SOW Annual Boiler Maintenance.pdf

PDF 82 KB Posted

Attached to
Annual Boiler Maintenance Service Federal contract opportunity
Solicitation number
31090PR260000285
Issued by
Department of Homeland Security US Coast Guard

About this file

This is a Statement of Work for annual preventative maintenance services on ten boilers located at U.S. Coast Guard Base Alameda in California.

The contractor must perform comprehensive overhaul, cleaning, inspection, and adjustment services on boilers located in buildings 1, 2, 4, 15, 16, 24, 49, and 55 across Coast Guard Island. Specific maintenance tasks include disassembling and reassembling boilers, cleaning flues with a flue brush, inspecting and cleaning waterside tubes, replacing igniters and electrodes, inspecting low water cutoff floats and sight glass, testing all safeties and interlocks, and measuring gas pressure and exhaust readings to verify proper combustion levels. The contractor must supply all labor, materials, and equipment necessary for these services. The boiler fleet consists of ten units from various manufacturers including Burnham, Weil McLain, Aerco, AJAX, Copper-Fin II, Crest, and Raypak models, with BTU ratings ranging from 1.2 to 1,500,000. Work must be performed between 7:00 AM and 5:00 PM, Monday through Friday, excluding federal holidays, to minimize disruption to Coast Guard operations. All work must commence within 15 business days after contract award and be completed within 90 days. Deliverables include written reports for each boiler detailing conditions found and recommended repairs, completed boiler operating certificates for all pressure vessels, and daily cleanup with all areas returned to original condition. Government furnishes potable water and electrical power. Technical points of contact are Jesse Williams, MK1, USCG (primary) and Mr. Julio S. Leto (secondary). Acceptance will be monitored by the Coast Guard Technical POC.

View the file

Other files for this federal contract opportunity

Other files attached to Annual Boiler Maintenance Service, newest first.
File Type Posted
BASE ACCESS LIST.xlsx XLSX spreadsheet
Combined Synopsis Solicitation - Boiler Maintenance.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Annual Services for Ten (10) Boilers

U.S. COAST GUARD BASE ALAMEDA

PART 1 GENERAL

1.1 The intent of this Statement of Work (SOW) is to have a contractor perform annual preventative maintenance on the below ten (10) boilers located in the spaces of buildings 1, 2, 4, 15, 16, 24, 49, and 55 located on Coast Guard Island, Alameda, CA. 94501.

PART 2 FACILITY AND SECURITY REQUIREMENTS

2.1 Vehicles must have valid registration and insurance, and vehicle operators must have a valid driver license. Due to mandatory compliance with the Real ID Act, driver’s licenses from American Samoa, Minnesota, Illinois, and Washington are NOT recognized as acceptable forms of identification.

2.2 The contractor shall clean up all areas to ensure they are clear of debris daily.

At completion of the project all construction areas will be returned to original condition. The contractor shall remove all waste material generated and dispose of in accordance with industry standards and applicable environmental rules and regulations.

2.3 Minimize impact to Coast Guard operations. Work performed onboard Coast Guard Island located in the mechanical spaces shall be completed between the hours of 7:00AM and 5:00PM, Monday thru Friday (excluding Federal Holiday) unless authorized by the Contracting OƯicer.

PART 3 TECHNICAL POINT OF CONTACT DESIGNATION

3.1 The Technical Points of Contact for this task are:

Primary POC:

Jesse Williams, MK1, USCG

Secondary POC:

Mr. Julio S. Leto

PART 4 SCOPE

4.1 The contractor shall supply all labor, materials, and equipment necessary to overhaul, clean, inspect, and adjust, perform annual preventative maintenance on ten (10) boilers located in the mechanical spaces of buildings 1, 2, 4, 15, 16, 24, 49, and 55 to include boiler flue cleaning, at the United States Coast Guard Base in the Alameda 94501.

PART 5 TASKS

5.1 The contractor shall perform the following tasks.

5.1.a Provide labor, materials and equipment to dissemble, clean, inspect, re-assemble, test, and make required adjustments to ensure proper combustion levels are achieved. will also thoroughly inspect and clean the entire flue on all boilers utilizing a flue brush.

5.1.b Open waterside covers and inspect tubes for scaling. Remove firebox covers, clean all fire tube risers, and replace igniter/electrode. Ensure drain tube is clear of debris and properly drains. Replace water side covers with new gaskets.

5.1.c Open, inspect, clean low water cutoƯ float and clean sight glass. Install new gaskets and close. Ensure float signals feed pump to energize and secure accordingly to manufactory’s specifications.

5.1.d Once boiler has been re-assembled, fill boiler to required level. Test all safeties/ interlocks for proper operation. Test gas pressure before and after regulator. Include exhaust readings to ensure proper combustion levels during normal operation.

5.1.e Upon completion will provide a written report for each boiler detailing the conditions found and suggested course of action for any repairs.

5.1.f If any repair/issues are discovered that are outside the parameters of this SOW they are to be addressed with Contracting OƯicer who will make a determination on how to proceed.

PART 6 GOVERNMENT FURNISHED INFORMATION:

6.1 Boiler Location & Description

Building #1:

One each (1ea) "Burnham" Boiler (Heating System Closed Loop) Model Number:

805B-WI Data Plate is not legible BTU Rating: 210,000 BTU

One each (1ea) “Burnham” boiler (Heating System Closed Loop) Model Number:

805B-WI Data Plate is not legible BTU Rating: 210,000 BTU

Building # 2:

One each (1ea) "Weil McLain" Boiler (Heating System Closed Loop) Model Number:

EG-45-PIDN Data Plate is not legible BTU Rating: 1.5

One each (1ea) "Weil McLain" Boiler (Heating System Closed Loop) Model Number:

EG-45-PIDN Data Plate is not legible BTU Rating: 1.5

Building #4:

One each (1ea) "Aerco" Boiler (Heating System Closed Loop) Model Number: AS- 154333 Serial Number: G-07-0918 BTU Rating 2 MBH

Building #15:

One each (1ea) AJAX Boiler (Low Steam Pressure Closed Loop) Model Number:

HNG4000 Serial: 47418 BTU rating: 3.2 MBH

Building #16:

One each (1ea) AJAX Boiler (Low Steam Pressure Closed Loop) Model Number:

HNG3000 Serial: 47421 BTU rating: 1.2 MBH

Building # 24

One each (1ea) Copper-Fin II (domestic water heater) Model Number :CFN0402PM Serial Number: 2221 129615365

One each (1ea) Crest condensing Boiler (Heating System Closed Loop) Model Number: FBN1001 Serial Number: 2419 138948794

Building 49:

One each (1ea) "Raypak" XTherm (Pump House) Model Number: P-1505A Serial Number: 1909494768 BTU Rating: 1,500,000

Building 55:

One each (1ea) "Raypak" XTherm Model Number: H7-1005 Serial Number:

1201335191 BTU Rating: 960,000

PART 7 GOVERNMENT FURNISHED MATERIAL

7.1 NONE

PART 8 GOVERNMENT FURNISHED SERVICES

8.1 Potable water and electrical power will be furnished free of charge to the contractor for the performance of work under this contract. All electrical connections shall be in accordance with the National Electric Code. Provide ground fault circuit interrupter (GFCI) devices when connecting to Coast Guard systems.

PART 9 DELIVERABLES

9.1 The contractor shall provide a written report for each boiler detailing the conditions found and suggested course of action for any repairs. Should the contractor discover any repair/issues that are outside the scope of the document, they are to immediately address them to Contracting OƯicer who will decide on how to proceed. Only the Contracting OƯicer is authorized to change the conditions of the contract and any additional work completed without approval from the Contracting OƯicer shall be done at the contractor’s risk of non-payment.

9.2 Provide completed boiler operating certificates for all inspected boiler pressure vessels.

9.3 All work shall commence within 15 business days after award and all work completed within 90 days of contract award.

PART 10 ACCEPTANCE

10.1 Completion of work under this contract will be monitored and accepted by Coast Guard Technical POC, Jesse Williams, MK1, or Mr. Julio S. Leto USCG.

END