Sheet1
| CONSTRUCTION COST ESTIMATE | ||||||||||
| PROJECT NO. | CSC-18761 | DRAWING NO. | 3-1684 (13 Sheets) | DATE: | ||||||
| PROJECT TITLE: | Repair and Seal Floors, Buildings 9 & 30 | |||||||||
| ARCHITECT/ENGINEER: | M. Rustam Ali | ESTIMATOR: | ||||||||
| PRELIMINARY DESIGN | FINAL DESIGN | X | OTHER | |||||||
| Work to be performed by General Contractor. | ||||||||||
| CLIN 001- BUILDING 9 BID FORMS | ||||||||||
| ITEM | QUANTITY | MATERIAL | LABOR | EQUIP COST | TOTAL DIRECT COST | |||||
| NO. OF UNITS | UNIT OF MEASURE | PER UNIT | TOTAL | UNIT MANHOUR | TOTAL MANHOURS | RATE PER HOUR | TOTAL | |||
| DIVISION 01-General Requirements | ||||||||||
| Project Management | ||||||||||
| Project Manager | JOB | |||||||||
| Technical Submittals & Documentation Preparation | JOB | |||||||||
| Quality Contol Testing & Inspecting Services on site | JOB | |||||||||
| Temporary Environmental Control & Waste Management on site | JOB | |||||||||
| Mobilization & Demobilization Costs | JOB | |||||||||
| Total Direct Cost | ||||||||||
| DIVISION 02-Existing Conditions | ||||||||||
| Removal of expansion joint materials from floor joints in Sections 5-13 | LF | |||||||||
| Total Direct Cost | ||||||||||
| DIVISION 03-Concrete | ||||||||||
| Concrete Rehabilitation: | ||||||||||
| Seal cracks sizes 1/4" x 1/2" and higher by using Eco-PJS ( semi-rigid two-component polyurea ) joint filler material for concrete floors @ the rate of 150 LF/ GAL in Sections 5-13. | LF | |||||||||
| Concrete Patching & Leveling Work- Grinding, cleaning and patching with epoxy grout, 1/4" thick on entire floor | SF | |||||||||
| Total Direct Cost | ||||||||||
| DIVISION 07-Thermal & Moisture Protection | ||||||||||
| Replacement of existing epoxy mortar with semirigid epoxy sealant expansion joint by using Eco-EJF Eco-PJS semi-rigid two-component polyurea joint filler to construct expansion joints in Sections 5-13 | LF | |||||||||
| Total Direct Cost | ||||||||||
| DIVISION 09-Finishes | ||||||||||
| High-Performance Coatings | ||||||||||
| Concrete Floor Surface Preparation- Clean dirt, oil, grease & previously coated epoxy system by grinding with grinder includes hauling & disposal off DSCC in Sections 5-13. | S.F. | |||||||||
| Coating Maretial Preparation- Mix & prepare coating materials for primer, seed coating with silica sand, grout coating & top coatings incl. Materials and labor only. | JOB | |||||||||
| Application of 9 mils prime coating Materials on cleaned prepared concrete floors @ the rate of 180 SF/GAL. | S.F. | |||||||||
| Application of 15 mils seed coating with silica sand over prime coated floors @ the rate of 107 SF/GAL. | S.F. | |||||||||
| Application of 15 mils grout coating with silica sand over seed coated floors @the rate of 107 SF/GAL. | S.F. | |||||||||
| Application of 3 mils Satin Urethane top coating Materials over new seal coating floors @ the rate of 500 SF/ GAL. | S.F. | |||||||||
| Total Direct Cost | 0 | 0 | ||||||||
| SUB-TOTAL OF DIRECT COSTS | ||||||||||
| ADDED OVERHEAD | ||||||||||
| ADDED PROFIT | ||||||||||
| ADDED BOND COSTS | ||||||||||
| TOTAL ESTIMATED PROJECT COST FOR BUILDING 9 | ||||||||||
| CONSTRUCTION COST ESTIMATE | ||||||||||
| PROJECT NO. | CSC-18761 | DRAWING NO. | 3-1684 (13 Sheets) | DATE: | ||||||
| PROJECT TITLE: | Repair and Seal Floors, Buildings 9 & 30 | |||||||||
| ARCHITECT/ENGINEER: | M. Rustam Ali | ESTIMATOR: | ||||||||
| PRELIMINARY DESIGN | FINAL DESIGN | X | OTHER | |||||||
| Work to be performed by General Contractor. | ||||||||||
| CLIN 002- BUILDING 30 BID FORMS | ||||||||||
| ITEM | QUANTITY | MATERIAL | LABOR | EQUIP COST | TOTAL DIRECT COST | |||||
| NO. OF UNITS | UNIT OF MEASURE | PER UNIT | TOTAL | UNIT MANHOUR | TOTAL MANHOURS | RATE PER HOUR | TOTAL | |||
| DIVISION 01-General Requirements | ||||||||||
| Project Management | ||||||||||
| Project Manager | JOB | |||||||||
| Technical Submittals & Documentation Preparation | JOB | |||||||||
| Quality Contol Testing & Inspecting Services on site | JOB | |||||||||
| Temporary Environmental Control & Waste Management on site | JOB | |||||||||
| Mobilization & Demobilization Costs | JOB | |||||||||
| Total Direct Cost | ||||||||||
| DIVISION 02-Existing Conditions | ||||||||||
| Removal of expansion joint materials from floor joints in Sections 5-13 | LF | |||||||||
| Total Direct Cost | ||||||||||
| DIVISION 03-Concrete | ||||||||||
| Concrete Rehabilitation: | ||||||||||
| Seal cracks sizes 1/4" x 1/2" and higher by using Eco-PJS ( semi-rigid two-component polyurea ) joint filler material for concrete floors @ the rate of 150 LF/ GAL in Sections 5-13. | LF | |||||||||
| Concrete Patching & Leveling Work- Grinding, cleaning and patching with epoxy grout, 1/4" thick at patching locations | SF | |||||||||
| Total Direct Cost | ||||||||||
| DIVISION 07-Thermal & Moisture Protection | ||||||||||
| Replacement of existing epoxy mortar with semirigid epoxy sealant expansion joint by using Eco-EJF Eco-PJS semi-rigid two-component polyurea joint filler to construct expansion joints in Sections 5-13 | LF | |||||||||
| Total Direct Cost | ||||||||||
| DIVISION 09-Finishes | ||||||||||
| High-Performance Coatings | ||||||||||
| Concrete Floor Surface Preparation- Clean dirt, oil, grease & previously coated epoxy system by grinding with grinder includes hauling & disposal off DSCC. | S.F. | |||||||||
| Coating Maretial Preparation- Mix & prepare coating materials for primer, 1/4" power-trowel epoxy overlay resurfacer & top coatings incl. materials and labor only. | JOB | |||||||||
| Application of 9 mils prime coating Materials on cleaned prepared concrete floors @ the rate of 180 SF/GAL. | S.F. | |||||||||
| Application of 1/4" Power-Trowel Epoxy Overlay Resurfacer over prime coated floors. | S.F. | |||||||||
| Application of 8 mils seal coating Materials over new 1/4" epoxy resurfacer floors @ the rate of 200 SF/GAL. | S.F. | |||||||||
| Application of 3 mils Satin Urethane top coating Materials over new seal coating floors @ the rate of 500 SF/ GAL. | S.F. | |||||||||
| Total Direct Cost | ||||||||||
| SUB-TOTAL OF DIRECT COSTS | ||||||||||
| ADDED OVERHEAD | ||||||||||
| ADDED PROFIT | ||||||||||
| ADDED BOND COSTS | ||||||||||
| TOTAL ESTIMATED PROJECT COST FOR BUILDING 30 | ||||||||||
| CONSTRUCTION COST ESTIMATE | ||||||||||
| PROJECT NO. | CSC-18761 | DRAWING NO. | 3-1684 (13 Sheets) | DATE: | ||||||
| PROJECT TITLE: | Repair and Seal Floors, Buildings 9 & 30 | |||||||||
| ARCHITECT/ENGINEER: | M. Rustam Ali | ESTIMATOR: | ||||||||
| PRELIMINARY DESIGN | FINAL DESIGN | X | OTHER | |||||||
| Work to be performed by General Contractor. | ||||||||||
| SUMMARY SHEET | ||||||||||
| ITEM | QUANTITY | MATERIAL | LABOR | EQUIP COST | TOTAL COST | |||||
| NO. OF UNITS | UNIT OF MEASURE | PER UNIT | TOTAL | UNIT MANHOUR | TOTAL MANHOURS | RATE PER HOUR | TOTAL | |||
| CLIN # 001-TOTAL COST FOR BUILDING 9 | ||||||||||
| CLIN # 002-TOTAL COST FOR BUILDING 30 | ||||||||||
| TOTAL ESTIMATED PROJECT COST |