SP0604-21-R-0402 Amendment 2- Q&A 8 March 2021
1. If an Offeror previously had customers complete and send Past Performance Questionnaires
(PPQ) to csTeam@dla.mil, as a part of our original submission, are we required to do so again for
Amendment 2, or do the previous PPQs stand?
DLA Response: Previous PPQs are acceptable. Vendors are not required to resubmit PPQs submitted in previous packages.
2. In our Proposal, should we renumber Task 6 – Program and Contract Management given the original Task 5 - Direct Customer Support has been deleted?
DLA Response: Task numbers will not be renumbered.
3. Is Amendment 1 Exhibit A- Rough Order of Magnitude still applicable to the solicitation PWS as amended in Amendment 2?
DLA Response: Exhibit A- Rough Order of Magnitude remains applicable.
4. Will all companies submitting a proposal receive notice of DLA’s decision whether we are awarded or not?
DLA Response: DLA will send out a general notice to all offerors regarding the award decision
5. Do we need to have past performance forms resubmitted by former clients if we are not changing the list?
DLA Response: Please reference Q&A #1.
6. Why was this solicitation put out to bid again – were there no acceptable bids from the first period?
DLA Response: Please reference Amendment_00002.pdf, Attachment 1 - PWS Amend 2.pdf, and
SP060421R0402 Amend 2 Americas Conformed_RFP.pdf. The Government descoped part of the requirement.
7. Based on the June 1 start date, when does DLA forecast an award will be made by?
DLA Response: The Government’s best effort will be to award before 05/15/21.