SOW 200455.pdf

PDF 65 KB Posted

Attached to
Replace Ceiling Grid FC303
Solicitation number
N40085-22-R-2502
Issued by

View the file

Other files

File Type Posted
Amend 0005 200455.pdf PDF
Amend 0004 200455.pdf PDF
Amend 0003 200455.pdf PDF
Amend 0002 200455.pdf PDF
Amend 0001 200455.pdf PDF
SUBMITTAL REGISTER 200455.pdf PDF
SPECS 200455.pdf PDF
RFP 200455.pdf PDF
20-0455 FC303 CEILING GRID DWG_.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT DESCRIPTION

The work includes Demo existing ceiling grid, light and most diffusers, install new plastic ceiling grid, new tiles, fire escutcheons, diffusers and lighting, Contractor is to supply lighting and ceiling plans and incidental related work.

SPECIAL SCHEDULING

The facility/activity will not remain in operation during the entire construction period. The contractor shall have unfettered access to the work area for the contract duration.

Within the overall project schedule, commence and complete the work in phases. Complete each phase as indicated.

PHASE DESCRIPTION SCHEDULED START DAY COMPLETION DAY

A ___________________________________________________

B ___________________________________________________

C ___________________________________________________

SUPERVISION

One person may fill the roles of Superintendent, Quality Control Manager, and

Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.