(SOW) ZFW ARTCC Renovate Gurd House.pdf
PDF 19 MB Posted
- Solicitation number
- 6973GH-25-R-00186
About this file
This is a Statement of Work (SOW) for renovating the guard house and replacing the HVAC system at the Fort Worth Air Route Traffic Control Center (ZFW ARTCC). The project requires the contractor to remove and replace three aluminum-framed glass entry doors with all associated hardware, demolish and repaint the bottom three feet of interior walls, replace the sink and toilet, install a new water filter, add ice/snow guards to the roof, and completely replace the existing R-22 HVAC system with a new 4-ton split unit heat pump/compressor.
Specific requirements include draining and disposing of existing R-22 refrigerant, installing a new Carrier Infinity heat pump model or equivalent, replacing multiple ceiling supply and return grills, and performing all electrical work associated with the HVAC replacement. The contractor must coordinate with FAA personnel, maintain facility operations during construction, and provide a closeout package with operations and maintenance manuals. The work will be performed at 13800 FAA Blvd, Fort Worth, TX 76155, with the facility remaining operational 24/7 throughout the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI RESPONSES 7.24.25.docx | DOCX document | |
| 6973GH-25-R-00186 0002.pdf | ||
| 6973GH-25-R-00186 0001.pdf | ||
| Organizational Experience Questionnaire.pdf | ||
| WD_TX20250033.pdf | ||
| 6973GH-25-R-00186 (14).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
November 26, 2024
ZFW RENOVATE GUARD HOUSE & REPLACE HVAC
JCN 24003233
STATEMENT OF WORK
ZFW RENOVATE GUARD HOUSE & REPLACE HVAC
ZFW ARTCC
November 26, 2024
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL AVIATION ADMINISTRATION
TABLE OF CONTENTS
SECTION 1A – GENERAL REQUIREMENTS
SECTION 1B – SPECIAL REQUIREMENTS
SECTION 1C – HIGH LEVEL SCOPE OF WORK
JCN 24003233
SECTION 1A – GENERAL REQUIREMENTS
1A.1 Summary of Work.
The Contractor is required to furnish all labor, materials, services, equipment, tools, and insurance to remove and replace glass entry doors (including all hardware), sand/repaint all interior walls, sink and water closet (toilet), furnish and install new under sink 3-stage water filter, furnish and install new ice/snow guard for standing seam metal roof, drain and dispose of existing R-22 refrigerant from existing HVAC system, demolish/remove and replace existing R-22 HVAC system with new HVAC system (new 4-ton split unit heat pump/compressor) and associated piping/electrical, remove and replace ceiling air return grills, provide temporary portable air conditioner and heater with associated temporary materials to provide adequate cooling and heating to comfortable temperatures, provide closeout package including O&M manuals/warrantee information at the Fort Worth Air Route Traffic Control Center (ZFW ARTCC) located at 13800 FAA Blvd, Fort Worth, TX 76155. This will include providing a means of offloading new materials and equipment as well as removing and disposing of old materials/equipment out of site. The contractor will provide a means of protecting all nearby equipment from debris, refrigerant spills, etc… and perform thorough cleanup of the entire area daily. Contractor will coordinate with local technicians to have existing HVAC system offline and locked-out/tagged-out prior to the start of the project. Portable air conditioner and heater shall be installed prior to removing the HVAC system offline. All quantities of materials given in these specifications shall be verified by contractor.
A contractor site walk-through is recommended preceding bid proposal preparation.
Advise that the ARTCC will remain operational 24/7 during all project work. The work performed will not impact AT operations as construction activity will be coordinated via a pre-construction meeting, either in person or virtual, which is to be conducted a minimum of two weeks prior to the scheduled start of construction. At the time of the pre-construction meeting a complete work schedule is to be submitted.
1A.2 Background.
The ZFW Guard House was installed in 2004 and has had no substantial improvements or renovations since its construction. It is a small space that is continuously manned with a security crew 24/7/365 days a year.
Continuous use and the high traffic nature of the building as the single point of access/egress to the facility has resulted in worn, malfunctioning doors and damaged interior walls. Additionally, the guard house roof is not equipped with snow/ice guards to prevent the dangerous movement of frozen precipitation which can be hazardous to the guard house personnel as well as entering traffic. Finally, the split unit HVAC has exceeded its end of life cycle and needs to be replaced.
1A.3 Action Plan.
This project will provide for the renovation of the ZFW Guard House and HVAC replacement with associated piping to extend the facilities’ life longevity.
END OF SECTION 1A
JCN 24003233
SECTION 1B – SPECIAL REQUIREMENTS
1B.1 Coordination.
1. All contracts between the contractor and ZFW ARTCC shall be coordinated through the FAA’s designated Contracting Officer (CO).
2. Contractor shall be always escorted by ZFW ARTCC designated FAA Contracting Officer
Representative (COR) or Point of Contact (POC) and/or Technicians.
3. Immediately on discovery of the need for additional information or interpretation of the contract documents, contractor shall prepare and submit an RFI (Request For Information) in the form specified to the designated FAA COR/POC and/or Technicians.
4. Air Traffic Control Safety: Contractor shall perform all work in a manner which does not conflict with, or adversely affect, the air traffic operational environment. In the event of any actual or potential conflicts, air traffic activities shall have priority over all construction activities.
5. All work must be accomplished by experienced workers in accordance with the highest standards of the various work trades involved. Workers must abide by safety requirements, set forth by OSHA, that correspond to the type of work being performed.
6. Restroom facilities are not available on site. Temporary facilities shall be provided by the contractor as required to meet the needs of the workers.
1B.2 Pre-Construction Conference.
As soon as practical after the award of the contract, the Contracting Officer will set a date for a preconstruction conference between the representatives of the Government (applicable ZFW managers and personnel will be invited to attend) and the contractor. This conference will be either virtual or at a location agreed upon by the CO and the contractor. The contractor shall attend the conference and shall abide by all agreements reached at the conference regarding:
• Detailed procedures for administration of the project.
• Identity of the ZFW COR/POC and/or Technicians, authorized representatives of the
Government/Contracting Officer, and the contractor’s superintendent(s).
• Exchange of telephone numbers and email information.
• Detailed procedures for submittals:
o Contractor shall submit list of materials for FAA approval prior to the commencement of construction.
o In making a formal request for substitution, the contractor represents that they have investigated the proposed product and have determined that it is equal to or superior in all respects to that specified.
o Contractor shall submit a construction schedule which shall be approved by FAA prior to construction.
o Material Safety Data Sheet (MSDS): Contractor shall submit MSDS for proposed paints, sealants, solvents, refrigerant, etc.
o Contractor shall allow up to 10 days for submittal review. A resubmittal would require additional time. No extension of the contract time will be authorized because of failure to transmit submittals enough in advance of the work to permit processing, including resubmittals.
o Procurement Before Approval: The contractor is advised not to procure any item for
JCN 24003233
which submittal approval is required but not yet granted. If approval is denied, the contractor will be prevented from installing the disapproved item(s). The contractor must transmit a new submittal package for the new items replacing the disapproved items and must procure only approved items. The contractor shall take responsibility for the delivery and installation of any items installed before submittal approval is granted. The FAA reserves the right to discontinue field work on any item furnished without submittal approval. Procuring and/or installing material which is later disapproved could result in substantial losses of money and time for the contractor.
• Available storage areas for contractor’s materials and equipment.
• Compliance with FAA safety practices, orders, general operating procedures, and security regulations.
• Availability of onsite power for use by the contractor as determined by the FAA COR/POC and/or Technicians.
• The FAA Pre-Construction and Maintenance Project Safety and Health Checklist, form 3900-18, will be reviewed and filled out during the meeting.
• Any additional subjects discussed pertinent to the contract.
1B.3 Product Requirements.
1. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft and vandalism. Comply with manufacturer's written instructions.
2. Delivery and Handling:
a. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces.
b. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.
c. Inspect products on delivery to determine compliance with the Contract Documents and to determine that products are undamaged and properly protected.
3. Storage:
a. Store products to allow for inspection and measurement of quantity or counting of units.
b. Store materials in a manner that will not endanger Project structure.
c. Comply with product manufacturer's written instructions for temperature, humidity, ventilation, and weather-protection requirements for storage.
d. Provide a secure location and enclosure at Project site for storage of materials and equipment by Owner's construction forces. Coordinate location with Owner.
1B.4 Working Hours.
1. All work hours will be dependent on impact to NAS facilities and locations throughout the ARTCC.
2. Work shall be generally performed during normal business working house of 7:00AM to 5:00PM, Monday through Friday, except otherwise indicated.
3. The start and stop time shall typically be coordinated with the schedules of the FAA COR/POC and/or Technicians to minimize or prevent the need for overtime work by FAA personnel.
1B.5 Ingress and Egress to Work Area.
The FAA POC and/or Technicians shall direct all ingress and egress to the work area. Security precautions against unauthorized facility entrance will be maintained. Contractor personnel shall be escorted at all times upon entry through the security gate by FAA COR/POC and/or Technicians.
JCN 24003233
1B.6 Security Requirements.
1. Security Guard: Contractor must use the existing guard house on the north entrance to the facility to check in prior to starting work for the day. The FAA COR/POC and/or Technicians will meet the contractor at the guard house to provide escort into the facility.
2. Personnel List: Contractor must provide the FAA COR/POC with a list of contractor's personnel who will require access to the site within twenty-four (24) hours of arrival to site. The list must be kept current during project duration.
3. Security Investigation and Identification: Contractor's personnel may be subject to security investigation by FAA. Upon request by the CO, the contractor must promptly complete all security forms provided by the CO. If Contractor's personnel do not hold a “yellow” security badge or a contractor PIV card, then they must report to the FAA security guard at entrance to the facility and submit proper identification when signing in to obtain a “red” FAA visitor badge which will be always worn on an outside garment while on the facility premises. This badge must be returned daily to the security guard when leaving the premises, unless otherwise noted.
4. Vehicle Identification: Contractors and contractor's employees' vehicles must park as designated in the staging plans or as directed by the FAA COR/POC.
5. Escort Requirement: Contractor's personnel will always be escorted by FAA POC and/or Technicians during the project. Contractor's personnel shall not violate any security regulations pertaining to the ARTCC facility.
6. Right to Search: Current procedures at FAA facilities include the "right to search." If in the judgment of the FAA a cause to search a vehicle or the person of personnel exists, such search will be made.
7. Prohibited Items:
a. Weapons. ABSOLUTELY NO WEAPONS in any way, shape, or form are allowed on the job site, facility premises, or inside contractor vehicles (company or personally owned).
This includes ammo, ammo casings, empty cartridges, etc... Any weapons found by Security guards, (Refer to No. 6: Right to Search), may be subject to confiscation. Security guards also reserve the right to contact local law enforcement and/or Homeland Security.
Contractor will then be banned for life from any access to the ZFW facility.
b. Other Projectile Weapons. This category includes items such as compressed air guns, flare guns, spear guns, stun guns, realistic replica or toy firearms and other electric weapons, ammunition, and slingshots.
c. Bladed, Edged, or Sharp Tools or Implements. This category includes items such as axes or hatchets, bows and arrows, ice axes, and martial arts weapons. It also includes bladed devices with a blade of 2½ inches or more and all straight razors excluding safety razors.
i. Exception: tools of the trade
d. Club-like Items and Striking Devices. This category includes items such as Billy clubs, night sticks, blackjacks, brass knuckles, and chains in excess of 12 inches (jewelry exceptions can be made).
e. Destructive Devices, Explosives or Combustible Chemical Compounds or Mixtures. This category includes items such as blasting caps, detonators, dynamite, fireworks, gunpowder, hand grenades, plastic explosives, realistic replicas of explosives or other devices, gas torches, and flammable liquids. Disabling Chemicals and Other Dangerous Items. This category includes items such as mace, pepper spray, tear gas or other chemical spray, spillable batteries except those in wheelchairs and similar devices, spray paint, and poisonous gases.
f. Controlled Items. Controlled items are those items that may be otherwise prohibited but are
JCN 24003233
“tools of the trade” and “sporting equipment” that are considered potentially dangerous.
FAA personnel may possess controlled items on federal property. Government-furnished items are authorized within facilities. Personal items are allowed within a facility if the item is necessary to perform a mission or maintenance operation (e.g., saws, screwdrivers) and its need is sanctioned by the FM or designee. Otherwise, personal items must remain in personal vehicles.
i. Bladed, Edged, or Sharp Weapons. This category includes items such as saws (including cordless, portable power saws), metal scissors with pointed tips, screw drivers (except eyeglass repair kits), drills (including portable power drills) and tools including wrenches, pliers, and folding utility tools.
ii. Club-like Items and Striking Devices. This category includes items such as hammers, crowbars, baseball/softball bats, golf clubs, hockey sticks, lacrosse sticks, pool cues, and ski poles.
iii. Destructive Devices, Explosives, or Combustible Chemical Compounds and Mixtures. This category includes items such as flares, gasoline, and aerosol sprays.
iv. Disabling Chemicals and Other Dangerous Items. This category includes items such as chlorine and bleach, compressed gas cylinders (including fire extinguishers), and toxic industrial chemicals or materials.
g. Drugs/ Drug Paraphernalia
h. Alcohol/ Alcohol Container (full or empty)
1B.7 Property Damage.
The contractor shall take all precautions to avoid damage to Government property or equipment (existing and new). Any damage to Government property or equipment by the contractor shall be repaired by the contractor to its original state or better condition at no additional expense to the Government.
1B.8 Parking of Contractor Vehicles.
All personnel will park their vehicles in pre-designated areas and all access doors or as authorized by the FAA COR/POC and/or Technicians. Materials and tools may be off-loaded at the work site by arrangements with the FAA COR/POC and/or Technicians.
1B.9 Storage of Materials.
The contractor shall store all materials in a manner to protect them from all elements of the weather.
Storage of reasonable quantities of material, supplies and tools on site is permissible providing the FAA COR/POC and/or Technicians authorizes the location. The FAA is not responsible for the security of the materials, supplies and tools owned by the contractor.
1B.10 Site Visit.
The contractor shall take steps necessary to ascertain the nature of the work and satisfy themselves to the conditions that can affect the work. The site visit shall include verifying field measurements and conditions. No subsequent extras will be allowed due to any claim of lack of knowledge for conditions that can be determined by examining the site. Errors, inconsistencies, or omissions discovered shall be reported to the contracting officer.
1B.11 Compliance with Local Codes and Other Codes.
The contractor shall comply with local and other codes of standard trade practices adopted by these contract documents. Where the requirements of the specifications exceed those of the local and adapted codes, the
JCN 24003233
contractor shall comply with the requirements of the specifications.
1B.12 Fire Protection.
The contractor shall have an equivalent of two 20 lb. Class A, B and D fire extinguishers in the work area through the progress of the job.
1B.13 Cleaning.
The contractor shall keep the working area in a clean and proper condition. All rubbish and waste resulting from the execution of the work shall be removed at the end of each day. Immediately after unpacking, all packing materials shall be removed from the building and the premises. Upon completion of work and before final inspection, the contractor shall remove his/her working tools, equipment, debris, rubbish, and unused materials from the building site. Disposal of rubbish and debris will be off site and at no additional cost to the FAA or as directed by the FAA COR/POC and/or Technicians.
1B.14 Non-interference with Existing Facility Operations.
The access to the facility shall be always kept unobstructed. If any interference with the existing facility operation or access seems to be unavoidable, the contractor shall advise the contracting officer through the RE/COR and/or Technicians 72 hours before such interference. FAA reserves the right to stop work at any time if the operation of this facility is jeopardized by the contractor’s work. This facility maintains air traffic control without shutdown. Various techniques are employed to achieve maximum system availability. Mechanical and electrical systems in direct support of air traffic operation and environmental systems have redundant configurations. Shutdown of equipment shall be scheduled with the FAA COR/POC and/or Technicians at least 72 hours prior to the control systems installer’s need. The reliability of mechanical and electrical systems is compromised when redundant equipment is not available. Every effort will be made by the FAA to allow work to be accomplished during the installer’s working hours.
FAA personnel shall accomplish equipment shutdown.
1B.15 Other Contracts.
The Government may undertake other contracts for additional work at or near the site of the work under this contract. The contractor shall fully cooperate with other contractors and with the Government employees and shall adapt scheduling and performing the work under this contract to accommodate the other work.
The contractor shall not commit or permit any act that will interfere with performance of work by any other contractor or by Government employees.
1B.16 Contractor’s Liability.
Damage to the existing facility or equipment caused by the contractor shall be immediately reported to the FAA POC and/or Technicians immediately. The contractor shall be responsible for repairing or having repaired all damaged areas of the facility or equipment directly caused by contractor related work. All repairs shall be accomplished, without delay, at the contractor’s expense to the satisfaction of the FAA COR/POC and/or Technicians.
1B.17 Permits.
The contractor shall be responsible for obtaining all state, city, county, etc. permits, if required, to complete the project, at no additional cost to the Government.
1B.18 Material.
All equipment, material, and articles incorporated into the work covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract.
JCN 24003233
References in the specifications to material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The contractor may, at his option, use any equipment, material, article, or process that, in the judgment of the FAA COR/POC and/or Technicians, is equal to that named in the specifications, unless otherwise specifically provided in this contract.
1B.19 Workmanship.
The contract shall be accomplished by workers experienced in each trade in accordance with the highest standards of the various trades involved. The FAA COR/POC and/or Technicians must approve all details to assure the professional and complete project, whether stated in the specifications or not. The COR/POC and/or Technicians may require, in writing, that the contractor will remove from the work site any employee the FAA COR/POC and/or Technicians deems incompetent, careless, or otherwise objectionable.
1B.20 Superintendence by the Contractor.
At all times during the performance of this contract and until the work is completed and accepted, the contractor shall directly superintend the work on site or assign and have on site a competent superintendent who is satisfactory to the FAA COR/POC and/or Technicians and has the authority to act for the contractor.
END OF SECTION 1B
JCN 24003233
SECTION 1C – HIGH LEVEL SCOPE OF WORK
Facility Photos (for reference):
Figure 1A: ARTCC Guard House in existing condition (north view)
Figure 1B: ARTCC Guard House in existing condition (west side view)
JCN 24003233
Figure 1C: ARTCC Guard House in existing condition (south view)
Figure 1D: ARTCC Guard House in existing condition (east side view)
JCN 24003233
Figure 2A: Glass entry door in existing condition (outdoor view, typical)
Figure 2B: Glass entry door in existing condition (inside view, typical)
JCN 24003233
Figure 3A: Extra heavy duty automatic door closer in existing condition (typical)
Figure 3B: Latch and plate in existing condition (typical)
JCN 24003233
Figure 3C: Door latch guard in existing condition (typical)
JCN 24003233
Figure 3D: Door hinges in existing condition (typical)
Figure 3E: Door hinges in existing condition (typical)
JCN 24003233
Fort Worth ARTCC: Renovate Guard House
The Contractor shall provide all labor, materials, and equipment in accordance with the contract provisions and specifications included herein. The work shall include, but is not limited to, the following:
1) Contractor shall remove and replace the QTY(3) existing aluminum framed, glass entry doors and ALL associated hardware that meets ALL FAA security requirements (this includes heavy duty automatic door closer, door hinges, door latches, striker plates, security approved hinges, etc.). Field verify associated hardware for FAA security requirements. Contractor shall match existing or approved equal. Doors are to be replaced one at a time. Dispose of all removed material.
2) Demolish the bottom three feet of the interior walls. Estimated a 200 sq. ft. Dispose of all removed material.
3) Sand and repaint all interior walls, from floor to ceiling, with two coats of zero-VOC latex paint.
4) Demo and replace the existing sink and water closet (toilet). Dispose of all removed material.
Provide and install new base cabinet for under new sink.
5) Furnish and install new under sink, 3-stage water filter. Include 12-month supply of spare filters.
6) Furnish and install new ice/snow guard for standing seam metal roof (Color Snap Snow Guards manufactured by AceClamp or approved equivalent).
7) Protect all equipment in the vicinity from debris and clean-up area at end of each shift.
Facility Photos (for reference):
JCN 24003233
Figure 4A: HVAC outdoor unit in existing condition back of facility
JCN 24003233
Figure 4B: HVAC outdoor unit in existing condition
Figure 4C: Date plate for existing HVAC outdoor unit
JCN 24003233
Figure 5A: HVAC indoor unit in existing condition
Figure 5B: Date plate for existing HVAC indoor unit
JCN 24003233
Figure 6A: HVAC safety switch and conduit in existing condition
Figure 6B: HVAC safety switch in existing condition
JCN 24003233
Figure 6C: HVAC safety switch and associate conductors in existing condition (open)
Figure 6D: Date plate for existing HVAC electrical safety switch
JCN 24003233
Figure 7: Existing panel GH-L (panel that feeds HVAC system)
Figure 7A: Panel schedule for existing panel GH-L (panel that feeds HVAC system)
JCN 24003233
JCN 24003233
Figure 8: HVAC Guard House Floor Plan and Air Device Schedule
Fort Worth ARTCC: Replace Existing HVAC System
The Contractor shall provide all labor, materials, and equipment in accordance with the contract provisions and specifications included herein. The work shall include, but is not limited to, the following:
1) Coordinate with POC and Technicians for the lock-out/tag-out (LOTO) of the HVAC system once the portable air conditioner and heater is installed and connected to the facility. Perform testing of temporary air conditioner and heater to ensure functionality prior to de-energizing HVAC system.
2) Drain and dispose of the R-22 refrigerant (12 lbs) from the existing HVAC system.
3) Demolish and dispose of the existing 4-ton split unit heat pump and compressor.
4) Furnish and install a new 4-ton split unit heat pump and compressor (Carrier Infinity model or approved equivalent) with new industry standard type refrigerant. Furnish and install new associated piping per manufacturer requirements.
5) Replace supply and return grills: CD-1 (QTY: 3), CD-2 (QTY: 1), RG-2 (QTY: 1), RG-3 (QTY: 1), SG-1 (QTY: 2), OG-1 (QTY: 2). Refer to HVAC Guard House Floor Plan and Air Device Schedule on Drawing ZFW-E-FSRM-M101 in Figure 8 for data.
6) Demolish and dispose of existing associated HVAC electrical (safety switch, associated conduit, and conductors from load side).
7) Ensure 0VAC prior to begin electrical demolition. HVAC system is fed out of existing panel GH-L.
Performing work in energized electrical panel, equipment, etc. is not permitted per FAA STD-1217.
8) Furnish and install new safety switch with new 3/4" flexible conduit and new conductors from load side of safety switch going to 4-ton unit per manufacturer requirements. Contractor may re-use existing conductors from the line side of HVAC safety switch.
JCN 24003233
9) Provide closeout package including O&M manuals and warrantee information.
10) Protect all equipment in the vicinity from debris and clean-up area at end of each shift.
END OF SECTION 1C