOCs) in Air, soil gas source, including Tedlar bag | 24 | EA | $0.00 | $0.00 | ||
| 246 | LAB | TO-17 (VOCs) in Air, soil gas, with sorbent tubes | 12 | EA | $0.00 | $0.00 | ||
| 247 | LAB | TO-3 (VOCs) in Air, soil gas source, including summa can rental | 24 | EA | $0.00 | $0.00 | ||
| 248 | LAB | TO-3 (VOCs) in Air, soil gas source, including Tedlar bag | 12 | EA | $0.00 | $0.00 | ||
| 0007 | Utilities (electricity, natural gas, water, sewer) | $250,000.00 | ||||||
| Decimal multiplier applied to unit price for Reference Items 193-248 for 24 hour expedited turn around time | ||||||||
| Decimal multiplier applied to unit price for Reference Items 193-248 for 72 hour expedited turn around time | ||||||||
| Decimal multiplier applied to unit price for Reference Items 193-248 for 5 day expedited turn around time | ||||||||
| Yearly Estimated Price | $250,000.00 | |||||||
| Base Period Price | $1,000,000.00 | |||||||
| Option Period Price | $125,000.00 | |||||||
| Total Evaluated Price | $1,125,000.00 | |||||||
| Instructions to Complete Form: Offeror must fill out all cells shaded in green. Other cells are locked for editing. Offeror must identify all assumptions and exceptions in Section I of Technical Management Proposal. | ||||||||
| Also, pricing for equipment is inclusive of an operator for an 8-hour shift, only when the Reference Item includes “operator” in the description. Otherwise the pricing provided is for the specified piece of equipment; the operator price will be billed using the applicable reference item. | ||||||||
| NOTES | ||||||||
| SVC | Services | |||||||
| DRL | Drilling and Well Installation | |||||||
| REP | Reporting | |||||||
| MIS | Miscellaneous | |||||||
| LAB | Laboratory Services |