This document is a Request for Quote (RFQ) issued by the U.S. Army Corps of Engineers Savannah District for a Laser Induced Fluorescence (LIF) System to be used at the McEntire Joint National Guard Base in Richland County, South Carolina. The solicitation (W912HN25Q5006) is a 100% small business set-aside with a NAICS code 238910 and size standard of $19,000,000. The contractor will provide a LIF System compatible with USACE drilling equipment (Vertek CPT or Geoprobe DPT systems) to investigate Light Nonaqueous Phase Liquid (LNAPL) contamination, collect and interpret real-time results to identify drilling locations, and produce a comprehensive report including data logs, technology descriptions, and cluster plots.

The solicitation requires quotes to be submitted electronically to Amy.L.Collins@usace.army.mil by 2 July 2025 at 11:00 a.m. Eastern Time, with a copy to Glenda A. Canty. Award will be made to the lowest-priced, responsible, and responsive quote meeting product specifications. The contract duration is estimated at 7 days plus mobilization, with the contractor providing equipment, personnel, and conducting daily 10-hour operations. The investigation aims to delineate the horizontal and vertical extent of LNAPL contamination in the subsurface, with borings anticipated to extend approximately 50 feet below ground surface and locations determined by real-time LIF data interpretation.

View the file

Other files

File Type Posted
MW-07 Well Record.pdf PDF
MW-08 Well Record.pdf PDF
Questions and Answers 1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912HN25Q5006

Section A - Solicitation/Contract Form

COMBINED SYNOPSIS/SOLICITATION

This notice is being posted as an avenue to provide Request for Quote on Solicitation W912HN25Q5006. This is a combined synopsis/solicitation for commercial services in accordance with the format in FAR Subpart 12.6 as supplemented with additional information in this notice. THIS ANNOUNCEMENT CONSTITUTES THE ONLY

SOLICITATION: QUOTES ARE BEING REQUESTED AND A WRITTEN

SOLICTATION WILL NOT BE ISSUED. This will be solicited as 100% Small Business set-aside. The NAICS Code is 238910 with a size standard of $19,000,000.00. This solicitation document incorporates provisions and clauses in effect through Federal Acquisition Circular 2025-03.

Title of Requirement: Laser Induced Fluorescence System

Description of Requirement: The contractor shall provide a Laser Induced Fluorescence (LIF) System capable of mounting to the USACE owned drilling equipment, either the Vertek CPT system or the Geoprobe DPT system.

Submission Requirements: Fill out pages 2-4 of the attached. Quotes should be emailed to Amy.L.Collins@usace.army.mil by 2 July 2025 at 11:00 a.m. Eastern Time with a copy to Glenda A. Canty at Glenda.A.Canty@usace.army.mil

Basis for Award: The award will be made to the lowest priced, responsible, responsive quote, that meets or exceeds the product specifications. This is in accordance with Federal Acquisition Regulation (FAR) 52.212-2, Evaluation – Commercial Products and Commercial Services, and FAR 9.104.

The Government reserves the right to cancel this solicitation.

mailto:Glenda.A.Canty@usace.army.mil

REQUEST FOR QUOTE (RFQ)

US Army Corps of Engineers – Savannah District

POC: Amy Collins Phone: (912) 652-5505

Email: amy.l.collins@usace.army.mil QUOTES DUE BY: 11:00 am (ET) on 2 July 2025

CONTRACTOR: ______________________________________________________

UNIQUE ENTITY ID: _________________________________________________

CAGE CODE: ________________________________________________________

TAX ID NO.: _________________________________________________________

E-MAIL: ____________________________________________________________

PHONE NO.: ________________________________________________________

DATE OF QUOTE: ____________________________________________________

QUOTE PREPARED AND CERTIFIED BY:

(Printed Name and Title)

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 2 Days

MOBILIZATION/DEMOBILIZATION____FFP

FOB: Destination

PSC CD: F999

NET AMT

0002 7 Days

USE OF LASER INDUCED FLUORESCENCE____FFP

SYSTEM

0003 7 Days

PER DIEM____FFP

0004 1 Job

MODELING/REPORTING____FFP

Section C - Descriptions and Specifications

Performance Work Statement

(Includes associated Performance Requirements Summary (PRS)

PERFORMANCE WORK STATEMENT (PWS)

Laser Induced Fluorescence System

McEntire Joint National Guard Base

Eastover, Richland County, South Carolina

April 24 2025

Part 1

General Information

1. General: This is a non-personal service(s) contract under which the personnel rendering the service(s) are not subject, either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees.

1.1 Description of Services/Introduction: This is a non-personal service(s) contract to provide a Laser Induced

Fluorescence (LIF) System capable of mounting to the USACE owned drilling equipment, either the Vertek CPT system or the Geoprobe DPT System.

1.2 Background: The US Army Corps of Engineers is conducting a Light Nonaqueous Phase Liquid (LNAPL) investigation at the Petroleum Oil and Lubricant (POL) Facility located at the McEntire Joint National Guard Base located in Eastover, Richland County South Carolina. The goal of the investigation is to accurately delineate the horizontal and vertical extent of the LNAPL contamination in the subsurface. Figure 1 is a map showing the site location. Figure 2 is a map of the POL site showing the estimated extent of the LNAPL based on the existing site wells.

1.3 Scope: The Contractor shall provide non-personal service(s). The Contractor shall provide a Laser Induced

Fluorescence (LIF) System capable of mounting to the USACE owned drilling equipment, either the Vertek CPT system or the Geoprobe DPT System. The contractor will provide all necessary equipment and personnel to collect and interpret LIF results in real time allowing for identifying step out locations and informing drilling depths and locations for delineating LNAPL. Upon completion of the investigation the contractor will provide a detailed report of the LIF data including logs of the collected data, technology descriptions, data interpretation. The logs will also include lifetime and wavelength information as well as cluster plots of the collected data.

1.4 Objectives: The goal of the investigation is to accurately delineate the horizontal and vertical extent of the

LNAPL contamination in the subsurface.

1.5 General Information: All drilling operations will be conducted by US Army Corps of Engineers drill crews and the site Geologist. USACE will be responsible for marking and clearing all utilities and obtaining all required drilling permits prior to initiating investigation activities. Initial LIF borings will be located in areas of known

LNAPL contamination. Step out locations will be based on a grid in all directions and on the real time results of the

LIF data. Borings are anticipated to extend approximately 50 feet below ground surface but may change based on the results of the LIF data. During the field investigation the contractor personnel will work closely with the site geologist and drill crew to provide LIF results and data interpretation to allow the team to make decisions on drilling locations and depths.

The LIF equipment use and personnel is anticipated to be required for 7 days plus mobilization. The contractor will only be paid based on number of days used since the overall number of days (7) are estimated based on the current customer needs. Customer needs may change during the course of the project based on drilling data.

Subsurface soils within the POL facility at McEntire JNGB consist mostly of sand, clay and silt with a lesser amount of gravel. Review of the geologic logs (Trinity, 2014) indicate that the upper 3 to 4 feet of soil is predominantly fill material consisting of well graded medium to coarse grained sand with silt and gravel. Below this layer, extending to approximately 20 feet below ground surface (bgs), is a well‐graded, dark reddish brown, sandy clay and clayey sand, mostly medium to coarse and angular to sub‐rounded, which transitions into a more silty sand to a depth of approximately 25 feet bgs. A poorly graded, medium to coarse grained sand with some clay and gravel beds is present from 25 to 35 feet bgs followed by approximately 5 feet of light gray silt with a high percentage of mica.

Below 40 feet there are wet poorly graded fine to coarse grained silty sand with silt layers ranging 1 to 7 feet thick.

Groundwater depth varies from 40 to 50 feet below ground surface. The terrain is level and finished with maintained lawn/grass.

Wage Determination: The contractor must adhere to the folliwng SCA Wage Determination below which can be found at www.sam.gov.

Wage Determination No. 2015-4429 Revision No. 28 dated 12/23/2024

1.5.1 Quality Control Plan (QCP): A QCP is not required however the contractor must provide QC data including calibration information

1.5.1.1 Not Applicable

1.5.1.2 Not Applicable

1.5.2 Quality Assurance: The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the

Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the acceptable quality levels (performance thresholds).

1.5.3 Recognized Holidays: The following provides information on recognized holidays for the purpose of the

PWS. If submittal of any documentation (e.g. deliverables, submittals, etc.) deadlines fall on a holiday, the closest work day prior to the holiday will apply as the deadline for submittal.

1.5.3.1 U.S. Holidays: Work shall not be performed on U.S. federally recognized holidays occurring during the normal workweek unless otherwise directed by the Contracting Officer. When a U.S. holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following Monday, respectively.

New Year’s Day January 1st M. L. King Memorial Day 3rd Monday in Jan

Presidents Day 3rd Monday in February Memorial Day last Monday in May

Juneteenth June 19th Independence Day July 4th

Labor Day 1st Monday in September Columbus Day 2nd Monday in October

Veteran’s Day November 11th Thanksgiving Day 4th Thursday in November

Christmas Day December 25th

1.5.3.2 Host Nation Holidays: Not Applicable

1.5.4 Operating Hours: The Government facility office hours, facility operating hours, and the Contractor support hour requirements often coincide, however, they may differ. Please refer to the following.

1.5.4.1 Government Facility Office Hours: Not Applicable

http://www.sam.gov/

1.5.4.2 Government Facility Operating Hours: The Government facility operating hours occur between the hours of 0700 to 1800, daily.

1.5.4.3 Contractor Support Hours: Not Applicable

1.5.4.3.1 Contractor Work Plan: Not Applicable

1.5.5 Training Holidays: Not Applicable

1.5.6 Place of Performance: The work to be performed under this contract will be performed at the Petroleum Oil and Lubricant (POL) Facility located at the McEntire Joint National Guard Base located in Eastover, Richland

County South Carolina.

1.6 Security Requirements: The following information is provided on security related matters.

1.6.1 Security Program: Not Applicable

1.6.2 Personnel Security Clearance Requirements: Not Applicable

1.6.3 Installation Access: Access to U.S. installations, buildings and controlled areas is limited to personnel who meet security criteria and are authorized. Failure to submit required information/data and obtain required documentation or clearances will be grounds for denying access to U.S. installations, buildings and controlled areas.

The Contractor shall ensure that any subcontractors used in performance of this contract complies with these requirements and that all employees, of both the Contractor and any subcontractor utilized by the Contractor, are made aware of and comply with these requirements.

The Contractor shall be aware of and comply with the requirements associated with Installation Access Control. The

Government is not liable for any costs associated with performance delays due solely to a firm’s failure to comply with Installation Access Control System (IACS) processing requirements.

The Contractor shall return installation passes to the issuing IACS office when the contract is completed or when a

Contractor employee no longer requires access.

1.6.3.1 Installation Pass Log: Not Applicable

1.6.3.2 Individual Termination or Expiration of Employment: Not Applicable

1.6.3.3 Contract Termination or Cancellation: Not Applicable

1.6.3.4 Common Access Cards (CAC) and CAC Log: Not Applicable

1.6.4 Background Checks: Not Applicable

1.6.4.1 U.S. Citizen: Not Applicable

1.6.4.2 Local Nationals and Third Country Nationals: Not Applicable

1.6.5 Physical Security: The Contractor shall safeguard all Government equipment, information, and property provided for Contractor use.

1.6.6 Operations Security (OPSEC) Requirements: Contractor personnel shall adhere to facility security policies and restrictions. The Contractor shall immediately report suspicious activities to security personnel.

1.7 Key Control: Not Applicable

1.8 Post Award Conference/Periodic Progress Meetings: Not Applicable

1.8.1 Not Applicable

1.9 Contracting Officer’s Representative (COR): Refer to Part 2 of this PWS for the definition of a COR. As determined by the Contracting Officer, a COR will be appointed and identified by letter of designation, a copy of which will be provided to the Contractor by the Contracting Officer. The designation letter states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is not authorized to obligate the Government. If the work is not written in the contract, the COR is not authorized to request new work.

The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract, perform inspections necessary in connection with contract performance, maintain written and oral communications with the Contractor concerning technical aspects of the contract, issue written interpretations of technical requirements, including Government drawings, designs, specifications, monitor

Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies, coordinate availability of Government property, and coordinate site entry of Contractor personnel.

1.10 Key Personnel: Not Applicable

1.11 Identification of Contractor Employees: Not Applicable

1.12.1 Not Applicable

1.12.2 Not Applicable

1.13 Contractor Travel: Not Applicable

1.14 Other Direct Costs (ODCs): Not Applicable

1.15 Data Rights: The Government has unlimited rights to all documents and materials produced under this contract. All documents and materials, to include the source codes of software, produced under this contract shall be

Government owned and are the property of the Government with all rights and privileges of ownership and copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the

Contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.

1.16 Non-Disclosure Requirements: Not Applicable

1.17 Protection of Government and Contract Information: Per Public Use Notice of Limitations stated by

Defense imagery Management operations Center and contained at www.dimoc.mil/resources/limitations/ , the

Contractor shall not cite any information (e.g., contract information, pictures, locations, etc.) obtained through this contract on any hard copy or digital marketing tools to include its company website.

1.18 Non-Disclosure Statements: Not Applicable

1.19 Organizational Conflict of Interest (OCI): Not Applicable

1.20 Phase In /Phase Out Period: Not Applicable

1.21 Safety: The following provides information pertaining to Safety and Accident Prevention:

http://www.dimoc.mil/resources/limitations/

1.21.1 Safety Laws and Regulations: The Contractor shall comply with FAR 52.236-13, Accident Prevention

(November 1991), the references contained therein (e.g. U.S. Army Corps of Engineers Safety and Health

Requirements Manual (EM 385-1-1).

The requirements under FAR 52.236-13 and specifically of the EM 385-1-1 include, but are not limited to the following:

(a) Before beginning each activity involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform work, activity hazard analysis (AHA) shall be prepared by the Contractor performing the work activity (See paragraph 01.a.09 of EM 385-1-1);

(b) In all areas where drilling, construction, demolition, alteration, building, or similar related activities take place, the Contractor shall have the following minimum personal protective clothing and equipment requirements in place for any person working on or visiting the site:

(i) Short sleeve shirt;

(ii) Long trousers;

(iii) Eye Protection;

(iv) Hearing Protection;

(v) Steel-toed safety boots; and

(vi) Hard hat.

1.21.1.1 Not Applicable

1.21.1.2 Not Applicable

1.22 Environmental Compliance: Not Applicable

1.22.1 Environmental Compliance Plan and Program: Not Applicable

1.23 Required Training: Not Applicable

1.23.1 Anti-Terrorism (AT) Level I Training: Not Applicable

1.23.2 OPSEC Training: Not Applicable

1.23.3 iWATCH Training: Not Applicable

1.23.4 Information Assurance (IA) Training Not Applicable

1.23.4.1 Not Applicable

1.23.4.2 Not Applicable

1.23.4.3 Not Applicable

1.23.5 Personally Identifiable Information (PII): Not Applicable

1.24 Not Applicable

1.25 Notice to Proceed: the notice to proceed will be provided as indicated below.

☒The effective date of contract will constitute the date of notice to proceed

☐A notice to proceed letter will be issued

☐The date of the letter transmitting the contract will constitute the date of the notice to proceed

1.26 Electromagnetic Compatibility Directive: Not Applicable

1.27 Government Property and Services: Not Applicable

1.28 Not Applicable

PART 2

DEFINITIONS & ACRONYMS

2. Definitions and Acronyms

2.1 Definitions: Although not inclusive of every term used within this PWS, the following provides a list of definitions used throughout this PWS and commonly used in the acquisition field.

Contracting Officer – means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.

Contracting Officer's Representative (COR) – As defined in DFARS 202.101, means an individual designated and authorized in writing by the Contracting Officer to perform specific technical or administrative functions. DoD

Instruction (DoDI) 5000.72, Part II Definitions states the following when defining a COR: “Defined in subpart

202.101 of Reference (f). Any individual delegated responsibilities pursuant to subpart 1.602-2 of Reference (e), regardless of local terminology, must be certified in accordance with this instruction. For example, local terminology can be COR, Contracting Officer’s technical representative, technical point of contact, technical representative, alternate COR, administrative COR, assistant COR, line item manager, task order manager, quality assurance personnel, quality assurance evaluator, or COR management.” In addition, Army Regulation 70-13, Chapter 2, paragraph 2-2g, states, in part, the following when providing other surveillance support personnel to assist the COR when needed, “…These other surveillance support personnel may serve as on-site representatives of the COR in performance of actual contract surveillance if they meet all COR requirements and have been appointed by the Contracting Officer as alternate CORs.”

Contractor – means a supplier or vendor awarded a contract to provide specific supplies or service to the

Government. The term used in this contract refers to the prime.

Contractor-acquired Property - means property acquired, fabricated, or otherwise provided by the Contractor for performing a contract and to which the Government has title.

Day – means, unless otherwise specified, a calendar day.

Defective Service – means a service output that does not meet the standard of performance associated with the

Performance Work Statement.

Deliverable – means anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.

Government-furnished Property – As reflected in FAR 52.245-1, Government-furnished Property

“means property in the possession of, or directly acquired by, the Government and subsequently furnished to the

Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes contractor-acquired property if the contractor-acquired property is a deliverable under a cost contract when accepted by the Government for continued use under the contract

Government Property - means all property owned or leased by the Government.Government property includes both Government-furnishedand Contractor-acquired property. Government property includes material, equipment, special tooling, special test equipment, and real property. Government property does not include intellectual property and software.

Property Administrator - means an authorized representative of the Contracting Officer appointed in accordance with agency procedures, responsible for administering the contract requirements and obligations relating to

Government property in the possession of a Contractor.

High Level Objective (HLO) – means a key overarching result-based objective for a project necessary to achieve the project’s vision. HLOs are similar to Level 2 in a Work Breakdown Structure. Each HLO may contain several statements to flesh out the areas necessary to meet the objective.

Physical Security – means that part of security concerned with physical measures designed to safeguard personnel;

to prevent unauthorized access to equipment, installations, material, and documents; and to safeguard against espionage, sabotage, damage, and theft.

Quality Assurance – (or Government contract quality assurance) means the various functions, including, inspection, performed by the Government to determine whether a Contractor has fulfilled the contract obligations pertaining to quality and quantity.

Quality Assurance Surveillance Plan (QASP) – means the key Government-developed surveillance process document, and is applied to Performance-Based Service Contracting (PBSC). The QASP is used for managing

Contractor performance assessment by ensuring that systematic quality assurance methods validate that Contractor quality control efforts are timely, effective, and are delivering the results specified in the contract or task order. The

QASP directly corresponds to the performance objectives and standards (i.e., quality, quantity, timeliness) specified in the Performance Work Statement (PWS). It provides specific details on how the Government will survey, observe, test, sample, evaluate, and document Contractor performance results to determine if the Contractor has met the required standards for each objective in the PWS. The QASP, with very few if any exceptions, is an internal to

Government document.

Quality Control – means all necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

Statement – means the specific results-based activities required to satisfy HLOs. A statement contains a result, the context of the statement, and the required action(s). Statements focus on “what” is to be accomplished; however they are not prescriptive in describing “how” the outcome is to be achieved. Each HLO may have several statements to flesh out the areas necessary to meet the objective. Statements are similar to Level 3 in a Work Breakdown

Structure.

Subcontractor – means one that enters into a contract with a prime Contractor. The Government does not have privity of contract with the subcontractor.

Work Day - The number of hours per day the Contractor provides services in accordance with the contract.

Work Week - Monday through Friday, unless otherwise specified.

2.2 Acronyms: Although not inclusive of every term used within this PWS, or that may be included in an acquisition, the following provides a list of acronyms commonly used in the acquisition field.

ACOR Alternate Contracting Officer's Representative

AE Army in Europe

AFARS Army Federal Acquisition Regulation Supplement

AHA Activity Hazard Analysis

AOR Area of Responsibility

AR Army Regulation

AT Anti-terrorism

ATCTS Army Training Certification Tracking System

CAC Common Access Card

CCE Contracting Center of Excellence

CFE Conventional Forces Europe

CFR Code of Federal Regulations

CONUS Continental United States (excludes Alaska and Hawaii)

COR Contracting Officer’s Representative

COTS Commercial-Off-the-Shelf

DA Department of the Army

DD250 Department of Defense Form 250 (Receiving Report)

DD254 Department of Defense Contract Security Requirement List

DFARS Defense Federal Acquisition Regulation Supplement

DMDC Defense Manpower Data Center

DoD Department of Defense

FAR Federal Acquisition Regulation

FRG Federal Republic of Germany

GFP Government Furnished Property

HLO High Level Objective

HIPAA Health Insurance Portability and Accountability Act of 1996

IA Information Awareness

IAC Installation Access Control

IACO Installation Access Control Office

ID Identification

IGCE Independent Government Cost Estimate

IT Information Technology

JTR Joint Travel Regulation

JPAS Joint Personnel Adjudication System

KO Contracting Officer

OCI Organizational Conflict of Interest

OCONUS Outside Continental United States (includes Alaska and Hawaii)

ODC Other Direct Costs

OPSEC Operations Security

PA Property Administrator

PII Personally Identifiable Information

PIPO Phase In/Phase Out

POC Point of Contact

PRS Performance Requirements Summary

PWS Performance Work Statement

QA Quality Assurance

QAP Quality Assurance Program

QASP Quality Assurance Surveillance Plan

QC Quality Control

QCP Quality Control Program

RA Requiring Activity

RCO Regional Contracting Office

SIGE Safety and Health Protection Plan

TE Technical Exhibit

USAG United States Army Garrison

USAREUR United States Army Europe

UOM Unit of Measure

PART 3

GOVERNMENT PROPERTY (GP) AND SERVICES

3. Government Property and Services

3.1 Services: Not Applicable

3.2 Facilities: Not Applicable

3.3 Utilities: Not Applicable

3.4 Equipment: Not Applicable

3.5 Special Tooling and Test Equipment: Not Applicable

3.6 Materials: Not Applicable

3.7 Training: Not Applicable

3.8 Common Access Cards (CAC): Not Applicable

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4. Contractor Furnished Property and Services

1. 4.1 General: The Contractor shall provide a Laser Induced Fluorescence (LIF) System capable of mounting to the USACE owned drilling equipment, either the Vertek CPT system or the Geoprobe DPT System. The contractor will provide all necessary equipment and personnel to collect and interpret LIF results in real time allowing for identifying step out locations and informing drilling depths and locations for delineating LNAPL.

Upon completion of the investigation the contractor will provide a detailed report of the LIF data including logs of the collected data, technology descriptions, data interpretation. The logs will also include lifetime and wavelength information as well as cluster plots of the collected data.

4.2 Secret Facility Clearance: Not Applicable

4.3 Materials: Not Applicable

4.4 Vehicles and Equipment: Not Applicable

4.5 Background Checks): Not Applicable

PART 5

SPECIFIC TASKS

5.1 Basic Services: The US Army Corps of Engineers is conducting a Light Nonaqueous Phase Liquid (LNAPL) investigation at the Petroleum Oil and Lubricant (POL) Facility located at the McEntire Joint National Guard Base located in Eastover, Richland County South Carolina. The goal of the investigation is to accurately delineate the horizontal and vertical extent of the LNAPL contamination in the subsurface.

5.2 Tasks: Tasks consist of the following:

5.2.1 Equipment and Personell Mobilization

5.2.1.1 Laser Induced Fluorescence (LIF) System: The Contractor shall provide a Laser Induced Fluorescence

(LIF) System capable of mounting to the USACE owned drilling equipment, either the Vertek CPT system or the

Geoprobe DPT System.

(a) Standard (STD): Mobilize the the equipment and personell to the project site. Equipment shall be clean and in workling order with all necessary tools and equipment available to mount to the USACE drilling system.

Acceptable Quality Level (AQL): Arrive onsite within 15 days of notification with all necessary equipment in working order.

5.2.1.3 Modeling and Reporting: The contractor will provide a detailed report of the LIF data.

(a) STD: Upon completion of the investigation the contractor will provide a detailed report of the LIF data including logs of the collected data, technology descriptions, data interpretation. The logs will also include lifetime and wavelength information as well as cluster plots of the collected data.

AQL: Acceptance of the final report with one round of comments and revisions. Report delivery within 30 calendar days of field work completion.

5.2.2 LIF Daily Use and Operation

5.2.2.1 LIF Operation: Daily use and operation of the LIF equipment by the contractor.

(a) STD: The contractor shall provide all necessary equipment and personnel to collect and interpret LIF results in real time allowing for identifying step out locations and informing drilling depths and locations for delineating LNAPL.

All drilling operations will be conducted by US Army Corps of Engineers drill crews and the site

Geologist. USACE will be responsible for marking and clearing all utilities and obtaining all required drilling permits prior to initiating investigation activities. Initial LIF borings will be located in areas of known LNAPL contamination. Step out locations will be based on a grid in all directions and on the real time results of the LIF data. Borings are anticipated to extend approximately 50 feet below ground surface but may change based on the results of the LIF data. During the field investigation the contractor personnel will work closely with the site geologist and drill crew to provide LIF results and data interpretation to allow the team to make decisions on drilling locations and depths.

The Contractor shall survey all boring locations. All horizontal locations shall be given in South

Carolina State Plane based on North American Datum 1983 (NAD83). Any vertical elevation corrections will be referenced to North American Vertical Datum 1988 (NAVD88).

The LIF equipment use and personnel is anticipated to be required for 7 days plus mobilization. The contractor will only be paid based on number of days used since the overall number of days (7) are estimated based on the current customer needs. Customer needs may change during the course of the project based on drilling data.

The Contractor shall ensure that the equipment and personnel are prepared to conduct daily 10-hour operations. One (1) USACE drilling crew will conduct 1-drilling shift within a 10-hour period. One drilling shift shall consist of a ten (10) hour day and may include a weekend. Some workdays may be extended due to reasons out of the Governments’ control such as weather delays, or mechanical breakdowns.

AQL: Equipment operational with less than 10% downtime.

5.2.3 Report Preparation and Delivery

5.2.3.1 Reporting: The contractor will provide a detailed report of the LIF data.

(a) STD: Upon completion of the investigation the contractor will provide a detailed report of the LIF data including logs of the collected data, technology descriptions, data interpretation. The logs will also include lifetime and wavelength information as well as cluster plots of the collected data.

AQL: Acceptance of the final report with one round of comments and revisions. Report delivery within 30 calendar days of field work completion

5.3 Service Contract Reporting – Not applicable

PART 6

APPLICABLE PUBLICATIONS

6. Applicable Publications (Current Editions): The following publications, manuals, regulations, etc. are mentioned in this PWS and are listed below.

6.1.1 Department Of Defense Contract Security Classification Specification (DD Form 254)

6.1.2 Department of Defense Security Agreement (DD Form 441)

6.1.3 National Industrial Security Program Operating Manual (DoD 5220.22-M)

6.1.4 Installation Access Control (AE Reg 190-16)

6.1.5 The Army Physical Security Program (AR 190-13)

6.1.6 Contractor Identification (AE Reg 27-715)

6.1.7 U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1)

6.1.8 Information Assurance Workforce Improvement Program (DoD 8570-M)

6.1.9 Information Assurance Training Certification and Workforce Management Directive (DoDD 8570.01)

6.1.10 Information Assurance (AR 25-2)

6.1.11 Electromagnetic Compatibility Directive (2004/108/EC)

6.1.12 Policies and Procedures for Property Accountability (AR 735-5)

PART 7

ATTACHMENT AND TECHNICAL EXHIBIT LISTING

7. Attachment and Technical Exhibit List

7.1 Technical Exhibit A – Performance Requirements Summary

7.2 Technical Exhibit B – Deliverables Schedule

7.3 Attachment 1 – Not Applicable

7.4 Attachment 2 – Not Applicable

7.5 Attachment 3 – Not Applicable

7.6 Technical Exhibit C – Figures 1 through 4

TECHNICAL EXHIBIT A

Performance Requirements Summary (PRS)

PERFORMANCE

OBJECTIVE

STANDARD PERFORMANCE

THRESHOLD

ACCEPTABLE

QUALITY LEVELS

(AQLs)

METHOD OF

SURVEILLANCE

PRS#1 - PWS para (5.2.1)

The Contractor shall provide a Laser Induced Fluorescence

(LIF) System capable of mounting to the USACE owned drilling equipment, either the Vertek CPT system or the Geoprobe DPT

System.

Mobilize the the equipment and personell to the project site. Equipment shall be clean and in workling order with all necessary tools and equipment available to mount to the USACE drilling system.

Arrive onsite within 15 days of notification with all necessary equipment in working order.

100% Inspection

PRS#2 - PWS para ( 5.2.2)

Daily use and operation of the LIF equipment by the contractor.

The contractor shall provide all necessary equipment and personnel to collect and interpret LIF results in real time allowing for identifying step out locations and informing drilling depths and locations for delineating LNAPL.

Equipment operational with less than 10% downtime.

PRS#3 - PWS para (5.2.3)

The contractor will provide a detailed report of the LIF data

Upon completion of the investigation the contractor will provide a detailed report of the LIF data including logs of the collected data, technology descriptions, data interpretation. The logs will also include lifetime and wavelength information as well as cluster plots of the collected data.

Acceptance of the final report with one round of comments and revisions.

Report delivery within

30 calendar days of field work completion

TECHNICAL EXHIBIT B

DELIVERABLES SCHEDULE

Deliverable Frequency # of Copies Medium/Format Submit To

LIF Data Report

(PWS 5.2.3)

Once within 30 days following completion of field work

One Copy Electronic Delivey via

Email, using

PDF, Microsoft Office

Maximino Simian:

Maximino.E.Simian

@usace.army.mil

Anna Butler:

anna.h.butler@usace

.army.mil

Jason Lennane:

jason.lennane@usac e.army.mil mailto:anna.h.butler@usace.army.mil mailto:anna.h.butler@usace.army.mil

ATTACHMENT 1

ESTIMATED WORKLOAD DATA

Not Applicable

ATTACHMENT 2

HISTORICAL WORKLOAD DATA

ATTACHMENT 3

GOVERNMENT FURNISHED PROPERTY (GFP)

TECHNICAL EXHIBIT C

SEE ATTACHED PICTURES

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 31-JUL-2025 2 SEE SCHEDULE

SEE SCHEDULE

SEE SCHEDULE

SCHEDULE GA 99999

999-999-9999

W912HN

0002 31-JUL-2025 7 (SAME AS PREVIOUS LOCATION)

0003 31-JUL-2025 7 (SAME AS PREVIOUS LOCATION)

0004 31-JUL-2025 1 (SAME AS PREVIOUS LOCATION)

Section I - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.204-23 Prohibition on Contracting for Hardware, Software, and

Services Developed or Provided by Kaspersky Lab Covered

Entities

DEC 2023

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment

NOV 2021

52.204-27 Prohibition on a ByteDance Covered Application JUN 2023

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013

52.232-40 Providing Accelerated Payments to Small Business

Subcontractors

MAR 2023

252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights DEC 2022

252.204-7003 Control Of Government Personnel Work Product APR 1992

252.204-7018 Prohibition on the Acquisition of Covered Defense

Telecommunications Equipment or Services

JAN 2023

252.204-7020 NIST SP 800-171 DoD Assessment Requirements NOV 2023

252.225-7048 Export-Controlled Items JUN 2013

252.244-7000 Subcontracts for Commercial Products or Commercial

Services

NOV 2023

CLAUSES INCORPORATED BY FULL TEXT

52.212-4 CONTRACT TERMS AND CONDITIONS--COMMERCIAL PRODUCTS AND COMMERCIAL

SERVICES (NOV 2023)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights-

(1) Within a reasonable time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation

(FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the

Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include--

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on

Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award

Management, or 52.232-34, Payment by Electronic

Funds Transfer--Other Than System for Award Management), or applicable agency procedures.

(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.

(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of

Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any

United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the

Contractor is reasonably notified of such claims and proceedings.

(i) Payment.--

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C.

3903) and prompt payment regulations at 5 CFR part 1315.

(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate

EFT clause.

(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the

Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall--

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the--

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected line item or subline item, if applicable; and

(D) Contractor point of contact.

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(6) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if--

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer

(see 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on--

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b.

destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The

Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the

Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.

(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.

(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The schedule of supplies/services.

(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to

Government Contracts, and Unauthorized Obligations paragraphs of this clause.

(3) The clause at 52.212-5.

(4) Addenda to this solicitation or contract, including any license agreements for computer software.

(5) Solicitation provisions if this is a solicitation.

(6) Other paragraphs of this clause.

(7) The Standard Form 1449.

(8) Other documents, exhibits, and attachments.

(9) The specification.

(t) Reserved.

(u) Unauthorized Obligations.

(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C.

1341), the following shall govern:

(i) Any such clause is…