SOW - Fire Protection Repairs April 12 Final.pdf

PDF 1 MB Posted

Attached to
Hangar Fire Alarm System
Solicitation number
W50S9J-26-B-A010
Issued by

About this file

This is a Statement of Work (SOW) for fire alarm system replacement at McLaughlin Air National Guard Base in Charleston, West Virginia.

The project involves the design, replacement, and installation of fire alarm and mass notification systems for hangars 407 and 421 at the West Virginia Air National Guard facility located at 1679 Coonskin Drive, Charleston, WV 25311-5000. The contractor must remove all conventional fire alarm system materials (pull stations, detectors, horns, strobes, and wiring) and install a new fully functional addressable fire alarm system in Building 421, while reusing the existing Siemens addressable panel in Building 407 Room 137. All work must comply with NFPA 72 and Unified Facility Criteria (UFC) 3-600-01 and UFC 3-601-02, performed by NICET Level II or higher certified technicians. The contractor must also remove existing mass notification system components and install a new add-on MNS panel to the existing Siemens control panel, meeting UFC 4-021-01 requirements. Critical deliverables include government-approved design documents submitted prior to installation, 100% system testing per NFPA 72 standards with completed Record of Completion Forms, and demonstration of full system functionality including alarm initiation, notification, voice communication, and integration between buildings in the presence of government representatives. The contract period is 90 days from Notice to Proceed, with a job plan required within 5 days of award. The contractor must handle all waste disposal at off-base locations in compliance with federal, state, and local regulations, provide dump receipts, and submit a final cleanup upon project completion. Additional requirements include security compliance with McLaughlin Air National Guard Base policies, personnel background checks, ADLS training registration, base badge acquisition (2-week processing), submission of material submittals with AF Form 3000 within 21 calendar days, and project closeout documents including a one-year warranty on all labor and materials, as-built drawings, and NFPA 72 test reports within 10 days of completion.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Hangar – FIRE ALARM REPLACEMENT

Attachment 1 As of 12 Apr 2026

1. SCOPE: The proposed work on this project consists of repairing by replacement or refurbishment of the fire alarm and mass notification system of hangar 407 & 421 for the West Virginia Air National Guard at McLaughlin ANGB, Charleston WV.

2. LOCATION: McLaughlin Air National Guard Base, West Virginia Air National Guard, 1679 Coonskin Drive, Charleston, West Virginia, 25311-5000.

3. WORK TO BE ACCOMPLISHED: The work to be performed by includes the following principal features:

1) Contractor shall be responsible for the design and construction of the fire alarm and mass notification system. This work must be performed in accordance with NFPA 72, and Unified Facility Criteria (UFC) 3-600-01 and UFC 3-601-02. All design documents shall be submitted for government review and approval prior to installation. Installation shall be performed by NICET Level II or higher technicians certified in Fire Alarm Systems.

2) Contractor shall remove all conventional all fire alarm (FA) system materials to include: pull stations, detectors, horns, strobes and all associated wiring.

Existing conduit is assumed to be sufficient for re-use and shall remain and will be re-used. Contractor shall notify base civil engineer if any conduit is found to be damaged or does not meet code.

3) Contractor shall replace the existing FA system with a new fully functional addressable fire alarm system in building 421. The existing Siemens FA panel in room 137 Building 407 is an addressable panel and shall be reused.

4) Contractor shall remove all existing Mass Notification System (MNS) components to include safe path voice system and associated local operating controls. New Mass Notification System to be an add-on MNS panel to the existing Siemans FA control panel. New MNS system shall meet the requirements of UFC 4-021-01 Mass Notification Systems.

5) Contractor shall ensure the fire alarm control panel in room 178, Building 421 fully communicates with fire alarm control panel in room 137, Building 407/

6) Contractor shall perform 100% system testing in accordance with NFPA 72 acceptance testing and provide record of satisfactory testing of fire alarm system to the 130th Base Civil Engineer, and provide the completed NFPA 72 Record of Completion Forms. Final acceptance is contingent upon successful demonstration of system functionality, including alarm initiation, notification, voice communication (MNS), and integration with Building 407 systems in the presence of Government.

Attachment 1 As of 12 Apr 2026

7) The following pictures are for reference and will be available during site visit.

Figure 1: Building 421 Room 137 FA Panel, MNS Panel and Notification Appliance Circuit(NAC) panels

Figure 2: Building 421 Room 137 FA Panel

Figure 3: Building 421 Annunciator Panel

Figure 4: Building 421 NAC Panels

Figure 5: Building 407 FA panel

Attachment 1 As of 12 Apr 2026

Figure 1

Figure 2

Figure 3

Attachment 1 As of 12 Apr 2026

Figure 4

Attachment 1 As of 12 Apr 2026

Figure 5

A. Special Notes -

1) Daily removal of debris shall be accomplished at the end of each work day. No materials may be left on the work site that may be wind-blown or picked up by passing aircraft.

2) If welding, cutting and burning operations are anticipated in this project.

The Contractor shall contact the Base Fire Department at 341-6220 to receive the Burning and Welding Permit prior to starting any operations that produce a spark or flame such as burning, welding, grinding, cutting or drilling.

B. Waste Disposal and Cleanup

Attachment 1 As of 12 Apr 2026

1) The Contractor shall dispose of all debris or materials at an off-base location in compliance with all State and Federal and local regulatory guidelines. The Contractor shall submit dump receipts or tickets to the Base Civil Engineer at the end of the project.

2) The Contractor is encouraged to recycle all recyclable materials recovered during the demolition process. The Contractor shall provide the BCE with a list of recycled materials. Include the approximate weight and cubic feet of each material recycled.

3) Prior to final acceptance the Contractor shall perform a final cleanup where all debris and waste materials from demolition and construction activities including packaging and/or surplus materials shall be cleaned-up and removed from the Base.

TIME FOR COMPLETION:

a. The Contractor shall submit the job plan for approval by the 130th Civil Engineer Squadron and 130th Fire Department within five (5) days of the notice of award of the contract.

b. The Contractor will be allowed to mobilize and store equipment on the project site during job plan review process.

c. The entire work shall be accomplished within 90 days after date of issuance of the Notice to Proceed.

2) TOUR OF THE JOB SITE: Site visit will be announced in the solicitation on SAM.gov

3) PERFORMANCE:

a. Submission of a bid by a Contractor shall be accepted as prima-facie evidence that he has examined the specifications and has satisfied himself as to the nature and location of the work and all other matters which can in any way effect the work or cost thereof under this contract. Any failure of the Contractor to acquaint himself with all available information, including a physical survey of the site of the proposed work, will not relieve him from successfully performing all the work required for a complete finished job.

b. The above brief outline of principal features of the work in no way limits the responsibility of the Contractor to perform all work and furnish all plant, labor, and

Attachment 1 As of 12 Apr 2026 materials required by the specifications and plans referred to herein.

c. Installation, workmanship, and all materials shall be guaranteed in writing by the Contractor to be free from defect under normal use for a period of at least one year.

All repairs by the Contractor shall be performed at no expense to the Government.

d. Material submittals shall be accomplished in accordance with instructions pertaining to AF Form 3000, “Material Approval Submittal”. Contractor is to submit all shop drawings and material submittals for this contract within 21 calendar days after Notice to Proceed, or as directed by the Contracting Officer, to the Contracting Officer Representative. All submittals shall consist of one completed AF Form 3000 and four copies of material specifications and Material Safety Data Sheets MSDS”.

e. Submittals, Drawings and Specifications shall be reviewed by the COR and approved by the KO prior to install.

f. Contractor is to submit shop drawing in four copies to Base Civil Engineering.

Two copies will be returned to the Contractor indicating approval or disapproval and the date of such action. The Contractor will not proceed with work that is detailed on shop drawings until the drawings are approved.

g. The contractor shall provide all safety equipment and instructions for use by his/her employees, and ensure that a copy is provided to the Contracting Officer Representative prior to commencing work.

g. Safety Data Sheets – A copy shall be submitted with the AF Form 3000 Material Approval Submittal form and the Contractor shall have a copy on display at the job site for all materials brought to and or stored at the job trailer site office or at the site storage location. The Contractor shall ensure that copies have been provided to the Contracting Officer Representative prior to transporting any materials on to the Base.

h. All construction materials and chemical compounds shall be stored in the original container or properly marked containers and approved storage containers supplied by the Contractor. All hazardous or flammable compounds shall be stored in approved lockable storage boxes that shall be locked when not in the Contractors’ or his employee’s direct supervision. All surplus materials and or compounds shall be removed from the Base when work on the project is complete.

4) SECURITY

Attachment 1 As of 12 Apr 2026

a. Contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the COR. CONTRACTOR shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. CONTRACTOR shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

b. CONTRACTOR and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10- 245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

c. Advance Distributed Learning Service (ADLS). All contractor employees and associated sub-contractor employees assigned to work on a government site and/or requiring access to a DoD network will be required to register with ADLS at commencement of services in order to complete the necessary training required of them initially and annually for the duration of the contract (i.e., DoD IAA CyberAwareness, Protecting Sensitive Information, Force Protection, etc.). ADLS website: https://golearn.csd.disa.mil/kc/rso/login/ADLS_login.asp.

d. Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area. Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

e. CONTRACTOR personnel shall comply with McLaughlin Air National Guard Base CONTRACTOR Escort and Security policies per this SOW. Violations of these policies may result in termination of the contract. Compliance with security requirements shall not be a basis for failing to complete work in the required PoP.

f. CONTRACTOR shall obtain base passes/badges for all personnel working onsite prior to arriving at the base. Badging process takes 2 weeks from date badging request is submitted.

CONTRACTOR shall submit 130 SFS Form and a copy of individuals Driver’s License for all personnel working on-base. Contractor shall receive a “Clear” or “Not Clear” from the badging office within 2 weeks of submission.

g. All deliveries shall be screened at the gate but do NOT require badge. Deliveries must be for

Attachment 1 As of 12 Apr 2026 material only and do not include any work/labor.

5) STANDARD PRODUCTS

a. The CONTRACTING OFFICER and COR must approve all material submittals prior to procurement. Materials substitution after submittal approvals shall not be allowed without approval by KO.

b. The CONTRACTING OFFICER and COR must approve all material submittals prior to procurement. Materials substitution after submittal approvals shall not be allowed without approval by KO.

c. CONTRACTOR shall allow for a 2 week turnaround on all RFI, Submittal, Permits, or badging requests to allow for GOVERNMENT review.

d. In the event of conflict among the Specifications, Drawings and/or Technical Instructions, the CONTRACTOR shall bring such conflict to the attention of the CONTRACTING OFFICER immediately for resolution before proceeding with the work involved.

e. Documentation shall be provided for each submittal. As a minimum, the documentation shall include the AF 3000 cover, a catalog sheet of the specific product and the product technical information. When required, a sample of the product/equipment or material must accompany the submission.

f. All chemical materials to be used in this SOW shall be documented on the Transient Organizational Hazardous Material Inventory form. An SDS (Safety Data Sheet) shall be submitted for all chemicals listed.

6) GOVERNMENT FURNISHED EQUIPMENT / PROPERTY

a. The GOVERNMENT shall provide basic/minimal documents describing the work required in this SOW.

b. The GOVERNMENT shall provide the CONTRACTOR access to the site to include all areas of work described in this SOW.

c. The GOVERNMENT shall provide no other equipment, services, or property.

d. CONTRACTOR shall ensure all Government Provided Equipment in work area remain protected, operational, and dust free throughout the project

7) PROJECT CLOSEOUT DOCUMENTS

a. CONTRACTOR shall submit Release of Claims to COR within 10 days of project completion

b. CONTRACTOR shall submit 1 Year Warranty of all labor, materials, programming and system components required to maintain full operational capability to COR within 10 days of project completion.

c. CONTRACTOR shall recover all base passes/badges upon job completion and return to COR within 5 days after project completion.

Attachment 1 As of 12 Apr 2026

d. CONTRACTOR shall submit Shop Drawings, product data (AF Form 3000), As-built drawings( Red Line Drawings), NFPA 72 Record of Completion test reports and warranty letter to COR within 10 days of project completion.