This Statement of Work (SOW) dated 11 August 2025 details the requirements for installing a smart locker system at the 20th Logistics Readiness Squadron's Deployment Processing Center. The system requires 18-22 lockers constructed of 18-gauge double-reinforced cold-rolled steel, capable of operating in temperatures from -13°F to +122°F, with industrial-grade touchscreens, cameras, keypads, barcode scanners, and smart package sensors. The lockers must accommodate general-purpose mobility bags (24" x 20" x 20") and chemical warfare bags (24" x 15" x 15") within a designated outdoor area measuring approximately 362" x 80" x 24".
The contractor will be responsible for site assessment, locker installation, software integration, and staff/user training. Installation will occur at the specified location with government facility access provided for 8 hours per day. Contractor personnel must comply with base security regulations, including obtaining base passes, submitting to vehicle searches, and adhering to traffic and safety guidelines. The project must be completed within 1 week of beginning on-site work, with final acceptance requiring inspection by the Combat Arms NCOIC to ensure proper system functionality and professional installation.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. DESCRIPTION OF SERVICES. The contractor is responsible with installing the smart locker system at the location specified by the government. The lockers will be assembled and firmly secured to the ground to deter tampering. Before installation, the contractor will conduct a site visit to determine the optimal setup for the area. After installation, the system must be integrated with software that enables users to receive notifications and access their packages effortlessly. Additionally, the contractor will offer training to both staff and users to enhance the advantages of the locker system, ensuring a seamless transition and continued satisfaction.
2. EQUIPMENT. The lockers will have, 18-gauge double-reinforced cold-rolled steel construction, Operational conditions: temperature -13°to +122°F -humidity up to 100%non-condensing, Rain, salt, and wind (category 3 cyclone) resistant, Control towers feature an industrial-grade touchscreen, a camera for photo capture, a keypad, a scanner supporting 1D and 2D barcode reading, and speakers, Camera and touchscreen are optimized for full functionality in bright sun, heat and cold conditions, Kiosk and screen are temperature controlled (air conditioning and heat) for operation in extreme conditions, Standard awnings provide users additional protection from outdoor elements and come with built-in lights, Each door features smart package sensors to detect packages and other items.
2.1. INSTALLATION. Installation of the smart locker system will be at the Deployment Processing Center (Bldg 1518). The government will supply access to facilities for 8 hours per day to conduct installation and training activities. The installation should include the total number of lockers that should be between 18 and 22, depending on the dimensions specified by the vendor, which must fit within a space of approximately W362" x H80" x D24" in the designated outdoor area. This configuration is crucial for storing the general-purpose mobility bag (A bag) and the chemical warfare bags (C bags) that will be accessible in the lockers after hours. The dimensions of the individual bags are as follows: A-bag: 24" x 20" x 20" - C-bag: 24" x 15" x 15". Each locker must be sized to accommodate both bags simultaneously.
3. GENERAL INFORMATION
3.1. Contract Personnel/Manager. The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate or alternates, who shall act for the contractor when the manager is absent, shall be designated in writing to the contracting officer prior to the contract start date. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager and alternate or alternates must be able to read, write, speak, and understand the English language.
3.2. Contractor Employees. Contractor personnel shall comply with all installation and facility safety and security regulations, as well as the health, safety, and security provisions of the contract. Contractor personnel shall report security or safety problems to the Security Police or Contracting Officer (CO) as appropriate.
Statement of Work 11 August 2025
3.3. Place of Performance. Contract performance will occur at the 20th Logistics Readiness Squadron. Delivery and installation of equipment shall be the responsibility of the receiver with coordination of the contractor.
3.4. Hours of Operations. Normal operation is Monday through Friday, 0700 to 1600, except for Federal holidays. There may be mission situations that require the contractor to work other than normal hours. Some of these situations are military exercises, contingency operations, or weather emergencies. When the contractor’s access to a work area conflicts with an Air Force mission requirement, the contractor shall schedule the work to minimize the disruption. Such scheduling may require work to be accomplished at times other than normal duty hours.
3.5. Security Requirements. N/A
3.6. Contractor Base Pass and Identification, Special Clearances, and Vehicle Passes. The contractor shall work with the end user to obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished contractor identification badges while visiting or performing work on the installation. Ten (10) business days prior to arrival, the Contractor will be responsible for obtaining written permission/ signature from each person’s name submitted for a background check to be completed. If a background check cannot be completed, entry onto the installation cannot be granted. Contact the installation site POC for further guidance.
3.7. Contractor-owned Vehicle Searches. Contractor-owned vehicles are subject to 100% security search prior to installation access.
3.8. Traffic Regulations. Contractor personnel shall comply with all base traffic regulations and are subject to random vehicle speed control checks. Contractor personnel cited for speeding on the installation may suffer loss of base driving privileges, debarment from the base, or other administrative action. The use of cell phones, except hands-free phones, is prohibited while driving on Shaw AFB.
3.9. Weapons, Firearms, and Ammunition. Contractor personnel are prohibited from possessing weapons, firearms, or ammunition, on themselves or within contractor-owned vehicles or privately owned vehicles while on Shaw Air Force Base.
3.10. Reporting Requirements. Contractor personnel shall immediately report any information or circumstances of which they are aware may pose a threat to the security of Department of Defense personnel, contractor personnel, resources, and classified or unclassified defense information to an appropriate Government authority.
3.11. Safety. Contractor personnel shall comply with all applicable laws and safety regulations. Compliance with Occupational Safety and Health Administration (OSHA) and other applicable laws and regulations for the protection of employees is exclusively the obligation of the contractor, and the Government will assume no liability or responsibility for the contractor’s compliance or non-compliance with such responsibilities.
3.12. Materials storage and clean up. Upon completion of work the contractor must ensure all debris from the work site has been removed and properly disposed of and the site be sanitized to the level it was given. Prior to the acceptance of the completed project, the contractor must arrange through the Combat Arms NCOIC for the appropriate inspections for the acceptance of work to make sure the system is up and running properly and the equipment is professionally and neatly installed.
3.13. Deliverables. Set-up shall be completed within 1 weeks on beginning work on-site. The contractor shall protect government property on hand to prevent damage during the period the property is under the control or in possession of the contractor.