The file's text, extracted by GovTribe without its formatting.
bid forms
| BID FORM (FOUO) | | | | | |
| PROJECT | CSC-19719 | SHEET | 1 | OF | 9 |
| Project Title: M & R TO BUILDING 20 FY19 | | DATE PREPARED | | | |
| LOCATION | CLIN-0001 | | ESTIMATOR | | |
| Building and/or Description: BUILDING 20 M & R ITEM-Repair Loading Dock Ceiling & Fire Suppression Systems in Pod C | | | CHECKED BY | | |
| NARRATIVE / DATA SOURCE | [EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request. | | | | |
| BID ITEM | | | | SUB CONTRACT COST | PRIME CONTRACT COST | TOTAL DIRECT COST |
| No. / Div. | Description | QTY. | Unit | | | |
| 1 | General Requirements | 1 | LS | | | |
| 2 | Existing Conditions | 1 | LS | | | |
| 3 | Concrete | 1 | LS | | | |
| 4 | Masonry | 1 | LS | | | |
| 5 | Metals | 1 | LS | | | |
| 6 | Wood, Plastics, and Composites | 1 | LS | | | |
| 7 | Thermal and Moisture Protection | 1 | LS | | | |
| 8 | Openings | 1 | LS | | | |
| 9 | Finishes | 1 | LS | | | |
| 10 | Specialties | 1 | LS | | | |
| 11 | Equipment | 1 | LS | | | |
| 12 | Furnishings | 1 | LS | | | |
| 13 | Special Construction | 1 | LS | | | |
| 14 | Conveying Equipment | 1 | LS | | | |
| 21 | Fire Suppression | 1 | LS | | | |
| 22 | Plumbing | 1 | LS | | | |
| 23 | Heating, Ventilating, and Air Conditioning | 1 | LS | | | |
| 26 | Electrical | 1 | LS | | | |
| 27 | Communications | 1 | LS | | | |
| 28 | Electronic Safety and Security | 1 | LS | | | |
| 31 | Earthwork | 1 | LS | | | |
| 32 | Exterior Improvements | 1 | LS | | | |
| 33 | Utilities | 1 | LS | | | |
| 34 | Transportation | 1 | LS | | | |
| SUB-TOTAL COST | | | | | | |
| OVERHEAD | | | | | | |
| PROFIT | | | | | | |
| BOND | | | | | | |
| TOTAL COST | | | | | | |
| BID FORM (FOUO) | | | | | |
| PROJECT | CSC-19719 | SHEET | 2 | OF | 9 |
| Project Title: M & R TO BUILDING 20 FY19 | | DATE PREPARED | | | |
| LOCATION | CLIN-0002 | | ESTIMATOR | | |
| Building and/or Description: BUILDING 20 M & R ITEM-Renovation to Nurse Station | | | CHECKED BY | | |
| NARRATIVE / DATA SOURCE | [EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request. | | | | |
| BID ITEM | | | | SUB CONTRACT COST | PRIME CONTRACT COST | TOTAL DIRECT COST |
| No. / Div. | Description | QTY. | Unit | | | |
| 1 | General Requirements | 1 | LS | | | |
| 2 | Existing Conditions | 1 | LS | | | |
| 3 | Concrete | 1 | LS | | | |
| 4 | Masonry | 1 | LS | | | |
| 5 | Metals | 1 | LS | | | |
| 6 | Wood, Plastics, and Composites | 1 | LS | | | |
| 7 | Thermal and Moisture Protection | 1 | LS | | | |
| 8 | Openings | 1 | LS | | | |
| 9 | Finishes | 1 | LS | | | |
| 10 | Specialties | 1 | LS | | | |
| 11 | Equipment | 1 | LS | | | |
| 12 | Furnishings | 1 | LS | | | |
| 13 | Special Construction | 1 | LS | | | |
| 14 | Conveying Equipment | 1 | LS | | | |
| 21 | Fire Suppression | 1 | LS | | | |
| 22 | Plumbing | 1 | LS | | | |
| 23 | Heating, Ventilating, and Air Conditioning | 1 | LS | | | |
| 26 | Electrical | 1 | LS | | | |
| 27 | Communications | 1 | LS | | | |
| 28 | Electronic Safety and Security | 1 | LS | | | |
| 31 | Earthwork | 1 | LS | | | |
| 32 | Exterior Improvements | 1 | LS | | | |
| 33 | Utilities | 1 | LS | | | |
| 34 | Transportation | 1 | LS | | | |
| SUB-TOTAL COST | | | | | | |
| OVERHEAD | | | | | | |
| PROFIT | | | | | | |
| BOND | | | | | | |
| TOTAL COST | | | | | | |
| BID FORM (FOUO) | | | | | |
| PROJECT | CSC-19719 | SHEET | 3 | OF | 9 |
| Project Title: M & R TO BUILDING 20 FY19 | | DATE PREPARED | | | |
| LOCATION | CLIN-0003 | | ESTIMATOR | | |
| Building and/or Description: BUILDING 20 M & R ITEM-Repair to Sanitary Lines within Kitchen Floor & Exterior Concrete Patio. | | | CHECKED BY | | |
| NARRATIVE / DATA SOURCE | [EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request. | | | | |
| BID ITEM | | | | SUB CONTRACT COST | PRIME CONTRACT COST | TOTAL DIRECT COST |
| No. / Div. | Description | QTY. | Unit | | | |
| 1 | General Requirements | 1 | LS | | | |
| 2 | Existing Conditions | 1 | LS | | | |
| 3 | Concrete | 1 | LS | | | |
| 4 | Masonry | 1 | LS | | | |
| 5 | Metals | 1 | LS | | | |
| 6 | Wood, Plastics, and Composites | 1 | LS | | | |
| 7 | Thermal and Moisture Protection | 1 | LS | | | |
| 8 | Openings | 1 | LS | | | |
| 9 | Finishes | 1 | LS | | | |
| 10 | Specialties | 1 | LS | | | |
| 11 | Equipment | 1 | LS | | | |
| 12 | Furnishings | 1 | LS | | | |
| 13 | Special Construction | 1 | LS | | | |
| 14 | Conveying Equipment | 1 | LS | | | |
| 21 | Fire Suppression | 1 | LS | | | |
| 22 | Plumbing | 1 | LS | | | |
| 23 | Heating, Ventilating, and Air Conditioning | 1 | LS | | | |
| 26 | Electrical | 1 | LS | | | |
| 27 | Communications | 1 | LS | | | |
| 28 | Electronic Safety and Security | 1 | LS | | | |
| 31 | Earthwork | 1 | LS | | | |
| 32 | Exterior Improvements | 1 | LS | | | |
| 33 | Utilities | 1 | LS | | | |
| 34 | Transportation | 1 | LS | | | |
| SUB-TOTAL COST | | | | | | |
| OVERHEAD | | | | | | |
| PROFIT | | | | | | |
| BOND | | | | | | |
| TOTAL COST | | | | | | |
| BID FORM (FOUO) | | | | | |
| PROJECT | CSC-19719 | SHEET | 4 | OF | 9 |
| Project Title: M & R TO BUILDING 20 FY19 | | DATE PREPARED | | | |
| LOCATION | CLIN-0004 | | ESTIMATOR | | |
| Building and/or Description: BUILDING 20 M & R ITEM-Repair to Low Level Walkway Lighting Systems | | | CHECKED BY | | |
| NARRATIVE / DATA SOURCE | [EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request. | | | | |
| BID ITEM | | | | SUB CONTRACT COST | PRIME CONTRACT COST | TOTAL DIRECT COST |
| No. / Div. | Description | QTY. | Unit | | | |
| 1 | General Requirements | 1 | LS | | | |
| 2 | Existing Conditions | 1 | LS | | | |
| 3 | Concrete | 1 | LS | | | |
| 4 | Masonry | 1 | LS | | | |
| 5 | Metals | 1 | LS | | | |
| 6 | Wood, Plastics, and Composites | 1 | LS | | | |
| 7 | Thermal and Moisture Protection | 1 | LS | | | |
| 8 | Openings | 1 | LS | | | |
| 9 | Finishes | 1 | LS | | | |
| 10 | Specialties | 1 | LS | | | |
| 11 | Equipment | 1 | LS | | | |
| 12 | Furnishings | 1 | LS | | | |
| 13 | Special Construction | 1 | LS | | | |
| 14 | Conveying Equipment | 1 | LS | | | |
| 21 | Fire Suppression | 1 | LS | | | |
| 22 | Plumbing | 1 | LS | | | |
| 23 | Heating, Ventilating, and Air Conditioning | 1 | LS | | | |
| 26 | Electrical | 1 | LS | | | |
| 27 | Communications | 1 | LS | | | |
| 28 | Electronic Safety and Security | 1 | LS | | | |
| 31 | Earthwork | 1 | LS | | | |
| 32 | Exterior Improvements | 1 | LS | | | |
| 33 | Utilities | 1 | LS | | | |
| 34 | Transportation | 1 | LS | | | |
| SUB-TOTAL COST | | | | | | |
| OVERHEAD | | | | | | |
| PROFIT | | | | | | |
| BOND | | | | | | |
| TOTAL COST | | | | | | |
| BID FORM (FOUO) | | | | | |
| PROJECT | CSC-19719 | SHEET | 5 | OF | 9 |
| Project Title: M & R TO BUILDING 20 FY19 | | DATE PREPARED | | | |
| LOCATION | CLIN-0005 | | ESTIMATOR | | |
| Building and/or Description: BUILDING 20 M & R ITEM-Repair to Loading Dock Enclosure Systems | | | CHECKED BY | | |
| NARRATIVE / DATA SOURCE | [EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request. | | | | |
| BID ITEM | | | | SUB CONTRACT COST | PRIME CONTRACT COST | TOTAL DIRECT COST |
| No. / Div. | Description | QTY. | Unit | | | |
| 1 | General Requirements | 1 | LS | | | |
| 2 | Existing Conditions | 1 | LS | | | |
| 3 | Concrete | 1 | LS | | | |
| 4 | Masonry | 1 | LS | | | |
| 5 | Metals | 1 | LS | | | |
| 6 | Wood, Plastics, and Composites | 1 | LS | | | |
| 7 | Thermal and Moisture Protection | 1 | LS | | | |
| 8 | Openings | 1 | LS | | | |
| 9 | Finishes | 1 | LS | | | |
| 10 | Specialties | 1 | LS | | | |
| 11 | Equipment | 1 | LS | | | |
| 12 | Furnishings | 1 | LS | | | |
| 13 | Special Construction | 1 | LS | | | |
| 14 | Conveying Equipment | 1 | LS | | | |
| 21 | Fire Suppression | 1 | LS | | | |
| 22 | Plumbing | 1 | LS | | | |
| 23 | Heating, Ventilating, and Air Conditioning | 1 | LS | | | |
| 26 | Electrical | 1 | LS | | | |
| 27 | Communications | 1 | LS | | | |
| 28 | Electronic Safety and Security | 1 | LS | | | |
| 31 | Earthwork | 1 | LS | | | |
| 32 | Exterior Improvements | 1 | LS | | | |
| 33 | Utilities | 1 | LS | | | |
| 34 | Transportation | 1 | LS | | | |
| SUB-TOTAL COST | | | | | | |
| OVERHEAD | | | | | | |
| PROFIT | | | | | | |
| BOND | | | | | | |
| TOTAL COST | | | | | | |
| BID FORM (FOUO) | | | | | |
| PROJECT | CSC-19719 | SHEET | 6 | OF | 9 |
| Project Title: M & R TO BUILDING 20 FY19 | | DATE PREPARED | | | |
| LOCATION | CLIN-0006 | | ESTIMATOR | | |
| Building and/or Description: BUILDING 20 M & R ITEM-Repair Window Leaks at Selected Locations | | | CHECKED BY | | |
| NARRATIVE / DATA SOURCE | [EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request. | | | | |
| BID ITEM | | | | SUB CONTRACT COST | PRIME CONTRACT COST | TOTAL DIRECT COST |
| No. / Div. | Description | QTY. | Unit | | | |
| 1 | General Requirements | 1 | LS | | | |
| 2 | Existing Conditions | 1 | LS | | | |
| 3 | Concrete | 1 | LS | | | |
| 4 | Masonry | 1 | LS | | | |
| 5 | Metals | 1 | LS | | | |
| 6 | Wood, Plastics, and Composites | 1 | LS | | | |
| 7 | Thermal and Moisture Protection | 1 | LS | | | |
| 8 | Openings | 1 | LS | | | |
| 9 | Finishes | 1 | LS | | | |
| 10 | Specialties | 1 | LS | | | |
| 11 | Equipment | 1 | LS | | | |
| 12 | Furnishings | 1 | LS | | | |
| 13 | Special Construction | 1 | LS | | | |
| 14 | Conveying Equipment | 1 | LS | | | |
| 21 | Fire Suppression | 1 | LS | | | |
| 22 | Plumbing | 1 | LS | | | |
| 23 | Heating, Ventilating, and Air Conditioning | 1 | LS | | | |
| 26 | Electrical | 1 | LS | | | |
| 27 | Communications | 1 | LS | | | |
| 28 | Electronic Safety and Security | 1 | LS | | | |
| 31 | Earthwork | 1 | LS | | | |
| 32 | Exterior Improvements | 1 | LS | | | |
| 33 | Utilities | 1 | LS | | | |
| 34 | Transportation | 1 | LS | | | |
| SUB-TOTAL COST | | | | | | |
| OVERHEAD | | | | | | |
| PROFIT | | | | | | |
| BOND | | | | | | |
| TOTAL COST | | | | | | |
| BID FORM (FOUO) | | | | | |
| PROJECT | CSC-19719 | SHEET | 7 | OF | 9 |
| Project Title: M & R TO BUILDING 20 FY19 | | DATE PREPARED | | | |
| LOCATION | CLIN-0007 | | ESTIMATOR | | |
| Building and/or Description: BUILDING 20 M & R ITEM-Repair to Storm Drain Pipes on Decks in PODS A & C | | | CHECKED BY | | |
| NARRATIVE / DATA SOURCE | [EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request. | | | | |
| BID ITEM | | | | SUB CONTRACT COST | PRIME CONTRACT COST | TOTAL DIRECT COST |
| No. / Div. | Description | QTY. | Unit | | | |
| 1 | General Requirements | 1 | LS | | | |
| 2 | Existing Conditions | 1 | LS | | | |
| 3 | Concrete | 1 | LS | | | |
| 4 | Masonry | 1 | LS | | | |
| 5 | Metals | 1 | LS | | | |
| 6 | Wood, Plastics, and Composites | 1 | LS | | | |
| 7 | Thermal and Moisture Protection | 1 | LS | | | |
| 8 | Openings | 1 | LS | | | |
| 9 | Finishes | 1 | LS | | | |
| 10 | Specialties | 1 | LS | | | |
| 11 | Equipment | 1 | LS | | | |
| 12 | Furnishings | 1 | LS | | | |
| 13 | Special Construction | 1 | LS | | | |
| 14 | Conveying Equipment | 1 | LS | | | |
| 21 | Fire Suppression | 1 | LS | | | |
| 22 | Plumbing | 1 | LS | | | |
| 23 | Heating, Ventilating, and Air Conditioning | 1 | LS | | | |
| 26 | Electrical | 1 | LS | | | |
| 27 | Communications | 1 | LS | | | |
| 28 | Electronic Safety and Security | 1 | LS | | | |
| 31 | Earthwork | 1 | LS | | | |
| 32 | Exterior Improvements | 1 | LS | | | |
| 33 | Utilities | 1 | LS | | | |
| 34 | Transportation | 1 | LS | | | |
| SUB-TOTAL COST | | | | | | |
| OVERHEAD | | | | | | |
| PROFIT | | | | | | |
| BOND | | | | | | |
| TOTAL COST | | | | | | |
| BID FORM (FOUO) | | | | | |
| PROJECT | CSC-19719 | SHEET | 8 | OF | 9 |
| Project Title: M & R TO BUILDING 20 FY19 | | DATE PREPARED | | | |
| LOCATION | CLIN-0008 | | ESTIMATOR | | |
| Building and/or Description: BUILDING 20 M & R ITEM-Repair to Floors of the Kitchen Rooms | | | CHECKED BY | | |
| NARRATIVE / DATA SOURCE | [EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request. | | | | |
| BID ITEM | | | | SUB CONTRACT COST | PRIME CONTRACT COST | TOTAL DIRECT COST |
| No. / Div. | Description | QTY. | Unit | | | |
| 1 | General Requirements | 1 | LS | | | |
| 2 | Existing Conditions | 1 | LS | | | |
| 3 | Concrete | 1 | LS | | | |
| 4 | Masonry | 1 | LS | | | |
| 5 | Metals | 1 | LS | | | |
| 6 | Wood, Plastics, and Composites | 1 | LS | | | |
| 7 | Thermal and Moisture Protection | 1 | LS | | | |
| 8 | Openings | 1 | LS | | | |
| 9 | Finishes | 1 | LS | | | |
| 10 | Specialties | 1 | LS | | | |
| 11 | Equipment | 1 | LS | | | |
| 12 | Furnishings | 1 | LS | | | |
| 13 | Special Construction | 1 | LS | | | |
| 14 | Conveying Equipment | 1 | LS | | | |
| 21 | Fire Suppression | 1 | LS | | | |
| 22 | Plumbing | 1 | LS | | | |
| 23 | Heating, Ventilating, and Air Conditioning | 1 | LS | | | |
| 26 | Electrical | 1 | LS | | | |
| 27 | Communications | 1 | LS | | | |
| 28 | Electronic Safety and Security | 1 | LS | | | |
| 31 | Earthwork | 1 | LS | | | |
| 32 | Exterior Improvements | 1 | LS | | | |
| 33 | Utilities | 1 | LS | | | |
| 34 | Transportation | 1 | LS | | | |
| SUB-TOTAL COST | | | | | | |
| OVERHEAD | | | | | | |
| PROFIT | | | | | | |
| BOND | | | | | | |
| TOTAL COST | | | | | | |
| BID FORM (FOUO) | | | | | |
| PROJECT | CSC-19719 | SHEET | 9 | OF | 9 |
| Project Title: M & R TO BUILDING 20 FY19 | | DATE PREPARED | | | |
| LOCATION | CLIN-0009 | | ESTIMATOR | | |
| Building and/or Description: BUILDING 20 M & R ITEM-Repair toPAVERS by Concrete Walkways | | | CHECKED BY | | |
| NARRATIVE / DATA SOURCE | [EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request. | | | | |
| BID ITEM | | | | SUB CONTRACT COST | PRIME CONTRACT COST | TOTAL DIRECT COST |
| No. / Div. | Description | QTY. | Unit | | | |
| 1 | General Requirements | 1 | LS | | | |
| 2 | Existing Conditions | 1 | LS | | | |
| 3 | Concrete | 1 | LS | | | |
| 4 | Masonry | 1 | LS | | | |
| 5 | Metals | 1 | LS | | | |
| 6 | Wood, Plastics, and Composites | 1 | LS | | | |
| 7 | Thermal and Moisture Protection | 1 | LS | | | |
| 8 | Openings | 1 | LS | | | |
| 9 | Finishes | 1 | LS | | | |
| 10 | Specialties | 1 | LS | | | |
| 11 | Equipment | 1 | LS | | | |
| 12 | Furnishings | 1 | LS | | | |
| 13 | Special Construction | 1 | LS | | | |
| 14 | Conveying Equipment | 1 | LS | | | |
| 21 | Fire Suppression | 1 | LS | | | |
| 22 | Plumbing | 1 | LS | | | |
| 23 | Heating, Ventilating, and Air Conditioning | 1 | LS | | | |
| 26 | Electrical | 1 | LS | | | |
| 27 | Communications | 1 | LS | | | |
| 28 | Electronic Safety and Security | 1 | LS | | | |
| 31 | Earthwork | 1 | LS | | | |
| 32 | Exterior Improvements | 1 | LS | | | |
| 33 | Utilities | 1 | LS | | | |
| 34 | Transportation | 1 | LS | | | |
| SUB-TOTAL COST | | | | | | |
| OVERHEAD | | | | | | |
| PROFIT | | | | | | |
| BOND | | | | | | |
| TOTAL COST | | | | | | |
| BID FORM (FOUO) | | | | | |
| PROJECT | CSC-19719 | SHEET | 1 | OF | 1 |
| Project Title: M & R TO BUILDING 20 FY19 | | DATE PREPARED | | | |
| LOCATION | COST SUMMARY | | ESTIMATOR | | |
| Building and/or Description: BUILDING 20 M & R ITEMS | | | CHECKED BY | | |
| NARRATIVE / DATA SOURCE | [EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request. | | | | |
| BID ITEM | | | | SUB CONTRACT COST | PRIME CONTRACT COST | TOTAL COST INCL. OH, PROFIT & BOND COSTS |
| CLIN NO | Description | QTY. | Unit | | | |
| 1 | Repair Loading Dock Ceiling & Fire Suppression Systems in Pod C | 1 | LS | | | |
| 2 | Renovation to Nurse Station | 1 | LS | | | |
| 3 | Repair to Sanitary Lines under Kitchen Floor | 1 | LS | | | |
| 4 | Repair to Low Level Walkway Lighting Systems | 1 | LS | | | |
| 5 | Repair to Loading Dock Enclosure Systems | 1 | LS | | | |
| 6 | Repair Window Leaks at Selected Locations | 1 | LS | | | |
| 7 | Repair to Storm Drain Pipes on Decks in PODS A & C | 1 | LS | | | |
| 8 | Repair to Floors of the Kitchen Rooms | 1 | LS | | | |
| 9 | Repair toPAVERS by Concrete Walkways | 1 | LS | | | |
SUB-TOTAL COST
TOTAL COST FOR THIS PROJECT
&"Arial,Bold"Defense Logistics Agency Confidential &KFF0000FOR OFFICIAL USE ONLY Page &P