This scope of work document outlines architectural and engineering services required for the demolition of three buildings at the VA Maine Healthcare System campus in Augusta, Maine. The A/E firm will be responsible for design services including site investigations, drawings, specifications, cost estimates and environmental assessments to demolish Building B222, Quarter 33 and Quarter 34. Construction period services will include support during bidding such as responding to requests for information, as well as construction phase oversight including site visits, submittal reviews, record drawing preparation and participation in project closeout. The design is to be completed within 88 calendar days according to the outlined schedule and submittal requirements. Relevant agencies include the VA Contracting Office Network 1 and VA Maine Healthcare System.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF330 RFI Answers.docx | DOCX document | |
| 36C24123R0147_1.docx | DOCX document | |
| Special Notice Request For Qualifications SF330 Updated.docx | DOCX document | |
| 36C24123R0147 0001_1.docx | DOCX document | |
| SOW Attachment 07 - Prevention of Healthcare Associated Legionella Disease.pdf | ||
| SOW Attachment 04 - VHA Required Division 01 Specification Section List.docx | DOCX document | |
| SOW Attachment 03 - PIV Request Form.pdf | ||
| SOW Attachment 06 - Sensitive Infrastructure Data Classification.pdf | ||
| SOW Attachment 05 - Program Guide.docx | DOCX document | |
| SOW Attachment 02 - Seasonal Influenza with Vaccines.pdf | ||
| SOW Attachment 01 - Togus Campus Map.pdf | ||
| Special Notice Request For Qualifications SF330.docx | DOCX document | |
| 36C24123R0147.docx | DOCX document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA Maine Healthcare System (Togus VAMC) 1 VA Center Augusta, ME 04330 06/01/2023
ARCHITECT-ENGINEER DESIGN SCOPE OF WORK
Demolish Building B222, Q33 & Q34
Project Number: 402-23-101 Project Name: Demolish B222, Q33 & Q34 Magnitude of Construction: Between $1,000,000.00 and $5,000,000.00
1. GENERAL INTENT:
The Contractor (herein referred to as “A/E”) shall provide Architect/Engineer (A/E) services to design a construction project at the VA Maine Health Care System (Togus VAMC) in accordance with this design scope of work.
2. STATEMENT OF WORK:
A/E Design Services for this project include site visits, field investigation, studies to prepare drawings, as well as specifications and cost estimates for all facets of work and disciplines/trades to facilitate a construction project to demolish Building B222, Quarter 33, and Quarter 34. Investigative services shall include but not be limited to investigation of any Asbestos Containing Material (ACM); lead paint investigation; investigation of utility locations to be terminated back to their source. AE must include an Environmental Assessment as part of their Scope of Work. Building B222, Quarter 33, and Quarter 34 are currently abandoned buildings. Building 222 was previously the sewage treatment plant for Togus VAMC. A disposal plan for any remaining raw sewage in the building and its systems must be taken into consideration.
A/E Construction Period Services include solicitation support comprised of a pre-bid meeting, responding to construction contractor Requests For Information (RFIs) during the solicitation and review and reconciliation or project estimate. Post award responsibilities include attendance at post-award and commissioning kick off construction project conferences, review of construction material submittals and shop drawings, approximately 4 site visits per month during construction (both scheduled and emergent) to ensure compliance with the design drawings and specifications, preparation of site visit reports, coordination with project commissioning requirements, review of any construction project modifications for cost and technical acceptability, attendance and participation during the final acceptance inspection, preparation of the punch list and preparation of record drawings of the completed construction project based on the construction contractor’s as-built drawings. The A/E shall prepare a submittal log to be utilized by the VA during construction period services, maintain RFI log and provide meeting minutes for weekly construction meetings throughout the duration of construction.
The above paragraphs constitute a basic outline of the work to be accomplished and in no way comprises all the details for design of this project. The A/E shall initiate detailed inspection of the project site to determine the needs and conditions for the design of this project. Copies of VA Maine Health Care System (Togus VAMC) record drawings will be made available to the highest rated A/E firm; the A/E will verify the validity of the record drawings prior to the start of design work and conduct site investigations as necessary throughout the design. SOW Attachment 01 – Togus Campus Map will give AE firm a basic understanding of the Togus VAMC.
The A/E shall be solely responsible for the management, including all associated labor, equipment, materials, mailing costs, and inspection, to meet the requirements of the design project. The A/E shall further provide meeting minutes for all meetings held under this design project.
The A/E firms’ representatives performing site investigations on Togus VAMC campus must have the following additional requirements before starting site investigations on campus:
| 1. Influenza and TB | |
| - Requirements follow national VA guidelines for vaccination and testing. | |
| - TB testing required. | |
| - SOW Attachment 02 – Seasonal Influenzas with Vaccines |
- All contractor employees to visit VA checkpoint daily to complete required screening. VA COR to provide locations upon award, as these are subject to change.
2. Badging
- All contractors are required to obtain a VA issued badge prior to starting any work on station.
- Badging form (SOW Attachment 03 – PIV Request Form) and directions for procuring one will be provided by the COR at the project kick-off meeting.
3. DESIGN WITHIN FUNDING LIMITATIONS:
The design shall be prepared by the A/E to permit the award of a construction contract, using Federal Acquisition Regulation procedures for the construction of the facilities, at a cost that does not exceed the project’s estimated Magnitude of Construction range between $1,000,000.00 and $5,000,000.00.
4. DESIGN INDEPENDENCE, FURNITURE AND EQUIPMENT:
Designs for construction must produce a “complete and usable” facility or improvement when constructed. VA policy (VHA Office of Capital Assets Management, Engineering and Support memo Updated Construction Guidance and Expectations dated Sep 12, 2016) requires the A/E to certify that their design (including all bid alternates/bid deducts) is independent of any future construction project. In addition, the A/E must certify that it has produced a design that does not include furniture and equipment that will be procured separately. Equipment that can be part of the design in the includes those items to meet code requirements for building occupancy, items covered in the VA’s Master Construction Specifications (PG-18-1) Divisions 1 through 10, 13 through 26 or 28 through 48, non-IT equipment items covered by Division 27 and items covered by Division Numbers 12 31 00, 12 32 00, 12 34 00 and 12 36 00.
The A/E shall submit as part of the Final Bid Documents submittal a signed letter on company letterhead stating the design’s independence.
5. DESIGN CRITERIA:
The VA Technical Information Library (TIL) available at http://www.cfm.va.gov/til/index.asp is managed by the VA Office of Construction and Facility Management and is the master repository for all VA Numbered Standards for Construction to include design and construction specifications, procedures, standard details, BIM/CAD standards, equipment guides, space planning and design guides. The documents of the TIL shall be the minimum design criteria for all VA projects performed in the construction of new facilities and the modernization, alteration, addition, or improvement of its real property. All design documents shall be developed in accordance with the VA TIL, including (but not limited to) the following listed Department of Veterans Affairs References:
| PG-18-1 |
| Master Construction Specifications |
| SOW Attachment 04 |
| VHA Required Division 01 Specification Section List |
| PG-18-3 |
| Design and Construction Procedures [Including but not limited to: Codes, Standards, and Executive Orders] |
| PG-18-4 |
| Standard Details and CAD Standards |
| PG-18-5 |
| Equipment Guide List |
| H-18-8 |
| Seismic Design Handbook |
| PG-18-9 |
| Space Planning Criteria |
| PG-18-10 |
| Design Manuals (by discipline) [Including but not limited to: Guiding Principles checklists as indicated for Minor Projects in Sustainable Design Manual, Life Cycle Cost Analysis] |
| PG-18-12 |
| Design Guides (graphical, by function) |
| PG-18-13 |
| Barrier Free Design Guides |
| PG-18-14 |
| Room Finishes, Door, and Hardware Schedules |
| PG-18-15 |
| Minimum Requirements for A/E Submissions |
| PG-18-17 |
| Environmental Compliance Manual |
| H-7545 |
| VA Cultural Resource Management Procedures |
Where conflicts exist between VA adopted codes and standards and the documents on the TIL, the A/E shall bring this to the attention of the VA. The resolution of the conflict shall be made by the authority having jurisdiction for VA to ensure consistency department wide.
6. DESIGN COLLABORATION:
The A/E during this design project shall collaborate with the VHA Office of Healthcare Environment and Facilities Programs Special Engineering Program (HEFP/SEP) staff, VISN 1 and the Independent Life Safety Review Agent (LS Agent) for the project. Design submittal comments from these contractors, if concurred with by VA, shall be incorporated into the design. HEPF/SEP and/or VISN deliverables shall be coordinated with the A/E’s design submittals to ensure compliance with all requirements are met. The A/E is required to ensure all elements of the design adhere to the Life Safety Code, including recommendations for temporary construction barriers, prior to the Independent Life Safety review.
7. INDEPENDENT LIFE SAFETY REVIEW:
The A/E shall incorporate any comments from the VA 3rd party life safety review.
8. ENVIRONMENTAL PROTECTION:
The A/E shall assist the VA with completion of a National Environmental Policy Act (NEPA) assessment as required by the VA Maine Health Care System (Togus VAMC). If the NEPA assessment results in potential environmental impacts, the A/E shall be responsible for completing any auxiliary documentation required per PG-18-17 NEPA Interim Guidance for Projects located on the TIL (http://www.cfm.va.gov/til/etc/NEPAGuidance.pdf). Additional requirements may include, but are not limited to, Environmental Assessment, Environmental Impact Statement, and Record of Decision. The NEPA analysis and concluding documentation must be completed by the Final Bid Documents submittal.
9. SUBMITTAL REQUIREMENTS:
Design submittals shall follow the requirements of Program Guide, PG-18-15, Volume C - A/E Submission Instructions for Minor and NRM Construction Program dated November 2008. This document is included as SOW Attachment 05 – Program Guide. Submittal documents shall be prominently marked “For Official Use Only (FOUO)” if they contain qualifying data as defined in VHA Memorandum 2019-11-13 Sensitive Infrastructure Data Classification – For Official Use Only (FOUO). This memo is included as SOW Attachment 06 – Sensitive Infrastructure Data Classification, as it is hosted on a non-public VHA site (https://vaww.va.gov/vhapublications/ViewPublication.asp?pub_ID=8949).
The A/E shall deliver design submittal documents that follow the iterative phase breakdown for design work in PG-18-15 and as additionally specified below. Specific requirements for each discipline/work product listed under each phase can be found in PG-18-15; it is expected for the phase of design that each of the checked items in the SD/DD/CD columns will be completed for the submittal. The A/E shall attend a review meeting following each design submittal as indicated under the Project Schedule section of this Scope of Work. Each new submittal will incorporate all VA comments from the previous submittal. The Asbestos Abatement requirements in PG-18-15 are applicable at VA Maine Health Care System Togus ME due to the age of the campus.
The following submittals will be required for this project:
· Quality Assurance/Quality Control (QA/QC) Plan
· Basis of Design (BD) - 10% - In addition to the requirements in PG-18-15, a Basis of Design is required. Basis of Design is a narrative presentation of facts, sufficiently complete, to demonstrate that the project concept is fully understood, and that subsequent design details, and their ultimate presentation in the final drawings and specifications, will be based on sound architectural and engineering decisions. Conceptual drawings of the planned design and the initial cost estimate will additionally be included.
· Schematic Design (SD)- 35%
· Design Development One (DD) – 65%
· Construction Documents (CD)- 95%
· Final Bid Documents (Bid) – 100%
10. SUBMITTAL FORMATS:
Submittals shall be submitted in electronic format and hard copy formats as listed below. Portable Document Format (.pdf), Microsoft Office Suite formats (.doc, .xls, and .ppt), Microsoft Project (.mpp) and Autodesk Revit Project (.rvt) files are acceptable. Submittals shall additionally be compliant with Section 508 of the Rehabilitation Act (29 U.S.C. '794 d); information on the requirements for accessible media can be found at http://www.section508.gov/. The A/E shall be responsible for providing:
Meeting/Conference Minutes Meeting minutes for all formal meetings and conferences held with the VA; including weekly construction meetings. Meeting minutes shall be submitted within seven (7) calendar days of the meeting or conference. All documents in any of the electronic formats listed above.
IF APPLICABLE
Minimum meeting minutes requirements
· Project name, number, meeting host, Meeting Name
· Date, Time, meeting ID, call in number, Duration, and consecutive number of total related meetings
· Participant list (Name, Title, Phone number (office and Mobile), Email, Attended Meeting (yes/no Check box)
· Meeting purpose, Roll call, COVID-19, and Additional Items
· Agenda items (Decisions, action items, and fixes or next steps)
· Next meeting date and time
· Detailed attachment list
Construction Cost Estimates Construction cost estimates shall comply with Manual for Preparation of Cost Estimates & Related Documents for VA Facilities dated March 8, 2011. This document is available on the TIL at http://www.cfm.va.gov/cost/index.asp. All estimates in any of the electronic formats listed above.
Quality Assurance/Quality Control (QA/QC) Plan
· All documents in any of the electronic formats listed above.
Basis of Design (BD)
· All documents in any of the electronic formats listed above.
· Two (2) half-size paper bond sets of drawings – 2 to VA
Schematic Design (SD)
· All documents in any of the electronic formats listed above.
· Two (2) half-size paper bond sets of drawings – 2 to VA
· Two (2) paper bond sets of specifications – 2 to VA
· Two (2) paper bond sets of investigation reports, design calculations, space planning data and cost estimate - 2 to VA
Design Development (DD), and Construction Documents (CD)
· All documents in any of the electronic formats listed above.
· Memo annotating what was not upgraded and corresponding justifications.
· One (1) full size paper bond sets of drawings - 1 to VA
· Two (2) half-size paper bond sets of drawings – 2 to VA
· Two (2) paper bond sets of specifications – 2 to VA
· Two (2) paper bond sets of investigation reports, design calculations, space planning data, construction schedule, construction statement of work (SOW) and cost estimate - 2 to VA
Final Bid Documents (Bid)
· PDF files of drawings, specifications, and any miscellaneous design analysis documents such as submittal log and physical security compliance report.
· Certified memo annotating what areas/times were not upgraded and the corresponding justifications.
· Certified memo that the A/E design is independent of future projects and includes all equipment required for the project to be activated/full functional.
· Word files of specifications.
· Revit and AutoCAD files of drawings.
· One (1) full size paper bond sets of drawings - 1 to VA
· Two (2) half-size paper bond sets of drawings – 2 to VA
· Two (2) paper bond sets of specifications – 2 to VA
· One (1) paper bond sets of investigation reports, design calculations, space planning data, construction schedule, construction SOW and cost estimate - 1 to VA
Construction Period Services (CPS)
Requests for Information (RFI) Requests for Information shall be submitted within three (7) calendar days of submittal to the A/E.
Submittal Reviews Submittal reviews shall be submitted within seven (7) calendar days of submittal to the A/E.
Site Visit Reports Site visit reports shall be submitted within seven (7) calendar days of the visit. All documents in any of the electronic formats listed above.
Modification/Change Order Requests Modification requests shall be submitted within seven (7) calendar days of submittal to the A/E. This includes the review of the contractor’s change order/modification proposal for construction change orders, as well as the formulation of an IGCE for the modification, as requested. The A/E's reply regarding his/her review of cost proposals and his/her recommendations shall include an independent breakdown of costs in detail, quantities, and unit prices and shall cover both additions and deductions of labor, materials, and equipment. The A/E shall also supply cost estimates as requested by the COR for Request for Proposals for anticipated changes.” All documents in any of the electronic formats listed above. Note - If major modification, VA will provide additional time and document format guidance.
Punch List Punch list shall be submitted within seven (7) calendar days of the final acceptance inspection. All documents in any of the electronic formats listed above.
Record Drawings Record drawings shall be delivered to the VA within thirty (30) calendar days after VA acceptance of the construction project. Autodesk Revit Project (.rvt) format and AutoCAD (.dwg) format.
CPS Project Meetings The Architect-Engineering firm shall attend at least 50% or every other construction project meeting.
11. PROJECT SCHEDULE/PERIOD OF PERFORMANCE:
The A/E shall perform Part One Services/Design Phase work according to the schedule shown below. If a due date on the timeline below falls on a Holiday or Weekend, the submittal shall be due the following business day. The remaining timeline will not be shifted to accommodate Holidays or Weekends.
| Administrative Time |
| 07 calendar days after receipt of Notice of Award |
| QA/QC Submittal & Basis of Design (BD) 10% Submittal |
| 10 calendar days after end of Administrative Time |
| QA/QC and BD 10% Submittal Review Meeting |
| 07 calendar days after VA receipt of QA/QC & BD 10% Submittals |
| 35% SD Submittal |
| 10 calendar days after acceptance of QA/QC & BD 10% Submittals |
| 35% SD Review Meeting |
| 07 calendar days after VA receipt of 35% SD Submittal |
| 65% DD Submittal |
| 10 calendar days after VA acceptance of 35% SD Submittal |
| 65% DD Review Meeting |
| 07 calendar days after VA receipt of 65% DD Submittal |
| 95% CD Submittal |
| 10 calendar days after VA acceptance of 65% DD Submittal |
| 95% CD Review Meeting |
| 07 calendar days after VA receipt of 95% CD Submittal |
| Final Bid Documents Submittal |
| 10 calendar days after VA acceptance of 95% CD Submittal |
| Final Bid Documents Acceptance Meeting |
| 10 calendar days after VA receipt of Final Bid Documents Submittal |
| Total Part One Services/Design Phase Schedule |
| 88 calendar days |
12. CONTRACT OVERSIGHT:
All contracts for this project shall be awarded by the NCO1; only a warranted VA Contracting Officer shall have authority to change the terms and conditions of a contract. These changes may involve the contract award amount, contract period of performance, issuance of stop work orders and changes to the statement of work.
NCO1 shall designate a Contracting Officer’s Representative (COR) to monitor and manage the A/E’s performance under the design project contract. The COR shall be a representative of the Togus VAMC’s Facilities Management and have the technical knowledge required to monitor and oversee the project.
A COR from the Togus VAMC shall also be designated for the construction project contract to monitor and manage the construction contractor’s performance under the construction project contract. This designation under the construction contract shall be considered equivalent to the industry standard of “Owner’s Representative” and does not supersede or eliminate the A/E’s responsibility for Part Two Services/Construction Period Services. The A/E ultimately shall be responsible for any errors and omissions with the design discovered during and after the construction phase.
13. Attachments:
The following list of documents are attached to this SOW for A/E use and incorporation into the project documents:
· SOW Attachment 01 – Togus Campus Map
· SOW Attachment 02 – Seasonal Influenza with Vaccines
· SOW Attachment 03 – PIV Request Form
· SOW Attachment 04 – VHA Required Division 01 Specification Section List
· SOW Attachment 05 – Program Guide
· SOW Attachment 06 – Sensitive Infrastructure Data Classification
· SOW Attachment 07 – Prevention of Healthcare Associated Legionella Disease
End of SOW