Questions and Ans.pdf
PDF 52 KB Posted
- Attached to
- DSCR Building 59 C Bay Break Room Renovation
- Solicitation number
- SP470325Q0025
- Issued by
-
Defense Logistics Agency
About this file
This is a Questions and Answers document for solicitation SP470325Q0025 regarding the DSCR Building 59 C Bay Break Room Renovation project. The document contains 11 contractor questions with government responses covering specifications and requirements for cabinet installation, construction details, and facility access.
Key clarifications include: all cabinets (both upper and lower) are to be replaced with commercial grade soft-close cabinets totaling 8LF plus 6' of additional base cabinets; work hours are 7:00am-5:00pm Monday-Friday; plastic dust barriers are required; ceiling vents/diffusers should match existing white ones; cabinet style should follow the "representative" photos but exact matching is not required; two electrical outlets on the north wall need to be raised above base cabinet height; contractor parking and dumpster location will be determined at pre-construction meeting; and ZEP High Traffic Floor Polish 4-step system or equivalent should be used for floor finishing. The SOW was updated to include relocating a refrigerator receptacle that may be affected by the new cabinet installation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW_V3 B59C Breakroom Statment of Work_V3.pdf | ||
| Site Visit Photos.pdf | ||
| Site Visit Attendance.pdf | ||
| SOW V2 B59C Breakroom.pdf | ||
| SF30 SP470325Q00250001.pdf | ||
| SP470325Q0025.pdf | ||
| Wage Determination.pdf | ||
| Tab 1 - SOW - B59C Break Room.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Confirm cabinet pull type/spec, as SOW states “match existing spec”, but no current cabinet pulls exist. Amerock Hardware cabinet pulls are made in the USA. This statement has been removed from the SOW.
2. Please confirm whether you desire both upper & lower cabinets to be replaced.
Cannot guarantee a match between the two & mention during site visit was that the uppers were not being replaced. Refer to the SOW which states” Remove and replace all cabinets with commercial grade cabinets with soft close hinges and soft close drawer glides. Replace the current LF of cabinets with 8LF of cabinets. Photos of a representative cabinet type in other areas on DSCR are shown at the end of this document. Provide color, finish samples for selection. Provide the same amount of draws and doors as existing.
Provide 6’ of additional base cabinets and countertop (match countertop no backsplash) on the wall where the microwaves are currently located”.
3. Regarding the north wall microwave base cabinet: Please confirm spec. Is it desired for the new cabinet to have a matching cabinet/countertop? See question 2
4. If the cabinets you desire are 8’, this may exposed/overlap the refrigerator receptacle. Can you please add an amended provision for relocating the receptacle over 12” O/C? SOW updated to include relocating current outlet.
5. Please confirm hours available to in facility. Refer to the SOW which states - Normal hours for contractor work on DSCR can range from 7:00am to 5:00pm Monday through Friday excluding holidays or base closures. Each project may have different work hours. The contractor shall request what hours they would like to work from the PM for approval.
6. Please confirm if a temporary dust wall is needed during remodel. Refer to the SOW which states - Hang plastic to cover the opening to the breakroom.
7. Please provide a specification to the new vents and diffusers. Plastic? Metal? Refer to the SOW which states - Replace ceiling vents and diffusers, match existing, white.
8. On page 46-47 of the solicitation, photos of cabinets that are not of the proposed area of work are included. Is this a spec you desire? If so, these are custom cabinets & will have to be built to match by our in-house millwork shop. The SOW references the photos on pages 46-47 as “representative cabinet type” desired by the customer. They don’t have to match the photos exactly.
9. Scope of work states “Raise the outlets on the north wall so they are above the base cabinet”. Please confirm that this is in reference to the west-wall base cabinets, or if this is in addition to another base cabinet elsewhere. The North wall is the wall where the credenza type cabinet is currently located. There are two outlets approximately 12” AFF behind this credenza. These are the two that need to be raised.
10. Please confirm parking/storage arrangements for the duration of the project. Are we utilizing a specific number of parking spaces, west of the parking lot buildings, for
(1) trailer, two vans & a supervisor’s truck, or will parking be elsewhere? Parking, dumpster etc. will be in the same location shown on page 45. The exact spots will be determined at the precon.
11. Please confirm what wax is utilized by the janitorial contractor, as the scope of work states to use the same. ZEP High Traffic Floor Polish, 4-step system, or equal.