SOW Chiller Unit_Updated.docx

DOCX document 79 KB Posted

Attached to
Chill Water System Rental
Solicitation number
N4215826R0001
Issued by

About this file

This Statement of Work (SOW) details a solicitation for renting a complete chill water system for Norfolk Naval Shipyard. The system must consist of two 30-ton chillers and one 60-ton chiller capable of supporting cooling capacity from 30 to 120 tons, with specific technical requirements including air-cooled units, a pumping system capable of 30-500 GPM, and water temperature range of 55-65°F. The rental is for a base period of 12 months with two additional option periods (12 months and 6 months).

Key contractor requirements include delivering and setting up the equipment at no additional cost to the government, performing preventative maintenance, providing 24/7 service response within 4-8 hours, and ensuring equipment meets detailed specifications such as electrical compatibility, environmental durability, and specific connection and monitoring capabilities. The solicitation is competitive and will be awarded on a Lowest Price Technically Acceptable (LPTA) basis. Quotes are due by 12:00 PM EST on 24 October 2025, with questions to be submitted by 12:00 PM EST on 17 October 2025 to specified Navy contracting personnel.

View the file

Other files

File Type Posted
Solicitation Notice ID N4215826R0001 Bidder Questions and Response.pdf PDF
Addendum to 52.212-1_Updated 2.docx DOCX document
SF 1449 - N4215826R0001.pdf PDF
Addendum to 52.212-1_Updated.docx DOCX document
SF 1449 - N4215826R0001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Scope:

1.1. Title: Chill Water System Rental Specifications

1.2. Purpose of Request: Service/Rental from vendor to provide Rental Chill Water System Capable of meeting the specifications outlined below.

1.3. Location of work:

1.3.1. Norfolk Naval Shipyard (NNSY), Portsmouth, VA 23709

2. General Specifications:

2.1. Design must be electrically powered, capable of starting and operating on a single 460/480V, 400-amp (maximum) circuit breaker. Male 500 mcm Camlock end connections are required.

2.2. Chiller Unit(s) must be capable of operating in an industrial environment where dust, dirt and sea air are present. The Chiller Unit(s) will be exposed to everyday weather. It is the contractor’s responsibility to provide any protective coverings for the units as necessary.

2.3. New or used equipment may be provided. NNSY reserves the right to inspect the proposed equipment prior to contract award.

3. Equipment Requirements:

3.1. Only Fresh Water will be circulated through the cooling system described below and depicted in Figure (1).

3.2. Chill Water System must consist of three chillers. System must be able to support varying capacity from 30 to 120 tons of cooling capacity. System shall consist of two 30-ton Chillers and one 60 Ton Chiller.

3.3. System shall be able to allow isolation of each chiller unit separately to support varying chill water loads shipboard.

3.4. Chiller units must be air cooled.

3.5. Must have a pumping system, consisting of at least two pumps. System must be able to provide a variable supply of 30 to 500 GPM. Each pumping apparatus must be capable of maintaining 250 feet of head supply pressure, at all GPM Ranges, at the contractor provided supply manifold. At a minimum, the pumping system shall have at least 100 GPM at 100 feet of head pressure of redundant capacity. The expansion tank shall supply water directly to the pumps as shown in Figure (1). Additional pumps downstream of the chiller unit(s) may be utilized to raise supply pressure to meet the required 250 feet of head pressure requirement at the contractor provided supply manifold.

3.6. Must have suction and discharge manifolds with a quantity of ten (10) 2-1/2” MNPT supply connection and a quantity of ten (10) 2-1/2” MNPT discharge connections. All manifold connections shall have isolation globe valves installed.

3.7. Within the cooling loop there must be a reservoir capable of holding at least 250 gallons of cooling water or as required to support system design. Reservoir is required to account for small leaks. Reservoir must be transparent in order to visibly verify the water level within the tank. Tank shall have a constant vent on top of the tank or shall be open to the atmosphere to aid in bleeding air out of the chill water system.

3.8. System shall include a bypass line in order to flow water when no services are connected to the contractor provided supply and discharge manifolds. This bypass line shall include globe valves so the flow can be throttled as required to suit the Ship’s demands and to keep the chiller units running under low flow/pressure conditions.

3.9. Desired output water temperature range is 55⁰F - 65⁰F.

3.10. Chill Water System must have necessary equipment to prevent freezing recirculating water with no cooling load at 0⁰F.

3.11. CRITICAL SYSTEM SUPPORT: Unit must be capable of operating 24 Hours a day Seven (7) Days a Week.

3.12. Chiller System must be operable at flow rates of as little as 30 GPM without needing to recirculate flow.

3.13. Contractor shall provide all equipment from the return manifold to the supply manifold. If pumps or tanks are separate from the Chiller Unit, the contractor is responsible for providing all piping, valves and/or fittings as required to couple pumps/tanks to the Chill Water Units. Vendor is to provide Extra fittings and hoses to support installation. If the system requires assembly, the assembly shall be accomplished in such a way that it minimizes or eliminates tripping hazards by minimizing the lengths of hoses between components. If length of hoses are longer than necessary, the hose should be able to be coiled and located somewhere out of the way of normal foot traffic. Hoses shall be routed in a way that does not cause the hoses to kink and/or reduce flow rates.

3.14. Contractor provided hoses and manifolds shall have insulation installed around them to reduce temperature losses in the chilled water and to reduce the amount of condensation buildup on the outside of the hoses.

3.15. Chiller Unit(s) must be equipped with operational Inlet and Outlet Temperature Gages.

3.16. Chiller Unit(s) must be equipped with operational Inlet and Outlet Pressure Gages. Pressure gages are to be installed on the contractor provided supply and return manifolds.

3.17. Unit shall have an electronic monitoring system capable of monitoring and displaying flow rate of the chilled water through the system.

3.18. If Chiller Unit(s) hold 55 gallons or more of fuel, oil or similar fluid, provide an environmental catch capable of holding at least 110% of the capacity of the fuel, oil and other fluids required to operate the rental unit.

3.19. Evaporator must be capable of delivering a leaving temperature of less than 55⁰F.

3.20. Condenser must be capable of operating in a wide ambient temperature range (0-125⁰F).

3.21. Chiller Unit(s) must be affixed with a metal tag designating the supplying company, a POC responsible for repairs and maintenance, and a phone number of the POC who is responsible for repairs and maintenance.

3.22. Contractor is to adhere to the rigging requirements as outlined in Attachment “A” for contractor equipment at Norfolk Naval Shipyard. Contractor provided equipment to have padeyes for crane movement.

3.23. The gross weight of the unit must be clearly marked on the outside of the unit as outlined in Attachment “A”. If the Chiller Assembly is not a complete unit, the gross weight of each component shall be clearly marked on each component.

3.24. Unit must be free standing and have forklift slots or is capable of being moved with a forklift.

3.25. Contractor must provide instruction manual and training as requested by NNSY.

Figure (1) – Line Diagram of Proposed System Note 1: Final system may consist of different quantities of Chillers and Pump(s) than shown in Figure (1) as long as the requirements above are met.

Note 2: Final system may change the order of components as long as the requirements above are met.

Note 3: Freeze protection methods are not shown in Figure (1). A Freeze Protection method shall be included for the system in the event there is no cooling load on the system.

Note 4: Figure does not represent the correct amount of supply and return manifold connections. See Paragraph 3.6 for the required amount of connections.

4. Period of Performance:

4.1. As listed in Section F- Deliveries or Performance for Period of Performance information in SF1449.

4.2. The government reserves the right to return one or all units at any time prior to the expiration of the rental period. The contractor agrees to prorate costs for the time the units are in use by NNSY only. The government agrees to give the contractor twenty-four (24) hours’ notice for return of units prior to expiration of the rental period.

5. Contractor Requirements:

Vendor certifies that vendor’s service meets or exceeds all specifications and contractor responsibilities stated in this solicitation, in their entirety, with no exceptions. Vendor is to provide a “Technical Submission Doc” outlining how the requirements listed herein will be met.

5.1. Equipment delivery, set up and removal is to be at no cost to the government. The Government will not pay additional delivery/removal fees after award. Units are to be delivered to Drydock 4 at Norfolk Naval shipyard. Final placement is to be determined and specified by the Temporary Service Zone Manager (TSZM) at during delivery of the units.

5.1.1. If the unit requires assembly, the contractor shall assemble the unit at no cost to the government.

5.2. Upon arrival to NNSY for Rental Chiller delivery, the contractor shall contact the Temporary Service Zone Manager (TSZM) for information regarding Chiller System placement on the job site.

5.3. Provide all parts requiring repair or replacement under circumstances of normal equipment wear and tear at no additional charge.

5.3.1. If the use of a transformer to step up voltage/protect contractor supplied Chiller Unit(s) and or components is desired it must be provided by the contractor at no additional cost.

5.4. Contractor is responsible for ensuring that all preventative maintenance is performed on equipment prior to delivery to the government as well as performing preventative maintenance as specified by the equipment’s manufacturer preventative maintenance schedule during the term of the rental period with the government. Contractor is responsible for all travel to associated with preventative maintenance. Contractor is responsible for providing service technicians that are able to meet the badging and security requirements of Norfolk Naval Shipyard.

5.4.1. Contractor shall provide a monthly report to the COR on preventative maintenance performed.

5.5. Post contact information for service/repair of equipment directly on the rental equipment. Contact information must be packaged to withstand being located in an outdoor environment.

5.6. The contractor shall dispatch a representative in response to a service request to perform any necessary repairs within four (4) hours of notification by NNSY at no additional charge, regardless if the request is placed during normal business hours. The contractor shall dispatch a representative in response to a service request to replace any rental Chiller Unit or components within eight (8) hours of notification by NNSY at no additional charge, regardless if the request is placed during normal business hours. Contractor is responsible for providing service technicians that are able to meet the badging and security requirements of Norfolk Naval Shipyard/NOB. NNSY Project Team has the authority to swap units if deemed necessary due to shipboard conditions.

5.7. Contractor personnel shall contact the Temporary Service Zone Manager (TSZM) for authorization prior to any work or maintenance on rental unit.

5.8. Contractor will not operate equipment without direct authorization from the Temporary Service Zone Manager (TSZM).

5.9. Contractor shall provide service technicians, upon request from the government, to assist with chiller operation and chill water system balancing at no additional charge.

5.10. “Per FAR 22.102-1(a) entitled ‘Safety’, Contractors are hereby informed that their employees or representatives present on property under Norfolk Naval Shipyard cognizance must follow Federal and State OSHA requirements and Norfolk Naval Shipyard OSHE Program Manual, NAVSHIPYDNORINST P5090.2 requirements for site specific location of the contract.

5.10.1. Contractors and Non-NNSY Government Agencies (NNGAs) are hereby informed that their employees or representatives present on property under Norfolk Naval Shipyard (NNSY) cognizance must adhere to Federal OSHA requirements for Hazardous Energy Control IAW 29 CFR 1915.89 and must follow Hazardous Energy Control (HEC) procedures as identified in NAVSEA’s Occupational Safety, Health, and Environment Corporate Manual (OSHECM) Chapter 250 (latest revision), when performing work under NNSY contract. All HEC work to be performed by Contractors and NNGAs requires that NNSY Technical Points of Contact (TPOCs) and/or Contracting Officer’s Representatives (CORs) be notified of the HEC scope of work prior to starting work. Any changes or deviations in the initial scope of HEC work requires the NNSY TPOCs and/or CORs be informed of the change/deviation. Appendix 250.B-1 through B-3 of OSHECM Chapter 250 for multiple employer work identifies when Contractors and NNGAs are required to assign their Lockout/Tags-Plus Coordinator (LOTC) to coordinate HEC work with the cognizant NNSY LOTC. HEC locks shall be provided by the contractor or NNGA for their employees use. The HEC locks shall have red bodies with name labels or name tags affixed, identifying who installed the HEC lock(s) and a point of contact telephone number. HEC lock name labels and tags must be made of materials that will hold up to the environment to which they are exposed. HEC tags used for Tags-Plus HEC work shall be provided by the cognizant NNSY LOTC to the contractor or NNGA for their use of machinery, equipment, or systems (MES) cannot be locked out. OSHECM Chapter 250 Tags-Plus procedures will be strictly followed.

5.10.2. Contractors and NNGA’s may obtain electronic copies of OSHECM Chapter 250 (latest revision) and access the OSHA 1915.89 web site by using the following link to NNSY’s public access web site: http://www.navsea.navy.mil/shipyards/norfolk/default.aspx

5.10.3. Names and contact information for NNSY LOTCs and/or the Facility Custodian will be provided by NNSY TPOC and/or CORs set for the elsewhere in this award document.”

5.11. When the equipment is required to be removed to the contractor’s facility for repair or replacement, the contractor shall be responsible for loss or damage from the time it leaves the government site until it is returned to the government.

5.12. Provide start up training of equipment to the government. Contractor is responsible for all travel associated with providing startup training of equipment to the government.

5.13. Contractor shall provide technical information for all mechanical equipment provided to satisfy the requirements of the contract. This includes model/unit technical specifications, user manuals, fault code descriptions, etc. Copies of these documents shall be provided to the lead shop zone manager and to engineering (Code 269) upon completion of system set-up. Further copies in the future shall be provided, if needed, at no additional cost to the government.

5.14. Clean the chiller unit(s) prior to delivery to the following requirements:

5.14.1. Chiller Unit(s) shall be cleaned to a degree of cleanliness that results in a surface free of grease, oil, flux, scale, dirt, loose particles and any other matter foreign to the base metal. Adherent, light, superficial rust on steel surfaces, caused by short time exposure to the atmosphere, is acceptable.

5.14.2. For uncoated surfaces: Adherent corrosion products typical on surfaces of the type material being considered (e.g. flash rust on steel) are acceptable. Loose corrosion products are not acceptable and must be removed.

6. Government Responsibility:

6.1. Temporary Service Zone Manager (TSZM) and Technical POCs will inspect equipment upon delivery to ensure equipment requirements are met.

6.2. Provide operators for equipment.

6.3. Perform basic monitoring/visual checks and minor adjustments to provided equipment as required.

6.4. Equipment movements within Norfolk Naval Shipyard.

6.5. Lost items and equipment damage beyond normal wear and tear that is caused by the Government.

7. Points of Contact:

7.1. TBA

STATEMENT OF WORK (SOW)

Chiller Unit Rental

Requirements for Lifting of Equipment:

1. The equipment shall be outfitted with suitable attachments for overhead lifting.

2. For multiple point lifts each lifting attachment shall be capable of supporting one half the gross weight of the equipment with a design factor of five to one based on ultimate strength. For single point lifts the lifting attachment shall be capable of supporting the gross weight of the equipment with a design factor of five to one based on ultimate strength.

3. For multiple point lifts, each lifting attachment shall be designed to accept a standard anchor shackle (Federal Specification RR-C-271D, type IVA) which is capable of supporting one half the gross weight of the equipment. For single point lifts, the lifting attachment shall be designed to accept a standard anchor shackle (Federal Specification RR-C-271D, type IVA) which is capable of supporting the gross weight of the equipment.

4. Design of the lifting attachments shall be such that the attachments and shackles are not side loaded more than 10° out of the plane. Lifting attachments shall be located such that the lifting slings do not contact the equipment, or alternatively a spreader beam certified to NAVFAC P-307 shall be provided. Whenever practical, the lifting attachments shall be located above the center of gravity, and such that the lifting slings do not contact the equipment housing.

5. Each lifting attachment shall be conspicuously marked in a contrasting color “Lift Here.” Letters shall have a minimum height of 1”.

6. The equipment shall be marked in a prominent location with the gross weight. Sand hoppers, tubs, or other containers that may contain material shall be marked with the empty and full weight (or alternatively the empty weight and working load limit). Marking shall be upper case letters of a contrasting color, with a minimum height of 1”. Marking shall include the units (i.e. “pounds”, “long tons”, etc.).

7. The equipment shall be provided with a lifting sketch / rigging diagram that meets the requirements as outlined below:

The lifting sketch shall detail any specific requirements and / or configurations that must be met prior to lifting (i.e. “engage swing lock”, “Tilt mast back fully”, “Rotate lifting basket over side”, “Utilize 10’ minimum length slings”, “Spreader beam required”, etc.).

8. The lifting sketch shall include the location of the center of gravity of the equipment (full fuel, hydraulic tanks, etc.), equipment model/manufacturer, and gross weight.

9. A copy of the lifting sketch shall be permanently posted on the equipment, and a copy of all lifting sketches shall be forwarded point of contact (TBA) for approval.

10. If specialized handling gear other than shackles, standard slings, or chainfalls (i.e. spreader beams, special lift rigs, etc.) is required, the contractor shall furnish it. This handling gear shall be provided verified in accordance with NAVFAC P-307, with written documentation of proof testing.

1.

Attachment A Rigging Sketch Requirements:

1. Rigging sketches, at a minimum, shall identify the following:

1.1. The weight of the load.

1.2. The location of the center of gravity.

1.3. The minimum crane capacity.

1.4. The minimum capacity / length of slings.

1.5. The minimum capacity of other standard rigging gear.

1.6. The attachment (lifting) points for the load.

1.6.1. The attachment points for multiple leg lifts shall be sized such that each attachment point can support half the load’s weight at the anticipated lift angle.

1.6.2. The attachment point for single leg lifts shall be sized such that the attachment point can support the entire load’s weight.

1.7. Limitations on allowable orientations for any parts making up the lifting assembly.

1.8. For single leg vertical lifts using twisted rope (wire or synthetic), two parallel ropes each capable of supporting the entire load alone shall be required unless a method is used to prevent unlaying the rope.

1.9. A minimum D/d ratio of one (1) shall be required where wire rope slings pass over any object, or in the eyes of wire rope slings. A minimum D/d ratio of two (2) shall be required where synthetic rope slings pass over any object, or in the eyes of synthetic rope slings.

1.9.1. “D” represents the diameter of the object the sling passes over.

1.9.2. “d” represents the diameter of the sling.

1.9.3. Table 14-2 of NAVFAC P-307 lists efficiency factors at various D/d ratios.

1.10. Components in each handling assembly shall be sized based on the worst case distribution of loads.

1.10.1. When making a two, three or four point lift, the handling gear shall be sized so that two legs can support the load without exceeding the safe working load (SWL) at the lift angle expected, unless an equalizing method is used.

1.11. When non-standard gear is required (i.e. round stock lifting bars), written instructions shall be provided that ensure:

1.11.1. The proper material is being used.

1.11.2. The item is certified IAW NAVFAC P-307.

1.11.3. Any special requirements or dimensions are followed to ensure that engineering assumptions are met (i.e. eccentricity of the bearing points).

Attachment A

ADDITIONAL DETAILS:

After Hours Base Access – Contractors are to go to Gate 15 and let the guards know they are to provide services/support via a contract. It would be helpful to have a copy of the contract and contract number. The guards at the gate will then call the Base Precinct and subsequently be escorted to Bldg. 1618 to have a badge made.

DBIDS:

1.1. Identification Badges and Installation Access.

· Any new contractor, vendor or supplier requesting base access AFTER 31 May 2017 will be required to obtain a DBIDS credential. NCACS credentials will no longer be issued.

· Only DBIDS credentials will be issued to ALL contractors, vendors and suppliers seeking base access AFTER 14 August 2017.

· Defense Biometric Identification System (DBIDS) increases installation security and communications by receiving frequent database updates on changes to personal/credential status, law enforcement warrants, lost/stolen cards, and force protection conditions. The system provides a continuous vetting anytime the DBIDS card is scanned at an installation entry point.

· If you currently have a Navy Commercial Access Control System (NCACS) card, the following is required to get a DBIDS credential:

· Present your NCACS Card and a completed copy of the SECNAV FORM 5512/1 to the base Visitor Control Center representative.

· The VCC will pull up your information in the computer, ensuring all information is current and correct.

· Once your information is validated, a temporary DBIDS credential is provided.

· Your temporary credential will have an expiration date, prior to which you will need to obtain your permanent DBIDS credential (~90 Days).

· For each additional U.S. Navy installation to which you need access, the first time you visit you only need to bring your DBIDS credential and statement of purposed for base access when arriving at the Visitor Control Center.

· The representative will enter base access authorization and then you may proceed to work.

· If you do NOT have an NCACS Card, the following is required to obtain a DBIDS credential:

· Present a letter or official document from your government sponsoring organization that provides the purpose for your access.

· Present valid identification, such as a passport or Real ID Act-compliant state driver’s license.

· Present a completed copy of the SECNAV 5512/1 form to obtain your background check.

· Upon completion of the background check, the Visitor Control Center representative will complete the DBIDS enrollment process, which includes your photo, fingerprints, base restrictions, and several other assessments; after all this is done, you will be provided with your new DBIDS credential.

· You may now proceed to work.

Attachment B FOR ADDITIONAL QUESTIONS ABOUT OBTAINING A DBIDS CARD, CONTACT YOUR LOCAL BASE VISITOR CONTROL CENTER INFORMATION IS ALSO PROVIDED AT:

www.cnic.navy.mil/om/dbids.html

1.2. One-Day Passes. Participation in the DBIDS is not mandatory, and if the Contractor chooses to not participate, the Contractor’s personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government will not be responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.

PORTABLE ELECTRONIC DEVICES (PEDs):

In accordance with COMSUBLANT/COMSUBPACINST 2075.1C, the use of Portable Electronic Devices (PEDs) while in or on Department of Navy Submarine spaces are prohibited. A Portable Electronic Device (PED) is defined as any non-stationary electronic apparatus with singular or multiple capabilities of, but not limited to recording, storing, and/or transmitting data, voice, video, or photo images (e.g. cell phones, laptops, tablets and wearable devices such as fitness bands and smart watches).

Authorization of Additional Work:

Any additional work outside the scope of this contract/purchase order shall have written authorization from the Contracting Officer prior to executing any additional work. Any work performed without the written authorization of the Contracting Officer shall be considered “At-Risk” and the government will have no legal obligation to pay for the work performed.

Attachment B image1.wmf oleObject1.bin