SOW ANC Boundary Stone Wall Ph VI 260511 FINAL v2.docx

DOCX document 1 MB Posted

Attached to
Arlington National Cemetery Boundary Wall Repairs Phase 6
Solicitation number
W912QV1-26-R-A056
Issued by

About this file

This is a Statement of Work (SOW) for the deconstruction and reconstruction of approximately 550 linear feet of the historic stone boundary wall at Arlington National Cemetery (ANC), specifically Sections 17 and 18, designated as Project No. ENG-26156. The work is part of Phase VI of a phased repair program with a period of performance of 468 calendar days from Notice to Proceed (NTP), issued April 21, 2026. The Government will award a firm-fixed-price contract under simplified acquisition procedures using a Lowest Price Technically Acceptable (LPTA) basis, requiring that the successful vendor's proposed price be the lowest of all technically acceptable proposals and be determined fair and reasonable by the Government.

The contractor must possess minimum qualifications including five years of experience with historical stonework, completion of at least three similar projects, and key personnel (stone masons, laborers, Project Manager, and Superintendent) with at least five years of relevant construction experience. Work requirements include site mobilization with erosion and sediment controls, tree protection, safety fencing, and utility locating; careful deconstruction and salvage of existing bluestone capstones, wall stones, and foundation materials; excavation and installation of a continuous steel-reinforced concrete footing with dimensions per engineer's design; reconstruction of the stonework using salvaged stones in their original positions and patterns; installation of lead-coated copper joint flashing under capstones; site restoration with sod installation; and comprehensive documentation including pre- and post-construction photography and weekly progress reports. The contractor must submit multiple pre-construction deliverables including a Quality Control Plan, Accident Prevention Plan, Site Access Plan, Work Plan with Safety and Quality Control components, Documentation Plan, Initial Condition Assessment, and Project Timeline within specified timeframes post-award. Work shall be performed Monday through Friday, 7:00 AM to 5:00 PM, except recognized federal holidays, with coordination required for any night or weekend work. The contract requires compliance with DOD security requirements, AT Level I training, iWATCH training, environmental protection measures including storm water pollution prevention and hazardous waste management, and adherence to ANC-specific policies regarding cemetery access, interment protection, and site restoration standards.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Historic Stone Boundary Wall Phased Repairs: Phase VI Sections 17 and 18.

PROJECT NO. ENG-26156

Arlington National Cemetery

21 Apr. 2026

PART 1

GENERAL

1.1.Introduction: Arlington National Cemetery is our nation's most sacred shrine and the final resting place for our most revered military and civilian leaders. ANC receives millions of visitors each year - including visits from the President of the United States of America, other heads of state, family members of the deceased, and millions of tourists from around the world. Six thousand or more funerals are conducted yearly – in addition to over 2,000 other ceremonies, such as commemorations, wreath ceremonies, and head-of-state visits. These ceremonies and funerals often receive the intense focus of the press and other media. Due to the significance and attention received, strict adherence to the project specifications is essential. The successful contractor forms a true partnership with the Federal Government to ensure those who served our nation are properly honored.
1.2.Description of Services: The contractor shall provide all management, labor, materials, supervision, and equipment necessary to deconstruct and re-construct approximately 550 linear feet of the Stone Boundary Wall at Section 17, and 18. The contractor shall conduct a site visit, prior to award to verify measurements. Following award, but prior to any construction activity, the Contractor shall also provide a technical sheet and provide an engineered design for the wall reconstruction using proven historical methods for ANC’s review and approval before NTP. For exact work locations, please see Wall Survey Drawings (Technical Exhibits C, D & E).

The contractor shall have the following minimum qualifications:

· Five (5) years of experience with historical stonework

· Completed at least three (3) projects performing similar work outlined in the SOW.

· Key personnel such as stone masons and laborers shall have at least five (5) years of experience on projects involving repairs and/or reconstruction to historical stonework structures

· Project Manager and/or Superintendent shall have at least five (5) years of construction experience.

Contractor shall provide documentation to verify their experience and qualifications as required above.

1.3. Objectives: To deconstruct and reconstruct approximately 550 linear feet of ANC boundary stonewall.

1.4.Scope: The contractor shall provide all management, labor, materials, supervision, and equipment necessary to deconstruct approximately 550 linear feet of wall in sections 17 and 18. The contractor shall carefully dismantle the existing stone of the Stone Boundary wall and pilasters at the noted location and length in Section 17 and 18. The bluestone capstones shall be removed, numbered, and mapped in order to ensure replacement in their existing order and position in the wall upon reconstruction. Capstones shall be removed and stored on pallets in an unstacked manner for reuse. The Contractor shall disassemble the stonework of the wall panels and pilasters and stage these to be re-laid within the same wall panel and pier locations. Pilasters shall be reconstructed at the same location and with the same pilaster-to-pilaster offset as was existing. All stone palletized for reconstruction will be staged at an area to be agreed upon by the ANC COR and the Contractor. Any and all foundation stones will be extracted, salvaged, and reused as fill or for general wall construction as needed. The Contractor shall carefully remove all bonded / attached mortar from wall stones and capstones. If required, the Contractor shall identify an appropriate substitute capstone material where existing capstones are currently damaged beyond utility preventing reuse. The Contractor shall provide a team that has experience with historical field stone wall stonework and past projects or documents to verify such work as indicated above. For exact work locations, please see Wall Survey Drawings / Maps: (Technical Exhibits A, C, D, and E).
1.5.Period of Performance: The period of performance (POP) shall be 468 calendar days from the NTP.
1.6.General Information
1.6.1.Quality Control (QC): The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this SOW. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which they assure themselves that their work complies with the requirement of the contract. As a minimum, the contractor shall develop quality control procedures that address the areas identified in Technical Exhibit H, “Performance Requirements Summary” (PRS). The contractor shall make any modifications required to the plan within seven (7) calendar days of notification; and obtain Contracting Officer (KO) approval in writing of any proposed change to his QC system. The Contractor’s QC Plan is to be submitted with the proposal.
1.6.2.Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s) – if any. The Contractor shall designate an employee for quality control and shall submit documentation of a monitoring system for assuring all line items are performed according to specification. This employee shall be available for consultation with the Contract Officer Representative (COR) on a daily basis. The presumed is Michael Imbergamo michael.t.imbergamo.civ@army.mil, pending official designation.
1.6.3.Recognized Holidays:
New Year’s DayLabor Day
Martin Luther King Jr.’s BirthdayColumbus Day
President’s DayVeteran’s Day
Memorial DayThanksgiving Day
JuneteenthChristmas Day

Independence Day

1.6.4.Workdays and Hours: The Contractor is responsible for conducting business, between the hours of 7:00 AM through 5:00 PM, Monday through Friday, except on Recognized Holidays (Section 1.6.3, which includes the weekdays they are observed on). Work during the night throughout the week or on weekends is possible, but shall first be coordinated with the COR. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this SOW when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential to the success of this requirement.
1.6.5.Place of Performance: The work under the resultant contract will be performed at Arlington National Cemetery (ANC), Arlington, Virginia 22211.
1.6.6.Types of Contracts: The government will award a firm-fixed-priced contract.
1.6.7.Security Requirements: Contractor and all associated sub-contractor employees will comply with applicable installation, facility and area commander installation/facility access, and local security policies and procedures (provided by the ANC Security Office). The contractor will also provide all information required for background checks to meet installation access requirements through the ANC Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy, including e-Verify. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) or security posture of ANC change, the Government may require changes in contractor security matters or processes.

1.6.7.1. Physical Security: The contractor shall be responsible for safeguarding all Government equipment, information and property provided for contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.

1.6.7.2. Key Control: Contractor shall be responsible for the accountability of all keys issue in support of their contractual obligations. Failure to maintaining positive control of all keys could result in a bridge of contract.

1.6.7.2.1. In the event keys, other than master keys, are lost or duplicated, the contractor shall, upon direction of the KO, re-key or replace the affected lock or locks. However, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from the monthly payment due the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the monthly payment due the Contractor.

1.6.7.2.2. The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the KO.

1.6.7.3.Lock Combinations: N/A
1.6.8.Special Qualifications: The Contractor is responsible for ensuring all employees possess and maintain current certifications and licenses during the execution of this contract.

1.6.9. Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The Contracting Officer (KO), Contracting Officer’s Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.

1.6.10.Contracting Officer Representative (COR): The (COR) will be identified by a separate letter. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract, perform inspections necessary in connection with contract performance, maintain written and oral communications with the Contractor concerning technical aspects of the contract, issue written interpretations of technical requirements (including Government drawings, designs, specifications), monitor Contractor's performance and notifies both the KO and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order, but should be informed of any changes prior to approval by the KO.
1.6.11.Key Personnel: The following personnel are considered key personnel by the government: David Gecewicz (KO) and Michael Imbergamo (COR). The contractor shall provide a Project Manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the Contractor when the Project Manager is absent shall be designated in writing to the KO. The Project Manager or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. The Project Manager or alternate shall be available between 7:00 a.m. to 5:00p.m. Monday thru Friday except Federal holidays or when the government facility is closed for administrative reasons.
1.6.12.Identification of Contractor Employees: All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed. All employees are required to wear a badge/name plate while performing their duties
1.6.13.Contractor Travel: N/A.
1.6.14.Other Direct Costs N/A
1.6.15.Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include architectural drawings to include As-builts produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the KO. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.6.16.Organizational Conflict of Interest: Contractor and their subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO and in the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he/she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.6.17Phase In /Phase Out Period: N/A
1.7.Access and General Protection/Security Policy and Procedures:
1.7.1The Contractor and all associated sub‐contractor employees shall provide all the information required for the background checks to meet installation access requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204‐9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in Contractor security matters or processes.
1.8.iWATCH Training: Contractor and all associated sub-contractor employees will brief all employees on the local iWATCH program (training materials are available from the ANC Security Office). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed prior to beginning performance. All Contractor employees and associated sub‐contractor employees must complete the DoD Cyber Awareness Challenge ( https://ia.signal.army.mil/dodiaa/default.asp ) before issuance of network access and annually thereafter.
1.8.1For Contracts that Require OPSEC Training: The Contractor shall comply with DoD Directive 5205.01, AR 530-1, and any applicable service regulation. The Contractors must comply with contractually imposed operations security requirements. Also, if Contractors have access to Government information, then they are required to follow the same requirements for protection of sensitive, unclassified Government information per Joint Ethics Regulation and Public Law. The Contractor shall implement OPSEC measures as ordered by the Director, USAASC. In addition, the contractor shall have an identified OPSEC coordinator. Contractor personnel shall receive OPSEC awareness training within 30 days of the beginning of the contract performance. The contents of the training shall comply with AR 530-1.
1.8.2.Antiterrorism Level I Training/OPSEC (AT LVL I): All Contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within fifteen (15) calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee, to the COR, within five (5) calendar days after completion of training by all employees and subcontractor personnel. AT Level I Awareness training is available at the following website: http://jko.jten.mil/courses/atl1/launch.html or https://jkodirect.jten.mil/Atlas2/page/login/Login.jsf (for non-CAC users)
1.9.Site Specific Regulations: ANC Contractor Support videos. All contractors and subcontractors working at ANC are required to watch the video and acknowledge via a memorandum that they have viewed and agreed to comply to the video requirements.

Contractor Support, in English: https://youtu.be/pFzsdnpHBVE Contractor Support, in Spanish: https://youtu.be/arUxvIu735E

1.10.Environmental Protection: The Contractor and Contractor representative shall manage all waste generated by any work performed under this contract in accordance with all applicable Federal (Clean Air Act; Toxic Substances Control Act; Solid Waste Disposal Act; Resource Conservation Recovery Act; Clean Water Act; Safe Drinking Water Act) and State laws and regulations; Executive Orders, or other types of rulings having the effect of the law. In case of a conflict among these laws and regulations, the most stringent law or regulation shall apply.
1.10.1.Storm Water Pollution Prevention: The Contractor shall implement measures to prevent storm water pollution in accordance with Federal and State laws and regulations, and ANC's Municipal Separate Storm Sewer System (MS4) permit. The Contractor shall furnish, install, maintain, and operate erosion and sediment control measures, such as silt fences, storm drain protection, soil retention blankets, etc., prior to the start of any work that could cause pollution to state waters. The Contractor shall keep paved roads, parking lots and walkways clear of dirt, debris, and other materials. The Contractor shall remove immediately any dirt, debris, or materials deposited onto these surfaces. The Contractor must furnish and use drip pans under equipment oil and fuel tanks, and cover equipment when not in use and during rain events.
1.10.2.Solid Waste Management and Recycling: The Contractor shall recycle materials, such as, cardboard, paper, aluminum/metal cans, plastic, and glass jars/bottles, scrap metal, concrete, asphalt, and manage solid waste generated during the project in accordance with Federal and State laws and regulations. The Contractor must provide the Government with records of the type, weight, and disposal/recycling location for all recyclable materials and solid waste sent offsite for recycling and/or disposal.
1.10.3.Hazardous Waste: The Contractor shall manage hazardous waste in accordance with Federal and State laws and regulations. The contractor may not sign waste profiles or manifests on behalf of ANC. Contractor must follow ANC’s Manifest SOP.

1.10.4. Hazardous Material: The Contractor shall furnish and store all hazardous materials in a storage container or other secondary containment system. Maintenance of on-site equipment is not authorized.

1.10.5.Air Quality: The Contractor shall take all necessary reasonable control measures to reduce air pollution by any material or equipment used to carry out the requirements of this contract. This includes, but is not limited to, wetting down dry materials as necessary to prevent blowing dust, and keeping waste and materials in covered containers.
1.10.6.Vehicle Pollutants: As efforts to improve air quality continue around the Commonwealth, the focus in Northern Virginia is to reduce emissions from motor vehicles. Vehicles are the single greatest source of pollutants in this region of the State. Vehicle emissions inspections are required for certain vehicles registered or operated in Northern Virginia. Provide copies of emissions certifications for commercial vehicles used at ANC.
1.10.7.Commercial Vehicles: Virginia prohibits public service and commercial vehicles from idling for more than 3 minutes while parked in commercial or residential urban areas. Exceptions include when the vehicle's propulsion engine is providing auxiliary power for purposes other than heating and air conditioning.

PART 2

DEFINITIONS & ACRONYMS

2.1.Definitions:
2.1.1.Contactor. A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
2.1.2.Contracting Officer (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.1.3.Contracting Officer’s Representative (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4.Defective Service. A service output that does not meet the standard of performance associated with the Statement of Work.
2.1.5.Deliverable. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.
2.1.6.Key Personnel. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the SOW/PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.7.Physical Security. Actions that prevent the loss or damage of Government property.
2.1.8.Quality Assurance. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.9.Quality Control. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.10.Subcontractor. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.1.11.Work Week. Monday through Friday, unless specified otherwise.
2.2.Acronyms:
ANCArlington National Cemetery
ARArmy Regulation
DODDepartment of Defense
FARFederal Acquisition Regulation
IAWIn Accordance With
KOContracting Officer
NRHPNational Register of Historic Places
NTPNotice to Proceed
OCIOrganizational Conflict of Interest
POCPoint of Contact
POPPeriod of Performance
PRSPerformance Requirements Summary
QAQuality Assurance
QAPQuality Assurance Program
QCQuality Control
SHPOState Historic Preservation Office
SOWStatement of Work

PART 3

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT AND SERVICES

3.1. General: The Government will provide, the facilities, equipment, materials, and/or services listed below.

3.2. Equipment: N/A

3.3. Utilities: Utilities in ANC will be available for the contractor’s use in performance of duties as outlined in this SOW but only as available near the worksite. Electric, gas, and phone lines are not guaranteed in designated staging or storage areas used by the Contractor. The Contractor shall instruct employees in utilities conservation practices. The Contractor shall be responsible for operating under conditions that preclude the waste of utilities.

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4.1.Materials: The Contractor shall provide all materials, equipment, labor and supervision necessary to perform the duties described in section 5 of this SOW, except as defined in Part 3 of this SOW.
4.2.Secret Facility Clearance: N/A
4.3.Equipment: The Contractor shall provide all the necessary equipment/machinery to perform the necessary task as describe on section 5 of this SOW.
4.4.Cemetery Access: The Contractor shall be responsible for ensuring that all contractor personnel authorized to perform work under this contract obtain Cemetery access. Within five (5) workdays after contract award, the Contractor shall submit to the Contracting Officer and COR the names and completed JBM-HH Form 190-16x (Joint Base Myer-Henderson Hall (JBMHH) Installation Access Request) of ALL personnel working under this contract. Changes of the contractor personnel list shall be submitted within 24 hours of the change-taking place. All Contractor employees shall have on them, at all times, positive/valid, photographic identification, and the JBMHH issues badge/paperwork certifying they completed the vetting process.
4.5.Limited Background Check: For contractors that do not require CAC but require access to a DoD facility or installation. Contractor and all associated sub-contractor’s employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative).
4.6.Parking: Limited parking is available at ANC. Commercial Vehicle passes are available to contractor for their staff and personnel. Parking on curbs, grassy areas or other landscaped areas is prohibited. Overnight parking of vehicles belonging to contractors is not authorized anywhere on cemetery grounds without prior coordination and approval from the COR and Security Office. Commercial parking is available in the parking garage, at the rate of $12 per day.

PART 5

SPECIFIC TASKS

5.1.Scope of Work: The contractor shall provide all necessary labor, materials, equipment, and other construction services, as required to perform the below tasks:
5.1.1Erosion and Sediment Controls: Contractor shall install erosion and sediment control measures at all areas subject to disturbance related to this scope of work. Contractor shall provide inlet protection as required at locations subject to runoff from the project work site. Final location of erosion and sediment control components shall be identified and agreed upon during a pre-construction site walk between the Contractor and ANC personnel.
5.1.2.Tree Protection: Contractor shall install tree protection in accordance with requirements set forth in section 8 (Technical Exhibits F & G)
5.1.3.Personnel and Worksite Safety: Contractor shall install orange mesh site and safety control fencing around the entirety of the work area related to this scope of work. Contractor shall install additional safety measures as required or advisable given the nature of the work and / or specific site features. Final location of safety components shall be identified and agreed upon during a pre-construction site walk between the Contractor and ANC personnel.
5.1.4.Protect Interments and Cemetery Feature: The contractor shall meet with Cemetery personnel at each project area to identify all / any interments, headstones, and other Cemetery features which may be at risk of damage during the course of work, and thereafter agree upon a clear course of action to fully protect said interments, headstones and Cemetery features to the fullest extent possible. The Contractor shall supply a written survey detailing identified interments, headstones, and Cemetery features which may be at risk at each work area, and provide a written plan to detailing planned measures to be taken by the Contractor to mitigate, reduce, or eliminate said risks. Type and location of protective features shall be identified and agreed upon during a pre-construction site walk between the Contractor and ANC personnel. Contractor shall provide matting / plywood or other protective measures to protect turf from damages from equipment, work activity, or other scope related items ( i.e. damage to asphalt or turf ) – areas at which matting has been placed shall receive new Sod. This written plan shall be supplied in hard-copy form and must be approved by the COR prior to commencement of any work.
5.1.5.Utilities: Contractor shall locate and identify all utilities within and near the work area of this scope of work. Contractor shall ensure that installation of preconstruction elements (erosion and sediment controls, safety fencing, etc.) as well as construction activity do not proceed until utilities have been identified and clearly marked. Contractor shall ensure that utilities remain clearly marked and protected for the duration of work related to this scope. Contractor shall provide verification of utility identification and locating by completed VA811 ticket subject to review and approval by ANC personnel. In addition to VA811, the contractor shall contact a third-party utilities locator to identify all private utilities not normally under the VA811 purview. The results of both the VA811 and the private utilities contractor shall be included in the ANC dig permit request.
5.1.6.Excavation and Dig Permit: Prior to any excavation, the Contractor must process an ANC Dig Permit with the COR and other relevant stakeholders within ANC – relevant stakeholders will be identified by the COR. The Contractor must mark areas intended for excavation and hold a site meeting with the COR to verify said areas. Excavation work may not proceed without a signed, dated Dig Permit.
5.1.7.Site Safety and Security: Contractor shall ensure the job site is secure at the conclusion of each workday. Contractor shall ensure that all required safety and protective features are intact and in place at the project site at all times during work and at the end of each day. Contractor shall maintain an orderly arrangement of materials and equipment at all times to ensure the safety of those performing work as well as that of ANC staff and personnel.
5.1.8.Construction Debris and Waste: Contractor shall ensure job premises is clean at the conclusion of each workday. Contractor shall ensure that all debris is placed in appropriate containers prior to vacating the project site at the end of each day. Contractor shall maintain an orderly arrangement of materials and equipment at all times to ensure minimal visual, environmental, and operational impact to the Cemetery. Contractor shall provide matting / plywood or other protective measures to protect roll-off and drop-off locations from damages (i.e., damage to asphalt or turf).
5.1.9.Documentation and Documentation Plan: The Contractor shall submit a Documentation Plan for ANC approval prior to commencement of any physical work including a map to reference wall section to be photographed. Contractor shall document all existing conditions before starting work and any stabilization tasks with high resolution digital photographs. The full length of the wall section to be rebuilt will be photographed on both sides to capture the pattern of stone placement and arrangement at wall panels and stone pilasters, in addition to other features. Photographic documentation shall occur prior to any work, and after all work is complete. A stadia rod or measuring devise shall be visible in every photograph and must be legible. Upon project completion include “before”, “during” and “after” conditions from the same locations. Include representative overall and details views.

Photographs shall be labeled and organized in digital format and shall be organized into before reconstruction, during reconstruction, and after reconstruction subcategories. Submit existing conditions of the wall before repair work begins.

Deliver in TIFF or JPEG format of six 6 megapixels or greater (2000 x 3000 pixel image) at 300 dpi on same CDs/DVDs as Final Report. A narrative key to photographs must also be included on the CDs/DVDs. Name photographs using the following convention; [Cemetery Section number] _[South to North Pilaster numbers the wall sets between] _[Side of Wall]_[three-digit sequential number]_[date as year month]. Use identical identification names for photographs used in the weekly report and duplicated in the Final Conservation Treatment Report.

Before Reconstruction photographs shall guide the reconstruction, be used for quality control and to document the work. Contractor shall establish, document, and mark the existing alignment of the wall for use in resetting the wall. Contractor shall establish and document the existing wall heights and variations in heights for use resetting the wall to the existing heights. Contractor shall establish and document the exact pier to pier center line distances and heights to use for reconstruction. Pilasters shall be rebuilt in the exact location as existing. Contractor shall establish and document the locations of existing protruding stones on the ANC side of the wall. A protruding stone will be reset within the same panel as it was removed from and at the same general location within the panel.

5.1.10. Archaeological Finding: In the event Archaeological Resources (or suspected Archaeological Resources) are discovered, the Contractor shall stop work immediately and report the discovery to the Contracting Officer Representative (COR). The Contractor shall implement interim measures to protect the site and shall take every precaution to eliminate any disturbance or damage to said Archaeological Resources. Identify non-sensitive areas where monitoring is not normally required where work may continue while the Archaeological Monitor is documenting resources in sensitive areas. Implement additional measures, e.g., surveillance or concealment as appropriate, to protect the discovery sites from looting, vandalism, further disturbance, and damage.

5.1.11. Excavate and Install a Continuous Concrete Footing with Reinforcement: Upon complete disassembly of the existing Stone Wall and associated footing, the contractor shall excavate a trench and fully compact the base (to 95%) in preparation for the placement of formwork required to place a continuous steel-reinforced concrete footing. Footer dimensions and footer reinforcement layout shall be per the Engineer’s Design documents. Footer configurations are to plan for the change in grade along the length of the stone wall to be deconstructed and rebuilt. Epoxy coated rebar will be fitted and placed in the trench as prescribed by the engineer’s design. This will include axial and intermittent cross axial rebar along the full length of the footing. All rebar intersections shall be tied with non-corrosive wire per best practices. The Contractor shall pour and finish the concrete to complete the footing and return leg. Concrete strength and slump shall be per the Engineer’s Design Documents.

5.1.12. Reconstruct Stonework of the Boundary Wall Section: Upon completion of the new concrete footing, the contractor shall reconstruct the stonework of the boundary wall section following the historic character of the stonework as closely as possible. The stonework of the wall pilasters will be reconstructed using the same stones as salvaged and documented for those features. The stonework of the wall section panels between each pier will be re-laid with the same random pattern and joint size and character to match the historic wall samples and outlined in the Spewick Report (SPC Project Test Panel Program, 2015). Pilasters shall be reconstructed in the same position as existing, using the same pilaster-to-pilaster offset as existing. Stonework tie-in to adjacent, non-repaired wall sections shall result in a finished appearance that to the greatest extent possible eliminates any visually identifiable transition from newly constructed and / or re-constructed sections with existing portions of the historic stone wall. Anomalies in the stonework of obvious later repairs will be removed and replaced following the historic characteristics of the wall.

5.1.13. Mortar: The contractor shall use the previously approved mortar by the COR. A 3/8” rope (beaded) profile will be applied to the stonework throughout the wall section. Finished mortar joints shall be held back from the edge and face of the stonework to provide a slight relief between stone faces and adjacent mortar work.

5.1.14. Capstones and Flashing: The Contractor shall reset the capstones in the same order as removed from the wall. Capstones shall be set onto a bed of the same mortar mixture as used in the rest of wall stonework. The Contractor shall fabricate and install lead-coated copper joint flashing channel under each of the capstone head joints to match existing historic flashing. New joint flashing pieces shall be made to match the existing in size and material and composition. Joints between capstones shall remain open and un-mortared. Flashing shall extend 2” laterally under each capstone and shall extend 1” beyond finished face of the Stone Wall at each side Wall. Drainage “channel” at the flashing shall be rounded in profile, approximately 1/2” to 5/8” across and 1/2” in depth (conceptual cross section shown in Part 8, Technical Exhibit B). Contractor shall provide replacement capstones of a matching material and dimensional profile for locations at which re-use of existing capstones is not feasible due to condition.

5.1.15. Stone and Mortar Cleaning: Stones placed during wall reconstruction which were previously located below grade, or subject to atypical conditions may be discolored, or have a non-conforming surface appearance. The Contractor shall, upon completion of each portion of wall to be reconstructed, lightly scrub stones identified by ANC in order to remove superficial dirt, soil residue, or other matter. The Contractor shall only utilize warm water and an approved soft nylon brush during such activity. Newly placed mortars may develop mild efflorescence, or superficial salt expiration. The Contractor shall, upon completion of each portion of wall to be reconstructed, lightly scrub areas of mortar identified by ANC in order to remove superficial salts or efflorescence. The Contractor shall only utilize warm water and an approved soft nylon brush during such activity.

5.1.16.Site Restoration: The contractor shall install sod at all turf areas disturbed by work related to this scope. Sod shall be of a type approved for use at ANC. See 5.3 for sod specifications. Contractor is responsible for watering and maintenance of sod until final turn-over of project site to ANC. Turn-over shall be mutually agreed upon by Contractor and ANC personnel within written form.
5.1.17.Demobilization: The project site shall be cleared of all construction tools, equipment, and debris. Remaining materials, products and supplies will be assembled and removed from the site or disposed of. All Fences, site protection, tree protection, erosion and sediment controls and other temporary protective components shall be removed. The Contractor shall restore the project site to found or better condition. Upon the completion of all construction tasks, the work site will be restored to as found or better condition subject to approval by ANC COR. All work area, staging areas and areas disturbed as a result of this work shall be restored to as found or better condition at the completion of the work. This includes all turf, trees, horticulture features, and other Cemetery features.
5.1.18.Final Inspection and Closeout: Progress meetings shall be conducted during all stages of this project undertaking. Periodic inspections will aid in successful and on-time completion. The final inspection will be scheduled and completed at this task of the project and prior to demobilization.
5.1.19.Project Site Return to Government: The contractor shall clean all construction debris, waste, and scrap from the job site. Contractor shall return area to as found or better condition. Contractor shall return project site free of debris, waste, and scrap.
5.1.20.Site Protection Plan: Contractor shall detail means by which Contractor intends to protect property and assets within and adjacent to the work area, including headstones, landscaping, trees, stone boundary wall, and other assets and property during performance of the work.
5.1.21.Product Data: Contractor shall submit a list of all products to be used with accompanying specifications, product data, MSDS / SDS, etc.
5.1.22.Site Access Plan: Contractor shall submit list with the following information: list of equipment to be used to prepare for and conduct the work, how said equipment will ingress / egress the work area, where said equipment will be stored and duration of storage, how the work area and site will be protected from heavy equipment and other damage, and a safety plan including relevant PPE and staff certifications.
5.1.23.Initial Condition Assessment: Contractor shall conduct an Initial Condition Assessment including digital photos and any necessary documentation and measurements. This Initial Condition Assessment shall be provided to the Government in a written report. Two ( 2 ) printed copies, and one electronic copy a .docx file compatible with Microsoft Word. Initial assessment shall include all information noted above at minimum.
5.1.24.Barriers: Contractor shall install perimeter fencing, barriers, or other components to assure public safety around the work area.
5.1.25.Project Timeline: Contractor shall prepare a Project Timeline for executing and completing the specifications of this requirement. The Timeline shall include Milestones and Deliverables for the project. A representative from ANC Engineering will be made available to the contractor to aid in the preparation of the project timeline. The project timeline shall be provided during the post-award kick-off meeting, to be scheduled after contract award at the Government and Contractor’s convenience.
5.1.26.Work Plan: Contractor shall conduct an assessment and develop a Work Plan that will also include a Safety Plan and Quality Control Plan. The Work Plan shall be written and may contain charts, timelines, and other graphics to effectively communicate the logistics, schedule, safety, and quality control. Weather may be a factor during this project and work will be performed when weather is conducive. The plan shall identify actions that will be taken during inclement weather. The Contractor shall provide a Draft Work Plan within ten (10) calendar days of contract award and FINAL within fifteen (15) calendar days of receipt of review comments. Within seven (7) calendar days of receipt of FINAL, COR will notify the contractor of approval / disapproval of the Work Plan.

5.1.27. MSDS and SDS: Contractor shall submit all Material Safety Data Sheets (MSDS) and Safety Data Sheets (SDS) as applicable.

5.1.28. ABA Compliance: Contractor shall verify compliance with the Architectural Barriers Act (ABA) as is applicable.

5.1.29Tools and Equipment: All work involving use of tools or equipment which would interfere with any interment service conducted in the immediate vicinity of the work sites shall cease until the service has been completed. Only tools, equipment and vehicles required to perform under this contract shall be permitted to be stored on Cemetery property.
5.1.30.Recordkeeping and Reporting: The Contractor’s Project Manager shall provide the COR or his representative with accurate records of the performance of all assigned work – including dates and locations for each workday. This information, in writing and in a single, legible format, shall be provided on not less than a weekly basis - and shall identify all of the above work that took place within the previous seven days. Project Manager shall carry an activated cellular phone specifically for communicating with the COR or his representative. Project Manager shall have designated an acting Project Manager for his or her absences and shall notify the COR in advance of such absences. The Contractor shall provide weekly and illustrated Weekly Progress Reports For each weekly progress report the Contractor shall describe all work completed during the preceding week and work to be accomplished during the subsequent week and include hours worked, detail staff activities, percent of work completed, visitors to the site, problems encounter and resolved. The Contractor shall identify any problems that have arisen but have not been completely resolved with an explanation. The Contractor Report shall contain any omissions in conditions that ANC should address to achieve proper completion of the work. The Contractor shall include any use of subcontractors employed during the week. The Contractor shall submit selected photographs as part of the report to illustrate work completed. (NTE 4 pages with photographs). The Contractor shall submit their weekly reports NLT noon Local Time on the Monday following the work week throughout the project’s duration.
5.1.31.Environmental Protection: The Contractor shall implement measures to prevent storm water pollution in accordance with Federal and State laws and regulations, and ANC’s Municipal Separate Storm Sewer System (MS4) permit. The Contractor shall furnish, install, maintain and operate erosion and sediment control measures, such as silt fences, storm drain protection, soil retention blankets, etc., prior to the start of any work that could cause soil to get into the drainage system. The Contractor shall remove any dirt, debris, or materials deposited onto paved roads, parking lots and walkways and keep it out of the Stormwater drainage system.
5.1.32.Final Report: Contractor shall provide a Final Report with photographs. The Final Report shall be a comprehensive illustrated written account of the work done and shall include organized Weekly Progress Reports, correspondence, compliance, labeled photographs with photographic narrative, shop drawings, materials and vendor list, mortar mix proportions along with suppliers of each mix component, any recommendations for cyclical inspections and short and long-term maintenance. The contractor shall deliver a DRAFT within thirty (30) calendar days of completion of treatments on all items under this contract and a FINAL within fifteen (15) calendar days of receipt of review comments.
5.2.General:
5.2.1.Final Inspection: The KO or COR will conduct the final inspection of the project; with the Contractor and Government QA inspector in attendance. Listed deficiencies on the punch list should have been corrected at this point. However, deficiencies that cannot be corrected due to operation or seasonal weather can be rectified in dates approved by the KO. All debris management shall be complete.

5.2.2. Contractor shall install safety caution tape around areas of immediate work.

5.2.3 All unserviceable material shall be removed off-site

5.2.4. Materials, colors and finishes shall match existing.

5.2.5. Contractor to submit list of proposed material for COR review using Form 4025-R.

5.2.6 Contractor shall submit a construction schedule. The schedule should make provisions for Federal Holidays, ANC and MWM special events, and unfavorable weather. Refer to specification section 013216 for additional requirements

5.2.7 The contractor shall furnish a written guarantee to replace or repair promptly and assume responsibility for all expenses incurred for any workmanship and equipment in which defects develop within one year from the date of final certificate for payment and/or from date or actual use of equipment or occupancy of spaces by the owner. Contractor will assume responsibility for all expenses incurred in repairing and replacing work of other trades affected by defects, repairs or replacements in equipment supplied by the contractor.

5.2.8 Safety: The Contractor shall safeguard and maintain all government property as well as provide for the safety and well-being of personnel employed in the administration of this contract. The Contractor is solely responsible and liable for, following all applicable Federal, Department of Army and State of District of Columbia mandates and guidelines; and ensuring safe work and otherwise safe actions, behavior, and conduct of employees while at ANC or…