SOW PR15804488_V6 CCTV Final.pdf
PDF 368 KB Posted
- Attached to
- INL Guatemala Border Security CCTV
- Solicitation number
- 191NLE26R0086
About this file
Statement of Work Summary: Replacement of CCTV System for Guatemalan Customs Agency
This Statement of Work (SOW) for Solicitation No. 191NLE26R0086 outlines requirements for replacing, configuring, and delivering an integrated IP-based, high-definition CCTV system for the Guatemala Customs Agency (SAT). The project supports INL Guatemala's efforts to improve customs operational capabilities at twelve strategically placed interagency highway checkpoints and official ports of entry throughout Guatemala, with integration to a Border Command Center in Guatemala City. The scope includes 122 units of hardware (cameras, NVRs, switches, NAS, joysticks), 12 PTZ cameras with 4MP dual-lens capability and 25X optical zoom, 77 bullet network cameras with 5MP resolution and intelligent intrusion detection, video monitoring software and storage for 126 systems, training for 10 SAT IT personnel, one year of 24/7/365 technical support in Spanish with 24-hour response time, direct labor for installation and removal of existing equipment, and travel as approved. All hardware and software must be new, in original packaging, provided through authorized OEM channels with OEM certification letters. The contractor must supply a local project manager throughout all project stages and provide comprehensive documentation including connectivity diagrams, testing plans, bills of material with serial numbers, warranty documentation, and quarterly warranty/support reports for the one-year warranty period.
Delivery is FOB Destination to Doral, Florida with all work completed within 120 calendar days of award. The contract type is Firm Fixed Price (FFP) payable entirely in US dollars with no adjustments for cost escalation or exchange rate fluctuations. The Government will not furnish any property or information; the contractor bears all responsibility for customs documentation, logistics, and site preparation approvals through the Contracting Officer's Representative (COR). Pre-award site visits are required at four locations in Guatemala, and contractors must attend or forfeit inspection opportunities. Minimum three past performance references completed within five years are required, along with OEM-certified employee credentials. Quality assurance standards permit no more than one customer complaint per month, with repeat complaints subject to contract termination action. All deliverables must be in English unless otherwise specified, with connectivity diagrams due 15 days after site visits, project schedules due 15 days post-award, and testing plans due two weeks before scheduled testing.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 191NLE26R0086_A0001.pdf | ||
| Answered Questions 191NLE26R0086.docx | DOCX document | |
| 191NLE26R0086 Signed.pdf | ||
| Attch 2 - Evaluation Criteria PR15804488 Final.pdf | ||
| Attch 1 - Instruction to Offerors Supplemental Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. 191NLE26R0086
Statement of Work
Replacement of CCTV system for Guatemalan Customs Agency
Date: June 12, 2026
Table of Contents
Section 1 – Required Supplies and Services
1.1. Background
1.2. Required Items / Services
1.3. Delivery Terms
1.4. Required Data Deliverables and Reports
1.5. Special Requirements
1.6. Project Schedule
1.7. Project Completion Documentation
1.8. Confidentiality of Information
1.9. Quality Assurance
1.10. Configuration
1.11. Testing
1.12. Escalation Table and Procedure
1.13. Project Manager
Section 2 – Special Conditions
2.1. Type of Task Order
2.2. Government Furnished Property (GFP)
2.3. Government Furnished Information (GFI)
2.4. Taxes and Import Duties
2.5. Required Tagging
Section 1 – Required Supplies and Services
1.1. Background
INL Guatemala provides targeted support to improve the operational capabilities of the Guatemala Customs Agency (SAT), thereby improving effectiveness of customs controls at Guatemala's official entry points. This support includes the establishment of twelve strategically placed interagency highway checkpoints throughout
Guatemala. INL Guatemala also supports SAT efforts to better manage its land border entries, including investments in infrastructure and technology. INL
Guatemala is now in the process of setting up a Border Command Center (BCC) in
Guatemala City and aims to create a technological platform to target and analyze passengers and cargo transiting INL checkpoints and all official POEs.
1.2. Required Items / Services
The contractor shall replace, configure and turn-key of integrated IP-based, high definition, day and night CCTV.
1.2.1 Technical Specifications and Quantities
CLIN Description Qty
Hardware
(Cameras, NVRs, Switch’s, NAS, Joystick)
PTZ Camara 4MP+4MP Dual-Lens network 25x
Features
• Fixed camera and PTZ camera integration, dual channels with one IP, look at the overall situation and consider details at the same time
• Ultra 265, H.265, H.264, MJPEG
• 25X optical zoom of the PTZ channel allows for closer viewing of subjects
• PTZ channel can be linked to the fixed channel’s smart intrusion prevention to track the objects triggering the rule
• Light hunter technology ensures ultra-high image quality in low illumination environment
• IR & warm light illumination to deal with different scenes and achieve full-color illumination
• DC12V or PoE+(IEEE 802.3at) power supply
• Alarm 2 in and 1 out, Audio 1 in and 1 out
Bullet Network Camara 5MP HD INTELLIGET IR VF
Features
• High-quality image with 5MP, 1/2.7"CMOS sensor
• 5MP (2880*1620)@ 30/25fps; 4MP (2560*1440)@ 30/25fps;
3MP (2304*1296) @30/25fps; 2MP (1920*1080) @30/25fps
• Ultra 265, H.265, H.264, MJPEG
• Smart intrusion prevention includes cross-line intrusion, enter area, leave area detection
• Based on target classification, smart intrusion prevention significantly reduce false alarm caused by leaves, birds, lights, etc., accurately focusing on human and, motor vehicle and non-motor vehicle
• Intelligent People Flow Counting and Crowd Density
Monitoring
• LightHunter technology ensures ultra-high image quality in a low illumination environment
• 120dB true WDR technology enables a clear image in a strong light scene
• Support 9:16 Corridor Mode
• Alarm:1 in/1 out, Audio: 1 in/1 out
• Smart IR, up to 50m (164ft) IR distance
• Supports 256 G Micro SD card
• IK10 vandal resistant and IP67 protection
• Support PoE power supply
Software and Physical Storage
(Video Monitoring system, video surveillance storage)
005 Training
Purpose: Train SAT IT personnel on operational capabilities of
CCTV equipment, recording and storage features and connection to
SAT HQ and Border Command Center
Location: The location where the training will be provided is in
SAT’s Central de Monitoreo in Guatemala City. SAT will provide a training room.
Personnel: 10 employees
Hours of training: To be confirmed by contractor depending on manufacturer guidance and certifications.
Time Frame: Mondays to Fridays from 9am to 4 pm.
Materials: Contractor shall provide all training materials, accessories or other needed items.
006 Support and Warranty
Contractor shall provide technical and IT support to SAT for a minimum of one (1) year after installation to ensure new hardware and system transition plus functionality.
This support must include onsite technical assistance and support at all locations where hardware and software are replaced.
On-Site Warranty: The contractor shall provide on-site warranty for at least one (1) year. The on-site warranty period shall commence immediately upon written COR acceptance of the completed system and shall continue for at least one (1) year thereafter
• Technical support shall be 24x7x365. As necessitated, support shall be provided on-site, via telephone, or on-line, and shall be provided in Spanish. The support period begins upon final acceptance of the system and shall be in force for one (1) year thereafter. The response time should be less than a 24 hour response and if the technical issue has not been properly dealt with via telephone, then a site visit should be required.
007 Labor
Direct labor costs for the installation of new equipment and removal of existing equipment being replaced, system configuration and testing
008 Other Direct Costs
009 Travel (if applicable)
All travel will be subject to approval by the CO/COR
All travel shall be in accordance with Federal Travel Regulations
(FTR) and Department of State Standardized Regulations (DSSR)
1.3. Delivery Terms
1.3.1 Contractor shall perform all hardware and software replacement at each specific location as detailed below:
Central Region
Location Hard Drive, video surveillance
Video Monitor
System
Central de Monitoreo, Guatemala City.
125 1
Central Region
Location NVR Switch PTZ Bullet LPR NAS Joystick
Aduana Central, Guatemala City.
1 1 - - 2 - -
Express Aereo, Guatemala City.
1 1 - 4 - -
Central de Monitoreo, Guatemala City.
2 1 - - - 2 -
CARCE / GSI / Spare - - - - - - 3
Guatemala City.
PCI Sanarate, El
Progreso.
1 1 2 8 2 - -
PCI Patzicia, Chimaltenango.
1 1 2 6 2 - -
South Region
Location NVR Switch PTZ Bullet LPR NAS Joystick
POE Puerto Quetzal, Escuintla.
1 1 - - 6 - -
POE Valle Nuevo, Jutiapa.
1 1 - - 2 - -
POE Pedro de Alvarado, Jutiapa.
1 1 - - 2 - -
POE San Cristóbal, Jutiapa.
1 1 - - 2 - -
PCI Jerez, Jutiapa. 1 1 - 4 - - -
PCI Escuintla, Escuintla. 1 1 - 6 - - -
PCI Retalhuleu, Nuevo
San Carlos.
1 1 - 4 - - -
PCI Pasaco, Jutiapa. 1 1 2 8 2 - -
West Region
Location NVR Switch PTZ Bullet LPR NAS Joystick
POE La Mesilla, Huehuetenango.
1 1 - - 3 - -
POE El Carmen, Huehuetenango.
1 1 - - 4 - -
POE Tecun Umán II, San Marcos.
1 1 - - 10 - -
POE Tecun Uman I, San
Marcos.
1 1 - - 4 - -
PCI Pajapita, San
Marcos.
1 1 2 8 2 - -
PCI Huehuetenango, Huehuetenango.
1 1 2 10 2 - -
Northeast Region
Location NVR Switch PTZ Bullet LPR NAS Joystick
POE Melchor de
Mencos, Huehuetenango.
1 1 - - 2 - -
POE Santo Tomas de
Castilla, Izabal.
1 1 - - 6 - -
POE Puerto Barrios, Izabal.
1 1 - - 6 - -
POE Agua Caliente, Chiquimula.
1 1 - - 2 - -
POE El Florido, Chiquimula.
1 1 - - 2 - -
POE La Ermita, Chiquimula.
1 1 - - 2 - -
PCI Vado Hondo, Chiquimula.
1 1 - 10 - - -
PCI Rio Dulce, Izabal. 1 1 2 6 2 - -
PCI Entre Rios, Izabal. 1 1 - 7 2 - -
Totals 29 28 12 77 73 2 3
All currently installed equipment that will be replaced, will be unistalled, placed in boxes and delivered to the project COR.
1.3.2 Site Visits and Delivery of equipment
Pre Award site visits for this project will be coordinated and scheduled in consultation with INL, SAT personnel, and the COR. These visits will ensure that all relevant locations are included, allowing the contractor to gather the information necessary to develop an effective work schedule.
For this project, there will be minimum of four site visits offered. These visits will allow the contractor to inspect existing equipment and connections, verify compatibility with the proposed new equipment or any necessary modifications that need to be implemented to ensure full integration.
1. Visit the “Central de Monitoreo” in Guatemala City.
2. Visit the “Aduana Central” in Guatemala City
3. Visit one of the PCI (“Puesto de Control Interinstitucional” / Interagency
Highway Checkpoints) around the country – PCI in Patzicia, Chimaltenango
4. Visit one of the POE (Ports of Entry) at the different borders of Guatemala –
POE Valle Nuevo Jutiapa.
On Tuesday, June 23 visit to locations 1, 2, and 3. At 08:00 am, meeting point in from of AC Marriott Cayala to start the visit to “Central de Monitoreo”. Departure at 09:00 am for visit to location 2 – Aduana Central. Departure at 11:00 am for visit to location 3 PCI in Patzicia, Chimaltenango. Wednesday, June 24 meeting point in McDonald’s zona 15, Vista Hermosa II at 07:30 am for departure to POE Valle
Nuevo Jutiapa. Offerors should provide their contact information to Oscar Lujan via email to LujanOE@state.gov and Charlie Walker at WalkerCE@state.gov.
Additional site visits may be scheduled as needed if it is determined that the characteristics of the various locations differ. Prior to site visits, the contractor shall provide the names and contact information of personnel who will conduct the visits.
The Department of State will not provide any travel or logistical support for the site visits nor will the offeror be reimbursed for any costs associated with the site visit.
Prospective Offerors will only be allowed to inspect the location of work during the scheduled site visit. Prospective Offerors that are unable to attend the scheduled site visit will not be provided another opportunity to inspect the site.
The purpose of the site visit is to allow prospective Offerors an opportunity to inspect the site where services are to be performed and to familiarize themselves regarding general and local conditions that may affect the cost of contract performance.
Attendance at the site visit is recommended, however, attendance is not a prerequisite for submission of a quotation and will not be considered a factor in the evaluation of quotations.
Any and all questions regarding this solicitation must be submitted in writing to the
Contracting Officer as described elsewhere in this solicitation. Questions will not be answered during the site visit. Offerors should submit all questions to the
Contracting Officer within 5 business days of completing the site visits. Responses shall be posted as an attachment to the solicitation on SAM.gov. Information provided at this site visit shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply.
mailto:LujanOE@state.gov mailto:WalkerCE@state.gov
The Contractor shall provide full delivery destination services (shipping, custom clearance, temporary warehousing, local delivery, loading/offloading at final destination). The Contractor shall ensure the protection and preservation of all goods during shipping and storage. The Contractor is responsible for customs documentation, if needed.
The Contractor shall provide an itemized commercial invoice of all cargo prior to delivery.
Contractor shall coordinate all deliveries with the designated COR(s). Partial deliveries are acceptable if approved in writing by the COR.
1.3.3 Period of Performance or Delivery Date
Delivery, installation, configuration, fine-tuning, testing and familiarization training for all systems: All work must be completed no later than 120 calendar days after award.
1.4. Required Data Deliverables and Reports
The Contractor shall deliver the documentation identified in the table below to the following individuals. Unless otherwise stated, all documentation must be in English and must be provided electronically via email.
CO: Information to be provided at time of award
COR: Information to be provided at time of award
Deliverable Reference Due Date Frequency Distributio n
D01 – Hardware and
Software OEM letter
PWS Section
1.5.2
Included in the proposal
Update as required
COR
D02 – Employee(s)
Resume and
Certifications
PWS Section
1.5.3
Included in the proposal
Update as required
COR
D03 – Connectivity
Diagrams
PWS Section
1.4.1
No later than 15 calendar days after field visits have been performed.
Updated as required
CO, COR
D04 – Project
Schedule
PWS Section
1.6
No later than 15 days after award of contract.
Updated as required
CO, COR
D05 – Testing Plan PWS Section
1.11
At least two (2) weeks before scheduled testing date.
Once CO, COR
D06 – Project
Completion
Documentation
PWS Section
1.7
No later than 120 calendar days after award of contract
Once CO, COR
D07 – Escalation table and procedure
PWS Section
1.12
Included in the proposal
Once CO, COR
D08 – Warranty and
Technical Support
Report
PWS Section
1.7.1
No later than 3 months after COR acceptance of completed system.
Quarterly CO, COR
Deliverable Reference Due Date Frequency Distributio n
D09 –
Confidentiality of
Information letter
PWS Section
1.8
Included in the proposal
Once COR
D10 – Contractor’s past performance
PWS Section
1.5.5
Included in the proposal Once COR
D11 – List of proposed equipment
PWS Section
1.5.6
Included in the proposal Once COR
1.4.1 Connectivity Diagrams
The contractor shall provide a digital copy of the connectivity diagrams for each location, describing how all components of the solution will be connected. The
Contractor shall submit a detailed explanation of the diagrams.
1.4.2 Electrical
The Contractor shall inform to the COR about any inadequate electrical connections that could affect the installation or could damage the new equipment, to that SAT personnel fix the issues.
1.5. Special Requirements
1.5.1 All required site preparations and alterations to the ILEA building must be approved in advance by the COR. All work must conform to the latest International
Building Code or the local equivalent. The Contractor shall perform all necessary work to restore temporary alterations of the building(s) to the original condition.
1.5.2 All hardware, software, and services must be provided through authorized distribution channels. All items provided under this project must be new and in original packaging. Used, discontinued, or refurbished materials are not allowed.
The Contractor shall provide a letter from the original equipment manufacturer
(OEM) demonstrating compliance with these requirements.
1.5.3 All services must be carried out under the supervision of OEM-certified employee(s). The Contractor shall provide the COR a copy of the employee(s) resume and certification(s) as part of the proposal. A minimum of one OEM-certified employees is required.
1.5.4 All the accessories should be included.
1.5.5 Contractor shall provide a minimum of three past performance references completed within the past five (5) years that include the following information:
• Company name (Client).
• Project start date.
• Project completion date.
• Project description.
• Project cost.
• Project point of contact name.
• Point of contact email.
• Point of contact telephone numbers.
1.5.6 A list of the proposed equipment shall be provided, it shall include: Item
Description, Name of Manufacturer, Model Number, Serial Numbers, Quantity, Fixed Unit Price and total price.
1.6. Project Schedule
The Contractor shall, within ten (10) days after award of the contract, prepare and submit for Government approval a practicable schedule showing the order in which the Contractor proposes to perform the work and the dates on which the Contractor contemplates starting and completing the several salient features of the work
(including but not limited to acquiring materials, installation, testing, and conducting training). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the project performance period.
The Contractor shall track actual project progress on the chart. The Contractor shall provide an electronic copy of the chart showing the actual progress whenever requested by the Contracting Officer or the Contracting Officer’s Representative.
The Contractor shall submit for Government approval any revision to the approved schedule
1.7. Project Completion Documentation
The contractor shall provide complete documentation for all hardware and software delivered under this contract. At a minimum, the closeout documentation must include:
• Comprehensive Bill of Material for all hardware and software delivered under the contract. The list shall include: Item Description, Name of Manufacturer, Model
Number, Serial Numbers, Delivered Quantity, Unit Price, Extended Price, and
Warranty Expiration Date.
• OEM manuals for all hardware and software delivered under the contract to be in Spanish and English.
• Results of system testing.
• Diagrams.
• Warranty and Technical Support documentation. Documentation shall include an explanation of coverage, the process of obtaining warranty or technical support services, and applicable contact information.
1.7.1 WARRANTY AND TECHNICAL SUPPORT REPORT
The Contractor shall, for the duration of the warranty period, provide a quarterly report describing in detail the technical support and warranty work performed for the reporting period. For the purposes of this requirement, quarterly means every three (3) months.
At a minimum, the report shall include:
• A list with all warranty / support ticket submitted, ticket number, date of submission, and person submitting the ticket;
• For each ticket, identify the actual response time and time required to restore;
• Explanation of how the issue was resolved;
• A list of all unresolved tickets, explanation of pending action items, and expected date of resolution.
1.8. Confidentiality of Information
The Contractor agrees to keep confidentiality of all of the information received, including but not limited to: equipment characteristics, passwords, blueprints, topology of the solution, software and hardware versions, security parameters, configurations, and any other information whether oral or written that may compromise in any way the security of the institution or may be counter-productive for the institution in the hands of third parties.
The requirements in the preceding paragraphs apply to all subcontractors and do not expire upon completion of the contract. The Contractor is solely responsible to ensure selected subcontractors comply with the preceding paragraphs.
1.9. Quality Assurance
1.9.1 The Contractor is responsible for performing or having performed all inspections and tests necessary to verify that the supplies or services furnished under this contract conform to contract requirements, including any applicable technical requirements for specified manufacturers’ parts. This requirement takes precedence over any Government inspection and testing required in the contract’s specifications.
Records of all inspections conducted by the Contractor and necessary corrective actions taken shall be maintained by the Contractor. The Contractor shall make these documents available to the Government at the request of the Contracting Officer or
Contracting Officer Representative.
1.9.2 This Quality Assurance and Surveillance Plan (QASP) is designed to provide an effective surveillance method to promote effective Contractor performance. The
QASP provides a method for the COR to monitor Contractor performance, and advise the Contracting Officer of unsatisfactory performance. The Contractor, not the Government, is responsible for management and quality control to meet the terms of the contract. The role of the Government is to conduct quality assurance to ensure that contract standards are achieved.
Performance
Objective
Standard and Acceptable
Quality Level (Maximum allowable deviation)
Incentive/
Disincentive
Calculation
Performs all services set forth in the performance
All required work is properly performed and no more than one (1) customer complaint is received per month.
Negative Incentive:
Low rating in
CPARS; appropriate action under the inspection and
Performance: number of valid written complaints during the month.
work statement
(PWS).
termination clauses of the contract.
1.9.3 Surveillance. The COR will receive and document all complaints from
Government personnel regarding the services provided. If appropriate, the COR will send the complaints to the Contracting Officer for transmittal to the Contractor for corrective action.
1.9.4 Standard. Acceptable performance standards are as described in the table above.
1.9.5 Procedures.
1.9.5.1 If any personnel observes unacceptable services, either incomplete work or required services not being performed, they should immediately contact the COR.
1.9.5.2 The COR will complete appropriate documentation to record the complaint.
1.9.5.3 If the COR determines the complaint is invalid, the COR will advise the complainant. The COR will retain the annotated copy of the written complaint for his/her files.
1.9.5.4 If the COR determines the complaint is valid, the COR will inform the
Contracting Officer who will contact the Contractor and give the Contractor additional time to correct the defect, if additional time is available. The Contracting
Officer shall determine how much time is reasonable.
1.9.5.5 The Contracting Officer shall, as a minimum, notify the Contractor by email of any valid complaints.
1.9.5.6 If the Contractor disagrees with the complaint and challenges the validity of the complaint, the Contractor shall notify the Contracting Officer. The Contracting
Officer will review the matter to determine the validity of the complaint.
1.9.5.7 The Contracting Officer will consider complaints as resolved unless notified otherwise by the complainant.
1.9.5.8 Repeat customer complaints are not permitted for any services. If a repeat customer complaint is received for the same deficiency during the service period, the COR will contact the Contracting Officer for appropriate action under the
Inspection clause.
1.9.5.9 If the contractor fails to meet the performance standard, the Government reserves the right to take action under the Inspection clause, including an invoice deduction.
1.10. Configuration
The Contractor shall bring together all subsystems, ensuring that they function together. The Contractor shall configure all components of the solution according to
OEM specifications and industry best practices.
1.11. Testing
The Contractor shall coordinate all testing with the assigned COR. A preliminary testing plan shall be submitted for COR approval at least two (2) weeks prior to the scheduled testing date.
Upon successful installation, configuration and fine-tuning of the entire solution the
Contractor shall perform all necessary system testing to ensure proper operation of the solution. The Contractor shall conduct testing in accordance with the approved
Testing Plan. The Contractor shall include testing results in the Project Completion
Documentation.
If the installed solution, or a portion thereof, fails the testing the Contractor shall correct all deficiencies at no additional cost to the Government.
1.12. Escalation Table and Procedure
Upon written COR acceptance of the completed system, the contractor shall provide the escalation table along with the procedure to open and scale tickets.
1.13. Project Manager
The contractor shall provide a local project manager during all project stages to serve as the main point of contact with COR/SAT. The Project Manager will be tasked with coordinating all activities and resources needed to adequately carry out the project. The Project Manager will be the communication channel between
COR/SAT and the contractor for all matters pertaining to meetings, minutes, planning, and implementation timelines, including progress reports.
Section 2 – Special Conditions
2.1. Type of Contract
The Government intends to award a Firm Fixed Price (FFP) contract payable entirely in US dollars (USD). No additional sums will be payable for any escalation in the cost of performance or because of the Contractor's failure to properly estimate or accurately predict the difficulty of completing this order. The
Government will not adjust the order price due to fluctuations in exchange rates.
2.2. Government Furnished Property (GFP)
The Department of State (DoS) will make the following GFP available for performance of this order: None
2.3. Government Furnished Information (GFI)
The Department of State (DoS) will make the following GFI available for performance of this task order: None
2.4. Taxes and Import Duties
This requirement is a part of technical assistance project registered with the
Government of Guatemala, which is not subject to taxation. USG will provide all necessary project registration documents for vendor to claim tax and import duty exemptions in Guatemala upon request. All requests must be submitted in writing to the COR.
2.5. Required Tagging
Delivery is FOB Destination – Doral, FL
Shipping Address:
Contract No. (provided at time of award) - GUATE
11380 NW 34TH ST
SUVI Global Services
DORAL, FL 33178-1828
UNITED STATES
• Boxes should be marked with numbers “one of xxx”
• Email commercial invoice and packing list to COR
File details come from the government source that posted it. Updated .