SECTION 01 11 00 Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL
REQUIREMENTS SECTION 01 11 00
SUMMARY OF WORK
08/08/ 2019
PART 1 GENERAL
1.1 SUBMITTALS
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Location
1.3 CONTRACT DRAWINGS
1.4 WORK RESCHEDULING
1.5 OCCUPANCY OF PREMISES
1.6 EXISTING WORK
1.7 ON-SITE PERMITS
1.7.1 Utility Outage Requests and Utility Connection Requests
1.7.2 Borrow, Excavation, Welding, and Burning Permits
1.8 LOCATION OF UNDERGROUND UTILITIES
1.8.1 Notification Prior to Excavation
1.9 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
1.9.1 Delivery Schedule
1.9.2 Delivery Location
1.10 GOVERNMENT-INSTALLED WORK
1.11 NAVY AND MARINE CORPS (NMCI) COORDINATION REQUIREMENTS
1.11.1 NMCI Contractor Access
1.12 SALVAGE MATERIAL AND
EQUIPMENT PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF
WORK
08/15
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01
33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals G
Utility Outage Requests Utility
Connection Requests Borrow Permits
Excavation Permits
Welding Permits
Burning Permits
Salvage Plan;
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The contractor shall furnish all plant, labor, equipment, materials, supplies and supervision required in performing all operations to perform the following maintenance and repair work to complete this project:
CLIN No. 1:
• Replacement of loading dock ceiling by EIFS Systems;
• Replacement of fire suppression systems over loading dock at POD C;
• Replacement of ceiling lighting over loading dock area at POD C by new
LED lighting systems;
SECTION 01 11 00 Page 3
CLIN No. 2:
• Renovation to Nurse Station to provide extra exam room for patient care
(Install new Walls, new door, new window & new horizontal sliding window, modify HVAC Ducts, Fire Suppression Sprinkler System, Alarms & Lighting, etc.);
• CLIN No. 3:
• Replacement of sanitary sewer lines within kitchen floor and exterior concrete patio at the south side of the building 20.
• CLIN No. 4:
• Replacement of low level walkway lighting in the front and rear of the building 20;
• CLIN No. 5:
• Installation of new dock enclosure over dock floor and high speed coiling service doors over the dock levelers;
CLIN No. 6:
• Repair Window Leaks by Caulking & Sealant for Selected Windows;
• CLIN No. 7:
• Repair Storm Drain Pipes on Decks in Pods A, B & C;
• CLIN No. 8:
• Replacement of Rubber Tiles by Slip-Resistant Floor Coatings in Rooms
C130, C123 & C133.
• CLIN No. 9:
• Replacement of paver tiles by installation of concrete Walkways at
North side of Building 20
The contractor shall perform all operations in conjunction with this project in strict accordance with
SECTION 01 11 00 Page 4 specifications & drawings # 3-1692, sheets 1 through 16.
1.2.2 Location
The work is located in Building 20, “OPERATIONS CENTER” at the DSCC Complex, Columbus, Ohio. The approximate location is shown on the drawings.
1.3 CONTRACT DRAWINGS
The following drawings accompany this specification and are a part thereof.
Drawing No. 3-1692
Sheets 1 through 16.
Electronic set of contract drawings, maps, and specifications will be furnished to the Contractor without charge. Reference publications will not be furnished. Immediately check furnished drawings and notify the Government of any discrepancies.
1.4 WORK RESCHEDULING
Normal duty hours for work are from 7:00 A.M. to 4:00 P.M., Monday through Friday. Requests for additional work requires written approval from the Contracting Officer 7 days in advance of the proposed work period.
1.5 OCCUPANCY OF PREMISES
NOT USED
1.6 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.7 ON-SITE PERMITS
SECTION 01 11 00 Page 5
1.7.1 Borrow, Excavation, Welding, and Burning Permits
1.8 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities. Verify existing utility locations indicated on contract drawings, within area of work.
1.8.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.9 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
NONE
1.10 GOVERNMENT-INSTALLED WORK
NONE.
1.11 NAVY AND MARINE CORPS (NMCI) COORDINATION REQUIREMENTS
1.12 SALVAGE MATERIAL AND EQUIPMENT
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --