SOO - B1030 UPS Replacement_22 Apr 26.pdf
PDF 76 KB Posted
- Attached to
- B1030 UPS Replacement Edwards AFB
- Solicitation number
- FA930226Q0041
About this file
This is a Statement of Objectives (SOO) for Uninterruptible Power Supply (UPS) maintenance and battery replacement services at Edwards Air Force Base.
The project requires preventative maintenance, component replacement, and battery replacement for four critical UPS units located in Building 1030 at Edwards Air Force Base, CA 93524-1185. The contractor must provide all supervision, labor, materials, equipment, and transportation, including removal and proper disposal of replaced parts and batteries in accordance with local, state, and federal regulations. Specific tasks include: UPS #1 (Eaton 93PM, 150kVA) requiring two power modules, fifteen fans, and eighty batteries; UPS #2 (Toshiba G9000, 225kVA) requiring forty contractor-provided batteries plus installation of forty government-furnished batteries for a total of eighty; UPS #3 (Toshiba G9000, 225kVA) requiring eighty batteries; and UPS #4 (Toshiba G9000, 225kVA) requiring eighty batteries. Deliverables include full installation of all specified components and batteries, testing and verification of operational status for all four units, and documentation confirming proper disposal of removed components. Work must be completed within the contractor's quoted lead time of approximately 2-5 weeks after order, with installation performed during normal business hours (Monday-Friday, 7:30 AM - 4:00 PM) and coordinated with the on-site government point of contact.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Objectives (SOO)
Project Title: Uninterruptible Power Supply (UPS) Maintenance and Battery Replacement
22 April 2026
1.0 Background
The 772TS/EWOX at Edwards Air Force Base, B1030, requires preventative maintenance, component replacement, and battery replacement for four (4) critical Uninterruptible Power Supply (UPS) units. The existing components and batteries are aging and approaching the end of their service life, necessitating replacement to ensure the continued and reliable operation of critical systems.
2.0 Objective
The primary objective is to procure and install all necessary parts and batteries to restore four (4) UPS units to optimal working condition. The contractor shall provide all supervision, labor, materials, equipment, and transportation required to perform the tasks outlined in this SOO.
3.0 Scope and Tasks
The contractor shall provide and install the specified components and/or batteries for the following four UPS systems. All work shall include the removal and proper disposal of all replaced parts and batteries in accordance with local, state, and federal regulations.
• 3.1 UPS #1
• System: Eaton 93PM, 150kVA (S/N: EM202UXX01)
• Location: Building 1030, Room 028, South Tower
• Tasks:
• Provide and install two (2) Power Modules (P/N: 744-A4535).
• Provide and install twelve (12) Fans (P/N: P-151000010).
• Provide and install three (3) Fans (P/N: 151101091-001).
• Provide and install eighty (80) new batteries (P/N: UPS12-545PLP).
• 3.2 UPS #2
• System: Toshiba G9000, 225kVA (S/N: 11-7E4189220012)
• Location: Control Unit Rm 028 / Battery Cabinet Rm 029
• Tasks:
• Provide forty (40) new batteries (P/N: UPS12-355PLP).
• Install a total of eighty (80) batteries, utilizing the 40 contractor-provided batteries and the 40 government-furnished batteries.
• 3.3 UPS #3
• System: Toshiba G9000, 225kVA (S/N: 13-7M1545330013)
• Location: Control Unit Rm 029 / Battery Cabinet Rm 029
• Tasks:
• Provide and install eighty (80) new batteries (P/N: 12-HX-400FR).
• 3.4 UPS #4
• System: Toshiba G9000, 225kVA (S/N: 18530422)
• Location: 1030 North EZ Street
• Tasks:
• Provide and install eighty (80) new batteries (P/N: 12-HX-400FR).
4.0 Deliverables
• All specified components and batteries, fully installed.
• Each of the four UPS units tested and verified to be fully operational.
• Documentation confirming proper disposal of all removed components and batteries.
5.0 Government-Furnished Equipment
• For task 3.2 (UPS #2), the government will provide forty (40) batteries (P/N: UPS12- 355PLP) on-site for installation.
6.0 Place of Performance
• Edwards Air Force Base, CA 93524-1185.
• Specific building and room numbers as detailed in Section 3.0.
7.0 Period of Performance
• Work shall be completed within the contractor's quoted lead time (approximately 2- 5 weeks ARO).
• Installation shall be performed during normal business hours (Monday-Friday, 7:30 AM - 4:00 PM). The contractor must coordinate the final installation schedule with the on-site government point of contact.
File details come from the government source that posted it. Updated .