Statement of Work Summary

This Statement of Work (SOW) describes the emergency replacement of Chiller #2 at Federal Correctional Complex (FCC) Pollock in Pollock, Louisiana (Project 25Z5AJ7). The contractor must provide a complete replacement of the existing 52-ton Air-Cooled Scroll Chiller (Trane Model CGAFC504 ACA, Serial Number C00A01605, or equal) located at 1000 Airbase Road. The replacement unit must be a 52-ton nominal capacity scroll chiller with R-410A refrigerant, 460V/3-Phase/60Hz power supply, and dual independent refrigerant circuits. The chiller must include a Tracer UC800 microprocessor-based controller compatible with BACnet, Lon Works, or Modbus for building automation system integration, along with factory-authorized submittals, three hard copies plus digital PDF of O&M manuals, and certified technician startup and commissioning support.

The contractor is responsible for all equipment, materials, labor, and supervision to complete the replacement, including removal and proper EPA-compliant disposal of refrigerant with documentation, modification and reconnection of existing piping, pressure testing using trace gas and dry nitrogen, charging with factory-recommended refrigerant and oil, evacuation to 1000 microns, and full startup verification. The maximum chiller downtime is 30 days, with work hours restricted to 7:00 AM–3:30 PM, Monday through Friday, excluding weekends and federal holidays. The contractor must provide a one-year parts and labor warranty plus a minimum five-year extended compressor warranty, and train facility personnel on chiller operation and maintenance. All work must comply with manufacturer installation recommendations, and the contractor is responsible for site housekeeping, material disposal per federal, state, and local laws, security clearance documentation for personnel, personal protective equipment compliance, tool inventory protocols, and adherence to federal smoking policies and facility security regulations.

View the file

Other files

File Type Posted
updated QA FCC POL 1.pdf PDF
update QA FCC POL.pdf PDF
QA FCC POL.pdf PDF
15BBNF26Q00000054.pdf PDF
CSS Project 25Z5AJ7.pdf PDF
WD 15-5175.txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

' STATEMENT OF WORK

FEDERAL CORRECTIONAL COMPLEX (FCC) POLLOCK

Emerg. Replace Chiller #2 FPC Dorm 1 FCC Pollock - PROJECT 25ZSAJ7

I. SPECIFICATIONS:

APPROVED

A. INTRODUCTION By FMB-CERS at 7:47 am, May 27, 2026

A.1 The Federal Prison Complex, FCC Pollock, located at 1000 Airbase Road, Pollock, LA 71467 seeks contract services to replace one (1) 52-ton Air Cooled Scroll Chiller for use at the Camp for Dorm 1. The chiller will replace the existing

Chiller #2 located at 1000 Airbase Rd, Pollock, LA 71467. This unit must be a factory replacement of Trane Model

Number CGAFC504 ACA, Serial Number C00A01605, or equal.

The contractor shall provide all equipment, materials, labor, supervision, and service necessary to provide a complete replacement.

B. CHILLER EQUIPMENT SPECIFICATIONS

1. (1) new 52-ton Air-Cooled Scroll Chiller or equal

2. Capacity: 52 nominal tons (cooling)

3. Application: Comfort cooling for commercial/industrial facility

4. Refrigerant: R-410A (non-ozone depleting, high efficiency)

5. Cooling Capacity: 52 tons nominal at AHRI conditions

6. Compressor: Scroll compressors, factory mounted, with internal motor protection

7. Condenser: Air-cooled, with aluminum fins and copper tubes

8. Evaporator: Brazed plate heat exchanger, insulated, with water-side flow control

9. Fans: Direct-drive, vertical discharge, low sound condenser fans with variable speed option

10. Refrigerant Circuits: Dual independent circuits for redundancy and efficiency

11. Power Supply: 460V / 3-Phase / 60 Hz

12. Unit-mounted control panel with factory-wired starter

13. Non-fused disconnect or circuit breaker (per project requirements)

14. BACnet or Lon Works compatible Tracer UC800 controller

15. Tracer UC800 microprocessor-based controller

16. BAS integration via BACnet, Lon Talk, or Modbus

17. Unit-mounted display with keypad for monitoring and diagnostics with remote monitoring capability

18. Factory-authorized submittals (shop drawings, wiring diagrams, dimensional data)

19. Manufacturers O&M manuals (3 hard copies+ digital PDF)

20. Startup and commissioning report startup assistance, testing, and support by certified technicians.

21. Warranty documentation with standard manufacturer's warranty: 1-year parts

22. Extended compressor warranty: 5 years minimum

23. Optional extended service contract available upon request

24. Training of owners operating personnel on chiller operation and routine maintenance.

C. SCOPE OF WORK

1. Replace current Trane Model Number CGAFC504 ACA, Serial Number C00A01605, or equal.

2. Modify and Re-connect existing piping to newly installed chiller.

3. Re-insulate any modified piping.

4. Government requires removal of old chiller, additionally a weight report is required by the facility for recycling purposes.

5. Remove of and dispose of refrigerant per EPA Guidelines and supply customer with report.

6. Furnish labor and materials to fully install replacement Chiller.

7. Pressure test and leak check the chiller using trace gas and dry nitrogen.

8. Furnish and charge the chiller with the factory recommended refrigerant charge.

9. Furnish and charge the chiller with the factory recommended oil charge.

10. Evacuate the chiller to 1000 microns and charge the chiller with proper refrigerant.

11. Perform startup of chiller and complete a full running check on the unit for proper operation.

12. Maximum chiller down time is {30) thirty days.

13. Provide one {l) full year parts and labor warranty.

Cl. WARRANTY

1. The contractor is required to provide the standard manufacture warranty upon completion of work required but prior to contract closeout. Please refer to the Warranty clause stated in the solicitation.

D. QUALITY ASSURANCE/INSTALLATION REQUIREMENTS

1. It is the Contractor's responsibility to repair and/or replace any Government property damaged by contractor/subcontractors' employees. Damage will be corrected and restored to previous conditions at NO cost to the government.

2. It shall be the Contractor's responsibility for obtaining all measurements and data requirements to comply with manufacturer's installation recommendations. All installations must be in accordance with product manufacture's recommendations.

E. UTILITIES

The FBOP will provide water, use of restrooms and minimal electricity service {120V) for small hand power tools including battery chargers. The contractor will provide all other equipment, supplies and materials needed to complete this project.

F. HOUSEKEEPING AND MATERIAL DISPOSAL

The contractor awarded the contract will be responsible to ensure the premises are always kept clean and free from accumulations of waste materials and rubbish. The contractor will remove all debris, scrap, and rubbish from the work area daily. Surplus materials and all equipment shall be promptly removed from the site upon completion of the work.

The Contractor shall be responsible to remove all debris and waste materials from the job site at FCC Pollock upon conclusion and acceptance of the project. These items must be disposed of in accordance with all Federal, State, and local laws.

G. SUBMITTALS & RESPONSIBILITIES

1. Submit the requested information of the persons who would perform the work inside the institution for background investigation.

2. Submit manufacturer's brochures, details, drawings, source certification for all material and equipment.

II. CONTRACTOR SECURITY /WORKING REGULATIONS

A. Work Hours:

Work Hours for the contractor are 7:00 AM - 3:30 PM, Monday - Friday, excluding weekends and federal holidays. Any work required to be completed at any other time than noted above must be requested in writing to the COR five (5) working days prior to the start of the work. In the event of any equipment being replaced that would result in downtime of the normal orderly running of the institution, alternate work hours may be authorized in accordance with the time frame stated above.