SOW SectionC_FY25ShenagoFenceInstall_7-22.docx
DOCX document 192 KB Posted
- Solicitation number
- 1240LU25Q0072
- Issued by
-
Department of Agriculture Forest Service
About this file
This Statement of Work (SOW) details a fence installation project for the Custer Gallatin National Forest's Shenango Helibase located in Gallatin Gateway, Montana. The project involves removing existing jack-leg fencing and installing approximately 1,450 linear feet of new chain-link fence with brown vinyl coating, including a 12' double-swing gate, a 20' cantilever slide gate with motor, and electric gate accessories. The government will furnish most fence materials and gate equipment, including a Liftmaster HDSL24UL Heavy-Duty Variable Speed Slide Gate Opener, digital keypad, and associated components.
The contract is valued between $25,000 and $100,000, with work estimated to begin in September 2025 and be completed within 61 calendar days of the Notice to Proceed. Key project requirements include installing fence posts 24" into the ground, connecting electrical power for gate operation, and potentially adding a 3-strand barbed wire extension. The contractor must handle all site cleanup, disposal, and adhere to specific work hours (7:00 am to 7:00 pm on weekdays) and site access restrictions. The project is solicited under Solicitation Number 1240LU25Q0072 by the USDA Forest Service, with a completion deadline of 10/31/2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GateOperator_hdsl24ul_Manual.pdf | ||
| Experience Questionnaire.pdf | ||
| Wage Determinations mt75.pdf | ||
| cp4Manual.pdf | ||
| 1240LU25Q0072 Shenango Helibase fencing.pdf | ||
| Gooseneck_Padmount_Dimensions.pdf | ||
| AK-11_Keypad.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site Plan Fence Install Location (Approximate, see flagging on site) Install Power Slide Gate and Motor Proposed Electrical Supply Trench/Conduit Office Install 12’ Double Swing Gate Helipad
SECTION C - DESCRIPTION AND SPECIFICATIONS
C.1 PROJECT DESCRIPTION AND LOCATION
| C.1.1 | Intent of Contract – The intent of the contract is to provide for the construction and completion of the work described below. The precise details of performing the work are not stipulated, except as considered essential for the successful completion of the work. Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract. |
| C.1.2 | Description of Work – The work shall consist of removing and disposing of an existing jack fencing and save existing gates at the work site; installing Government furnished new chain-link fence, gates and motor to include electric keypad for main gate, located south of Gallatin Gateway, Mt on the Bozeman Ranger District, Shenango Helibase. |
ITEM 1, Mobilization: Work shall consist of preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies, and incidentals to the project site; and for other work and operations that must be performed or costs incurred prior to beginning work on the various items on the project site.
ITEM 2, Demolish and Dispose of Existing Fence: Work shall consist of removing and disposing of the existing wood jack-leg fence and transportation to landfill, including landfill fees.
ITEM 3, Install Security Fence, Gates, and Appurtenances: Work shall consist of installing posts, gates, rails, braces, fabric, caps, ties, and all accessories to ensure for a complete project along with Item 3 below to be included for a complete project, as described in Section 323113 of the specifications.
· Approximately 1450’ of fence
· One 12’ double-swing gate
· One 20’ cantilever slide gate and motor
· See list of Government provided materials
· Posts set 24” in ground with concrete grout/anchoring, 10’ max spacing
· Gate posts require deeper / larger posts/holes per gate manufacturer instructions
ITEM 4, Install and Connect Power Supply for Electric Gate: Work shall consist of supply connection, 1.25” Sch. 80 PVC conduit, underground power supply, pedestal, and motor connection and all accessories to ensure for a complete project, as described in Section 323113 of the specifications. Provide all necessary supplies for electrical connection to gate motor.
· Approximately 250’ of 18” trench with 1.25” Sch.80 PVC conduit
· 120v power with amperage sufficient to operate gate (24v DC) and Heater (110AC)
· Install gate keypad post and keypad
· (Linear AK-11 Digital Gate Keypad Outdoor Rated, Elite Gooseneck Post – Adjustable Height)
· (To include 20’ trench, ½” conduit, and power cable, Voltage: 12-24 Volts AC or DC Current: 10 mA typical, 150 mA maximum) (Trench length included in 250’ estimate above)
· Install gate exit probe (Liftmaster CP4 Exit Probe) with 50’ of ½” conduit, buried next to road.
· Install opener heater kit in gate opener enclosure
OPTION ITEM 1, Install 3-strand Barbed Wire: Work shall consist of supplying and installing Extension arms for attachment of barbed wire, bent at an angle of 40° to 45° from the vertical, at every vertical post. Extension arms with holes for the attachment of three lines of barbed wire. Zinc coated extension arms, brown paint to match fence, and unpainted barbed wire. Also provide vertical extension arms for attaching 3-strand barbed wire to the top of gates.
C.1.3 Project Location – This project is located at 301 Storm Castle Road, Gallatin Gateway, Montana on the Bozeman Ranger District of the Custer Gallatin National Forest.
C.1.4 Price Range – Between $25,000 and $100,000
C.1.5 Pre-bid Tour - No pre-bid tour of the project will be conducted.
Prospective bidders wishing to visit the site on their own may obtain direction information by contacting Joe Rock at the Supervisors Office, Custer-Gallatin National Forest, Bozeman, Montana, telephone (406)581-1301, or email norman.rock@usda.gov
C.1.6 Start Work - It is estimated that work will begin in September 2025.
C.1.7 Period of Performance – Contract on base items to be completed in 61 calendar days from Notice to Proceed.
C.1.8 Government Furnished Materials
· Staking by Government
· Motor: Liftmaster HDSL24UL Heavy-Duty Variable Speed Slide Gate Opener
· And associated materials listed below
· Galvanized metal with brown vinyl coating (see list below)
· Slide gate and materials listed below
Slide Gate Supplies: (Government Furnished)
| Description |
| Quantity |
| Pipe post 2 7/8" x 11' |
| 1 |
| Pipe post 4" x 11" |
| 2 |
| Dome Cap 2 7/8" |
| 1 |
| Dome Cap 4" |
| 2 |
| 72" x 20' Cantilever Gate |
| 1 |
| Gate Latch |
| 1 |
| Gate Roller (4" x 2 7/8") |
| 4 |
Materials for the gate motor Liftmaster HDSL24UL Heavy-Duty Variable Speed Slide Gate Opener (Government Furnished)
a. Linear AK-11 Digital Gate Keypad Outdoor Rated
b. Liftmaster 811LMX Gate Remote Control
c. Liftmaster CP4 Exit Probe - 50ft
d. Elite Gooseneck Post - Adjustable-Height for Keypads & Intercoms
e. Heater kit up to -40 degrees
Government Furnished Fence Materials
| Item Description |
| Color |
| Unit |
| Quantity |
| 6' high x 11-1/2ga. chain link fabric (2-1/4x11-1/2x72GAW), KK, 50' roll |
| Brown |
| EA |
| 30 |
| 1-5/8" x 21' x .085 Swedged End Pipe |
| Brown |
| EA |
| 72 |
| 2" x 8' x .090 Cut Post |
| Brown |
| EA |
| 149 |
| 2-1/2" x 8'6" x HF20 Cut Post |
| Brown |
| EA |
| 10 |
| 2" x 1-5/8" Loop Cap (H-4813) |
| Brown |
| EA |
| 149 |
| 2-1/2" Post Cap (H-4058) |
| Brown |
| EA |
| 10 |
| 2-1/2" Round Brace Band (H-4934) |
| Brown |
| EA |
| 4 |
| 1-5/8" Combo Rail End Cup (H-4832) |
| Brown |
| EA |
| 2 |
| 72" x 5/8" Tension Bar |
| Brown |
| EA |
| 2 |
| 2-1/2" Beveled Tension Band (H-4914) |
| Brown |
| EA |
| 10 |
| carriage bolt/hex. nut 5/16" x 1-1/4" (H-0002) |
| Brown |
| EA |
| 14 |
| Tension Wire - 6 Gauge Coated - 500' Roll |
| Brown |
| EA |
| 3 |
| Steel Hog Ring - Brown |
| Brown |
| EA |
| 750 |
| Pigtail Tie Wire fits 2" post - Bag of 100 |
| Brown |
| EA |
| 15 |
| 6' High x 12' Wide Commercial Chain Link Double Swing Gate |
| Brown |
| EA |
| 1 |
| 2-1/2" Butt Hinge (Fits 1-5/8" and 2" Gate Frames), Malleable |
| Brown |
| EA |
| 4 |
| 1-5/8" Commercial Drop Rod Assembly |
| Brown |
| EA |
| 1 |
C.1.9 Submittals - The contractor shall submit Work Schedule at least 10 days prior to beginning work. Contractor is responsible for calling 811 prior to digging electrical trench or post holes.
C.1.10 Disturbances – Noise, lights, or other activities that disturb residents shall not be permitted between the hours of 7:00 pm and 7:00 am. No work shall be permitted on weekends or Federal Holidays.
C.1.11 Staging Area - The Contractor shall coordinate with the COR on a staging area location. The Contractor shall operate all equipment and store, transport, and handle materials in a manner that will not damage the existing roads, parking lots, and landscaping. Access must be maintained to the residence, and other facilities on the site. Storage of material will not be permitted in the office.
C.1.12 Potable Water- Contractor may use the water on-site with permission from the CO.
C.1.13 Wastewater Facilities – The Contractor is required to supply portable toilets for use
C.1.14 Electrical – The Contractor may use on-site electrical service for operation of small power tools.
C.2 – CLEANUP AND DISPOSAL
C.2.1 Cleanup and Disposal – The Contractor shall be responsible for solid waste disposal. The Contractor shall at all times keep the area in a clean, neat, and orderly condition. Construction related debris, including but not limited to used motor oil, oil cans, grease cartridges and refuse shall be removed promptly from the site and disposed of in a lawful manner off National Forest System lands. Fees for the use of landfills or transfer stations shall be paid for by the Contractor if there is a charge.
C.3 – SECURITY AND PROTECTION
C.3.1 Security and Protection – Security is the responsibility of the Contractor. The Contractor shall be responsible for protecting all equipment and supplies for use on the project and stored on the site. The Contractor shall be responsible for all costs required to provide such protection.
The Contractor shall complete sequences of construction activity in order to prevent damage to equipment, material, and articles incorporated into the work covered by this contract.
C-4 – OTHER RELATED DOCUMENTS AND DRAWINGS
C4.01 The following CSI formatted specifications are part of this solicitation and any resulting contract.
| Section |
| Description |
| 01000 |
| Mobilization |
| 01025 |
| Measurement and Payment |
| 01400 |
| Quality Control and Quantity Measurement |
| 07000 |
| Building Maintenance |
| 323113 |
| Chain Link Fence and Gates |
SECTION 01000
MOBILIZATION
PART I: GENERAL
1.1 SUMMARY
A. Section Includes: Preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site; and for other work and operations which must be performed or costs incurred prior to beginning work on the various items on the project site. This specification does not include moves between project sites.
PART II: PRODUCTS
(There are no applicable requirements.)
PART III: EXECUTION
(There are no applicable requirements.)
PART IV: MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT:
A. Units: Progress payments will be made as follows:
1. When 5% of the original Contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original Contract amount, whichever is lesser, will be paid.
2. When 10% of the original Contract amount is earned from other bid items, 100% of the amount bid for mobilization or 10% of the original Contract amount, whichever is lesser, will be paid.
3. Upon completion of work for the project, payment of the amount bid for mobilization in excess of 10% of the original Contract amount will be paid.
4. The total sum of all payments shall not exceed the original Contract amount bid for mobilization, regardless of the fact that the Contractor may have shut down the work on the project or moved equipment away from the project and then back again.
4.2 BASIS OF PAYMENT:
Payment: No direct payment for moves between project sites will be made. The Contractor shall include consideration for moves between project sites in the bid price for other items of the Contract. Prices and payment will be full compensation for the work described in this section. Payment will be made under:
Pay Item Pay Unit
(1) Mobilization. . . . . . . . . . . . . . . . . Lump Sum
END OF SECTION
SECTION 01025
MEASUREMENT AND PAYMENT
PART I - GENERAL
1.1 Measurement and Payment - Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered as included in the payment for items shown.
When more than one class, size, or thickness is specified in the SCHEDULE OF ITEMS for any pay item, suffixes will be added to the item number to differentiate between items to be bid.
1.2 Determination of Quantities - The following methods of measurement are used to determine contract quantities for payment.
For individual construction items, longitudinal and lateral measurements for area computations will be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for seeding, mulching, geotextiles, netting, erosion control blankets, and sodding will be along slope lines.
Structures will be measured according to neat lines SHOWN ON THE DRAWINGS or as altered by the COR in writing to fit field conditions.
For standard manufactured items, such as fence, wire, plates, rolled shapes, pipe conduits, etc., identified by gauge, weight, section dimensions, etc., such identification shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances will be accepted.
1.3 Units of Measurement - Payment will be by units defined and determined according to U.S. Standard measure as follows:
A. Acre – Make longitudinal and transverse measurements for area computations horizontally.
B. Cubic Yard - A measurement computed by one of the following methods:
1. Excavation, Embankment, or Borrow - The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
2. Material in Place or Stockpile - The measurement computed with dimensions of the in-place material.
3. Material in the Delivery Vehicle - The measurement computed using measurements of material in the hauling vehicles at the point of delivery. Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
C. Cubic Yard Mile - A combination of linear and volumetric measurement meaning the movement of a cubic yard of material 1 mile.
D. Each - One complete unit, which may consist of one or more parts.
E. Gallon – The quantity may be measured by any of the following methods:
1. Measured volume container.
2. Metered volume. Use an approved metering system
3. Commercially packaged volumes.
F. Hour – Measurement will be for the actual number of hours ordered and performed by the Contractor.
G. Linear Foot – Measure from end to end, parallel to the base or foundation being measured, or horizontal.
H. MFBM - One thousand board feet measure based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job.
I. Mile – Measure horizontal along the centerline of each roadway, approach road, or ramp.
J. Pound – If sacked or packaged material is furnished, the net weight as packed by the manufacturer may be used.
K. Square Foot - Measure on a plane parallel to the surface being measured or horizontal.
L. Square Yard – Measure on a plane parallel to the surface being measured or horizontal.
M. Station - One hundred linear feet measured horizontally.
N. Station Yard - A combination of linear and volumetric measurement meaning the movement of a cubic yard of material one station.
O. Thousand Gallons Mile - A combination of linear and volumetric measurement meaning the movement of 1,000 gallons of material 1 mile.
P. Ton - Short ton consisting of 2,000 pounds.
Q. Ton Mile - A combination of linear and weight measurement meaning the movement of 1 ton of material 1 mile.
1.4 Methods of Measurement - One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item:
A. Contract Quantities (CQ) AND Design Quantities (DQ) - These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:
1. As a result of changes in the work authorized by the Contracting Officer.
2. As a result of the Contracting Officer determining that errors exist in the original design data used to determine designed quantities that cause a pay item to change by more than 15 percent.
3. As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design data used to determine design quantities that cause a pay item total to change by more than 15%. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
B. Staked Quantities (SQ) - These quantities are determined from staked measurements prior to construction.
C. Actual Quantities (AQ) - These quantities are determined from measurements of completed work.
D. Vehicle Quantities (VQ) - These quantities are measured or weighed in hauling vehicles.
E. Lump Sum Quantities (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They will not be measured.
PART II - PRODUCTS (Not Applicable)
PART III - EXECUTION (Not Applicable)
SECTION 01400
QUALITY CONTROL AND QUANTITY MEASUREMENT
PART I - GENERAL
1.1 Scope - This work shall consist of providing quality control in conformance with the Inspection of Construction provisions of this contract to ensure compliance with the drawings, specifications, and provisions of the contract, and measuring the quantities of completed work in conformance with the provisions of the applicable specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of this specification.
1.2 Measurement and Payment - No separate payment will be made for the work included under this section. Payment for this work is considered incidental to other items of work.
PART II - PRODUCTS (Not Applicable)
PART III – EXECUTION (Not Applicable)
SECTION 07000
BUILDING MAINTENANCE
PART I - GENERAL
1.1 Scope - Furnish all labor, materials, and equipment required to remove all wooden jack fence. Install 6ft chain link fence and rails to include one motorized gate and one manual gate. It is highly recommended a site visit be scheduled to ensure the correct material be priced and purchased.
PART II - PRODUCTS
2.1 Materials:
A. List of material for the fence already purchased on site in section C.1.8 Government Furnished Materials.
2.2 Submittals:
A. Submit all product information, warranties, and manufacturer installation instructions before ordering for all materials.
Written approval from the COR is required prior to ordering materials. Allow 7 days for COR approval.
PART III - EXECUTION
3.1 Installation
A. Before ordering materials or starting work, inspect existing fencing to ensure the proper materials and replacements are correct and will function properly, examine, clean and repair, replace if necessary any adjoining work on which this work is in any way dependent for its proper installation. Submit warranty, specifications, and installation instructions to C.O. prior to construction. The Contractor is required to provide any additional materials or appurtenances in order to properly install and finish all items. All costs for completing any item shall be included in bid items in the schedule.
B. Install all items in according to manufacturer’s instructions, Latest Version of the International Building Code standards shall be met, and according to industry standard. A professional installation is required as well as all codes must be met. The system shall be in functioning condition when the project is complete.
C. Install and test all gates and motor for correct installation D. Remove and dispose of old fencing and leave any old gates on site.
E. Hook up all necessary electrical power needed for gate motor and keypad F. Install and manual gate
PART IV – PAYMENT
A. Payment shall be as shown on the schedule of items.
SECTION 323113 - CHAIN LINK FENCES AND GATES
GENERAL
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
SUMMARY
Section Includes:
Chain-link fences.
Swing gates.
Horizontal-slide, motor-operated gates.
PREINSTALLATION MEETINGS
Preinstallation Conference: Conduct conference at Project site.
Inspect and discuss electrical roughing-in, equipment bases, and other preparatory work specified elsewhere.
Review sequence of operation for each type of gate operator.
INFORMATIONAL SUBMITTALS
Sample Warranty: For special warranty.
FIELD CONDITIONS
Field Measurements: Verify layout information for chain-link fences and gates shown on Drawings in relation to roads and existing structures. Verify dimensions by field measurements.
WARRANTY
Special Warranty: Contractor agrees to repair or replace components of chain-link fences and gates that fail due to workmanship within specified warranty period.
Failures include, but are not limited to, the following:
Failure to comply with performance requirements.
Faulty operation of gates.
Warranty Period: Five years from date of Substantial Completion.
PRODUCTS
GROUT AND ANCHORING CEMENT
Nonshrink, Nonmetallic Grout: Factory-packaged, nonstaining, noncorrosive, nongaseous grout complying with ASTM C1107/C1107M. Provide grout, recommended in writing by manufacturer, for exterior applications.
Anchoring Cement: Factory-packaged, nonshrink, nonstaining, hydraulic-controlled expansion cement formulation for mixing with water at Project site to create pourable anchoring, patching, and grouting compound. Provide formulation that is resistant to erosion from water exposure without needing protection by a sealer or waterproof coating, and that is recommended in writing by manufacturer for exterior applications.
EXECUTION
EXAMINATION
Examine areas and conditions, with Installer present, for compliance with requirements for site clearing, earthwork, and other conditions affecting performance of the Work.
Proceed with installation only after unsatisfactory conditions have been corrected.
PREPARATION
Stake locations of fence lines, gates, and terminal posts. Do not exceed intervals of 300 feet or line of sight between stakes. Indicate locations of utilities, lawn sprinkler system, underground structures, benchmarks, and property monuments.
CHAIN-LINK FENCE INSTALLATION
Install chain-link fencing according to ASTM F567 and more stringent requirements specified.
Post Excavation: Drill or hand-excavate holes for posts to diameters and spacings indicated, in firm, undisturbed soil.
Post Setting: Set posts in concrete at indicated spacing into firm, undisturbed soil.
Verify that posts are set plumb, aligned, and at correct height and spacing, and hold in position during setting with concrete or mechanical devices.
Concrete Fill: Place concrete around posts to dimensions indicated and vibrate or tamp for consolidation. Protect aboveground portion of posts from concrete splatter.
Concealed Concrete: Place top of concrete 2 inches below grade to allow covering with surface material.
Terminal Posts: Install terminal end, corner, and gate posts according to ASTM F567 and terminal pull posts at changes in horizontal or vertical alignment of 15 degrees or more. For runs exceeding 500 feet, space pull posts an equal distance between corner or end posts.
Line Posts: Space line posts uniformly at 10 feet o.c.
Post Bracing and Intermediate Rails: Install according to ASTM F567, maintaining plumb position and alignment of fence posts. Diagonally brace terminal posts to adjacent line posts with truss rods and turnbuckles. Install braces at end and gate posts and at both sides of corner and pull posts.
Locate horizontal braces at midheight of fabric 72 inches or higher, on fences with top rail. Install so posts are plumb when diagonal rod is under proper tension.
Tension Wire: Install according to ASTM F567, maintaining plumb position and alignment of fence posts. Pull wire taut, without sags. Fasten fabric to tension wire hog rings of same material and finish as fabric wire, spaced a maximum of 24 inches. Install tension wire fully before stretching fabric. Provide horizontal tension wire at the following locations:
Extended along bottom of fence fabric. Install bottom tension wire within 6 inches of bottom of fabric and tie to each post with not less than same diameter and type of wire.
Top Rail: Install according to ASTM F567, maintaining plumb position and alignment of fence posts. Run rail continuously through line post caps, bending to radius for curved runs and terminating into rail end attached to posts or post caps fabricated to receive rail at terminal posts. Provide expansion couplings as recommended in writing by fencing manufacturer.
Chain-Link Fabric: Apply fabric to outside of enclosing framework. Leave 1-inch bottom clearance between finish grade or surface and bottom selvage unless otherwise indicated. Pull fabric taut and tie to posts, rails, and tension wires. Anchor to framework so fabric remains under tension after pulling force is released.
Tension or Stretcher Bars: Thread through fabric and secure to end, corner, pull, and gate posts, with tension bands spaced not more than 15 inches o.c.
Tie Wires: Use wire of proper length to firmly secure fabric to line posts and rails. Attach wire at one end to chain-link fabric, wrap wire around post a minimum of 180 degrees, and attach other end to chain-link fabric according to ASTM F626. Bend ends of wire to minimize hazard to individuals and clothing.
Maximum Spacing: Tie fabric to line posts at 12 inches o.c. and to braces at 24 inches o.c.
Fasteners: Install nuts for tension bands and carriage bolts on the side of fence opposite the fabric side.
GATE INSTALLATION
Install gates according to manufacturer's written instructions, level, plumb, and secure for full opening without interference. Attach fabric as for fencing. Attach hardware using tamper-resistant or concealed means. Install ground-set items in concrete for anchorage. Adjust hardware for smooth operation.
GATE-OPERATOR INSTALLATION
Install gate operators according to manufacturer's written instructions, aligned and true to fence line and grade.
Excavation: Hand-excavate holes for posts, pedestals, and equipment bases/pads, in firm, undisturbed soil to dimensions and depths and at locations according to gate-operator component manufacturer's written instructions and as indicated.
Ground electric-powered motors, controls, and other devices according to NFPA 70 and manufacturer's written instructions.
GROUNDING AND BONDING
Comply with requirements in Section 260526 "Grounding and Bonding for Electrical Systems."
Connections:
Make connections with clean, bare metal at points of contact.
Make aluminum-to-steel connections with stainless-steel separators and mechanical clamps.
Make aluminum-to-galvanized-steel connections with tin-plated copper jumpers and mechanical clamps.
Make above-grade ground connections with mechanical fasteners.
Make below-grade ground connections with exothermic welds.
Coat and seal connections having dissimilar metals with inert material to prevent future penetration of moisture to contact surfaces.
ADJUSTING
Gates: Adjust gates to operate smoothly, easily, and quietly, free of binding, warp, excessive deflection, distortion, nonalignment, misplacement, disruption, or malfunction, throughout entire operational range. Confirm that latches and locks engage accurately and securely without forcing or binding.
Automatic Gate Operator: Energize circuits to electrical equipment and devices, start units, and verify proper motor rotation and unit operation.
Test and adjust operators, controls, alarms, and safety devices. Replace damaged and malfunctioning controls and equipment.
Lubricate operator and related components.
Lubricate hardware and other moving parts.
END OF SECTION 323113