Solicitation - W911SG25BA002.pdf

PDF 6 MB Posted

Attached to
Repair Rebuild Route 219
Solicitation number
W911SG25BA002
Issued by

About this file

This solicitation (W911SG25BA002) is for a roadway repair and rebuild project at White Sands Missile Range (WSMR), New Mexico. The Department of the Army's Mission and Installation Contracting Command is seeking a service-disabled veteran-owned small business (SDVOSB) to widen Route 219 from 18' to 24', involving complete removal and replacement of the existing roadway. The project scope includes removing existing asphalt and base, processing subgrade, applying new base course, tack coat, SP-IV asphalt, and installing thermoplastic pavement markings and traffic signs.

The contract is a firm-fixed-price procurement with an estimated value between $500,000 and $1,000,000, and a 90-calendar day performance period after Notice to Proceed. The solicitation, classified under NAICS code 237310 (size standard $45 million), will be publicly opened on 09 June 2025 at 09:00 AM MST in Fort Bliss, TX. A mandatory pre-bid conference and site visit is scheduled for 20 May 2025, and all questions must be submitted by 27 May 2025. Bidders must submit comprehensive documentation including a bid bond, representations and certifications, and digitally signed drawings.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR

INFORMATION CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF PAGES

Created On:

08 May 2025, 09:06 AM Central Daylight Time

AWARD (To be completed by Government)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES

CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Section A - Solicitation/Contract Form

Repair Rebuild Route 219

W911SG25BA002

Section B - Supplies or Services & Prices or Costs

Additional Information/Notes

Item Supplies/Service Quantity Unit Unit Price Amount

Product Service Description:

Repair/Rebuild Route 219 Section 1

Pricing Arrangement: Firm Fixed Price

1 Job

Section C - Description/Specifications/Statement of Work

Directorate of Public Works

Engineering Services Division

White Sands Missile Range, New Mexico

STATEMENT OF WORK

DPW057522P REV 1, 07 APRIL 2025

Repair/Replace Route 219

Table of Contents

PART 1 - DESCRIPTION OF WORK.. 6

1.1. Objectives. 6

1.2. Period of Performance. 6

1.3. Place of Performance. 6

1.4. Occupancy. 6

1.5. Specific Work Requirements. 6

1.5.1. Civil 6

1.5.2. Demolition. 6

1.5.3. Cast in Place Concrete. 6

1.5.4. Architectural 7

1.5.5. Structural 7

1.5.6. Fire Protection. 7

1.5.7. Electrical 7

1.5.8. Telecommunications. 7

1.5.9. Mechanical/Plumbing/HVAC.. 7

PART 2 - GENERAL REQUIREMENTS. 7

2.1. Basic Guidelines. 7

2.1.3. Construction Documents 7

2.1.4. Construction Project Information Signage. 7

2.1.5. Licenses and Permits. 7

2.1.6. Installation Property. 7

2.1.7. Contractor Vehicles. 8

2.1.8. Limited Access. 8

2.1.9. Parking. 8

2.1.10. Buy American Act Construction Materials. 8

2.2. Key Personnel. 8

2.2.1. PM. 8

2.2.2. Superintendent. 9

2.2.3. SSHO. 9

2.2.4. QCM. 10

2.3. Temporary Utilities. 10

2.3.1. Water Service. 10

2.3.2. Electric Power Service. 11

2.3.3. Utilities Cutovers and Interruptions. 11

2.4. Portable Latrines. 11

2.5. Hours of Operation. 11

2.5.1. Normal Work Hours. 11

2.5.2. Entry Restrictions and Roadblocks. 11

2.5.3. Federal Government Holidays. 11

2.5.4. Excused Absence. 12

2.5.5. Furlough. 12

2.6. Environmental Quality Program.. 12

2.6.1. Cleanup and Disposal of Waste Materials. 12

2.6.2. Waste Hauler Requirements. 12

2.6.3. Waste Disposal. 12

2.6.4. Prohibitions. 13

2.6.5. Air Pollution Prevention. 14

2.6.6. Dust Control. 14

2.6.7. Water Pollution Prevention. 14

2.6.8. Archeological and Cultural Resources. 14

2.6.9. Wildlife Conservation. 14

2.7. Safety. 14

2.7.1. Safety Compliance. 14

2.7.2. Coordination with Sub-Contractors. 15

2.7.3. Traffic Control. 15

2.7.4. Site Specific Safety Plan. 15

2.7.5. Internal Job Site Safety Inspections. 16

2.7.6. Activity Hazard Analysis (AHA). 16

2.7.7. Accident Reporting Requirements. 16

2.7.8. Safety Meetings. 17

2.7.9. Display of Safety Information. 17

2.7.10. Work in Confined Spaces. 17

2.7.11. Safety Data Sheets for Hazardous Materials. 17

2.7.12. Radiation Permits and Authorizations. 17

2.7.13. Hot Work Permits. 18

2.8. Quality Control (QC) 18

2.8.1. QC Program Requirements. 18

2.8.2. Acceptance. 18

2.8.3. Notifications. 18

2.8.4. QCM. 18

2.9. Contractor Quality Control (CQC) Plan. 18

2.9.1. Quality Control Plan. 18

2.9.2. Contractor Daily Reports. 19

2.9.3. Construction Phasing. 19

2.9.4. Work Area Maintenance. 19

2.9.5. Utilities Clearances and Outages. 19

2.9.6. Emergency Suspension of Work. 20

2.9.7. Government Witness. 20

2.9.8. Documentation. 20

2.10. Product Requirements. 21

2.10.1. General Information. 21

2.10.2. Delivery, Storage, and Hauling. 21

2.10.3. Installation. 21

2.10.4. Product Data. 21

2.11. Required Employee Training. 21

2.11.1. Unexploded Ordnance Training. 21

2.11.2. Oryx Video - Safe Driving Video. 21

2.11.3. AT Level-I Training. 21

2.11.4. iWATCH Training. 21

2.12. Installation Access and Security. 22

2.12.1. Installation Access. 22

2.12.2. Contractor Responsibilities. 22

2.12.3. Removal of Personnel. 22

2.12.4. Photography. 22

2.13. Project Submittals. 22

2.13.1. Submittals. 22

2.13.2. Submittal Requirements. 22

2.13.3. List and Timeline of Submittals. 22

2.13.4. Government Review of Submittals. 23

2.13.5. Training of Government Personnel. 23

2.13.6. Equipment Manuals, Shop Drawings, and Product Data Manuals. 24

2.13.7. As-Build Drawings. 24

2.13.8. Operation and Maintenance Manual. 24

2.13.9. Warranties. 24

2.14. Construction Schedule. 24

2.14.1. Construction Schedule. 24

2.14.2. Payment and Performance Bonds. 25

2.14.3. Site Clearance and Utility Locate Permit. 25

2.14.4. Project Submittal Register. 25

2.15. Hazardous Building Material Abatement. 26

2.15.1. General 26

2.16. Schedule of Items. 26

2.16.1. Base Items. 26

2.17. Construction Drawings. 26

2.17.1. Construction Drawings. 26

PART 3 - Applicable Codes/Standards. 26

PART 1 - DESCRIPTION OF WORK

1.1. Objectives. All work shall comply with State, Local and Federal laws and regulations, industry and construction codes and standards, manufacturer's specifications and recommendations, and all contract special provisions, terms and conditions. The Contractor shall be responsible for obtaining all required licenses and permits to perform construction work on a Federal installation, and be properly bonded and insured in accordance with Federal Acquisition Regulation (FAR)requirements. The intent of the contract is to provide for the construction and completion of the work described. The precise details of performing the work are not stipulated except as considered essential for the successful completion of the work. The Contractor shall furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract. The project consists of widening the roadway from 18' to 24', existing roadway will need to be removed and replaced. Remove existing asphalt and base, dispose of off-site.

Process subgrade and new basecourse, apply tack coat and new SP-IV asphalt. Apply thermoplastic pavement markings and traffic signs. Do not disturb existing tank trails.

1.2. Period of Performance. After contract award, the Contracting Officer will issue a Preconstruction Authorization.

The Preconstruction Authorization is for Administrative and Pre-construction Activities (i.e., pre-construction tasks including coordination with any Government office or the Contracting Officer Representative for example bonds, submittals in accordance with (IAW) Section 2.13.3.2, traffic control plans, digging permits, utility outage requests, oral presentations, approvals for safety plans, and schedules). Preconstruction Authorization is limited to 30days and non-construction activities. After the first 30 days (Preconstruction Authorization),the Contracting Officer will issue Construction Notice to Proceed (NTP). Construction NTP authorizes the contractor to begin actual construction or physical work on the project. All work shall be completed according to the awarded contract period of performance of no later than [90] calendar days after Construction NTP is issued by the Contracting Officer (KO).

The Contractor shall not commence work unless authorized by the Contracting Officer (KO). All technical questions shall be addressed to the Contracting Officer's Representative (COR)for resolution and clarification.

Barring any contingencies that arise during construction, the Government requires the construction project to be completed within [90] calendar days.

Note: The total POP, including Preconstruction Authorization and Construction NTP shall not exceed [120] calendar days.

1.3. Place of Performance. The work is located approximately 6 miles east of WSMR main cantonment (Route219) on White Sands Missile Range (WSMR), New Mexico in Dona Ana county.

1.4. Occupancy. N/A

1.5. Specific Work Requirements.

1.5.1. Civil. - Widen the roadway from 18' to 24', process subgrade and new base course, apply tack coat and new SP-IV asphalt.

Apply thermoplastic pavement markings and traffic signs.

1.5.2. Demolition. - existing roadway will need to be removed and replaced. Remove existing asphalt and base, dispose of off-site.].

1.5.3. Cast in Place Concrete. -Not Applicable

1.5.4. Architectural. -Not Applicable

1.5.5. Structural. Not Applicable

1.5.6. Fire Protection. Not Applicable

1.5.7. Electrical. Not Applicable

1.5.8. Telecommunications. Not Applicable

1.5.9. [Mechanical/Plumbing/HVAC. Not Applicable

GENERAL REQUIREMENTSPART 2 - .

2.1. Basic Guidelines.

2.1.1. The Contractor shall attend a pre-construction meeting held by the Government prior to Preconstruction Meeting.

construction. Construction shall NOT begin until this meeting is held. This meeting serves to answer any questions from the Contractor and to discuss building issues such as storage, security, access, working hours, notifications, etc. The Contractor shall also provide the names of Key Personnel (see Section 2.2). The Contractor shall take minutes of the meetings and submit the minutes to the COR, KO, and Contract Specialist (KS) via the Contract Daily Report (see Section 2.9.2)within five (5) days.

2.1.2. The Contractor's project manager and superintendent shall attend any progress meetings held by the Progress Meetings.

Government on a scheduled or unscheduled basis (with 48 hour notice), or on dates determined by the Government. This meeting is for the Contractor to discuss their current progress, to discuss schedule, and to discuss and resolve any other project related issues. The Contractor shall take minutes of the meetings and submit the minutes to the COR, KS, and KO via the Contract Daily Report(see Section 2.9.2) within five (5) days.

2.1.3. Construction Documents. Contractor shall have a copy of the Scope of Work (SOW), Drawings, and specifications at the construction site at all times.

2.1.4. Construction Project Information Signage. The Contractor shall install a 4' x 8' project information sign at the work site. The sign will contain information such as project name, Contractor information, etc. A template will be provided by the COR. The sign shall be placed where it can safely be viewed by the general public. In addition to this sign, a worksite bulletin board and Safety and Occupation Health bulletin board (see Section 2.7.9) shall be placed where they are accessible to workers performing work for this project. These signs shall remain in place for the duration of the construction until project acceptance.

2.1.5. Licenses and Permits. The Contractor shall verify all dimensions and investigate existing site conditions prior to submitting proposal. The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits. The Contractor shall comply with all applicable laws and regulations, including but not limited to Building Codes, Federal Law, [New Mexico] State Law, Occupational Safety and Health Administration (OSHA) regulations, Army and installation regulations.

2.1.6. Installation Property. Contractor shall exercise extreme caution to protect building finishes, private property, military property, historic material, cultural resources, etc., from damage during the performance of these contract requirements. Contractor shall be responsible for all loss or damage to Government and private property while executing contract requirements as a result of negligence on behalf of the Contractor, subcontractors, or any representatives of the Contractor or subcontractors."

2.1.7. Contractor Vehicles. Contractor's personnel, whose tasks involve operation of any vehicles, shall possess a valid U.S. state driver's license, certificates and permits, applicable for the type and class of vehicle being operated.

2.1.8. Limited Access. The Contractor shall only use existing roadways when transporting personnel and/or material during the execution of the contract. The Contractor shall strictly adhere to the foregoing and shall not develop new ingress or egress roads.

2.1.9. Parking. The Contractor shall ensure that its personnel use designated parking areas only. Personal and non-construction related vehicles shall not be parked on grassy, gravel, or landscaped areas (unless identified as acceptable in drawings).

2.1.10. Buy American Act Construction Materials. Applying to contracts for the construction, alteration, or repair of any public building or public work in the United States, the Contractor shall utilize commercially available off-the-shelf (COTS) construction materials in accordance with Executive Order 10582 and 41 U.S.C. chapter 83, Buy American.

2.2. Key Personnel.

The Contractor shall, at a minimum, provide a full-time dedicated Superintendent (IAW52.236-6, Superintendence by the Contractor) dedicated Site Safety and Health Officer/Quality Control Manager (SSHO)/(QCM) for the duration of the contract.

The Contractor shall provide to the Contracting Officer (KO), within seven (7) calendar days after Preconstruction Authorization, a letter designating the key personnel prior to any work commencing. No substitutions of the key personnel proposed is authorized without prior written approval of the Contracting Officer. See Section 2.13 for submittal requirements.

In the event of short absences of the key personnel under this contract (or the release of the individual currently performing the work), the Contractor shall request to substitute another fully qualified individual. This request shall be provided, to the Contracting Officer, in writing, no less than three business days prior to the need to substitute.

2.2.1. Project Manager (PM). The Contractor shall provide a PM. The role of the Construction PM is to be the Government's Point of Contact (POC)for projects and administration of construction. Per ,the PM is accountable for:DPW057522P

Management of performance of all trade Contractors, review and analysis of SOW, architectural and engineering drawings and specifications; ensuring contract documents and regulations are comprehended and followed; supervision of Construction Superintendent(s), reviewing and approving their reports, submittals, monitor reported difficulties, and correcting safety violations/ deficiencies; developing, tracking, updating and controlling construction schedule; project management plan, and associated costs to achieve completion of project; coordinating the closure of a project.

The PM shall possess the following:

Language. Full professional working proficiency at speaking, listening, reading, and writing in English.

Experience. Five (5) years of experience (within the last ten (10) years) working as a Construction PM (or in a position with equivalent responsibilities) managing multiple construction projects simultaneously related to the project.

2.2.2. Superintendent. The Contractor shall assign one competent superintendent for each project. The superintendent shall be accountable for overall supervision and management of job site coordination, day-to-day operations, schedule adherence, enforcement of safety and quality, managing subcontractors, has authority to act for the Contractor, and shall be on site at all times during Construction. The superintendent is required to attend facility turnover meetings (Red Zone meetings), partnering meetings, and quality control meetings. The qualification requirements for the alternate superintendent are the same as for the superintendent.

The Superintendent shall possess the following:

Language. Full Professional working proficiency at speaking, listening, reading, and writing in English.

Experience. Five(5) years' experience (within the last ten (10) years) working as a Construction Superintendent (or in a position with equivalent responsibilities), managing multiple construction projects simultaneously related to the project. The superintendent must be familiar with the requirements of Engineering Manual (EM) 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The KO may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

2.2.3. SSHO. The SSHO shall be accountable for overall supervision and management of the Contractor's safety program(s) and plan(s). Contractor shall assign one SSHO for each project who will work simultaneously as the SSHO and QCM. The SSHO shall be onsite at all times during construction to implement and administer the Contractor's safety program and Government-accepted Accident Prevention Plan. An alternate shall be identified in the Construction Safety Plan to serve in the event of the SSHO's absence.

The requirements for the alternate are the same as the SSHO. The SSHO shall meet the requirements of EM 385-1-1 Section 1. The SSHO must ensure that the requirements of 29 CFR 1926.16 are met for the project. Itis responsibility of the Contractor to express to the KO in the event that due to the complexity of the project, one employee will be required for each position.

The SSHO shall be the Government's POC for all aspects relating to safety. The SSHO responsibilities include, but are not limited to facilitating and ensuring the completion of facility safety assessments/investigations of reportable and non-reportable mishaps involving personal injury accidents, property damage, and cases of occupational illnesses; recording accident reports in an accurate, complete, and timely manner; assuring that claims for injuries and illnesses are posted in the Occupational Safety and Health Administration log; promoting and furnishing applicable safety and health, accident prevention, and investigation training for Contractor's employees; assessing and evaluating work environment, identifying potential hazards, and aiding Contractor, Construction PM, and Construction Superintendent during work place inspections; supporting Contractor, Construction PM(s), and Construction Superintendents in investigating accidents and developing measures to prevent recurrences.

The Safety Manager shall possess the following:

Language. Full professional working proficiency at speaking, listening, reading, and writing in English.

Experience. Five(5) years' experience (within the last ten (10) years) working as a SSHO (or in a position with equivalent responsibilities), identifying potential risks and hazards, investigating accidents, and promote occupational safety on multiple construction projects, simultaneously, related to the project.

Certification. SSHO shall possess active credentials as a Certified Safety and Health Official(CSHO) in construction or Master Certification (MC) from an OSHA Training Institute Education Centers.

2.2.4. QCM. The QCM shall be accountable for overall supervision and management of the construction's quality control and management program(s) and plan(s). Contractor shall assign one QCM for each project who will work simultaneously as SSHO and QCM. The QCM shall be on site at all times during construction and alternate shall be identified in the Construction Quality Control Plan to serve in the event of the QCM's absence. The requirements for the alternate are the same as the QCM. It is the responsibility of the Contractor to express to the KO in the event that due to the complexity of the project, one employee will be required for each position.

The QCM is to be the Government's POC for all aspects relating to quality control. the QCM responsibilities include but are not limited to the supervision and management of the Contractor's quality control and management program(s) and plan(s)in accordance with specifications; inspecting work for conformance to project plans and specifications identifying issues arising during construction and verifying that deficiencies have been corrected; recording and notifying the PM and/or Superintendent of problems on a timely basis so that corrections can be made without impact to the project schedule; creating, updating and maintaining the project submittal log and all other project specific quality control reports; reviewing shop drawings and submittals for conformance with project specifications by direct review and by leveraging the knowledge and experience of others in the project team when necessary;

scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, designers of record, consultants, manufacturers, offsite fabricators, suppliers, and purchasing agents; tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation; continuing development of the project Quality Control Plan to address the specific needs of task orders, as required; examining the work area to assure that all required preliminary work has been completed and is in compliance with the contract; reviewing drawings and each paragraph of applicable specifications, reference codes, and standards applicable to work being performed in the field.

The QCM shall possess the following:

Language. Full professional working proficiency at speaking, listening, reading, and writing in English.

Experience. Five(5) years' experience (within the last ten (10) years) working as a QCM (or in a position with equivalent responsibilities), managing multiple construction projects simultaneously related to the project.

2.3. Temporary Utilities.

2.3.1. Water Service. The Contractor may use water from the Government's existing water system. When connecting to the Government's water system, including attaching water hoses to spigots, the Contractor must install a back flow prevention device that is approved by WSMR Water Plant manager (Mr. Andres Serna) at 575-678-1917 (Projects located on main cantonment, downrange, and North of Hwy 70/South of Route 6). For projects located North of Route 6,up-range to Stallion, Contractor must contact Mr.

Casey Masterson at 575-202-5341or Mr. Mark Vega at 575-679-4221. Water usage shall be reported to the COR monthly. Standpipe located on Headquarters Ave. approximately 6.5 miles from project. (LAT: 32.3690, LONG: -106.4793.

2.3.2. Electric Power Service. Power is not needed.

2.3.3. Utilities Cutovers and Interruptions. All anticipated utility outages shall be coordinated with DPW through the COR. A Make utility cutovers and interruptionsminimum advance notice of fourteen (14)calendar days shall be provided by the Contractor.

after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise. Conform to procedures required in paragraph Work Outside Regular Hours.

2.4. Portable Latrines. The Contractor shall provide a portable latrine for Contractor use. The designated restroom(s) must be properly maintained, and all Contractor debris removed. The facility must be kept clean. All liquid and solid waste from portable latrines shall be disposed at an approved off-site location.

2.5. Hours of Operation.

2.5.1. Normal Work Hours. White Sands Missile Range operates on a five-day work schedule and observes Federal Holidays.

Normal working hours for the installation are from 07:00 am to 4:30pm. The KO may authorize the Contractor to perform work outside of normal working hours and/or working days. If the Contractor desires to work during periods other than the days and hours listed above, a written request shall be made to the KO within four (4) calendar days of their intention.

2.5.2. Entry Restrictions and Roadblocks. The Contractor's and all associated sub-contractor's employees may be required to work in areas subject to entry restrictions, evacuations, and roadblocks. Roadblocks on public highways are normally set for a duration of at least one (1)hour. Internal roadblocks (on non-public WSMR roads) are normally set for a duration of at least two (2) Hours.

However, on occasion the duration may be as longas all day. If the Contractor is able to reach the work site and perform at least five

(5) hours of work, the Government will consider the day as an official work day. The Contractor is responsible for scheduling operations to avoid unnecessary delays and missed services. Range and roadblock status may be obtained by calling 575-678-1178 or 575-678-2222. Roadblocks time and duration are subject to change without prior notification.

2.5.3. Federal Government Holidays. For Government holidays visit https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=Overview.

This list of holidays relates to Government duty days and is not intended to supplement or otherwise alter the provisions of any Wage Determination regarding applicable paid holidays.

It is understood and agreed between the Government and the Contractor that observance of such days by Government personnel will not be a reason for an additional period of performance, or entitlement of compensation except as set forth within the contract. In the event the Contractor's personnel work during the holiday, the Contractor may reimburse them; however, no form of holiday or other premium compensation will be reimbursed either as a direct or indirect cost, other than their normal compensation for the time worked, unless stipulated otherwise. This provision does not preclude reimbursement for authorized overtime work if applicable.

2.5.4. Excused Absence. When the Department of Defense grants excused absence to its employees, the Contractor agrees to continue to provide sufficient personnel to perform critical tasks already in operation or scheduled, and shall be guided by the instructions issued by the KO or the COR.

2.5.5. Furlough. If Government personnel are furloughed, the Contractor shall contact the KO or the COR to receive direction. It is the Government's decision as to whether the contract price/cost will be affected as a result of Government shutdown and/or furloughed Government employees. In the event that Government shutdown and/or furloughed Government employee does impact contract price /cost, a negotiated settlement will be reached as deemed appropriate by the KO.

2.6. . Environmental Quality Program

2.6.1. Cleanup and Disposal of Waste Materials. The Contractor shall be responsible for the cleanup and disposal of waste and debris generated during and at the completion of this project. The Contractor shall be responsible for the payment of all disposal costs, fees for obtaining permits and licenses, and transportation costs. In addition, the Contractor shall pay, at no additional cost to the Government, all fines and clean-up costs due to improper disposal or due to spills, leaks, or releases. In general, the waste and debris shall be disposed of IAW all applicable Federal, State, and Local laws and regulations. Specifically, the waste and debris shall be disposed of IAW the jurisdiction having authority, including, any disposal site outside the State of New Mexico. The Contractor shall ensure that all waste and debris is containerized IAW the U.S. Department of Transportation and the jurisdiction having authority laws and regulations. The Contractor shall ensure that all waste is containerized in a manner to prevent uncontrolled and improper spills, leaks, and releases.

2.6.2. Waste Hauler Requirements. All waste haulers shall be licensed IAW the requirements specified in the appropriate New Mexico Administrative Code (NMAC) for the type of waste to be disposed of. In addition, all waste haulers are responsible for obtaining all required licenses and permits for jurisdictions outside of the State of New Mexico if crossing state lines to dispose of the waste.

2.6.3. Waste Disposal. The Contractor shall dispose of all waste and debris as follows:

2.6.3.1. Construction waste and debris.: All construction waste, as defined by the New Mexico Environment Department (NMED) Solid Waste Bureau (SWB) shall be disposed of at an off-site location that has been permitted, by the jurisdiction having authority, to accept and dispose of construction waste and debris.

2.6.3.2. Municipal solid waste: All municipal type waste and debris, as defined by the NMED SWB shall be disposed of at an off-site location that has been permitted, by the jurisdiction having authority, to accept and dispose of municipal solid waste.

2.6.3.3. Hazardous Waste, Universal Waste, and Polychlorinated Biphenyl (PCBs): All hazardous/universal waste and PCBs shall be disposed of through the WSMR Hazardous Waste Management Center (HWMC), Building 1870 (Main Post), 575-678-4641. The COR will coordinate with the HWMC to determine if the Contractor is responsible for disposing of the waste directly or if the waste is to be turned over to the HWMC for disposal. The Contractor is responsible for containerizing and transporting the waste in accordance with the U.S. Department of Transportation (USDOT) and the jurisdiction having authority regulations for the transportation of hazardous materials. In addition, the Contractor shall be responsible for completing and managing the waste manifest whenever transporting hazardous waste/universal waste and PCBs.

2.6.3.4. Defense Reserve Ozone Depleting Refrigerants: Ozone depleting refrigerants (R-22) shall be turned over to WSMR Environmental through the DPW HVAC section, Building 1751(Main Post), 575-678-1750. Cylinders shall be obtained from DPW HVAC section, and returned to the DPW HVAC section. For all other refrigerants and ozone depleting chemicals, the Contractor is responsible for proper disposal offsite, including containerizing and transporting the refrigerants in accordance with USDOT and the jurisdiction having authority regulations for the transportation of refrigerants.

2.6.3.5. Asbestos Waste and Debris: All asbestos waste and debris shall be disposed of at an off-site location that has been permitted, by the jurisdiction having authority, to accept and dispose of the asbestos waste and debris. The Contractor shall ensure that all asbestos waste and debris is containerized and transported in accordance with the USDOT and the jurisdiction have authority regulations. In addition, containers such as roll-offs and trailers shall have rigid sides, bottoms, and tops to transport asbestos waste and debris. Containers with soft covers(e.g. tarps) are prohibited. The Contractor shall be responsible for completing and managing the asbestos waste shipment record in accordance with EPA regulation 40 CFR Part 61 and the State of New Mexico Environment Department Solid Waste Regulations.

2.6.3.6. Liquid, semisolid, and sludge waste: All liquid, semisolid, and sludge waste shall be disposed of at an off-site location that has been permitted, by the jurisdiction having authority, accept and dispose of the waste.

2.6.3.7. Waste from Portable Latrines ("Port-a-Potties"): All waste from portable latrines shall be disposed of at an off-site location that has been permitted, by the jurisdiction having authority to accept and dispose of the waste.

2.6.3.8. Scrap Metal: To the extent possible or if required as part of this project, scrap metal, including electrical wiring, shall be disposed of at the WSMR Metal Scrap Yard(575-678-3160 or 575-640-8522), located 3.5 miles east of Main Post. All glass shall be removed from metal windows and metal doors before transporting the scrap metal to the Metal Scrap Yard.

2.6.3.9. All other waste and debris not specifically noted: Dispose of all other waste and debris IAW the laws and regulations of the jurisdiction having authority.

2.6.3.10. NOTE: The Hughes Diversion Area has been permanently closed and WILL NOT be available for contractor use.

All construction debris and waste shall be disposed of at an off-site location that has been permitted, by the jurisdiction having authority, to accept and dispose of construction waste and debris.

2.6.4. Prohibitions. The Contractor shall be prohibited from performing the following:

2.6.4.1. On-site burning or incineration of waste and debris.

2.6.4.2. On-site burial.

2.6.4.3. Dumping at locations not permitted by the jurisdiction having authority to accept and dispose of the waste and debris.

2.6.4.4. Use of unlicensed waste haulers.

2.6.4.5. Using containers that are not appropriate for the disposal of waste and debris.

2.6.5. Air Pollution Prevention. The Contractor shall comply with applicable Federal, State, and Local laws and regulations concerning the prevention and control of air pollution. The Contractor shall utilize such methods and devices as are reasonably available to prevent, control, and otherwise minimize atmospheric emissions or discharges of air contaminants. For examples, equipment and vehicles that show excessive emissions of exhaust gases shall not be operated until corrective repairs or adjustments reduce such emissions to acceptable levels.

2.6.6. Dust Control. During the performance of work required, the Contractor shall comply with applicable Federal, State, and Local laws and regulations regarding the prevention, control, and abatement of dust pollution. Materials other than water used for dust control shall be approved by the WSMR Environmental Division. The Contractor shall be responsible for all damages resulting from dust originating from Contractor operations IAW the clause at FAR 52.236-7 entitled "Permits and Responsibilities." The Contractor shall provide all labor, equipment, and materials, and shall use efficient, methods wherever and whenever required to prevent, dust nuisance or damage to persons, property, or activities, including, but not limited to crops, orchards, cultivated fields, wildlife habitats, traffic, and similar conditions.

2.6.7. Water Pollution Prevention. Contractor shall control point source discharges by use of sediment and erosion controls;

wastewater and storm water management controls; construction site management practices; best management practices (BMP); and other controls; including Federal, State, and Local control requirements.

2.6.8. Archeological and Cultural Resources. report any inadvertent archeological or cultural resourceThe Contractor shall discoveries to the COR immediately. If bone is encountered, stop digging immediately and contact the COR.

2.6.9. Wildlife Conservation. Personnel should be aware of snakes, and various other species of wildlife in the area that could cause harm if encountered or disturbed. Report any nuisance, injured, or dead wildlife discovered at project site immediately. Do not harass, collect, possess, harm, or destroy wildlife or their habitat. Do not provide water or feed wildlife. Do not leave uneaten food at buildings and in the field, to prevent attracting wildlife. Do not litter and clean up all trash left at work site Contact DPW Environmental Division - for assistance with Wildlife at 575-678-2225. Migratory bird nesting season is between 1 March through 31 August. Any ground disturbance or work that has the potential to remove an active nest needs to be surveyed. Area will be surveyed for nesting migratory birds by people who have been determined to be qualified by PW Environmental within 24 hours prior to start of work. For any active nest found with eggs or nestlings, the area of the nest will be avoided by workers IAW PW Environmental instructions.

2.7. Safety.

2.7.1. Safety Compliance. Army construction contracts fall within the purview of the US Army Corps of Engineers Safety and Health Requirements Manual, Engineer Manual (EM) 385-1-1,and Occupational Safety and Health Administration (OSHA) Title 29 Part 1910 and1926. The version in effect at time of contract award will be used. OSHA 29 CFR1910 Safety and Health Regulations as well as 29 CFR 1926 Safety and Health Regulations for Construction are available online at:

2.7.1.1. http://www.osha.gov/

2.7.1.2. EM-385-1-1is available online at: http://www.publications.usace.army.mil/USACE-Publications/Engineer-Manuals/

2.7.2. Coordination with Sub-Contractors. The Contractor is the "controlling employer" and is responsible for all work site safety and health conditions including those of the subcontractors. The Contractor shall be responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one task from interfering with or creating hazardous working conditions for other tasks, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

2.7.3. Traffic Control.

2.7.3.1. Traffic Control shall allow for two-way traffic to continue. When traffic must be rerouted or controlled to accomplish the work, provide necessary warning signs, flag persons, and related equipment for the safe passage of vehicles.

2.7.3.2. Informational Traffic Signs. Contractor shall provide and install informational traffic signs on all road construction projects to alert motorists of upcoming construction dates. Signs shall be properly secured to ensure they are not affected by weather conditions. Signs shall be installed 30 days prior construction and shall be located on adjacent roads approaching construction site. Signs shall indicate: "Road will be closed on X date" or "Road will be partially closed on X date". All temporary signs shall comply with the latest edition of the Manual on Uniform Traffic Control Devices (MUTCD).

2.7.3.3. Contractor shall notify the KO five (5) working days in advance before any demolition work is started to ensure traffic control measures are adequate and coordination is accomplished with other activities on the installation in a timely manner.

2.7.4. Site Specific Safety Plan. Construction contracts shall include a site and project specific safety plan. See Section 2.13 for submittal requirements. EM 385-1-1 refers to a safety plan as an Accident Prevention Plan (APP). The safety plan shall be tailored to the project, based on the size and complexity of the construction to be accomplished and shall include a fall protection and prevention program. A typical safety plan will address such issues as, but will not be limited to, the following:

2.7.4.1. The company's safety and health policy.

2.7.4.2. Company safety inspections of the job site.

2.7.4.3. Use of personnel protective equipment (PPE).

2.7.4.4. Safety rules and penalties associated with not following the rules.

2.7.4.5. Safety training and frequency (identifying hazards, explaining precautions and proper use of equipment /machinery, and the PPE required for the job including how to use and maintain PPE).

2.7.4.6. The steps to be followed to report unsafe working conditions and practices.

2.7.4.7. Special hazards.

2.7.4.8. Hazardous materials.

2.7.4.9. Confined spaces, i.e. entry procedures and ventilation requirements, etc.

2.7.4.10. Lockout tag procedures.

2.7.4.11. Instruction concerning safe operations and appropriate emergency action in the event of accidental exposure.

2.7.4.12. Emergency procedures.

2.7.4.13. Identifying personnel on site who have had first aid training.

2.7.4.14. Identify where communication devices (such as phones, radios or other approved communication devices) are located with appropriate phone numbers posted.

2.7.4.15. Post how to exit the work area in an expeditious and safe manner.

2.7.4.16. The plan will identify the person with lead responsibility for safety, where protective equipment may be obtained and the procedures for reporting a safety hazard.

The person identified as the lead responsible for Safety may also perform Contractor Quality Control(CQC) upon approval by the KO (see Section 2.9.1).

Approval of the Safety Plan does not relieve the Contractor of complying with all applicable safety requirements.

2.7.5. Internal Job Site Safety Inspections. Frequent and regular Contractor internal job site inspections shall focus on identifying and removing hazards. The Contractor's Safety Plan shall explain the disciplinary process that will be followed when the Contractor job inspections find violations to the safety rules. The disciplinary process shall be included in the employee's training and reviewed during regular safety briefings. The Government will review the Contractor's Safety Plan for adequacy, completeness and compliance with OSHA and EM 385-1-1requirements. The Contractor shall review and amend the safety plan, as necessary, throughout the life of the contract. Amended safety plans shall be submitted to the COR and KO for approval. The Contractor shall incorporate unusual or high-hazard activities not identified in the original safety plan as they are discovered.

2.7.6. Activity Hazard Analysis (AHA). Before beginning each work activity involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity shall prepare an Activity Hazard Analysis (AHA) (sometimes called a job hazard analysis). See section

2.13 for deliverable requirements.

Approval of the Activity Hazard Analysis does not relieve the Contractor of complying with all applicable safety requirements.

2.7.7. Accident Reporting Requirements.

2.7.7.1. The Contractor shall immediately report all accidents or injuries to the COR or his/her designee. If COR or Project Representative is not available, report accidents or injuries to the Garrison Safety manager (575-678-3221).Forward a written report through the COR using Contractor's format or similar IAW DAPAM 385-40 to the Installation Safety Office (ISO) within seven (7)calendar days of occurrence.

2.7.7.2. Damage to Army property. This includes Government furnished material, property, or equipment provided to a Contractor. Contractor must complete DA Form 285 or 285-AB-R (available at http://armypubs.army.mil/),when damage to Army property is equal to or greater than $5,000.00. If Contractor has an issued Common Access Card (CAC), Contractor is required to complete the report through REPORT IT, the Army's online accident reporting system (https://safety.army.mil/).

If the Contractor has not been issued a CAC, the forms identified in DA PAM 385-40 must be utilized and provided to the ISO Director or designated representative within seven (7) calendar days of occurrence.

2.7.7.3. The COR shall immediately notify the ISO of a Contractor accident or injury and ensure a written accident report is sent to the ISO within seven (7) calendar days of occurrence.

2.7.7.4. Contractors shall report to the Local OSHA office accidents and injuries in accordance with OSHA reporting requirements(https://www.osha.gov/sites/default/files/OSHA-RK-Forms-Package.pdf).

2.7.8. Safety Meetings. The Contractor shall conduct and document meetings as required by EM 385-1-1. Attach minutes showing contract title, signatures of attendees and a list of topics discussed to the Contractor's daily report (see Section 2.9.2).

2.7.9. Display of Safety Information. The Contractor shall erect a safety and occupational health (SOH) bulletin board at the job site at least one (1) calendar day prior to commencement of work. Include and maintain information on safety bulletin board as required by EM 385-1-1, section 01.A.07"SOH Bulletin Board". Where size, duration, or logistics of project do not facilitate a bulletin board, an alternative method, acceptable to the COR, that is accessible and includes all mandatory information for employee and visitor review, shall be deemed as meeting the requirement for a bulletin board.

2.7.10. Work in Confined Spaces. The Contractor shall comply with the requirements in Section 34 of USACE EM 385-1-1, OSHA 29 CFR 1910.146, and OSHA 29 CFR1926.21(b)(6). Any potential for a hazard in the confined space requires a permit system to be used. WSMR Fire Department issues permits for confined space entry. Please call575-678-0470 or 575-678-4187 to obtain a permit. Permits shall be requested no later than two(2) working days in advance of the work to be performed. The Contractor shall coordinate with the COR to submit the permit request.

2.7.11. Safety Data Sheets for Hazardous Materials. The Contractor shall submit a List of Hazardous Materials (LHM) and Safety Data Sheets (SDS) IAW requirements of FAR 52.223-3, Hazardous Material Identification and Material Safety Data. See Section 2.13 for submittal requirements.

2.7.12. Radiation Permits and Authorizations. Civilian Contractors bringing radioactive devices (e.g. nuclear soil density meters, X- Ray Fluorescence (XRF) equipment) onto the Installation must have approval from the Garrison Radiation Safety Manager, 575-678- 8234/1211. Contractor shall prepare and submit an application (DA Form 3337, http://armypubs.army.mil) to bring in radiation devices at least sixty (60) calendar days prior to anticipated use. Applications shall be submitted through the COR. Contractor shall not bring in any devices without a Government approved application. License requirements are listed below:

2.7.12.1. Nuclear Regulatory Commission (NRC) Licensees will need to complete DA Form 3337 and provide a copy of the license.

2.7.12.2. NM Licensees will need to complete DA Form 3337 and include copy of NM License if work is north of Hwy 70; work south of Hwy 70 will require NRC reciprocity.

2.7.12.3. Agreement State Licensees will need to complete DA Form 3337 and include copy of NRC or New Mexico Reciprocity for work north of Hwy70; work south of Hwy 70 will require NRC reciprocity.

2.7.13. Hot Work Permits. The Contractor shall obtain a hot work permit for any activity that requires an open flame or involves activities such as welding, burning, brazing, soldering, cutting and grinding materials. Hot work permits can be obtained from the WSMR Fire Department. Please call 575-678-3585 or 575-678-4020 or 575-678-7866 to obtain a permit. Permits shall be requested no later than two (2) working days in advance.

2.8. Quality Control (QC).

2.8.1. QC Program Requirements. Establish and maintain a QC system that complies with FAR 52.246-12 Inspection of Construction and as described in this section. The QC program consists of a QC Manager, a QC plan, a Coordination and Mutual Understanding Meeting, QC meetings, three phases of control, submittal review and approval, testing, and QC certifications and documentation necessary to…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .