This is a Request for Quotation (RFQ) for mold remediation services at Colebrook River Lake Office in Colebrook, Connecticut, issued by the U.S. Army Corps of Engineers New England District. The solicitation number is W912WJ26QA044, with an issue date of 6 February 2026 and offer due date of 17 February 2026 at 2:00 PM. The contract is set aside for Women-Owned Small Businesses (WOSB) under NAICS code 562910, with a size standard of USD 25,000,000. The solicitation incorporates FAR 52.212-1, 52.212-4, and 52.212-5 by reference and uses firm fixed pricing for two line items: Item 0001 for mold remediation services and Item 0002 for installation of new building materials. Both items have a delivery deadline of 15 May 2026 and are priced on a per-job basis. The contract period of performance runs from award through 15 May 2026.
The Performance Work Statement requires the contractor to provide all labor, materials, equipment, and transportation for mold remediation services in six areas totaling approximately 784 square feet (main office approximately 200 sqft, utility room approximately 144 sqft, locker room approximately 120 sqft, bathroom approximately 100 sqft, hallway approximately 120 sqft, and garage ceiling 4x8 feet). Work must comply with IICRC S520 standards using full negative air pressure containment with HEPA filtration. The contractor must submit pre-work submittals within 21 days of award, including an Accident Prevention Plan (ENG Form 6293), Activity Hazard Analysis, Site Safety and Health Officer Designation Letter (ENG Form 6282), and a Mold Remediation Plan developed by a Certified Industrial Hygienist with three years of microbial remediation experience. All work must be performed Monday through Friday from 7:00 AM to 3:30 PM with seven days' notice prior to start. The contractor must account for approximately 10 percent excess material for unforeseen remediation areas, install rock wool insulation with minimum R-Value 15, moisture-resistant drywall, and provide final detailed cleaning using HEPA vacuuming and antimicrobial cleaner. Contact Specialist Alicia N. LaCrosse (978-318-8902) or Technical Point of Contact Marissa L. Wright (978-318-8374) for inquiries.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment W912WJ26QA044-0002.pdf | ||
| Amendment W912WJ26QA044-0001.pdf | ||
| Solicitation Survey 26QA044.pdf | ||
| Attachments 26QA044.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WOMEN-OWNED SMALL
BUSINESS (WOSB)
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
1. REQUISITION NUMBER PAGE 1 OF
2. CONTRACT NUMBER 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect 8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/
OFFEROR
CODE
FACILITY
CODE
CODE
TELEPHONE NUMBER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
REQUEST
FOR QUOTE
(RFQ)
INVITATION
FOR BID
(IFB)
REQUEST
FOR
PROPOSAL
(RFP)
SEE ADDENDUM
19.
ITEM NUMBER
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Government Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH
AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND
ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS
SPECIFIED
29. AWARD OF CONTRACT: REFERENCE OFFER
DATED . . YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 11/2021)
Prescribed by GSA - FAR (48 CFR) 53.212
10. THIS ACQUISITION IS UNRESTRICTED OR
NORTH AMERICAN
INDUSTRY CLASSIFICATION
STANDARD (NAICS):
SIZE STANDARD:
13a. THIS CONTRACT IS A
RATED ORDER UNDER
THE DEFENSE PRIORITIES
AND ALLOCATIONS
SYSTEM - DPAS (15 CFR 700)
SET ASIDE: % FOR:
11. DELIVERY FOR FREE ON
BOARD (FOB) DESTINATION
UNLESS BLOCK IS MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3
AND 52.212-5 ARE ATTACHED. ADDENDA
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
8(A)
ECONOMICALLY
DISADVANTAGED
WOMEN-OWNED SMALL
BUSINESS (EDWOSB)
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
(SDVOSB)
HUBZONE SMALL
BUSINESS
SMALL BUSINESS
NOTE: OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30.
calls)
Solicitation/Contract Form Continuation
Mold Remediation Services, Colebrook River Lake, Colebrook, CTInstrument Name:
W912WJ26QA044
Continuation of Supplies or Services and Prices/Costs
Additional Information/Notes
Item Supplies/Service Quantity Unit Unit Price
Amount
0001 Contractor shall provide all labor, materials, equipment, and transportation to provide mold remediation services at the office at Colebrook River Lake, Colebrook, CT in accordance with the Performance Work Statement.
Pricing Arrangement: Firm Fixed Price
1 Job
0002 Contractor shall provide all labor, materials, equipment, and transportation to install new building materials on remediated areas at the office at Colebrook River Lake, Colebrook, CT in accordance with the Performance Work Statement.
Pricing Arrangement: Firm Fixed Price
1 Job
Continuation of Description
PERFORMANCE WORK STATEMENT:
MOLD REMEDIATION
U.S. ARMY CORPS OF ENGINEERS
COLEBROOK RIVER LAKE OFFICE
COLEBROOK, CT
PERFORMANCE WORK STATEMENT
A. General
1. Scope - Furnish all labor, materials and equipment to perform cleaning and structural remediation for mold damage in the Colebrook River Lake office, per IICRC (Institute of Inspection Cleaning and Restoration Certification) S520 standards, to include six areas less than 200sqft each (one main office room, one locker room, one hallway, one utility room, one bathroom and one section of garage ceiling (4x8')), using full negative air pressure containment, air fan/scrubber with HEPA filtration. Contractor is responsible for verifying all measurements. Contractor shall perform treatment and encapsulation, as well as cleaning and installation of new building materials upon completion of remediation. All work shall be completed in accordance with the following Performance Work Statement, state and local building codes.
2. Locations - Colebrook River Lake Office is located at 426 Colebrook River Road, Colebrook, CT
3. Site Visit - Contact the Technical Point of Contact, Marissa Wright at (978) 318-8374 or Marissa.L.Wright@usace.army.mil to arrange a site visit.
4. Schedule - The contract period of performance shall be from contract award through 15 May 2026. Work shall be performed Monday through Friday 7:00 AM to 3:30 PM unless otherwise approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays. The contractor shall provide a minimum of seven days' notice prior to the start of work.
All pre-work submittals shall be submitted within 21 days of contract award. The Government reserves up to 14 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall be resubmitted to the Government in an acceptable form within 7 days of the Government's response, unless additional time is granted by the Government in writing.
No field work may proceed prior to the acceptance of pre-work submittals.
5. Safety Requirements
i. General:
All work shall be conducted in accordance with the U.S. Army Corps of Engineers (USACE) Safety and Occupational Health Requirements (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration (OSHA), federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at the following link:
https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE% 2015March2024.pdf
Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.
ii. Accident Prevention Plan (APP):
The Contractor shall prepare a site-specific Accident Prevention Plan. The APP must be written by a Competent Person (CP) and document the specific work processes, equipment, materials to be used, hazards and applicable control measures.
The mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) must be submitted and accepted prior to beginning on site work:
https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_2023Aug31.pdf
A preparatory meeting shall be conducted by the Prime Contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
Daily safety meetings shall be held and documented. Records shall be available to the Technical Point of Contact upon request.
iii. Activity Hazard Analysis (AHA):
An AHA shall be submitted and accepted for each definable feature of work (DFOW) in accordance with EM 385-1-1, Chapter 2-6. A DFOW is defined as any task, which is separate and distinct from other tasks, has separate control requirements, or is identified as different trades or disciplines. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.
For a non-mandatory formatted outline of an AHA, see ENG Form 6206 (Activity Hazard Analysis) https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf
iv. Site Safety and Health Officer (SSHO) Requirements:
The Contractor shall employ a minimum of one person to function as a Level 3, SSHO. A Level 3 SSHO is a designated Qualified Person (QP) or Competent Person (CP) with Safety and Occupational Health (SOH) responsibility that meets the requirements of EM 385-1-1, Chapter 2-3.b and 2-4.b.
Level 3 SSHOs must have training, knowledge, and/or experience identifying hazards and implementing controls for the work being performed.
The SSHO shall be present at the project site and be responsible for overseeing the implementation of the Prime Contractor's SOH program. Contractor shall designate all SSHOs on a mandatory ENG Form 6282 (Site Safety and Health Officer Designation Letter):
https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf
v. First-Aid and CPR Personnel Requirements:
For shifts with multiple employees, provide at least two employees that are certified to administer First Aid and CPR. When employees work alone, they must be certified in First Aid and be provided an effective means of communication to call for assistance in the event of an emergency. Minimum First Aid and CPR qualifications are outlined in EM 385-1-1, Chapter 3-
vi. Additional Personnel Requirements:
Other Competent Person (CP) or Qualified Persons (QP) may be required per EM 385-1-1 and /or other sections of this Scope of Work, based on the definable features of work for this project.
vii. Accident Reporting:
All accidents and near misses shall be investigated by the Contractor and reported to the Technical Point of Contact in accordance with EM 385-1-1, Table 2-1.
The mandatory ENG Form 3394 shall be completed and submitted to the Technical Point of Contact within seven (7) days of an incident:
https://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms /Eng_Form_3394_2021Aug.pdf
viii. Employee Exposure Data:
The Contractor shall electronically report total employee work hours (including subcontractors) to the Technical Point of Contact by close of business on the 10th calendar day of the following month.
6. Specific Safety Section - Mold Remediation
a. General: The requirements of this section are applicable to contracts involving "Mold Remediation". All mold remediation activities, training, and submittals shall comply with EM 385- 1-1, Section 06-7.h; as well as other Federal, State, and local requirements.
b. Submittals: A site-specific Mold Remediation Plan is required to be developed by the Contractor's Certified Industrial Hygienist (CIH) and submitted to the Technical Point of Contact for final approval prior to start of work. The CIH must provide documentation of qualifications and have 3 years of experience in microbial investigation and remediation. This plan must be accepted by the Technical Point of Contact prior to initiating mold abatement tasks. This plan shall be developed as an appendix to the Accident Protection Plan and describe procedures to be followed to protect employees and the environment from mold hazards while performing work. Specifically, the Mold Remediation Plan shall address the following items at a minimum:
i. Description of materials to be remediated, providing location and quantities (map if available), and methods to be used for remediation.
ii. Products: Disinfectants, detergents, biocides, sanitizing solutions, and fungicidal agents, (Environmental Protection Agency (EPA)).
iii. Containment procedures to include description and locations of engineering controls and decontamination unit to include entry and exit procedures (provide sketch of floor plan showing location of containment barriers and decontamination units). Include locations of Air Filtration Units (AFUs) and Air Filtration Unit (AFU) discharges to the outside.
iv. Description of personal protective equipment to be used during the remediation.
v. Construction barricades and barriers in occupied areas.
vi. Employee training and certifications.
7. Pre-Work Conference:
Prior to the start of any work, the Technical Point of Contact will schedule and conduct a Pre- Work Conference. The Contractor's Project Manager and Quality Control Personnel will be physically present to attend this meeting. The Contractor shall directly oversee all work on the project and the Project Manager and Quality Control Personnel shall have the authority to act on behalf of the Contractor. This conference will be held at the time and location agreeable to the Government and Contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's administration and inspection of contract work or obtain other pertinent information that might be required. At the Pre-Work Conference the Contractor shall provide the name of the project superintendent with a telephone number for project coordination.
The following is a general list of items for discussion during this Pre-Work Conference:
i. Authority of the Technical Point of Contact and Quality Assurance Inspectors
ii. Contractor's Safety Program (including sub-contractors)
iii. Mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) and Activity Hazard Analysis for each Definable Feature of Work (DFOW)
iv. Safety Meetings
v. ENG Form 3394 (Mandatory if needed for Accident Reporting)
vi. Safety Data Sheet (SDS) requirements
vii. Correspondence, Communication and Administrative Procedures
viii. Invoice and Payment
8. Permits:
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, state, county, and municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.
9. Security:
The Contractor shall comply with all established security policies at each Project Office identified. If applicable, Contractor shall comply with Projects Key Control Management Program. Due to periods of heightened security, which may affect access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the Contractor's ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent service in an area. The Contractor shall be given at least a 24-hour notice of any such closure.
10. Contractor's Personnel:
i. Employee Conduct:
The Contractor shall be responsible for seeing that the Contractor's employees strictly comply with all Federal, state, and municipal laws. Any personnel activity, which, in the opinion of the Government, is deemed detrimental to the performance of the contract may result in the removal of Contractor employee/employees.
Examples of unbecoming actions or conduct include but are not limited to the following:
1. Cursing, harassment, or discrimination of and/or unwarranted physical contact with visitors, USACE personnel, or other contractors
2. Recurring written and/or verbal complaints from visitors, USACE personnel, or other contractors.
3. Unsafe operation of vehicles while on USACE property.
ii. Removal of Contractor's Employees:
The Technical Point of Contact may require the Contractor to immediately remove from the work site any employee of the Contractor or subcontractor, who, in the opinion of the Technical Point of Contact, endangers persons or property, or whose physical or mental condition is such that it would impair the employee's ability to satisfactorily perform assigned work. Notification to the Contractor shall be promptly made in writing if time and circumstances permit. Otherwise, notification shall be verbal or by telephone and shall be confirmed in writing as soon as possible. No such removal, however, will reduce the Contractor's obligation to perform all work required under this contract, and immediate replacement will be made as required. This requirement shall not be made the basis of any claim for compensation or damages against the United States or any of its officers or agents.
Note: At least one of the Contractor employees on site shall be able to communicate effectively and efficiently with all project staff.
11. Payment:
After final inspection and acceptance by the Government, the Contractor shall submit an invoice to the Technical Point of Contact. The invoice shall include the following: Invoice Date;
Contract Number; Dates of Service; Description of Work; Quantities; and total amount due per line item. For jobs greater than 30 days the Contractor may request multiple payments.
All invoices may be Emailed to: Marissa.L.Wright@usace.army.mil
B. Technical Requirements:
General Requirements:
1. Summary -
Furnish all labor, materials and equipment to perform structural remediation for mold damage in the Colebrook River Lake Office and garage, to include six areas under 200sqft each, using full negative air pressure containment, air fan/scrubber with HEPA filtration. The work will include cleaning, building material removal 4 feet up from the ground, as well as disposal, treatment and encapsulation and installation of new building materials.
2. Existing Conditions -The Colebrook River Lake Office, located in Colebrook, CT, was constructed in the 1950s and has a total of six definable areas of work - one main office room, one utility room, one locker room, one bathroom, one hallway and one area on the ceiling of the garage area (See Informational Photos). Current insulation primarily consists of fiberglass. The building structure is primarily 2x4 stick framing, but materials and room measurements shall be verified by the Contractor in the field. Each room may have multiple areas of remediation and may have multiple layers of drywall.
A. Main Office Approximately 200sqft
B. Utility Room Approximately 144sqft
C. Locker Room Approximately 120sqft
D. Bathroom Approximately 100sqft
E. Hallway Approximately 120sqft
F. Garage Ceiling Approximately 4x8' area of drywall
3. Clean Up and Waste Disposal - The Contractor shall keep the work area free from accumulation of waste materials. Any and all disturbed areas resulting from Contractor activities shall be restored by the Contractor to the satisfaction of the Technical Point of Contact.
4. Environmental Protection - Water, air and land resources shall not be adversely impacted during the course of the work. Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met.
5. Government Resources - The Contractor may use the existing restroom facilities at the Project Office. The Government will supply any electricity and water necessary for the project work from points of existing outlets. The Contractor shall carefully conserve the use of electricity and water provided. The Contractor shall supply his own means of communication (telephone).
6. Omissions - This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.
7. Quality Assurance - The Contractor is responsible for the quality control of the contract work.
The Government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.
8. Receiving and Storing Materials - The U.S. Army Corps of Engineers will provide a storage area and parking for contractor personnel. The contractor is responsible for protecting any stored material until it is placed in service. The contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive material or supplies for the contractor and will not be responsible for damage to the contractor's equipment or materials.
9. Submittals -
Although the Government reviews submissions required by this Performance work statement it is emphasized that the Contractor's work must be completed using proper internal controls and review procedures. The Government reserves up to 21 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall resubmit to the Government in an acceptable form within 14 days of the Government's response, unless additional time is granted by the Government in writing.
The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review and must be accepted by the Government.
Pre-Work Submittals: Submitted within 21 days of contract award. Submittals must be accepted prior to the commencement of any field work activities.
ENG Form 6293 (Accident Prevention Plan Worksheet)
Activity Hazard Analysis; non-mandatory template available: ENG Form 6206
ENG Form 6282 (Site Safety and Health Officer Designation Letter)
First-Aid and CPR Personnel requirements
Safety Data Sheet (SDS) for applicable materials
Basic work sequence plan
Building material and product spec sheets
Mold Remediation Plan
License or certifications determined by this Performance Work Statement, including Certified Pesticide Applicator and Certified Industrial Hygienist (CIH).
10. Products
a. Drywall, Joint Tape and Joint Compound:
i. Field measurements shall be taken to ensure correct drywall thickness and amounts.
ii. Drywall shall be moisture & mold resistant.
iii. All drywall components shall be free of asbestos or other harmful products.
iv. Any associated drywall fastening hardware shall also be provided by the Contractor.
b. Insulation
i. Insulation shall be rock wool with a minimum R-Value of 15 for each respective location.
ii. Field measurements shall be taken to ensure correct insulation thickness and amount.
c. Door Threshold
i. Compatible and sized for existing door.
ii. Must be for exterior use.
iii. Shall be installed with mechanical fasteners and weather-resistant adhesive.
iv. Must be installed to prevent trip hazards.
d. Flashing Tape
i. Waterproof
ii. Self-adhesive
iii. UV resistant
iv. Compatible with sealants and caulks
e. Mold Inhibitor
i. Acrylic sealer with fungicide
f. Antimicrobial Cleaner
i. Bio-based
ii. Safe for food contact surfaces
11. Sustainability
Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels. Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.
Execution
1. General
a. Equipment - It is the Contractor's responsibility to furnish and supply personnel with the proper personal protective equipment (PPE).
b. Workmanship - The Contractor shall establish and maintain a quality control system to assure compliance with the contract requirements.
2. Mold Remediation
a. Cleaning, Demolition & Removal - All materials that are in the way of the work, shall be removed and stored in a safe location. Using IICRC S520 approved methods and procedures, all drywall and insulation from approximately 4 feet up from the floor, as well as any other wall trim, and wall paneling, will be removed and disposed of from each room with mold damage, as well as the area on the garage ceiling. The door threshold in the utility room will require repair after remediation. The contractor shall account for an estimated 10% excess in material, should additional areas in need of remediation be discovered. If work is performed where electrical equipment is present, the equipment will need to be de-energized. In utility room where electrical equipment is present, equipment and drywall shall not be removed, however area shall be cleaned and encapsulated around equipment to best extent possible. Please see attached photos. All areas, including framing and foundation, will be thoroughly cleaned to per IICRC S520 standards. The Contractor shall assume that the mold is hazardous and provide a containment barrier with decontamination chamber. The contractor shall thoroughly clean all surfaces using Center for Disease Control (CDC) approved methods and HEPA vacuum to remove surface mold and debris. The area shall be sprayed with fungicide, concentrating on any sheathing and joists that may be contaminated. The treatment shall be left in place for the amount of time recommended by the manufacturer. The contractor shall thoroughly re-clean all surfaces using CDC approved methods and HEPA vacuum, removing dead mold spores.
b. Encapsulation- Wood structures shall be treated with mold inhibiting acrylic sealer with fungicide, to inhibit future microbial growth. Shall be applied by certified pesticide applicator.
c. Negative Air Pressure Containment System & Air Filtration - Contractor shall set up full negative pressure containment and shall provide 3 days of HEPA filtration. The containment system shall meet IICRC S520 standards.
3. Disposal
a. Disposal- Contractor shall comply with applicable laws, ordinances, criteria, rules and regulations of Federal, State, regional, and local authorities regarding handling, storing, transporting and disposing of construction and contaminated materials.
Note: all debris piles show in the informational photos have been disposed by the Government.
4. Installation of Building Materials
a. Installation- Contractor shall install new insulation in all walls and in ceiling where insulation was removed. Additionally, the Contractor shall install new drywall on all walls and ceiling that required mold remediation. Insulation shall be rock wool with a minimum R-Value of 15 for each respective location. The Contract shall install new drywall on entire exposed wall in the locker room shown in the informational photo #14. New drywall shall be flush with existing drywall and shall be mudded, taped and sanded so that the final surface is ready for primer and paint.
Contractor is not required to install new wall trim or perform any painting services. Additionally, Contractor shall also repair door threshold in the utility room. Contractor shall flash the door opening before installing. If any concrete damage is found, the Contractor shall notify the Technical Point of Contact before proceeding. Contractor shall provide a final detailed cleaning after the installation of all new materials. The cleaning will consist of using a HEPA vacuum on all surfaces followed by damp wiping with an antimicrobial cleaner or detergent solution working from the top down. Antimicrobial cleaner or solution shall be applied according to manufacturer's recommendation.
*** END OF NARRATIVE 1 ***
Requirements Mold Remediation Services, Colebrook River Lake, Colebrook, CT
Product Service Code : F999 North American Industry Classification System (NAICS) : 562910
Product Service Code : F999 North American Industry Classification System (NAICS) : 562910
Continuation of Packaging and Marking
Continuation of Inspection and Acceptance
Overall Contract Inspection/Acceptance Locations
Continuation of Deliveries or Performance
0001 Delivery Schedule Delivery On Or Before Delivery Date 15 May 2026
1 JobQuantity
Address and POC Place of Performance DoDAAC: 961108 CountryCode: USA
CORPS OF ENGINEERS NEW ENGLAND DIST
PROJECT MANAGER, COLEBROOK RIVER LAKE RIVERTON, CT 06065
UNITED STATES
MARISSA L. WRIGHT, DELIVER_TO_EMP_ID_NO
Email: marissa.l.wright@usace.army.mil Telephone: 978-318-8374
0002 Delivery Schedule Delivery On Or Before Delivery Date 15 May 2026
1 JobQuantity
Address and POC Place of Performance DoDAAC: 961108 CountryCode: USA
CORPS OF ENGINEERS NEW ENGLAND DIST
PROJECT MANAGER, COLEBROOK RIVER LAKE RIVERTON, CT 06065
UNITED STATES
MARISSA L. WRIGHT, DELIVER_TO_EMP_ID_NO
Email: marissa.l.wright@usace.army.mil Telephone: 978-318-8374
Continuation of Accounting and Appropriation Data
Contract Clauses
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.
2017-01
52.204-13 System for Award Management- Maintenance.
2026-02
52.212-4 Terms and Conditions-Commercial Products and Commercial Services.
2026-02
52.219-6 Notice of Total Small Business Set-Aside. 2026-02
52.222-36 Equal Opportunity for Workers with Disabilities.
2026-02
52.222-41 Service Contract Labor Standards. 2026-02
52.222-50 Combating Trafficking in Persons. 2026-02
52.222-62 Paid Sick Leave Under Executive Order 13706.
2026-02
52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving.
2024-05
52.232-33 Payment by Electronic Funds Transfer- System for Award Management.
2018-10
52.232-40 Providing Accelerated Payments to Small Business Subcontractors.
2023-03
52.233-3 Protest after Award. 2026-02
52.233-4 Applicable Law for Breach of Contract Claim.
2026-02
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
252.203-7000 Requirements Relating to Compensation of Former DoD Officials.
2011-09
252.203-7002 Requirement to Inform Employees of Whistleblower Rights.
2022-12
252.204-7004 Antiterrorism Awareness Training for Contractors.
2023-01
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. (DEVIATION 2024-O0013
REVISION 1)
2024-05 Deviation 2024- O0013
2024-05
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.
2023-01
252.204-7020 NIST SP 800-171 DoD Assessment Requirements.
2023-11
252.223-7008 Prohibition of Hexavalent Chromium. 2023-01
252.225-7001 Buy American and Balance of Payments Program.
2024-02
252.225-7012 Preference for Certain Domestic Commodities.
2022-04
252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime.
2023-01
252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region.
2023-06
252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.
2018-12
252.232-7010 Levies on Contract Payments. 2006-12
252.247-7023 Transportation of Supplies by Sea. 2024-10
FAR Clauses Incorporated by Full Text
Date
Alternate Deviation
Variation Effective Date
52.219-28 Postaward Small Business Program Rerepresentation.
2026-02
Postaward Small Business Program Rerepresentation (Feb 2026)
(a) . As used in this clause-Definitions
Long-term contract means a contract of more than five years in duration, including options.
However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern-
(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.
(2) , as used in this definition, means business concerns, one of whom directly or Affiliates indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.
(b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts-
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at https://www.sba.gov /document/support--table-size-standards.
(d) The small business size standard for a Contractor providing an end item that it does not manufacture, process, or produce itself, for a contract other than a construction or service contract, is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition-
(1) Was set aside for small business and has a value above the simplified acquisition threshold;
(2) Used the HUBZone price evaluation preference regardless of dollar value, unless the Contractor waived the price evaluation preference; or
(3) Was an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation(s) required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting officer in writing within the timeframes specified in paragraph (b) of this clause, that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
(1) The Contractor represents that it is, is not a small business concern under 562910 NAICS Code assigned to contract number.W912WJ26PXXXX
(2) [Complete only if the Contractor represented itself as a small business concern in .] The Contractor represents that it is, is not, a small paragraph (g)(1) of this clause disadvantaged business concern as defined in .13 CFR 124.1001
(3) . Women-owned small business (WOSB) joint venture eligible under the WOSB Program The Contractor represents that it is, is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [ The Contractor shall enter the name and unique ____ entity identifier of each party to the joint venture: __.]
(4) . Economically disadvantaged women-owned small business (EDWOSB) joint venture The Contractor represents that it is, is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [ The Contractor shall enter the name and unique ____ entity identifier of each party to the joint venture: __ .]
(5) Service-disabled veteran-owned small business (SDVOSB) joint venture eligible under . The Contractor represents that it is, is not an SDVOSB joint venture the SDVOSB Program eligible under the SDVOSB Program that complies with the requirements of 13 CFR
128.402. [ The Contractor shall enter the name and unique entity identifier of each party ____ to the joint venture: __.]
(6) [ HUBZone joint venture eligible under the HUBZone Program. Complete only if the ] The offeror represents, as part of its offer, offeror is a HUBZone small business concern.
that It is, is not a HUBZone joint venture that complies with the requirements of 13 CFR 126.616(a) through (c). [ The Contractor shall enter the name and unique entity identifier ____ of each party to the joint venture: .] Each HUBZone small business concern participating in the HUBZone joint venture must be certified as a HUBZone concern. [ Contractor to sign ____ and date and insert authorized signer's name and title.]
(End of clause)
52.222-42 Statement of Equivalent Rates for Federal Hires.
2014-05
Statement of Equivalent Rates for Federal Hires (May 2014)
In compliance with the Service Contract Labor Standards statute and the regulations of the Secretary of Labor ( 29 CFR Part 4), this clause identifies the classes of service employees expected to be employed under the contract and states the wages and fringe benefits payable to each if they were employed by the contracting agency subject to the provisions of 5 U.S.C.5341 or 5 332.
This Statement is for Information Only: It is not a Wage Determination
Employee Class Monetary Wage-Fringe Benefits (End of clause)
DFARS Clauses Incorporated by Full Text
Date
Alternate Deviation
Variation Effective Date
252.232-7006 Wide Area WorkFlow Payment Instructions.
2023-01
WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)
(a) Definitions. As used in this clause-
"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.
"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.
"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall-
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web- Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/
(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:
(1) Document type. The Contractor shall submit payment requests using the following document type(s):
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items-
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
(Contracting Officer: Insert either "Invoice 2in1" or the applicable invoice and receiving report document type(s) for fixed price line items for services.)
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial financing, submit a commercial financing request.
(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC ____ Issue By DoDAAC ____ Admin DoDAAC ____ Inspect By DoDAAC ____ Ship To Code ____ Ship From Code ____ Mark For Code ____ Service Approver (DoDAAC) ____ Service Acceptor (DoDAAC) ____ Accept at Other DoDAAC ____ LPO DoDAAC ____
DCAA Auditor DoDAAC ____ Other DoDAAC(s) ____ (*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert "See Schedule" or "Not applicable.")
(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)
(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
(Contracting Officer: Insert applicable information or "Not applicable.")
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
Addendum to 52.212-4, Contract Terms and Conditions - Commercial Products and Commercial Services
Contract Terms and Conditions Required To Implement Statutes or Executive Orders — Commercial Products and Commercial Services
Addendum to Contract Clauses
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.204-9 Personal Identity Verification of Contractor Personnel.
2011-01
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations.
2026-02
52.222-3 Convict Labor. 2026-02
52.223-23 Sustainable Products. 2026-02
52.240-91 Security Prohibitions and Exclusions. 2026-02
52.244-6 Subcontracts for Commercial Products and Commercial Services.
2026-02
DFARS Clauses Incorporated by Reference
Date
Alternate Deviation
Variation Effective Date
252.237-7010 Prohibition on Interrogation of Detainees by Contractor Personnel.
2023-01
252.243-7001 Pricing of Contract Modifications. 1991-12
252.244-7999 Subcontracts for Commercial Products or Commercial Services.
(DEVIATION 2026-O0015)
2026-02 Deviation 2026- O0015
2026-01
FAR Clauses Incorporated by Full Text
Number Title Effective Alternate Variation
Date Deviation Effective Date
52.252-2 Clauses Incorporated by Reference.
1998-02
Clauses Incorporated By Reference (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address (es):
https://www.acquisition.gov/
(End of clause)
52.252-6 Authorized Deviations in Clauses.
2020-11
Authorized Deviations in Clauses (Nov 2020)
The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR (a) Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
The use in this solicitation or contract of any (48 CFR ) clause with an (b) DFARS Chapter 2 authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
List of Contract Documents, Exhibits, or Attachments
ATTACHMENTS:
PLEASE SEE ATTACHMENTS INCLUDED SEPARATELY FOR ADDITIONAL INFORMATION.
SECURITY REQUIREMENTS:
General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (eg., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures -this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clauses of this contract, should FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
WAGE DETERMINATIONS:
The Wage Determination for this project can be found at:
https://sam.gov/wage-determination/2015-4133/35
Wage Determination No.: 2015-4133
Revision No.: 35
Revised Date: 03 December 2025
*** END OF NARRATIVE 1 ***
W912WJ26QA044
https://sam.gov/wage-determination/2015-4133/35
Solicitation Provisions
FAR Provisions Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.204-7 System for Award Management- Registration.
2026-02
52.212-1 Instructions to Offerors-Commercial Products and Commercial Services.
2026-02
DFARS Provisions Incorporated by Reference
Date
Alternate Deviation
Variation Effective Date
252.203-7005 Representation Relating to Compensation of Former DoD Officials.
2022-09
252.204-7008 Compliance with Safeguarding Covered Defense Information Controls.
2016-10
252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements.
2023-11
252.204-7024 Notice on the Use of the Supplier Performance Risk System.
2023-03
252.225-7055 Representation Regarding Business Operations with the Maduro Regime.
2022-05
252.225-7059 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region-Representation.
2023-06
DFARS Provisions Incorporated by Full Text
Date
Alternate Deviation
Variation Effective Date
252.204-7016 Covered Defense Telecommunications Equipment or Services-Representation.
2019-12
COVERED DEFENSE TELECOMMUNICATIONS EQUIPMENT OR SERVICES-
REP…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .