Attachment 25 TE 4.5.1 Task List VLM PM Schedule.pdf

PDF 204 KB Posted

Attached to
Warehousing and Distribution Services at DLA Distribution San Diego, CA
Solicitation number
SP330025R5002
Issued by

About this file

This Technical Exhibit 4.5 details the Vertical Lift Machine (VLM) Preventative Maintenance (PM) Program Schedule for Modula Inc. The maintenance program is structured across four levels with specific mission-based intervals for routine inspections and parts replacement. Level 1 PM is an annual maintenance performed by certified technicians, which must occur at least once per year and no later than 15,000 missions, involving routine inspections, calibration, lubrication, and adjustment to ensure proper machine operation and longevity.

The maintenance program includes progressive parts replacement at increasing mission milestones: Level 2 PM occurs every 30,000 missions and involves replacing sprockets, chains, pawls, guides, and door parts; Level 3 PM occurs every 45,000 missions and replaces wheel-tubes and external bay slides; and Level 4 PM occurs every 150,000 missions, replacing critical components such as vertical belts, pulleys, E-chain, cradle movement cables, motors, and gear motors. The document emphasizes a comprehensive maintenance kit replacement strategy designed to maximize machine performance and extended operational life.

View the file

Other files

File Type Posted
Attachment 11.pdf PDF
Attachment 7 Subcontracting Plan Template 10.1.2025.docx DOCX document
Attachment 2 Supplemental_PWS_10_29_25.docx DOCX document
Amendment 0004.pdf PDF
SF1449 Solicitation Pages.pdf PDF
Attachment 27 TE 5.0 APLs.xlsx XLSX spreadsheet
SP3300-25-R-5002 DDDC 10_29_2025 updated.docx DOCX document
Attachment 1 Performance Work Statement 10_14_25.docx DOCX document
Attachment 20 TE 3.5.1 VLM Equipment Listing.xlsx XLSX spreadsheet
Amendment 0002.pdf PDF
Attachment 35 Past Performance Questionnaire.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Exhibit 4.5 VLM Preventative Maintenance (PM) Program Schedule

PREVENTIVE MAINTENANCE LEVELS

The Scheduled LVL 1 Maintenance recommended by MODULA INC must be performed at least ONE a YEAR and not beyond No. 15,000 Missions.

During the LVL 1 PM the Certified Technicians will perform all routine inspections, calibration, lubrication, and adjustment activities to ensure the proper operation and increase the longevity of the machines.

The Maintenance KIT replacement program is design to ensure to the machine the proper operation during the years and to max its longevity, replacing some consumable parts at certain time.

• PM LVL 2 Every 30,000 missions (Replace Sprocket, Chains, Pawls, Guides, and Door parts if it is present)

PM LVL 3 Every 45,000 missions (Replace Wheel-tubes, and external bay slides if an EB is present) PM LVL 4 Every 150,000 missions (Replace Vertical Belt, Vertical Pulleys, Vertical E-Chain, Cradle Movement Cables, Motors, Gear motors)

Annual LVL 1 PM Maintenance

Level 2,3,4 - PM parts replacement