Amendment_0002_SP330019Q0031.pdf
PDF 1 MB Posted
- Solicitation number
- SP3300-19-Q-0031
- Issued by
-
Defense Logistics Agency Distribution
About this file
Amendment 0002 SP330019Q0031
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0003_SP330019Q0031.pdf | ||
| Amendment_0003_Attachment_3_-_Schedule.xlsx | XLSX spreadsheet | |
| Amendment_0003_Attachment_1_-_SOW.pdf | ||
| Amendment_0003_Attachment_2b_-_Drawings_AutoCAD.dwg | DWG drawing | |
| Amendment_0003_Attachment_2a_-_Drawings.pdf | ||
| Amendment_0002_Attachment_1_-_SOW.pdf | ||
| Amendment_0001.pdf | ||
| Attachment_4-_Subcontracting_Plan_Template.pdf | ||
| SP3300-19-Q-0031.docx | DOCX document | |
| Attachment_1_-_Statement_of_Work.pdf | ||
| Attachment_2b_-_Drawings_AutoCAD.dwg | DWG drawing | |
| Attachment_5_-_SBPP.pdf | ||
| Attachment_3_-_Schedule.xlsx | XLSX spreadsheet | |
| Attachment_2a_-_Drawings.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
SP3300-19-Q-0031
Amendment 0002
Pg. 2 of 2 The purpose of this Amendment is as follows:
1. Answer contractor’s questions regarding the Statement of Work (SOW).
2. Replace Attachment 1 – Statement of Work with revised Amendment 0002 Attachment 1
– SOW.
Contractor Submitted Question Government Response
1. Will the sheet metal be on pallets? 1. No, they will be stored in trays. The trays will accommodate up to 4 ins. high of material. Refer to SOW paragraph 3.2.1.
2. How much weight will be on one pallet load (maximum)?
2. Up to 5,000 lbs. per cassette. Refer to SOW paragraph 3.2.2.
3. What is the overhead clear height? 3. 17 ft.
4. How much clearance do you need for each beam level? 6” is standard to add for lift out height so whatever your load height is plus 6”.
4. 2 ins., but there are steel angle supports, not beams.
5. Regarding Fill Height. If you fill a cassette with 5’x12’ steel sheets, the maximum load capacity is reached with a 2” stack. If you are filling with Aluminum then the nominal 4” stack height is OK. But if you try and load with steel sheet over 2” the cassette will be overloaded.
5. Concur.
6. In the SOW, the fill height is given at 2” in places (SOW 3.2.1) and 4” in other places (SOW 1., 3.2.1, 3.4). Can you confirm if we should use 2” or 4”?
6. 2”