SF30_SP470217R00320001.pdf

PDF 34 KB Posted

Attached to
CSC-16749 & CSC-16778, Repair Heating Systems BLDG 9 & 17
Solicitation number
SP4702-17-R-0032
Issued by

About this file

Amendment #1 - SP4702-17-R-0032

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO.

See Block 14

4. REQUISITION/PURCHASE REQ. NO.

CSC-16749 & CSC-16778

5. PROJECT NO. (If applicable)

6. ISSUED BY CODE SP4702 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE FACILITY CODE

SP470217R0032

X

2017 SEP 08

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of OffersX is extended, X is not extended.

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

12. ACCOUNTING AND APPROPRIATION DATA (If required)

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A NAME AND TITLE OF SIGNER (Type or print)

NSN 7540-01-152-8070

Previous edition unusable

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

16B. UNITED STATES OF AMERICA15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

(a) By completing Items 8 and 15, and returning

DCSO COLUMBUS

ATTN DCSO-C

PO BOX 3990

COLUMBUS OH 43218-3990

15C. DATE SIGNED 16C. DATE SIGNED

D. OTHER (Specify type of modification and authority)

9/8/2017

3. EFFECTIVE DATE

See Attached Continuation Sheet(s).

(X)

CHECK ONE

PAGE OF PAGES

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

Amendment #1 is being posted to update the following information with respect to Solicitation

SP4702-17-R-0032:

1. The sign-in sheet from the site visit held on 8/30/2017 is being posted. It is attached to this amendment.

2. The drawings for project CSC-16749, sheets 9 & 10, BLDG 17 have been updated. The updates make changes to the electrical panels referenced in the drawings.

3. Project CSC-16778, sheets 11 - 14, BLDG 9, have not yet been updated. These drawings also need updated to change the electrical panels referenced in the drawings. The same changes that were made to the drawings for BLDG 17 will be made to the drawings for BLDG 9. However, due to time constraints and issues with making updates to these drawings, vendors are asked to submit proposals for this project as-is.

4. Vendor questions submitted in response to this solicitation are being answered. Below are the questions that were received and the answers to those questions:

Question 1:

Will all conduit have to be PVC coated rigid conduit? The existing conduit doesn’t appear to be, but the specs referenced on 26 05 00, Part 2, list multiple types of conduit. I just need to know what they want. I don’t see a reason, based on the scope of work, for more than EMT with compression couplings and connectors.

Answer 1:

Disregard the PVC coated rigid conduit. EMT with compression couplings and connectors is acceptable.

Question 2:

You call for the domestic water lines to be re-insulated but there is no sizes shown on the drawings. Can you please provide Domestic Water line sizes?

Answer 2:

The attached PDF titled “BLDG 9 – water line sizes” provides the details for the Domestic Water Line sizes.

There are no further changes made by way of amendment #1 to this solicitation.

PAGE 2 OF 2 PAGESCONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED:

SP470217R0032-0001

File details come from the government source that posted it. Updated .