SOW AE Design - Parking Garage Expansion - Omaha Final.docx
DOCX document 61 KB Posted
- Attached to
- C1DZ--Project 636-508 - VHA A-E Design Expansion of Parking Garage - Omaha, Nebraska Amendment 1
- Solicitation number
- 36C77625R0027
About this file
This Statement of Work outlines A/E design services required for expanding an existing parking garage at the Omaha VA Medical Center. The project involves vertical expansion to maximum height and horizontal expansion to the east, with phasing to minimize lost parking during construction.
The A/E services include two parts: Part One (Design Phase) requires site visits, field investigation, studies, user interviews, and preparation of complete construction documents within 217 calendar days after award. Part Two (Construction Period Services) involves responding to RFIs, attending conferences, reviewing submittals, conducting site visits, and preparing various documentation during construction. The estimated construction magnitude is $10-20 million. Key design requirements include structural expansion, architectural facade matching, fire suppression, electrical/lighting systems, plumbing/drainage, and elevator expansion. The A/E must also incorporate VA design standards, physical security requirements, and environmental protection measures. Third-party commissioning is required for multiple building systems including vertical transportation, HVAC, electrical, communications, and security systems. The contract will be awarded by the Program Contracting Activity Central (PCAC) and is designated as a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| Nebraska-Western Iowa | 636-508 Construct Additional Floors Parking Garage |
| VA Health Care System | Design Statement of Work |
PROJECT NO: 636-508
PROJECT NAME: Construct Additional Floors Parking Garage VAAR Magnitude of Construction: $10,000,000 - $20,000,000
1. GENERAL INTENT:
The Contractor (herein referred to as “A/E”) shall provide Architect/Engineer (A/E) services to design a construction project at the NWI VA Medical Center (NWI VAMC) in Omaha, NE in accordance with this design scope of work.
2. STATEMENT OF WORK:
A/E Part One Services (also known as Design Phase) for this design project includes site visits, field investigation, studies, and user interviews to prepare drawings, specifications, and cost estimates for all facets of work and disciplines/trades to facilitate a construction project to expand the existing parking garage vertically to the maximum extent possible. The VA intends to expand the garage horizontally by building a full-height expansion to the east to match the final vertical elevation. The A/E shall also develop a phasing and scheduling plan that will minimize lost parking stalls during construction.
A/E Part Two Services of this design project (also known as Construction Period Services) includes responding to construction contractor Requests For Information (RFIs) during the solicitation (solicitation support) and construction phases of the construction project, attendance at pre-bid, post-award and commissioning kick off construction project conferences, review of construction material submittals and shop drawings, approximately two site visits per month during construction (both scheduled and emergent) to ensure compliance with the design drawings and specifications, preparation of site visit reports, coordination with project commissioning requirements, review of any construction project modifications for cost and technical acceptability, attendance and participation during the final acceptance inspection, preparation of the punch list and preparation of record drawings of the completed construction project based on the construction contractor’s as-built drawings. The A/E shall prepare a submittal log to be utilized by the VA during construction period services, maintain RFI log and provide meeting minutes for weekly construction meetings throughout the duration of construction. The A/E shall also review the construction contractor’s as-built drawings with the COR and Superintendent at least monthly scheduled site visits. The A/E shall also maintain a digital ‘stick file’ that contains all current drawing sheets and specifications; updates made to construction documents during bid period and through ASI/RFI documents shall be reflected within the stick file, with outdated documents replaced at time of issuance for no-cost changes and at time of award for changes requiring modification by the contracting officer. All Part Two Services are optional line items and will not be exercised at the time of award.
The above paragraphs constitute a basic outline of the work to be accomplished and in no way comprises all the details for design of this project. The A/E shall initiate detailed inspection of the project site to determine the needs and conditions for the design of this project. Copies of NWI VAMC record drawings will be made available to the highest rated A/E firm; the A/E will verify the validity of the record drawings prior to the start of design work and conduct site investigations as necessary throughout the design. SOW Attachment 01 – Omaha Campus Site Plan will give AE firm a basic understanding of the NWI VAMC campus.
The A/E shall be solely responsible for the management, including all associated labor, equipment, materials, mailing costs, and inspection, to meet the requirements of the design project. The A/E shall further provide meeting minutes for all meetings held under this design project.
3. DESIGN WITHIN FUNDING LIMITATIONS:
The design shall be prepared by the A/E to permit the award of a construction contract, using Federal Acquisition Regulation procedures for the construction of the facilities, at a cost that does not exceed the project’s estimated construction which will be included in the Request for Proposal (RFP) issued to the highest rated firm. A minimum of 10% of the estimated construction cost shall be included as ‘Bid-Alternate – Deduct’ options to ensure the final project fits within the VA’s construction budget.
4. DESIGN INDEPENDENCE, FURNITURE AND EQUIPMENT: Designs for construction must produce a “complete and usable” facility or improvement when constructed. VA policy (VHA Office of Capital Assets Management, Engineering and Support memo Updated Construction Guidance and Expectations dated Sep 12, 2016) requires the A/E to certify that their design (including all bid alternates/bid deducts) is independent of any future construction project. In addition, the A/E must certify that it has produced a design that does not include furniture and equipment that will be procured separately. Equipment that can be part of the design in the includes those items to meet code requirements for building occupancy, items covered in the VA’s Master Construction Specifications (PG-18-1) Divisions 1 through 10, 13 through 26 or 28 through 48, non-IT equipment items covered by Division 27 and items covered by Division Numbers 12 31 00, 12 32 00, 12 34 00 and 12 36 00.
The A/E shall submit as part of the Final Bid Documents submittal a signed letter on company letterhead stating the design’s independence.
5. DESIGN CRITERIA: The VA Technical Information Library (TIL) available at http://www.cfm.va.gov/til/index.asp is managed by the VA Office of Construction and Facility Management and is the master repository for all VA Numbered Standards for Construction to include design and construction specifications, procedures, standard details, BIM/CAD standards, equipment guides, space planning and design guides. The documents of the TIL shall be the minimum design criteria for all VA projects performed in the construction of new facilities and the modernization, alteration, addition, or improvement of its real property. All design documents shall be developed in accordance with the VA TIL, including (but not limited to) the following listed Department of Veterans Affairs References:
| PG-18-1 |
| Master Construction Specifications |
| SOW Attachment 02 |
| VHA Required Division 01 Specification Section List |
| PG-18-3 |
| Design and Construction Procedures [Including but not limited to: Codes, Standards, and Executive Orders] |
| PG-18-4 |
| Standard Details and CAD Standards |
| PG-18-5 |
| Equipment Guide List |
| H-18-8 |
| Seismic Design Handbook |
| PG-18-9 |
| Space Planning Criteria |
| PG-18-10 |
| Design Manuals (by discipline) [Including but not limited to: Guiding Principles checklists as indicated for Minor Projects in Sustainable Design Manual, Life Cycle Cost Analysis] |
| PG-18-12 |
| Design Guides (graphical, by function) |
| PG-18-13 |
| Barrier Free Design Guides |
| PG-18-14 |
| Room Finishes, Door, and Hardware Schedules |
| PG-18-15 |
| Minimum Requirements for A/E Submissions |
| PG-18-17 |
| Environmental Compliance Manual |
| H-7545 |
| VA Cultural Resource Management Procedures |
OIT Infrastructure Standard for Telecommunications Spaces v3.0 (21 August 2020)
The following references should also be used to complete the design documents:
· VA Standards Alert 017 – Infrastructure Standards for Telecommunications Spaces and all standards, guides, and manuals incorporated by reference (https://www.cfm.va.gov/til/sAlert/sAlert017.pdf)
Where conflicts exist between VA adopted codes and standards and the documents on the TIL, the A/E shall bring this to the attention of the VA. The resolution of the conflict shall be made by the authority having jurisdiction for VA to ensure consistency department wide.
6. DESIGN COLLABORATION: The A/E during this design project shall collaborate with the VHA Office of Healthcare Environment and Facilities Programs Special Engineering Program (HEFP/SEP) staff, VISN 23 and the Independent Life Safety Review Agent (LS Agent) for the project. Design submittal comments from these contractors, if concurred with by VA, shall be incorporated into the design. HEFP/SEP and/or VISN deliverables shall be coordinated with the A/E’s design submittals to ensure compliance with all requirements are met. The A/E is required to ensure all elements of the design adhere to the Life Safety Code, including recommendations for temporary construction barriers, prior to the Independent Life Safety review.
8. ENVIRONMENTAL PROTECTION: The A/E shall assist the VA with completion of an assessment of environmental and cultural impact as required by the National Environmental Policy Act (NEPA). If the NEPA assessment results in potential environmental impacts, the A/E shall be responsible for completing any auxiliary documentation required per PG-18-17 NEPA Interim Guidance for Projects located on the TIL (http://www.cfm.va.gov/til/etc/NEPAGuidance.pdf). Additional requirements may include, but are not limited to, Environmental Assessment(EA), Environmental Impact Statement(EIS), and Record of Decision. The NEPA analysis and concluding documentation must be completed by the Final Bid Documents submittal. The NWI VAMC believes this project to fit within a categorical exclusion rating. Include pricing for completing EA or EIS documents as optional line items for inclusion via modification if the NWI VAMC’s initial assessment is incorrect.
9. PHYSICAL SECURITY: The A/E must include a certified physical security specialist. The specialists must be involved with the design beginning with the concept phase and the qualifications must be submitted to the COR for review and approval prior to the concept/basis of design phase. The specialists shall meet the specific requirements listed in the latest edition Physical Security and Resiliency Design Manual (PSRDM), provided as part of PG18-10, see links above. The A/E shall ensure that all aspects of the applicable VA Physical Security Design Manual (either Life-Safety Protected or Mission Critical Facilities; both will be applicable depending on the area the work is taking place) are incorporated into the design and shall prepare a written report acknowledging compliance as required by the VAMC. The A/E must inform the COR of any physical security items that will be difficult to achieve during the concept/basis of design phase of the design and assist the VA with waiver requests as necessary.
10. TELECOMMUNICATIONS DESIGN: In accordance with “Telecommunications and Special Telecommunications Systems Design Manual,” February 2016 (https://www.cfm.va.gov/til/dManual/dmTelecomm.pdf), paragraph 1.2 (d), Telecommunications design must be performed and stamped by a BICSI Registered Communications Distribution Designer (RCDD) for all projects.
11. SUBMITTAL REQUIREMENTS: : Design submittals shall follow the requirements of Program Guide, PG-18-15, Volume C - A/E Submission Instructions for Minor and NRM Construction Program dated November 2008. This document is included as SOW Attachment 3 Submittal documents shall be prominently marked “For Official Use Only (FOUO)” if they contain qualifying data as defined in VHA Memorandum 2019-11-13 Sensitive Infrastructure Data Classification – For Official Use Only (FOUO). This memo is included as SOW Attachment 4 , as it is hosted on a non-public VHA site (https://vaww.va.gov/vhapublications/ViewPublication.asp?pub_ID=8949).
The A/E shall deliver design submittal documents that follow the iterative phase breakdown for design work in PG-18-15 and as additionally specified below. Specific requirements for each discipline/work product listed under each phase can be found in PG-18-15; it is expected for the phase of design that each of the checked items in the SD/DD/CD columns will be completed for the submittal. The A/E shall attend a review meeting following each design submittal as indicated under the Project Schedule section of this Scope of Work. Each new submittal will incorporate all VA comments from the previous submittal.
The following submittals will be required for this project:
· Quality Assurance/Quality Control (QA/QC) Plan
· Basis of Design (BD) - 15% - In addition to the requirements in PG-18-15, a Basis of Design is required. Basis of Design is a narrative presentation of facts, sufficiently complete, to demonstrate that the project concept is fully understood, and that subsequent design details, and their ultimate presentation in the final drawings and specifications, will be based on sound architectural and engineering decisions. Conceptual drawings of the planned design and the initial cost estimate will additionally be included.
· Investigation/site visit reports, space programming reports, design calculations, draft construction schedules shall all be submitted in electronic format only.
· Design Documents – refer to table below for number and size of hard-copy review documents required.
12. DRAWING FORMAT:
All drawings shall adhere to VA project software requirements for Computer Aided Design (CAD)] available at http://www.cfm.va.gov/til/projReq.asp.
13. SUBMITTAL FORMATS: Submittals shall be submitted in electronic format and hard copy formats as listed below. Portable Document Format (.pdf), Microsoft Office Suite formats (.doc, .xls, and .ppt), and AutoCAD (.dwg) files are acceptable. Submittals shall additionally be compliant with Section 508 of the Rehabilitation Act (29 U.S.C. '794 d); information on the requirements for accessible media can be found at http://www.section508.gov/. The A/E shall be responsible for providing:
Meeting/Conference Minutes Meeting minutes for all formal meetings and conferences held with the VA; including weekly construction meetings. Meeting minutes shall be submitted within seven (7) calendar days of the meeting or conference. All documents in any of the electronic formats listed above.
Minimum meeting minutes requirements
· Project name, number, meeting host, Meeting Name
· Date, Time, meeting ID, call in number, Duration, and consecutive number of total related meetings
· Participant list (Name, Title, Phone number (office and Mobile), Email, Attended Meeting (yes/no Check box)
· Meeting purpose, Roll call, and Additional Items
· Agenda items (Decisions, action items, and fixes or next steps)
· Next meeting date and time
· Detailed attachment list
Construction Cost Estimates Construction cost estimates shall comply with Manual for Preparation of Cost Estimates & Related Documents for VA Facilities dated March 8, 2011. This document is available on the TIL at http://www.cfm.va.gov/cost/index.asp. Estimates shall be produced in CSI Master format. Uniformat estimates are not acceptable.
Quality Assurance/Quality Control (QA/QC) Plan
· All documents in electronic format.
Schematic Design (SD)
· All documents in electronic format.
· See table below for hard copy deliverables.
Design Development (DD), and Construction Documents (CD)
· All documents in electronic format.
· Memo annotating what was not upgraded and corresponding justifications.
· See table below for hard copy deliverables.
Final Bid Documents (Bid)
· PDF files of drawings, specifications, and any miscellaneous design analysis documents such as submittal log and physical security compliance report.
· Certified memo annotating what areas/times were not upgraded and the corresponding justifications.
· Certified memo that the A/E design is independent of future projects and includes all equipment required for the project to be activated/full functional.
· Word files of specifications.
· AutoCAD files of drawings.
· See table below for hard copy deliverables.
14. OPTION ITEM REQUIREMENTS
Solicitation Support Services Pre-bid site visit to include meeting and project walk around. This is the meeting where contractors are invited to the job site to visually inspect the construction site to accurately develop a construction bid package.
Answer any technical questions/requests for information (RFIs) received from contractors over the duration of the solicitation, including questions asked during the site visit. Questions from contractors may come at multiple times and cover several questions over the course of the solicitation period. Technical question responses will be provided to the Contracting Officer who will distribute the information via amendment to the solicitation.
Answers to RFIs will be required from the A-E within five calendar days of the date the questions are sent to the A-E from either the project COR or CO. An alternate response period may be submitted for review, however, unless approved by the CO and COR, the A-E is required to comply with the five-calendar-day requirement.
Throughout the solicitation period, the A-E shall provide addenda as necessary if required to revise specs and drawings.
In response to any technical questions and/or addenda issued during the solicitation period, the A-E shall provide any final revisions to the 100% FC CD as part of the construction contract. These documents shall be labeled Final Construction.
Construction Period Services (CPS) Requests for Information (RFI) Requests for Information shall be answered within three business days of submittal to the A-E.
Submittal Reviews Submittal reviews shall be completed within seven calendar days of submittal to the A-E Site Visit Reports Site visit reports shall be distributed within two business days of the visit. Corrections may be requested by any party to the site visit within 3 business days of report distribution. If no corrections are requested in this time, the report shall be considered complete and accurate.
Modification/Change Order Requests Modification requests shall be reviewed within seven calendar days of submittal to the A-E. This includes the review of the contractor’s change order/modification proposal for construction change orders. The A-E's reply regarding their review of cost proposals and their recommendations shall include an independent breakdown of costs in detail, quantities, and unit prices and shall cover both additions and deductions of labor, materials, and equipment. The A-E shall also supply cost estimates as requested by the COR for Requests for Proposals for anticipated changes. All documents in any of the electronic formats listed above. Note: If major modification, VA will provide additional time and document format guidance.
Punch List Punch list shall be submitted within seven calendar days of the final acceptance inspection. All documents in any of the electronic formats listed above.
Record Drawings Record drawings shall be delivered to the VA within 30 calendar days of receipt of GC as-built documentation. Autodesk Revit Project (.rvt) format and AutoCAD (.dwg) format.
Third-Party Commissioning The A-E shall provide Commissioning and Commissioning Agent services and deliverables in accordance with the reference document, OCFM Whole Building Commissioning Process Manual located on the TIL (https://www.cfm.va.gov/til/Cx-RCx/CxManual.PDF). See “Commissioning Agent Tasks” in each section of the reference document. The Commissioning Agent shall be involved in all phases of the project, including both design and construction. It is anticipated that the Commissioning Agent will participate in the following: design reviews, owner’s requirements updates, design phase commissioning planning (facilitate), commissioning specification reviews (facilitate), construction project meetings, construction observation visits, equipment startup and testing, Testing Adjusting and Balancing (TAB) verification, and project commissioning (facilitate in coordination with General Contractor). The commissioning process shall be adapted to the size and complexity of the project. Deliverables shall be as described in the reference document. Additionally, the A-E or CxA shall develop the commissioning plan, pre-functional checklists, systems functional performance test checklists, integrated system test checklists, and edited master specification templates to serve as a starting point for the commissioning process on all projects based on the following Systems to be Commissioned.
· Vertical transportation: Elevators
· HVAC (VA Master Specification Section 23 08 00): Direct Digital Control System, Chilled Water System, Condenser Water System, Steam/Heating Hot Water System, HVAC Air Handling System, HVAC Ventilation/Exhaust Systems, HVAC Terminal Unit Systems, Decentralized Unitary HVAC Systems, Humidity Control Systems, Hydronic Distribution Systems
· Electrical (VA Master Specification Section 26 08 00): Grounding and Bonding Systems, Electric Power Monitoring Systems, Low-Voltage Distribution System, Emergency Power Generation Systems
· Communications (VA Master Specification Section 27 08 00): Grounding and Bonding Systems, Structured Cabling System
· Electronic Safety and Security (VA Master Specification Section 28 08 00): Grounding and Bonding, Physical Access Control Systems, Access Control Systems, Security Access Detection Systems, Video Surveillance System
15. PROJECT SCHEDULE/PERIOD OF PERFORMANCE/DELIVERABLES: The A/E shall perform Part One Services/Design Phase work according to the schedule shown below. If a due date on the timeline below falls on a Holiday or Weekend, the submittal shall be due the following business day. The remaining timeline will not be shifted to accommodate Holidays or Weekends.
| Milestone |
| Deliverables |
| Due Date |
| Detailed work plan and schedule. Preliminary design meeting with VA team |
| Provide design schedule to CO and COR |
| 14 calendar days after award |
| Basis of Design (BOD) – 15% |
| Digital copy plus one conceptual elevation rendering (30”x42”) and one conceptual site and floor plan (30”x42”) |
| 35 days after award, review meeting to be held virtually. |
| SD-1 35% |
| Provide digital copy along with one 30”x42” and one 15”x21” hardcopies of drawings. |
| 60 calendar days after award |
| SD-1 Review Meeting |
| Meeting |
| 21 calendar days after VA receipt of SD-1 Submittals |
| DD-1 65% Design Submittal |
| Provide digital copy along with one 30”x42” and two 15”x21” hardcopies of drawings. Printed copies shall be bound by discipline instead of one large drawing set. Coordinate section breaks with COR. |
| 40 calendar days after SD-1 Review Meeting |
| DD-1 65% Review Meeting |
| Meeting |
| 21 calendar days after VA receipt of DD-1 Submittals |
| CD-1 95% Design Submittal |
| Provide digital copy along with one 30”x42” and two 15”x21” hardcopies of drawings. Printed copies shall be bound by discipline instead of one large drawing set. Coordinate section breaks with COR. |
40 calendar days after DD-1 Review meeting
| CD-1 95% Review Meeting |
| Meeting |
| 21 calendar days after VA receipt of CD-1 Submittal |
| CD-2 100% FOR BIDDING Submittal |
| Provide digital copies only |
| 14 calendar days after CD-1 Review meeting |
Total Part One Services/Design Phase Schedule
217 calendar days
Optional Services
| CD-3 “FOR CONSTRUCTION” Documents Submittal |
| Provide digital copy along with one 30”x42” and one 15”x21” hardcopies of drawings. |
| 14 calendar days after close of construction solicitation |
Final Bid Documents Acceptance Meeting for CD-3 “FOR CONSTRUCTION”
7 calendar days after VA receipt of CD-3 “FOR CONSTRUCTION”
The 217 days listed in part one project schedule may fluctuate based on when submittals meet all VA guidelines and acceptance is issued. If submittals are not accepted due to insufficient design requirements throughout the design period and additional time is deemed necessary. It is the responsibility of the AE firm to cover all costs associated with such delays. For submittals other than the CD2 “For Bidding” and CD3 “For Construction” sets, delivery dates may be adjusted based on A/E suggestions/proposals made at time of award.
Part Two Services/Construction Period Services (optional Line Items) shall be performed for the length of time between the time the option(s) are exercised and acceptance of Construction Completion. The VA has 365 calendar days from final acceptance of the design to exercise the option(s) for Construction Period Services.
16. CONTRACT OVERSIGHT: All contracts for this project shall be awarded by the Program Contracting Activity Central (PCAC); only a warranted VA Contracting Officer shall have authority to change the terms and conditions of a contract. These changes may involve the contract award amount, contract period of performance, issuance of stop work orders and changes to the statement of work.
PCAC shall designate a Contracting Officer’s Representative (COR) to monitor and manage the A/E’s performance under the design project contract. The COR shall be a representative of the NWI VAMC Engineering Project Section and have the technical knowledge required to monitor and oversee the project.
A COR from the NWI VAMC Engineering Project Section shall also be designated for the construction project contract to monitor and manage the construction contractor’s performance under the construction project contract. This designation under the construction contract shall be considered equivalent to the industry standard of “Owner’s Representative” and does not supersede or eliminate the A/E’s responsibility for Part Two Services/Construction Period Services. The A/E ultimately shall be responsible for any errors and omissions with the design discovered during and after the construction phase.
17. REPORTING REQUIREMENTS:
The Contractor shall be required to report to the VA Engineering Service (Building 1, Room B618) to log in and obtain Contractor ID badge during normal working hours. This check-in is mandatory. Issued badges must be returned at the end of the workday.
18. SECURITY REQUIREMENTS:
The A/E is responsible for assuring that all employees and consultant employees working on the project comply with these regulations.
1. Employees shall not be on site without appropriate badge. Key personnel (PM, architect) shall be issued a PIV Card. Employees are responsible for reporting to VA Engineering obtain a badge until a PIV card can be issued. VA approved badge shall be worn with the identification facing forward and visible above the waist. The employees may also be subject to inspection of their personal effects when entering or leaving the facility.
2. No photography or video recording of VA premises is allowed without prior authorization.
3. VA issued keys are to remain on VA property. Keys that are checked out from the Engineering Office shall be returned each day.
4. Before starting any work, the A-E shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
5. The A/E is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
6. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
19. NARA RECORDS MANAGEMENT CONTRACT LANGUAGE:
1. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chapters 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.
2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.
3. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.
4. VA Nebraska-Western Iowa Health Care System and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of VA Nebraska-Western Iowa Health Care System or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701.
In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to VA Nebraska-Western Iowa Health Care System. The agency must report promptly to NARA in accordance with 36 CFR 1230.
5. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records, or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the contract. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to VA Nebraska-Western Iowa Health Care System control, or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the contract. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).
6. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government and VA Nebraska-Western Iowa Health Care System guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.
7. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with VA Nebraska-Western Iowa Health Care System policy.
8. The Contractor shall not create or maintain any records containing any non-public VA Nebraska-Western Iowa Health Care System information that are not specifically tied to or authorized by the contract.
9. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.
10. The VA Nebraska-Western Iowa Health Care System owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which VA Nebraska-Western Iowa Health Care System shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.
11. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take VHA-provided records management training. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.
Notes:
1. The contractor shall incorporate the substance of this clause, its terms and requirements including this paragraph, in all subcontracts under this contract, and require written subcontractor acknowledgment of same.
2. Violation by a subcontractor of any provision set forth in this clause will be attributed to the Contractor.
20. Privacy – VA Mandatory Training
1. VA Privacy Training for employees without access to VA computer systems or VA sensitive information.
a. VA Talent Management System (TMS) training course VA20939 provides the mandatory Privacy Training requirements for any contractor without access to VA computer systems or VA sensitive information. This training will be provided as a read, acknowledge and sign worksheet by the COR after award.
2. Each employee self-enrolls for a profile on the VA TMS by visiting https://www.tms.va.gov/plateau/user/login.jsp. Once there, employees should follow the steps below to create a profile, launch the mandatory training, and complete the content prior to starting work at VA.
3. Provide the COR with each employee’s printed certificate of completion from the TMS. This certificate displays the employee’s TMS User ID.
4. Each employee self-enrolls for a profile on the VA TMS by visiting https://www.tms.va.gov/plateau/user/login.jsp. Once there, employees should follow the steps below to create a profile, launch the mandatory training, and complete the content prior to starting work at VA.
5. Provide the COR with each employee’s printed certificate of completion from the TMS. This certificate displays the employee’s TMS User ID.
21. PROMOTION OF FULL AND OPEN COMPETITION:
1. A/E agrees to assure specifications are not restrictive. Specifications will be based performance criteria when possible and will not use brand names.
2. If the use of a brand name is necessary, the A/E will provide a justification, including:
a. Why the particular brand must be used or why a specification cannot be written (Proprietary design, etc.).
b. The criteria alternate items must meet to be considered equal.
3. If it is necessary to pre-qualify major components, the A/E will notify the Contracting Officer so that necessary actions can be taken to establish a Qualified Products List.
4. The A/E shall provide a written certification stating the solicitation is not restrictive, it has been written to provide full and open competition and will list at least three manufacturers who can supply major components or systems of the project.
5. The final design documents from a resultant task order will be subject to review and approval (by signature) of all members of an Integrated Project Team (IPT) consisting of medical center personnel. These individuals will be identified by the VA Contracting Officer’s Representative (COR) at the first design meeting.
22. SOW and ATTACHMENTS:
The following list of documents are attached to this SOW for A/E use and incorporation into the project documents:
· SOW Attachment 01 - Omaha Garage Expansion
· SOW Attachment 02 - VHA Required Div 01 Specification Sections
· SOW Attachment 03 - PG18-15 AE Submission Requirements
· SOW Attachment 04 - Memo 2019-11-13 SIDC-FOUO
· SOW Attachment 05 - 219-265 VAMC Parking Garage-Test Pile Installation Report 11-21-2019
· SOW Attachment 06 - VDCI VAMC Mechanical Asbuilt 03262021
· SOW Attachment 07 - Post Award Specs-Drawings Review Checklist - FINAL – 20221117
· SOW Attachment 08 - Seasonal Influenza w Vaccines
· SOW Attachment 09 - 316316 VDCI VAMC 316316 Closeout 011822 Guidon NAE
· SOW Attachment 10 - Farris Engineering 282300
End of SOW