This is a Scope of Work (SOW) for concrete repair services at USCG Air Station North Bend in Oregon.

The contractor must repair approximately 50 square feet of spalling around select drains in the apron pavement at the air station located at 2000 Connecticut Ave, North Bend, OR 97459. The work is a firm fixed price contract awarded to the low cost responsive bidder. The contractor must provide all labor, materials, equipment, transportation, supervision, and other necessary items and services. Key responsibilities include: setting up foreign object debris (FOD) barriers, covering drains to block debris, inspecting damage boundaries using acoustic sounding, removing deficient concrete to a minimum 1-inch depth with 90-degree saw-cut perimeter edges, chipping out all loose and cracked concrete at least 2 inches beyond the spalled zone, drilling and epoxy-grouting steel dowel bars horizontally at perimeter locations if structural reinforcing is compromised, cleaning and coating exposed steel reinforcement per ASTM A955 criteria, cleaning cavities to saturated surface dry condition, applying heavy-duty fast-setting shrinkage-compensated structural mortar rated for aircraft wheel loads, maintaining a ¼-inch-per-foot slope at drain inlets, installing closed-cell backing rod and fuel-resistant polyurethane or silicone sealant at joints, applying curing compound per manufacturer specifications, and performing final magnetic and vacuum sweeps for FOD removal. The government will provide 120V and 240V, 60 Hz single phase power and potable water. Contractor personnel must have REAL ID-compliant driver's licenses or federal photo identification, and all deliveries require 24-hour advance notice. Invoicing must be submitted electronically via the Invoice Processing Platform (IPP) per FAR 52.232-33. A mandatory site visit is required. Contact information: Contracting Specialist CWO Ava Stow (541-991-0079, Ava.M.Stow@uscg.mil) and Unit POC LT Jennifer Hansen (541-965-8509, Jennifer.P.Hansen@uscg.mil). Work must comply with OSHA Safety and Health Standards (29 CFR Part 1926) and International Concrete Repair Institute (ICRI) standards.

View the file

Other files

File Type Posted
USCG_North Bend_Airfield_Drawing.pdf PDF
Overview of Pavement .png PNG image
QandA.pdf PDF
Amendment 002 to 70Z033Q2027601.pdf PDF
Amendment 001 to 70Z033Q2027601.pdf PDF
Solicitation Provisions and Clauses.pdf PDF
Wage Determination.txt TXT text file
SF1442-22.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK (SOW)

U.S. COAST GUARD

USCG Air Station North Bend Repair Apron Pavement

SECTION 1 – GENERAL INFORMATION

1.1 Scope of Work:

The contractor shall provide all labor, materials, equipment, transportation, supervision and other items and services necessary to repair approximately 50 square feet of spalling around select drains in the apron pavement at Air Station North Bend. The contractor must perform to the standards in this Scope of Work (SOW) contract.

1.1.1 Performed for:

USCG Air Station North Bend Location: 2000 Connecticut Ave, North Bend, OR 97459

1.1.2 Contracting Specialist:

Name: Chief Warrant Officer Ava Stow Unit: USCG Base North Bend

PH: 541-991-0079

E-mail: Ava.M.Stow@uscg.mil

1.1.3 Unit Point of Contact (POC):

Name: Lieutenant Jennifer Hansen Unit: USCG Base North Bend

PH: (541) 965-8509

E-mail: Jennifer.P.Hansen@uscg.mil

1.1.4 Contact for questions:

1.1.4.1 Any questions regarding scope of work must be directed to the Contracting Officer.

1.1.4.2 Unless specifically annotated below all requests for site visits must be scheduled through the POC.

Requests can be submitted via phone call or e-mail.

1.1.4.3 A site visit is mandatory.

mailto:Ava.M.Stow@uscg.mil mailto:Jennifer.P.Hansen@uscg.mil

1.2 Contractor Personnel

1.2.1 Contract Manager:

The contractor must provide a contract manager who must be responsible for the performance of the work.

The name of this person, and an alternate or alternates, who must act for the contractor when the manager is absent, must be designated in writing to the contracting officer.

1.2.1.1 The contract manager or alternate must have full authority to act for the contractor on all contract matters relating to daily operation of this contract.

1.2.1.2 The contact manager and alternate or alternates must be able to read, write, speak, and understand the English language.

1.2.2 Contractor Employees:

The contractor must not employ persons for work on this contract if such employee is considered by the contracting officer to be a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population.

1.2.2.1 The contractor must not employ any person who is an employee of the U. S. Government if employing that person would create a conflict of interest. Additionally, the contractor must not employ any person who is an employee of the U. S. Coast Guard unless such person seeks and receives approval according to U. S. Coast Guard regulations.

1.2.2.2 The Contractor or employees oof the contractor must have a REAL ID-compliant driver’s license or an alternative accepted federal photo identification. It is the responsibility of the Contractor to ensure that their personnel have federally acceptable personal photo identification and comply with any other requirements for base access. Contractors shall provide the Contracting Officer's Technical Representative with 24 hours of advance notice of every delivery to the site (e.g., concrete, lumber, parts, etc.) and provide the company name, delivery person, and phone number of the firm(s) making deliveries. All vehicle access to government property requires vehicle registration and proof of liability insurance. Otherwise access to the Coast Guard facility may be denied.

1.3 Award:

It is the governments’ intent to make award to the low cost responsive offered through issuance of a firm fixed price contract.

1.4 Invoicing:

All invoices from the Contractor shall be submitted electronically IAW FAR 52.232-33, Payment by Electronic Funds Transfer-System for Award Management.

1.4.1 Definitions. As used in these instructions:

1.4.1.1 “Payment request” means a bill, voucher, invoice, or request for contract financing payment with associated supporting documentation. The payment request must: comply with the requirements identified in FAR 32.905(b), “Content of Invoices” and the applicable Payment clause included in this contract. In addition, discount offerings and small business status if available shall be stated. If travel was allowable and approved, components in accordance with FAR 31.205-46 shall be provided.

1.4.1.2 Except as provided in paragraph 1.4.1.3 of this clause, the contractor shall submit payment requests electronically using the Invoice Processing Platform (IPP). Information regarding IPP, including IPP Customer Support contact information, is available at www.ipp.gov or any successor site.

1.4.1.3 The contractor may submit payment requests using a method other than IPP only when the contracting officer authorizes alternate procedures in writing in accordance with Coast Guard procedures.

http://www.ipp.gov/

1.4.1.4 If alternate payment procedures are authorized, the contractor shall include a copy of the contracting officer's written authorization with each payment request.

1.4.1.5 IPP enrollment information is at https://www.uscg.mil/fincen/IPP/.

SECTION 2 – DEFINITIONS

2.1 General Definitions:

When the scope of work, solicitation provision, or contract clause uses a word or term that is defined in the Federal Acquisition Regulations (FAR), the word or term has the same meaning as the definition as contained in section 2.101 of the FAR. The FAR index is available via the Internet at http://www.acqnet.gov at the end of the FAR, after the FAR Appendix.

2.1.1 Defective Service: A service or commodity output that does not meet the standard of performance requirement specified in the contract for that service or commodity.

2.1.2 Quality Assurance: A planned and systematic pattern of all government actions necessary to provide confidence that adequate technical requirements are established; products and services conform to established technical requirements; and satisfactory performance is achieved. Quality assurance refers to actions by the government assurance functions for a contracted service.

2.1.2 Quality Control Plan: Those actions taken by a contractor to control the production of outputs to ensure that they conform to the contract requirements.

2.1.3 Technical Definitions: Not applicable to contract.

SECTION 3 – GOVERNMENT FURNISHED PROPERTY AND SERVICES

3.1 General Information:

The Government must provide the facilities, equipment, materials, and services listed here:

3.1.1 Government Furnished Facilities: 120V and 240V, 60 HZ, single phase power; potable water.

3.1.2 Government Furnished Equipment: None

3.1.3 Government Furnished Material: None

3.1.4 Government Furnished Services: None

SECTION 4 – CONTRACTOR FURNISHED ITEMS AND SERVICES

Except for those items, services, or commodities specifically stated in section 3.1 as government furnished, the contractor must furnish everything needed to perform this contract according to all its terms.

SECTION 5 - SPECIFIC TASKS/REQUIREMENTS

5.1 General:

5.1.1 The Contractor shall repair existing concrete spalling around one drain and a stretch of perimeter concrete on the airport apron, located at US Coast Guard Air Station North Bend. Concrete shall match or exceed industry standard grade and specifications for helicopter apron use.

5.2 Demo:

5.2.1 The Contractor shall remove and dispose of all removed concrete.

5.3 Specifications:

5.3.1 The work includes but is not limited to the following:

5.3.1.1 Set up foreign object debris (FOD) barriers around the location of work to prevent loose particles from entering the airfield.

https://www.uscg.mil/fincen/IPP/ http://www.acqnet.gov/

5.3.1.2 Cover the drain to block debris, slurry and dust from entering the drainage system. Clear area of all debris and standing water.

5.3.1.3 Inspect the exact boundary of the damage using acoustic sounding.

5.3.1.4 Remove deficient concrete to a minimum sound substrate depth of a minimum of 1 inch, with saw-cut perimeter edges at 90-degree angles or slightly undercut to prevent feathered edges.

5.3.1.5 Chip out all loose, cracked and carbonated concrete around the drain basin or damaged area until reaching a solid, sound concrete substrate. Cut at least 2 inches outside the perimeter of the spalled zone.

5.3.1.6 For the perimeter location, drill and epoxy-grouted steel dowel bars horizontally into the sound slab if the perimeter edge has lost its structural reinforcing tie-ins.

5.3.1.7 If steel reinforcement is exposed, inspect the bar per ASTM A955 criteria. Clean rust and scale off exposed steel bars using a wire brush or mechanical abrasive blasting, if necessary. Coat all new and existing exposed steel with an airfield-approved, polymer-modified cementitious or epoxy-resin corrosion inhibitor.

5.3.1.8 Clean the cavity via oil-free compressed air, then bring the concrete to a saturated surface dry (SSD) condition.

5.3.1.9 Use a heavy-duty, fast-setting, shrinkage- compensated structural mortal (such as polymer-modified cementitious or polymer-resin mortar), rated for heavy aircraft wheel loads.

5.3.1.10 Pack the mortar tightly under the drain flange and trowel smooth, maintaining a strict ¼-in per foot slope dropping down into the drain inlet to prevent pooling.

5.3.1.11 Install a closed-cell backing rod and a heavy-duty, fuel-resistant polyurethane or silicone sealant along the joint where the new concrete patch meets the metal drain frame.

5.3.1.12 Apply a heavy-duty curing compound or execute continuous moist curing according to the aviation mortar manufacturer’s specifications.

5.3.1.13 Perform a final magnetic and vacuum sweep of the apron to remove all potential FOD.

5.4 Testing:

5.4.1 None

5.5 Documentation

5.5.1 None.

5.6 Training

5.6.1 None.

5.7 Safety

5.7.1 During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 289 CFR Part 1926 – Safety and Health Regulations for Construction. All work shall be conducted in a safe manner and shall comply with all applicable Federal, State, and local safety standards and requirements.

5.8 Control and Disposal of Waste:

5.8.1 Except for materials specifically indicated or specified by the POC to be salvaged or turned over to the Government for reuse in construction, all wastes and demolished materials become the contractor’s property and shall be removed from the job site daily in accordance with all local, state, and federal environmental regulations.

5.8.1 Hazardous Waste Disposal: Any hazardous waste generated by work under this contract is the responsibility of the Contractor and shall be disposed of in accordance with all applicable federal, state, and local regulatory requirements.

5.10 Operations and Storage Facilities:

The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the on-site representative with the concurrence of the Contracting Officer.

The Contractor shall hold and save the Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor’s performance.

SECTION 6 – APPLICABLE PUBLICATIONS AND FORMS

Publications and forms that apply to the PWS are listed below. The publications and forms have been designated as either mandatory or informational. The contractor is obliged to follow those publications and use those forms designated as mandatory to the extent specified in other sections of this scope of work. The contractor must be guided by those publications or use those forms designated as informational to the extent necessary to accomplish requirements in this scope of work.

6.1 Mandatory Publications:

6.1.1 OSHA Safety and Health Standards, 29 CFR Part 1926 – Safety and Health Regulations for Construction.

6.1.2 Follow all standards set by the International Concrete Repair Institute (ICRI). Pay particular attention to the requirements of Concrete Surface Profile (CSP), for required surface texture for bonded repair materials.

6.2 Informational Publications:

6.2.1 None

Figure 1. Damaged concrete around drain.

Figure 2. Damaged concrete at perimeter drain.

Figure 3. Damaged concrete in apron.

Figure 4. Damaged pavement around drain.