This document is a Request for Information (RFI) related to a federal contract opportunity for CSC-24502 Electrical Equipment Maintenance at the Defense Supply Center Columbus (DSCC).
The key details are:
The objective is to provide inspecting, testing, monitoring, analyzing, and maintenance of substations, exterior electrical distribution systems, interior electrical systems, and emergency/standby power systems to maintain safe electrical equipment.
The RFI contains questions and responses regarding the Performance Work Statement (PWS) requirements, including scheduling of service interruptions, maintenance documentation and records, meeting requirements, and references to applicable standards.
The federal agency involved is the Defense Logistics Agency.
The solicitation number is SP4702-24-R-0008.
View the file
Other files for this federal contract opportunity
Other files attached to CSC-24502 Electrical Equipment Maintenance, newest first.
The file's text, extracted by GovTribe without its formatting.
CSC-24502 GOV RFI List 08-16-2024
Document Name
Page #
Paragraph, Section # or Context
Question/Comment
Response
CSC-24502 PWS
6
3.10 Post Award Conference/Periodic Meetings
What is the schedule for periodic meetings?
A single monthly meeting date/time will be determined with the contractor at the kick-off meeting. This monthly meeting will include all other periodically scheduled meetings noted in the contract unless specifically noted otherwise. Meetings to address urgent specific issues can be coordinated as required.
CSC-24502 PWS
7
3.13 Interruption of Utilities
Should multiple interruptions in the same building/area (multiple individual pieces of equipment need de-energized, some of which may be “upstream” or “downstream” of other equipment that will also need to be de-energized) be scheduled congruently, consecutively, or independently; regarding frequency of facility/occupant disruptions.
To the greatest extent possible, all items listed in the maintenance contract that require de-energizing should be performed concurrently, if possible, to minimize downtime to the facility. Items which cannot meet these scheduling requirements must be specifically noted and supporting documentation provided to the government to approve. All the above information should be detailed in the Authorized Service Interruption request noted in Section 3.13.1
CSC-24502 PWS
7
3.13.1 Scheduling for Interruption, Paragraph 1: (30) days prior to date
Calendar days or working days?
Calendar days
CSC-24502 PWS
7
3.13.1 Scheduling for Interruption, Item d): Hours, date and estimated length of time of interruption
Clarify hours/estimated length must consist of a start and completion time (for coordination with affected site) as this seems to be indicated as a requirement in the 2nd paragraph of 4.3 Task Area 3 – Testing and Preventive Maintenance (out/on time)
Section 3.13.1 Scheduling for Interruption Item d) shall include a specific start/stop time as part of the estimated length of time of interruption
CSC-24502 PWS
7
3.13.1 Scheduling for Interruption, General Question:
Must the Authorized Service Interruption be validated on the scheduled date prior to commencing?
Yes. Contact the COR to confirm there are no last-minute issues.
CSC-24502 PWS
9
4.1 Task Area 1 – Project Management, Paragraph 2: The contractor shall verify deliverables for each task, on a monthly status report….
Is there a specific monthly due by date?
A single monthly meeting date/time will be determined with the contractor at the kick-off meeting. This monthly meeting will include all other periodically scheduled meetings noted in the contract unless specifically noted otherwise. All deliverables currently available at the date of each monthly meeting will be submitted at said meeting. Meetings to address urgent specific issues can be coordinated as required.
CSC-24502 PWS
9
4.2 Task Area 2 – Electrical Site Assessment: …purpose of the assessment is to create an accurate equipment inventory and to determine the condition of electrical equipment…
(1) What are the parameters of the inventory [items fitting description of PWS equipment scope (i.e., equipment/circuits rated for 20 Amps and above and also listed under one of the maintenance interval categories noted in Section 4.3.3.1 Maintenance Interval Table 5.3.1.2), items fitting one of the NFPA 70B maintenance interval categories but not listed in PWS, ALL electrical items discovered including low voltage (define low voltage), or another parameter.
(1) Inventory and document equipment condition that falls into the product categories listed in Table 5.3.1.2 of the PWS. If any equipment found poses an imminent risk of injury to personnel shall be brought to the Government’s attention immediately.
CSC-24502 PWS
11
4.3.2.1 Minimum Records Reporting Requirements: Records shall contain…
(1) Should records be submitted as individual documents per specific equipment/individual maintenance requirements (monthly, quarterly, and such.), as a grouping of all maintenance per specific equipment for the period, as a single document for all maintenance performed for all equipment during the period, or is there another desired method? (2) Should this match the submitted maintenance schedule? In essence, how should the “work orders”/records for each unique maintenance activity be grouped and when should these records be submitted?
(1) Records be submitted as individual documents per specific equipment/individual maintenance event (e.g., XFMR-1 monthly PM, quarterly PM, or corrective maintenance #1) (2) Yes
CSC-24502 PWS
11
4.3.2.1 Minimum Records Reporting Requirements, Item f): Indication of test/maintenance performed
What are the specific requirements: listing of each action/step performed as part of the maintenance action (a task list), semi-generic statement such as insulation testing, generic statement such as annul PM performed?
Listing of each action/step performed as part of the maintenance action (a task list), source & frequency of task list, and results of testing or maintenance action.
CSC-24502 PWS
15
4.3.4 Emergency Power Supply Systems, Paragraph 1:
Is it the intent this section also covers NFPA 70 Chapter 7 categories of transfer switches/generator combinations as follows: emergency systems (Chapter 700), legally required systems (Chapter 701), critical operations power systems (Chapter 708), and optional standby systems (Chapter 702), with maintenance provided per the appropriate requirements for each category; basically all categories of generators, not just generators as defined in NFPA 70 Chapter 700 emergency and Chapter 702 standby?
Yes
CSC-24502 PWS
28
8.4 Lock Out/Tag Out:
Page 10 Paragraph 4 of 4.3 Task Area 3 – Testing and Preventive Maintenance states government electricians will energize/de-energize equipment for the contractor. Will government electricians also apply LOTO to the equipment at the same time as the contractor, in accordance with the contractor’s LOTO procedure?
No
CSC-24502 PWS
29
9.1 Documentation and Records:
(1) When should documentation and records that do not have a specified submittal period be submitted to the government? (2) Should this be done as part of the Monthly Status Report noted in 9.1 Monthly Status Reports, at the monthly meeting required by 9.3 Meeting Notes, prior to performance of work (if applicable), or some other defined point/time?
(1) & (2) At the first scheduled monthly meeting after the documents and records become available unless otherwise agreed upon by the government
CSC-24502 PWS
29
9.3 Meeting Notes:
What is the submittal process for meeting notes corrections?
Submission of correction request to COR within 2 business days of meeting, and approval of correction by government
CSC-24502 PWS
35
Appendix C, 2.3.1 Progress Meetings, Paragraph 1:
Will/can these meetings be combined with the required monthly meeting noted in 9.3 Meeting Notes?
Yes
CSC-24502 PWS
General Question
There are multiple references throughout of performing maintenance per more than one standard/authority, such as page 15 4.3.4 Emergency Power Supply Systems, items a-d. Should the maintenance schedule and all related documents default to the most restrictive requirement if there are conflicts in the documents, and should the specific maintenance event source be noted on all documentation?
Where more than one standard is available provide a recommendation and coordinate with the Government which standard shall prevail.